1.0 COMPANY PROFILE
1.1 Introduction
1.2 Organisation Chart
2.0 PRELIMINARY STUDY
2.1 Project Scope
2.2 S.W.O.T. Analysis
2.3 Project Viability
3.0 PROJECT MANAGEMENT
3.1 Work Breakdown Structure
3.2 Pert’s Chart/Gantt Chart
3.3 Risk Analysis
3.4 Success Criteria
3.5 Maintenance Proposal
4.0 DESIGN DEVELOPMENT
4.1 Architecture
4.1.1 Plans
4.1.2 Elevations
4.1.3 Elevations (Colour Selection)
4.1.4 Sections
4.1.5 Site Elevations
4.2 Civil & Structural Engineering
4.2.1 Ground Floor Structural Plan
4.2.2 First Floor Structural Plan
4.2.3 Roof Level Structural Plan
4.2.4 Structural Model
4.2.5 Calculation of Column Loads and Feasibility
4.2.6 Reinforcement of Existing Structure
4.2.7 Staircase Details
4.3 Mechanical & Electrical Engineering
4.3.1 Electrical System
4.3.2 Hot & Cold Water Supply System
4.3.3 Sanitary System
4.3.4 Rainwater Harvesting System
4.4 Interior Design
4.4.1 Case Studies
4.4.2 Proposals of Interior Design Styles
4.4.3 Furniture Layout Plans
4.4.4 Finishes Selection
4.4.5 Interior Spaces Overview
4.4.6 Interior Openings
4.4.7 Interior Fittings
4.5 Landscape Design
4.5.1 Concept
4.5.2 Conceptual Visuals
4.5.3 Proposed Landscaping
4.6 Quantity Surveying
4.6.1 Return On Investment
4.6.2 Breakdown of Renovation Cost
5.0 REFERENCES
6.0 APPENDIX
6.1 Attendance Records
6.2 Meeting Agenda
6.3 Meeting Minutes
CONTENT
1.1 INTRODUCTION
A young and free spirit design studio established in 2012 that
specializes in small residential projects. We aim to achieve the home
spirit within the team in every single projects. Running wild in exploring
wow inspiration from different elements in daily life.
VISION
To be creative and distinctive
We dedicated to transform design idea into tangible reality through
our professionalism and great passion with a visionary approach. We
strive to create unique yet practical design exclusively just for the
clients.
1.2 ORGANISATIONAL CHART
1.0 COMPANY PROFILE
SCOPE
Architecture. Interior Design
We provide full range of services from preliminary feasibility studies and
programming, schematic design, design development, contract documents,
tendering and construction administration, and finally post-construction
services.
LOGO
From A –Z
Our logo carries the meaning of our
job scope of covering the project from
head to toe. Besides, it is also the last
Initials of our founder which is the
architect in our company.
C&S
ENGINEER
IR. LIM
SHU YIN
M&E
ENGINEER
IR. ANGELINE
KON
QUANTITY
SURVEYOR
SR. NICOLE
LIM
INTERIOR
DESIGNER
LIM SU YING
LANDSCAPE
ARCHITECT
HELSA
JOSEPHINE
ARCHITECT
AR. NICK LIM WEI ZE
PROJECT MANAGER
CHAN JASMINE
architecture . Interior
2.1 PROJECT SCOPE
Client : Ms Fernn Ang
Proposal : Redesigning Compact Living
Objective : To design a comfortable living space that would provide
yield enhancement (rental) or capital gain (sale)
Usage type : Residential (long term/short stay)
Market Value : RM420,000; Rental – RM1000 per month, yield of 2.85%
Returns : 1. Capital gains of at least 20% per annum
2. Rental yield of at least 3.5% for long term
Budget : Up to RM100,000
Timeline : Up to 6 months
SITE PLAN
Reference: Project brief from Ms Fernn AngReference: Project brief from Ms Fernn Ang
2.0 PRELIMINARY STUDY
LOCATION PLAN
PROJECT DETAILS
LOCATION : SS19, Subang Jaya
PROPERTY TYPE : Double-Storey Link House (End Lot)
LAND SIZE : 16’ x 45’
TOTAL BUILT-UP : 82.80 m2
2.2 S.W.O.T ANALYSIS
2.0 PRELIMINARY STUDY
TO RENT COMPARISONS FOR SALE
RM1000 - RM1500 RATE RM550,000 – RM600,000
2 Months
ESTIMATED CONSTRUCTION
DURATION
3 Months
Rental yield of 3.5% based on current
market value with renovation cost
RETURNS
Capital gains of 20% based on current
market value with renovation cost
Regular basis after each rent MAINTENANCE Ends after renovation
PROPOSALS
2.3 PROJECT VIABILITY
HELPFUL HARMFUL
INTERNAL
The house exposes to three faces ( front, back and side)
which slows more natural light to penetrate through.
Location of the house is subtle.
EXTERNAL
Rich surrounding context with educational buildings(primary
school) and retails.
Quiet area might leads to safety issue.
COMPARISONS BETWEEN TO RENT AND FOR SALE
DECISION: FOR SALE
1. WITHIN RESIDENTIAL ZONE
Redesigning the house for young family is a suitable choice as it is within the
residential area in SS19. There are shops within walking distance from the house
which provides convenience to the buyer. Besides the nearby public primary
school is an advantage towards our house.
2. HIGHER RETURN
Compare to long term rental basis, getting a buyer can earn a higher
percentage of profit within a shorter time. As the colleges and universities are
not within the area, renting the unit for students might not be a wise choice.
Furthermore, poor public transport system is also the disadvantage for students
who do not own a car. Hence, finding a buyer who is looking for permanent stay
is a better option.
3. LOW MAINTENANCE
There will be minimal maintenance or even no maintenance needed after the
house is sold off as it will be the responsibility of the buyer who is the new
owner of the unit. Whereas if the house is being rented out regular maintenance
fee will be an expensive cost.
2.0 PRELIMINARY STUDY
PROS & CONS
TO RENT FOR SALE
PROS
1. Easier to get a tenant.
2. Lower budget for minor
renovation.
1. Nearby public schools and
retail shops.
2. Low or no maintenance.
3. Higher return.
CONS
1. No surrounding college or
university.
2. Inconvenience of public
transport.
3. High maintenance.
4. Lower return or no return
1. Longer time to get a buyer.
2. Higher budget for major
renovation.
2.3 PROJECT VIABILITY
Design Stage
Architect
Civil &
Structure
Schematic Design
Detail Design
Renovation
Pre-Design
Stage
Project Brief & Budget
Constraints
Scope & Schedule
Site Study & Local
Authority Visit
Design Requirement
Feasibility Study
Final Proposal
Schematic Design
Construction
Detail Design
Final Proposal
Mechanical &
Electrical
Schematic Design
System Detail
Design
Interior Design
Layout Design
Selection of
Materials &
Fixtures
Landscape
Design
Layout Design
Selection of
Landscaping
Materials
Quantity
Surveying
Preliminary
Costing
Cost Breakdown
Post Design
Stage
Final Proposal
Submission to Local
Authority
Preparation of Tender
Documents
Tender
3.1 WORK BREAKDOWN STRUCTURE
3.0 PROJECT MANAGEMENT
3.2 GANTT CHART
CLIENT-CONSULTANT MEETING
Client: Ms Fernn Ang
Proposed House Renovation At Lot PT7632, No. 123, Jalan SS19/6A, Petaling Jaya, Selangor.
3.0 PROJECT MANAGEMENT
Stages Type of Risks Likelihood Severity Impact Strategy Contingency
PRE-DESIGN
Change of program 3 4
Time and effort wasted in
preparing the previous
proposal
Prepare new proposal for the
new program
Regular meetings and
discussions with the client
Misunderstanding of project
brief
2 4
Inappropriate design
proposal
Understand the project scope
and follow the schedule
planned
Regular meetings and
discussions with the client
Reduction of budget 2 4 Team being underpaid
To convince the client
Reduce the scope of project
Design that is beyond client’s
expectation
Cancellation of project 1 5 Losing the project To convince the client
Design that is beyond client’s
expectation.
DESIGN
Internal conflict 3 4 Poor performance
Project manager to resolve
the conflict.
Project manager to build up
the teamwork.
Miscommunication between
client and team
2 4
Not meeting client’s
requirement
Discussions with client for
clarification of project
Update the result of discussion
consistently
Costing error 3 3 Resulting in over budgeting
Considering reducing budget
in materials (replaced with
recycled materials)
Detail drawings to be
supervised.
Untallied drawings 2 3
Inconsistency in project
presentation
Technical meetings within
the team to ensure the
consistency before
presentation
Regular meetings and
discussions with the client
POST
DESIGN
Late approval by local
authority
2 4 Delay in project
Changes for submission
requirements
To check with the local
authority before finalizing
design
3.3 RISK ANALYSIS
3.0 PROJECT MANAGEMENT
Exceeds customer’s expectation by completing the project within three
constraints: deadline, budget and quality.
KEY SUCCESS INDICATORS
1. Project efficiency
- Meeting schedule
- Completing within budget
2. Impact on the customer
- Fulfilling customer’s needs
- Meeting functional performance
3. Direct and business success
- Immediate revenue and profit enhanced
- Larger market share generated
4. Preparing for the future
- Create new opportunity
- Increase capability and competency
A success project is with the help of proper management and planning.
Meeting the objective of the project shows the understanding in business
drivers and brings satisfaction to the client. Project manager is able to keep
track with the objective and improve the whole performance through these
measurable regulators.
3.4 SUCCESS CRITERIA
A successful project is the one being delivered on time, within budget and meet
scope specifications.
1. Understanding the project scope
- Redesigning compact living within a budget of RM100,000
2. Starting the project with a plan ahead
- Gives direction to the team with each responsibilities
3. Good communication
- Meeting for discussion in regular basis to update the each progress and ensure
everyone is on the same path
4. Widen resources, skills and knowledge
- Research and development in skills for each role in order to produce qualitative
outcome
5. Well management & control of project
- Following the management framework in an ongoing project to ensure success
6. Learn from the past mistakes
- Improvise and rework from the error
3.0 PROJECT MANAGEMENT
TIME
SCOPECOST
QUALITY
SATISFACTION
SCHEDULE
BUDGET
VOLUME
QUALITY
3.5 MAINTENANCE PROPOSAL
As the design approach is to redesign the house into a compact living and
sell it off instead of renting, a lower maintenance is required compared to
rental basis as it will be the buyer’s responsibility to take care of the house.
Therefore, much precautions should be taken before handing the house to
the client.
Management
A structured working schedule should be planned in the early stage of the
preparation for the project so that each team member will be guided to work
according to the flow. Besides, the working environment should be inspiring
to boost the member’s productivity during the project.
Architect
The architect has to make sure that the house is practical and promising up
to the client’s requirement. Besides, he will have to ensure that the extension
of the building is according to by-law and did not break any rules and
regulations set by the local authority.
C&S Engineer
As the building is extended with a new roof structure, the engineer has to
make sure that the building structure can withstand the load from the new
added elements. Besides, the engineer has to enhance the existing structure
due to lack of maintenance from the previous tenant.
M&E Engineer
Mostly all the existing system will be renewed for further usage hence the
engineer has to make the renewal is done appropriately to avoid accident or
leakage. Besides, proposing system that is energy saving could enhance the
sale of the house.
3.0 PROJECT MANAGEMENT
Interior Designer
As the client wanted an easy maintain and minimal look new interior, the
designer will have to make sure that the selected design concept is meeting
the requirement which is simple yet practical. Besides, as a lot of openings are
being proposed to enhance the lighting in the house, privacy of the owner of
the house is one of the issues that should be taken care of.
Landscape Architect
The landscape designer will have to ensure that the proposed landscape is
not only nice to view at, but also easy maintained. The outdoor furniture has
to be durable and weather resistance so that it can last long.
Quantity Surveyor
Costing is one of the major factor in the project hence it should be calculated
as precise as possible according to the constraints set by the client.
Furthermore, the surveyor has to make sure that each of the team member is
paid accordingly and sufficiently from the project.
4.0 DESIGN DEVELOPMENT
4.1 ARCHITECTURE
4.1.1 PLANS
4.0 DESIGN DEVELOPMENT
4.1 ARCHITECTURE
4.1.2 ELEVATIONS
4.0 DESIGN DEVELOPMENT
4.1 ARCHITECTURE
4.1.3 ELEVATIONS (COLOR SELECTION)
4.0 DESIGN DEVELOPMENT
4.1 ARCHITECTURE
4.1.4 SECTIONS
4.0 DESIGN DEVELOPMENT
4.1 ARCHITECTURE
4.1.5 SITE ELEVATIONS
Existing structural planNew structural plan
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.1 GROUND FLOOR STRUCTURAL PLAN
Existing structural planNew structural plan
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.2 FIRST FLOOR STRUCTURAL PLAN
Existing structural planNew structural plan
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.3 ROOF LEVEL STRUCTURAL PLAN
Structural model (Front perspective) Structural model (Rear perspective)
New structural members Existing structural members
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.4 STRUCTURAL MODEL
Column B1, 1
Dead load:
Roof = 45.55 kN
First floor = 96.78 kN
Live load:
Roof = 6.37 kN
First floor = 9.56 kN
Column C1, 1
Dead load:
Roof = 18.97 kN
First floor = 62.82 kN
Live load:
Roof = 3.21 kN
First floor = 6.45 kN
Column C, 1
Dead load:
Ground floor = 56.11 kN
Live load:
Ground floor = 8.33 kN
Ultimate Load of column C, 1
Total dead load x 1.4 = 392.3 kN
Total live load x 1.6 = 54.28 kN
Ultimate load = 392.3 + 54.28
= 446.58 kN
Assumption
Fcu = 30N/mm² (concrete strength)
Fy = 460N/mm ² (yield strength of reinforcement)
Ac = 120mm x 250mm =30000mm ² (Column section area)
Asc = 30000 x 2% = 540mm ²
N, capacity of concrete
= 0.4 x Fcu x Ac + 0.8 x 540 x 460
= 0.4 x 30 x 30000 + 0.8 x 540 x 460
= 558.72 kN
Original column size of 120mm x 225mm is sufficient to sustain the new ultimate load.
Transfer of load from the roof to the ground
along column B1,1, column C1, 1 and column
C,1.
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.5 CALCULATION OF COLUMN LOADS AND FEASIBILITY
Small cracks restoration & Reinforcing weak walls
Jointing new walls
Small cracks found within the existing structure can be restored
to its original tensile strength by pressure injection of grout or
epoxy into the cracks of the wall. The old structure may require
reinforcement for weak walls, in which the same technique is
applied through making injection holes on the wall which is to
be reinforced. Construction of a new lateral structure
to reinforce existing walls. Connection
steels are grouted in drilled holes to
create the jointing between the
existing structure and the new
structure.
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.6 REINFORCEMENT OF EXISTING STRUCTURE
Cable turnbuckle suspension cable
Cable turnbuckle hinge
Tension cable
Stainless steel U plate welded to tread and wall
Steel pin bolted to tread and wall
Bolt and washer securing the U plate
Open riser tread
Threaded washer and bolt support at cable end
Suspension bolt
Bolt securing and attached
Chrome washer
Bolt
Cable end
Cable anchor that attaches to
to tension cable
steel plate bolted to underside of
beam
Cable suspended open riser
staircase
Normal staircase supported by
masonry wall below
The design of the staircase includes that of a
standard concrete stairs with timber finishing and
also steps that are cable suspended and mounted to
the wall.
The structure is constructed above the masonry
walls of the storeroom space beneath the staircase.
The cable suspended staircase is securely anchored
to the First floor beams as well as the wall.
U-plates grip and supports the tread as
they are welded & bolted to the wall.
Tension cables support the other side of
the treads which also forms the
balustrade for the whole staircase.
4.0 DESIGN DEVELOPMENT
4.2 CIVIL AND STRUCTURAL
4.2.7 STAIRCASE DETAILS
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.1 ELECTRICAL SYSTEM
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.1 ELECTRICAL SYSTEM
Note: COP 28, Cables installed behind walls (MS 1979:2007)
Where cables are installed buried behind walls, they shall be installed horizontally or vertically.
i.e. parallel to the edges of the room. Subject to the dimensions of the columns and beams, they shall be
within 150 mm from the top of the walls and 150 mm from the edge of the wall
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.1 ELECTRICAL SYSTEM
Electrical Schematic Layout
Water Heater
Features:
- Sleek and Stylish In-Mould Casing Technology
- Stepless Electronic Power Control
- IP25 Splash Proof Protection
- 1 Touch Shower On / Off Safety Switch Technology
- Reinforced 3 Layer Flexi-Hose
Volume : 1000 liters
Dimensions : 240 X 360 X 70 mm
Inlet/ Outlet Connection : ø15mm (1/2” BSP)
– Single Point System
Min. Water Pressure :10 kPa
Max. Water Pressure: 380 kPa
Min. Water Flow : 2 litres per minute
Max. Water Flow : 8 litres per minute
Hot and Cold Water Supply System Schematic Layout
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.2 HOT & COLD WATER SUPPLY
Total Water Heater: 3
Total Cost : RM 770 x 3 units
= RM2310
Sanitary System Schematic Layout
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.3 SANITARY SYSTEM
80 Gallon Rainwater Harvesting Tank
The Minister of Housing and Local Government on 7
May 1998 has expressed the Government’s interest for
houses to be designed for collecting rainwater. In
1999, the Ministry of Housing and Local Government
has produced a Guideline on Installing a Rainwater
Collection and Utilization System.
Rainwater is collected from roof of the and filtered
before entering below ground rainwater harvesting
tank.
The water can then either be pumped either directly to
WCs and vehicle jet washes, or to a high level break
tank within the house which will then service the non-
potable appliances as per normal.
Potential Rainwater From Roof
Roof Yield = Roof Area x Average Annual Rainfall
= (32.3+26.7) X 2400mm
= 141,600 litres per year
Features:
- Made from 100% pre-consumer waste
- UV-resistant LLDPE polyethylene
- 45% more water than a 55 gallon container
- No bisphenol A in our plastic!
- Unlimited number of units can be connected in series
- Assembly Required
- Built-in store/divert diverter valve
- Garden hose shut off valve included
- Child safe design
- The bottom of the diverter box is designed to accept
4 inch landscape pipe.
Capacity : 80 Galloons (302.8 litres)
Dimensions : 711.2 X 711.2 X 1320.8
mm
Inlet/ Outlet Connection : ø101.6mm diameter (4”)
Cost for tank : RM 764.6100
Cost for drain pipe : RM 69.81
80-gallon Molded Plastic Rain Water Harvesting Tank Schematic Section
Rainwater Harvesting System Schematic Design
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.4 RAINWATER HARVESTING SYSTEM
Rainwater Harvesting System Layout
4.0 DESIGN DEVELOPMENT
4.3 MECHANICAL & ELECTRICAL
4.3.4 RAINWATER HARVESTING SYSTEM
Location: Taman Tun Dr Ismail, Kuala Lumpur, Federal Territory of Kuala Lumpur, Malaysia
Terrace 23
GROUND FLOOR PLAN FIRST FLOOR PLAN
Case Study 1
• Linear and narrow layout.
• Double-story unit.
• Family living of design layout.
• Contemporary interior design with simple, raw finishes to outline a clean visual
layout, giving an illusion of “enlargement” in space.
HIGHLIGHTS:
• Green building feature – Roof Garden
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.1 CASE STUDIES
GROUND FLOOR PLAN FIRST FLOOR PLAN
Case Study 2
Location: Jalan Kaloi, 59100 Kuala Lumpur,
Wilayah Persekutuan Kuala Lumpur.
L 45 – Community Library & Student Housing
• Narrow rooms/ limited
spaces.
• Double-story unit.
• Student dormitory
interior design layout.
• Industrial interior
design furniture and
fixtures.
• Easy cleaning and
maintenance.
HIGHLIGHTS:
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.1 CASE STUDIES
• Living Area
• Dining Area
• Kitchen
• Bathroom
• Staircase
MOOD BOARD 1 – Ground Floor:
• Bedroom 1
• Bedroom 2
• Bathroom
• Master Bedroom
• Master Bathroom
MOOD BOARD 2 – First Floor:
Design Style - Industrial
• CLEAN LINES
• FORM FOLLOW FUNCTION
• LOWER SITTING FURNITURE
• EMPHASIZE NEGATIVE SPACES
• HELP SMALL SPACES APPEAR LARGER
• NEUTRAL COLOURS
• 20 YEARS IN THE FUTURE – “RETRO”
| CONTEMPORARY
| ADVANTAGES
| MINIMALIST
• NATURAL LIGHTS TO HIGHLIGHT SPACES &
SHAPES
• BARE MINIMUM OF FURNITURE
• HIDEEN STORAGE
(CABINETS BLEND INTO WALL)
• SIMPLE & TIDY
• VISUALLY ENLARGE SMALL SPACES
• EASY MAINTENANCE
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.2 PROPOSALS OF INTERIOR DESIGN STYLE
First Floor Plan
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.3 FURNITURE LAYOUT PLANS
Ground Floor Plan
Wall Finishes
Floor Finishes
TIMBER STAIR STEPS
- Give contrast and warm-up the cold
tone of industrial design.
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.4 FINISHES SELECTION
Industrial Cold Series
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.5 INTERIOR SPACES OVERVIEW
Ground Floor Plan
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.5 INTERIOR SPACES OVERVIEW
First Floor Plan
Large openings are selected to allow more natural light penetration and natural
wind to flow into the narrow spaces, it celebrates the realm of industrial design,
meantime creating lively and brighter ambience in the house.
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.6 INTERIOR OPENINGS
Ground Floor Plan
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.6 INTERIOR OPENINGS
First Floor Plan
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.7 INTERIOR FITTINGS
Ground Floor Plan
4.0 DESIGN DEVELOPMENT
4.4 INTERIOR DESIGN
4.4.7 INTERIOR FITTINGS
First Floor Plan
• Ornamental grass
• Water feature
• Grass
• Gravels
LANDSCAPING
4.0 DESIGN DEVELOPMENT
4.5 LANDSCAPE DESIGN
4.5.1 CONCEPT
4.0 DESIGN DEVELOPMENT
4.5 LANDSCAPE DESIGN
4.5.2 CONCEPTUAL VISUAL
3D RENDERINGS
Ground Floor Plan
CAR PORCH
LANDSCAPE
4.0 DESIGN DEVELOPMENT
4.5 LANDSCAPE DESIGN
4.5.3 PROPOSED LANDSCAPING
Minimalist Gate
• Simple design
• Complementing the design approach of
industrial design
• Not overpowering the façade
• Can be constructed from construction waste
Concrete Tiles
• Non-slip tiles
• Suitable for outdoor purposes
• Easy maintenance
• Complementing the design approach of
industrial design
Bamboo Palm
• Plant type: House Plant
• Height: Ranging from 1.7 m to 3m
• Leaf Colour: Green
• Growth Rate: Average
Water Feature
• 1.7 m in height
• Gives a strong sense of nature to
compliment the small area of the landscape
• Provide the sound of nature
• Gives a strong aesthetic value
• Gives a calm effect through the sense of
hearing
Fake Grass
• Wide range of grass colour shade selection
• Comes in role or tiles; for easier
customization of size needed
• Offer a real aesthetic value with a real grass
• Very easy maintenance as watering and
trimming is not needed
4.0 DESIGN DEVELOPMENT
4.5 LANDSCAPE DESIGN
4.5.3 PROPOSED LANDSCAPING
SELL
Property Gains = Selling Price – Acquisition Price
Selling Price = (Acquisition Price + Renovation Cost) x 20% Capital Gain
= (RM420,000 + RM100,000) x 20% Capital Gain
= RM624,000
Property Gains = RM624,000 – RM420,000
= RM204,000
Net Property Gains = Property Gains – Property Gain Tax of 30% – Agency Fee of 2% – Legal Fee of 1% & 0.7%
= RM204,000 – (RM204,000 x 30%) – (RM624,000 x 2%) – (RM150,000 x 1% + RM474,000 x 0.7%)
= RM204,000 – RM61,200 – RM12,480 – RM4818
= RM125,502
Selling of property would obtain a net property gain of RM125,502 at its minimum. Depending on which year the property is being sold, the longer it takes to sell the
property, the lower the percentage of property gain tax.
Thus, selling of property is viable for this project.
4.0 DESIGN DEVELOPMENT
4.6 QUANTITY SURVEYING
4.6.1 RETURN OF INVESTMENT
Rent For Short Stay
Rental Yield Per Annum
= [(Rental Per Year – Maintenance Fee of 10%) / (Acquisition Price +
Renovation Cost)] x 100%
According to rental yield per annum of 6.5%,
Rental Per Year
= [(6.5 /100) x (RM420,000 + RM100,000) x 110%]
= [RM33,800 x 110%]
= RM37,180
Occupied Period
= Rental Per Year After Renovation / Rental Per Night
= RM37,180 / RM300
= 124 days
= 1/3 of a year
In order to obtain a rental yield per annum of 6.5% for short stay, the rental per
year ought to be at the value of RM37,180 and the occupied period per year is
124 days, which is equivalent to 1/3 of a year. The number of short or long
holidays per year is only about 7 times. It means that the probability of the house
being rented for short stay would only be about 7 times per year.
7 times x Average of 3-day stay= 7 times x 3 days x RM300
= RM6,300
Thus, renting the house for short stay is not viable for the project.
Rent For Long Term
Rental Yield Per Annum
= [(Rental Per Year – Maintenance Fee of 10%) / (Acquisition Price +
Renovation Cost)] x 100%
According to rental after renovation of RM1500 per month,
Rental Per Year = RM1500 x 12 months
= RM18,000
Rental Yield Per Annum
= [(RM18,000 – RM1800) / (RM420,000 + RM100,000)] x 100%
= 3.1%
According to rental yield per annum of 3.5%,
Rental Per Month
= [(3.5 /100) x (RM420,000 + RM100,000) x 110%] / 12
= [RM18,200 x 110%] / 12
= RM20020 / 12
= RM1668
In order to obtain rental yield per annum of 3.5% for long term stay, the
monthly rental ought to be at the value of RM1668. As compared to the
current rental value of RM1500, the difference is only RM168.
Thus, renting the house for long term is viable for this project.
4.0 DESIGN DEVELOPMENT
4.6 QUANTITY SURVEYING
4.6.1 RETURN OF INVESTMENT
4.0 DESIGN DEVELOPMENT
4.6 QUANTITY SURVEYING
4.6.2 BREAKDOWN OF RENOVATION COST
4.0 DESIGN DEVELOPMENT
4.6 QUANTITY SURVEYING
4.6.2 BREAKDOWN OF RENOVATION COST
Superstructure
19%
Interior
18%
Mechanical and
Electrical
11%
Water Supply
2%
Sanitary System
12%
Landscape
4%
Other
11%
Consultant Fees
23%
The total renovation cost for this project is RM142,651.10, inclusive of furniture and fixture.
Excluding furniture and fixture, the total renovation cost would be RM130,651.10.
Renovation Cost
4.0 DESIGN DEVELOPMENT
4.6 QUANTITY SURVEYING
4.6.2 BREAKDOWN OF RENOVATION COST
5.0 REFERENCES
Arya, Anand S. Guidelines For Earthquake Resistant Non-Engineered Construction. Tokyo, Japan: International Association for Earthquake
Engineering, 1986. Print
Aquabarrel. (n.d.). Overview of ALL Complete Rain Containment Kits. Retrieved October 11, 2015, from
http://www.aquabarrel.com/product_rain_barrel_complete.php
Board of Engineers. (2005, July 19). A Guide to Engineering Practice for M&E Engineers. Retrieved September 14, 2015, from
http://www.bem.org.my/v3/pdf/circulars/Guide%20M&E.pdf
Cawangan Kejuruteraan Mekanikal, JKR. (2011). Mechanical System Design and Installation Guidelines for Architects and Engineers. Retrieved
October 10, 2015, from https://www.jkr.gov.my/cawmekanikal/Dokumentasi/Garis%20Panduan/Garispanduan%20Arkitek%20dan%20Jurutera.pdf
Joven. (n.d.). Instant Water Heater- i-Series. Retrieved October 10, 2015, from
http://www.jovenelectric.com/product_details.php?p_id=81&category_id=2&series_id=5
Rainharvesting Systems. (2005, March 31). Rainharvesting Systems. Retrieved October 10, 2015, from
http://rainharvesting.co.uk/pdfs/Domestic%20Indirect%20system.pdf
Rosly, B. (2014, September 23). Real Property Gains Tax in Malaysia. Retrieved from Ringgit Plus: https://ringgitplus.com/en/blog/Personal-Finance-
News/Real-Property-Gains-Tax-in-Malaysia-What-Who-Where-and-How-Much.html
Unknown. (2014, November 17). Calculating Rental Yield and ROI. Retrieved from Property Guru: http://www.propertyguru.com.my/resources/for-
rent-guide/calculating-rental-yield-and-roi?gclid=Cj0KEQjw-b2wBRDcrKerwe-S5c4BEiQABprW-
L4821cuEcatzTzqLeRIPRS8pknUi02zHPupKvfdGMsaApOb8P8HAQ
Unknown. (2015, September 25). Building Materials Price. Retrieved from CIDB Malaysia:
http://www.cidb.gov.my/cidbv4/index.php?option=com_content&view=article&id=184&Itemid=328&lang=en
Unknown. (2015, October 2). Calculation Method (Legal Fees). Retrieved from eLawyer: http://www.elawyer.com.my/legal_calculator_info.php
Unknown. (2015, September 20). Preliminaries Rates. Retrieved from Quantity Surveyor Online: http://quantitysurveyoronline.com.my/preliminaries-
rates.html
Unit Perancang Ekonomi, Jabatan Perdana Menteri Malaysia. (2005). Garis Panduan Dan Peraturan Bagi Perancangan Bangunan Oleh Jawatankuasa
Kecil Piawaian Dan Kos Bagi Jppn Jabatan Perdana Menteri. Retrieved September 14, 2015, from
http://www.jpph.gov.my/V2/pdf/GarisPanduanBangunan.pdf
6.0 APPENDIX
6.1 ATTENDANCE RECORDS
6.0 APPENDIX
6.1 ATTENDANCE RECORDS
6.0 APPENDIX
6.1 ATTENDANCE RECORDS 6.2 MEETING AGENDA
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 1
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 2
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 2
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 3
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 3
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 4
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 4
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 5
6.0 APPENDIX
6.3 MEETING MINUTES
CLIENT-CONSULTANT MEETING 5

Weitere ähnliche Inhalte

Was ist angesagt?

Project management
Project managementProject management
Project managementAidiel Azhar
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 
Building services report
Building services report Building services report
Building services report Soh Shing
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Pang Khai Shuen
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnosticAdiirfan Che-ani
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdfJoshua Lee
 
Architectural Analysis Report of Concorde Hotel, Kuala Lumpur
Architectural Analysis Report of Concorde Hotel, Kuala LumpurArchitectural Analysis Report of Concorde Hotel, Kuala Lumpur
Architectural Analysis Report of Concorde Hotel, Kuala LumpurCarmen Chan
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
HIGH RISE BUILDINGS-opload.pptx
HIGH RISE BUILDINGS-opload.pptxHIGH RISE BUILDINGS-opload.pptx
HIGH RISE BUILDINGS-opload.pptxPrarthnaRoy
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Pm assignment-2-report
Pm assignment-2-reportPm assignment-2-report
Pm assignment-2-reportChong Yu Xuan
 

Was ist angesagt? (20)

Pm final
Pm finalPm final
Pm final
 
Project management
Project managementProject management
Project management
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Building services report
Building services report Building services report
Building services report
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnostic
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
UBBL 1984 pdf
UBBL 1984 pdfUBBL 1984 pdf
UBBL 1984 pdf
 
Architectural Analysis Report of Concorde Hotel, Kuala Lumpur
Architectural Analysis Report of Concorde Hotel, Kuala LumpurArchitectural Analysis Report of Concorde Hotel, Kuala Lumpur
Architectural Analysis Report of Concorde Hotel, Kuala Lumpur
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Project management
Project managementProject management
Project management
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
HIGH RISE BUILDINGS-opload.pptx
HIGH RISE BUILDINGS-opload.pptxHIGH RISE BUILDINGS-opload.pptx
HIGH RISE BUILDINGS-opload.pptx
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Pm assignment-2-report
Pm assignment-2-reportPm assignment-2-report
Pm assignment-2-report
 

Andere mochten auch

1st Primary School of Sitia-Erasmus+-Project-Sea Breeze
1st Primary School of Sitia-Erasmus+-Project-Sea Breeze1st Primary School of Sitia-Erasmus+-Project-Sea Breeze
1st Primary School of Sitia-Erasmus+-Project-Sea Breezemari kou
 
ICI Final Project Proposal
ICI Final Project ProposalICI Final Project Proposal
ICI Final Project ProposalJunXiang97
 
Intelligent Systems Project: Bike sharing service modeling
Intelligent Systems Project: Bike sharing service modelingIntelligent Systems Project: Bike sharing service modeling
Intelligent Systems Project: Bike sharing service modelingAlessio Villardita
 
Town & gown presentation
Town & gown presentationTown & gown presentation
Town & gown presentationfeds_waterloo
 
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...Angeline KH
 
BookShelf Pitch
BookShelf Pitch BookShelf Pitch
BookShelf Pitch Lauren Byrd
 
e01_grader_h3.xlsx (answer)
e01_grader_h3.xlsx (answer)e01_grader_h3.xlsx (answer)
e01_grader_h3.xlsx (answer)JackCandtona
 
C:\Fakepath\Urban Cape Presentation To Upload To Slide Share
C:\Fakepath\Urban Cape Presentation To Upload To Slide ShareC:\Fakepath\Urban Cape Presentation To Upload To Slide Share
C:\Fakepath\Urban Cape Presentation To Upload To Slide ShareCharlotte Candillier
 
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting Plans
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting PlansBUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting Plans
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting PlansAngeline KH
 
House rental project final
House rental project   finalHouse rental project   final
House rental project finalMerima Turcinhodzic
 
Funky Asia Bar and Restaurant - London
Funky Asia Bar and Restaurant - LondonFunky Asia Bar and Restaurant - London
Funky Asia Bar and Restaurant - LondonSpace Projects Ltd
 
Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Alex Osborne
 
Rental Housing
Rental HousingRental Housing
Rental HousingUsha Batra
 
My parents professions. English project. Primary School.
My parents professions. English project. Primary School.My parents professions. English project. Primary School.
My parents professions. English project. Primary School.claudiapons
 
Project Management
Project ManagementProject Management
Project ManagementTing Yin
 
Room rental system
Room rental systemRoom rental system
Room rental systemNikhil Kumawat
 

Andere mochten auch (20)

Part 2
Part 2Part 2
Part 2
 
Part 1
Part 1Part 1
Part 1
 
1st Primary School of Sitia-Erasmus+-Project-Sea Breeze
1st Primary School of Sitia-Erasmus+-Project-Sea Breeze1st Primary School of Sitia-Erasmus+-Project-Sea Breeze
1st Primary School of Sitia-Erasmus+-Project-Sea Breeze
 
ICI Final Project Proposal
ICI Final Project ProposalICI Final Project Proposal
ICI Final Project Proposal
 
Houses in india
Houses in indiaHouses in india
Houses in india
 
House rental project
House rental projectHouse rental project
House rental project
 
Intelligent Systems Project: Bike sharing service modeling
Intelligent Systems Project: Bike sharing service modelingIntelligent Systems Project: Bike sharing service modeling
Intelligent Systems Project: Bike sharing service modeling
 
Town & gown presentation
Town & gown presentationTown & gown presentation
Town & gown presentation
 
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
 
BookShelf Pitch
BookShelf Pitch BookShelf Pitch
BookShelf Pitch
 
e01_grader_h3.xlsx (answer)
e01_grader_h3.xlsx (answer)e01_grader_h3.xlsx (answer)
e01_grader_h3.xlsx (answer)
 
C:\Fakepath\Urban Cape Presentation To Upload To Slide Share
C:\Fakepath\Urban Cape Presentation To Upload To Slide ShareC:\Fakepath\Urban Cape Presentation To Upload To Slide Share
C:\Fakepath\Urban Cape Presentation To Upload To Slide Share
 
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting Plans
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting PlansBUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting Plans
BUILDING TECHNOLOGY 2 [ARC 3524]- Project 1: Building Plans/Fire-Fighting Plans
 
House rental project final
House rental project   finalHouse rental project   final
House rental project final
 
Funky Asia Bar and Restaurant - London
Funky Asia Bar and Restaurant - LondonFunky Asia Bar and Restaurant - London
Funky Asia Bar and Restaurant - London
 
Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)Project Plan for Construction of School in Africa (Congo)
Project Plan for Construction of School in Africa (Congo)
 
Rental Housing
Rental HousingRental Housing
Rental Housing
 
My parents professions. English project. Primary School.
My parents professions. English project. Primary School.My parents professions. English project. Primary School.
My parents professions. English project. Primary School.
 
Project Management
Project ManagementProject Management
Project Management
 
Room rental system
Room rental systemRoom rental system
Room rental system
 

Ă„hnlich wie ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIAL CONSTRUCTION PROJECT

Project Management Project 1 Report
Project Management Project 1 Report Project Management Project 1 Report
Project Management Project 1 Report Sharon Yu Jung Lim
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 
MAGAZINE.ppt
MAGAZINE.pptMAGAZINE.ppt
MAGAZINE.pptShze Hwa Lee
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1JamesMoy7
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)Pinky Chan
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a projectJing Fan Koh
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1zerospaces_
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Project brief
Project brief Project brief
Project brief Haziq1511
 
Ici individual
Ici individualIci individual
Ici individualKlaus Chiang
 
Project Management Assignment 1
Project Management Assignment 1Project Management Assignment 1
Project Management Assignment 1DavidJPCChai
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 
Project Management (Group)
Project Management (Group)Project Management (Group)
Project Management (Group)FabienFoo
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
ICI Final Project
ICI Final ProjectICI Final Project
ICI Final ProjectLek Yuen
 

Ă„hnlich wie ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIAL CONSTRUCTION PROJECT (20)

Project background
Project backgroundProject background
Project background
 
Project Management Project 1 Report
Project Management Project 1 Report Project Management Project 1 Report
Project Management Project 1 Report
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Magazine (ICI)
Magazine (ICI)Magazine (ICI)
Magazine (ICI)
 
MAGAZINE.ppt
MAGAZINE.pptMAGAZINE.ppt
MAGAZINE.ppt
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)
 
ICIP2G
ICIP2GICIP2G
ICIP2G
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a project
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Project brief
Project brief Project brief
Project brief
 
Ici individual
Ici individualIci individual
Ici individual
 
Project Management Assignment 1
Project Management Assignment 1Project Management Assignment 1
Project Management Assignment 1
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 
Project Management (Group)
Project Management (Group)Project Management (Group)
Project Management (Group)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
ICI Final Project
ICI Final ProjectICI Final Project
ICI Final Project
 

Mehr von Angeline KH

BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction DrawingBUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction DrawingAngeline KH
 
B sc a2 lighting proposal
B sc a2  lighting proposalB sc a2  lighting proposal
B sc a2 lighting proposalAngeline KH
 
A3-Lighting and Acoustic Research
A3-Lighting and Acoustic ResearchA3-Lighting and Acoustic Research
A3-Lighting and Acoustic ResearchAngeline KH
 
Angeline-BSc2- Integration with Design Studio 5
Angeline-BSc2- Integration with Design Studio 5Angeline-BSc2- Integration with Design Studio 5
Angeline-BSc2- Integration with Design Studio 5Angeline KH
 
Project 1-Lighting & Acoustic Performance Evaluation and Design
Project 1-Lighting & Acoustic Performance Evaluation and DesignProject 1-Lighting & Acoustic Performance Evaluation and Design
Project 1-Lighting & Acoustic Performance Evaluation and DesignAngeline KH
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline KH
 
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068ARC2615 REPORT FILE_AngelineKonKeeHooi0302068
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068Angeline KH
 
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068Angeline KH
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...Angeline KH
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...Angeline KH
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...Angeline KH
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...Angeline KH
 
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...Angeline KH
 
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal Angeline KH
 
Asian Architecture [ARC2234]- Project 1: Case Study Paper Presentation
Asian Architecture [ARC2234]- Project 1:  Case Study Paper PresentationAsian Architecture [ARC2234]- Project 1:  Case Study Paper Presentation
Asian Architecture [ARC2234]- Project 1: Case Study Paper PresentationAngeline KH
 
[ARC 1215] Methods of documentation and Measured Drawings
[ARC 1215] Methods of documentation and Measured Drawings[ARC 1215] Methods of documentation and Measured Drawings
[ARC 1215] Methods of documentation and Measured DrawingsAngeline KH
 
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...Angeline KH
 
[ARC2423] Building Services- Project 2 : The inspiration and the intervention
[ARC2423] Building Services- Project 2 : The inspiration and the intervention[ARC2423] Building Services- Project 2 : The inspiration and the intervention
[ARC2423] Building Services- Project 2 : The inspiration and the interventionAngeline KH
 

Mehr von Angeline KH (18)

BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction DrawingBUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
BUILDING TECHNOLOGY 2: Project 2- Working Drawing- Construction Drawing
 
B sc a2 lighting proposal
B sc a2  lighting proposalB sc a2  lighting proposal
B sc a2 lighting proposal
 
A3-Lighting and Acoustic Research
A3-Lighting and Acoustic ResearchA3-Lighting and Acoustic Research
A3-Lighting and Acoustic Research
 
Angeline-BSc2- Integration with Design Studio 5
Angeline-BSc2- Integration with Design Studio 5Angeline-BSc2- Integration with Design Studio 5
Angeline-BSc2- Integration with Design Studio 5
 
Project 1-Lighting & Acoustic Performance Evaluation and Design
Project 1-Lighting & Acoustic Performance Evaluation and DesignProject 1-Lighting & Acoustic Performance Evaluation and Design
Project 1-Lighting & Acoustic Performance Evaluation and Design
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
 
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068ARC2615 REPORT FILE_AngelineKonKeeHooi0302068
ARC2615 REPORT FILE_AngelineKonKeeHooi0302068
 
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068
ARC2615 LOG SHEETS FILE_AngelineKonKeeHooi0302068
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Synopsis: Interpret...
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]- Project Part 2 Anal...
 
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...
THEORIES OF ARCHITECTURE & URBANISM [ARC61303] [ARC2224]-Project 1A: Ar. Lum ...
 
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...
ASIAN ARCHITECTURE [ARC 2234]- Project 1: Case Study Paper: Openings as a Met...
 
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal
Asian Architecture [ARC2234]- Project 1: Topic & Issue Proposal
 
Asian Architecture [ARC2234]- Project 1: Case Study Paper Presentation
Asian Architecture [ARC2234]- Project 1:  Case Study Paper PresentationAsian Architecture [ARC2234]- Project 1:  Case Study Paper Presentation
Asian Architecture [ARC2234]- Project 1: Case Study Paper Presentation
 
[ARC 1215] Methods of documentation and Measured Drawings
[ARC 1215] Methods of documentation and Measured Drawings[ARC 1215] Methods of documentation and Measured Drawings
[ARC 1215] Methods of documentation and Measured Drawings
 
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...
[ARC 1215] Methods of Documentation & Measured Drawing: Lot 40-42, Jalan Laks...
 
[ARC2423] Building Services- Project 2 : The inspiration and the intervention
[ARC2423] Building Services- Project 2 : The inspiration and the intervention[ARC2423] Building Services- Project 2 : The inspiration and the intervention
[ARC2423] Building Services- Project 2 : The inspiration and the intervention
 

KĂĽrzlich hochgeladen

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 

KĂĽrzlich hochgeladen (20)

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 

ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIAL CONSTRUCTION PROJECT

  • 1. architecture . Interior SCHOOL OF ARCHITECTURE, BUILDING & DESIGN ARC 3612 PROJECT MANAGEMENT PROJECT 1: DEFINING AND DOCUMENTING A RESIDENTIAL CONSTRUCTION PROJECT TUTOR: AR. BADRUL HISHAM ANGELINE KON KEE HOOI 0302068 CHAN JASMINE 0308513 HELSA JOSEPHINE 0305813 LIM SHU YIN 0307795 LIM SU YING 0308502 LIM WEI ZE 0305863 NICOLE LIM XU TENG 0307814
  • 2. 1.0 COMPANY PROFILE 1.1 Introduction 1.2 Organisation Chart 2.0 PRELIMINARY STUDY 2.1 Project Scope 2.2 S.W.O.T. Analysis 2.3 Project Viability 3.0 PROJECT MANAGEMENT 3.1 Work Breakdown Structure 3.2 Pert’s Chart/Gantt Chart 3.3 Risk Analysis 3.4 Success Criteria 3.5 Maintenance Proposal 4.0 DESIGN DEVELOPMENT 4.1 Architecture 4.1.1 Plans 4.1.2 Elevations 4.1.3 Elevations (Colour Selection) 4.1.4 Sections 4.1.5 Site Elevations 4.2 Civil & Structural Engineering 4.2.1 Ground Floor Structural Plan 4.2.2 First Floor Structural Plan 4.2.3 Roof Level Structural Plan 4.2.4 Structural Model 4.2.5 Calculation of Column Loads and Feasibility 4.2.6 Reinforcement of Existing Structure 4.2.7 Staircase Details 4.3 Mechanical & Electrical Engineering 4.3.1 Electrical System 4.3.2 Hot & Cold Water Supply System 4.3.3 Sanitary System 4.3.4 Rainwater Harvesting System 4.4 Interior Design 4.4.1 Case Studies 4.4.2 Proposals of Interior Design Styles 4.4.3 Furniture Layout Plans 4.4.4 Finishes Selection 4.4.5 Interior Spaces Overview 4.4.6 Interior Openings 4.4.7 Interior Fittings 4.5 Landscape Design 4.5.1 Concept 4.5.2 Conceptual Visuals 4.5.3 Proposed Landscaping 4.6 Quantity Surveying 4.6.1 Return On Investment 4.6.2 Breakdown of Renovation Cost 5.0 REFERENCES 6.0 APPENDIX 6.1 Attendance Records 6.2 Meeting Agenda 6.3 Meeting Minutes CONTENT
  • 3. 1.1 INTRODUCTION A young and free spirit design studio established in 2012 that specializes in small residential projects. We aim to achieve the home spirit within the team in every single projects. Running wild in exploring wow inspiration from different elements in daily life. VISION To be creative and distinctive We dedicated to transform design idea into tangible reality through our professionalism and great passion with a visionary approach. We strive to create unique yet practical design exclusively just for the clients. 1.2 ORGANISATIONAL CHART 1.0 COMPANY PROFILE SCOPE Architecture. Interior Design We provide full range of services from preliminary feasibility studies and programming, schematic design, design development, contract documents, tendering and construction administration, and finally post-construction services. LOGO From A –Z Our logo carries the meaning of our job scope of covering the project from head to toe. Besides, it is also the last Initials of our founder which is the architect in our company. C&S ENGINEER IR. LIM SHU YIN M&E ENGINEER IR. ANGELINE KON QUANTITY SURVEYOR SR. NICOLE LIM INTERIOR DESIGNER LIM SU YING LANDSCAPE ARCHITECT HELSA JOSEPHINE ARCHITECT AR. NICK LIM WEI ZE PROJECT MANAGER CHAN JASMINE architecture . Interior
  • 4. 2.1 PROJECT SCOPE Client : Ms Fernn Ang Proposal : Redesigning Compact Living Objective : To design a comfortable living space that would provide yield enhancement (rental) or capital gain (sale) Usage type : Residential (long term/short stay) Market Value : RM420,000; Rental – RM1000 per month, yield of 2.85% Returns : 1. Capital gains of at least 20% per annum 2. Rental yield of at least 3.5% for long term Budget : Up to RM100,000 Timeline : Up to 6 months SITE PLAN Reference: Project brief from Ms Fernn AngReference: Project brief from Ms Fernn Ang 2.0 PRELIMINARY STUDY LOCATION PLAN PROJECT DETAILS LOCATION : SS19, Subang Jaya PROPERTY TYPE : Double-Storey Link House (End Lot) LAND SIZE : 16’ x 45’ TOTAL BUILT-UP : 82.80 m2
  • 5. 2.2 S.W.O.T ANALYSIS 2.0 PRELIMINARY STUDY TO RENT COMPARISONS FOR SALE RM1000 - RM1500 RATE RM550,000 – RM600,000 2 Months ESTIMATED CONSTRUCTION DURATION 3 Months Rental yield of 3.5% based on current market value with renovation cost RETURNS Capital gains of 20% based on current market value with renovation cost Regular basis after each rent MAINTENANCE Ends after renovation PROPOSALS 2.3 PROJECT VIABILITY HELPFUL HARMFUL INTERNAL The house exposes to three faces ( front, back and side) which slows more natural light to penetrate through. Location of the house is subtle. EXTERNAL Rich surrounding context with educational buildings(primary school) and retails. Quiet area might leads to safety issue. COMPARISONS BETWEEN TO RENT AND FOR SALE
  • 6. DECISION: FOR SALE 1. WITHIN RESIDENTIAL ZONE Redesigning the house for young family is a suitable choice as it is within the residential area in SS19. There are shops within walking distance from the house which provides convenience to the buyer. Besides the nearby public primary school is an advantage towards our house. 2. HIGHER RETURN Compare to long term rental basis, getting a buyer can earn a higher percentage of profit within a shorter time. As the colleges and universities are not within the area, renting the unit for students might not be a wise choice. Furthermore, poor public transport system is also the disadvantage for students who do not own a car. Hence, finding a buyer who is looking for permanent stay is a better option. 3. LOW MAINTENANCE There will be minimal maintenance or even no maintenance needed after the house is sold off as it will be the responsibility of the buyer who is the new owner of the unit. Whereas if the house is being rented out regular maintenance fee will be an expensive cost. 2.0 PRELIMINARY STUDY PROS & CONS TO RENT FOR SALE PROS 1. Easier to get a tenant. 2. Lower budget for minor renovation. 1. Nearby public schools and retail shops. 2. Low or no maintenance. 3. Higher return. CONS 1. No surrounding college or university. 2. Inconvenience of public transport. 3. High maintenance. 4. Lower return or no return 1. Longer time to get a buyer. 2. Higher budget for major renovation. 2.3 PROJECT VIABILITY
  • 7. Design Stage Architect Civil & Structure Schematic Design Detail Design Renovation Pre-Design Stage Project Brief & Budget Constraints Scope & Schedule Site Study & Local Authority Visit Design Requirement Feasibility Study Final Proposal Schematic Design Construction Detail Design Final Proposal Mechanical & Electrical Schematic Design System Detail Design Interior Design Layout Design Selection of Materials & Fixtures Landscape Design Layout Design Selection of Landscaping Materials Quantity Surveying Preliminary Costing Cost Breakdown Post Design Stage Final Proposal Submission to Local Authority Preparation of Tender Documents Tender 3.1 WORK BREAKDOWN STRUCTURE 3.0 PROJECT MANAGEMENT
  • 8. 3.2 GANTT CHART CLIENT-CONSULTANT MEETING Client: Ms Fernn Ang Proposed House Renovation At Lot PT7632, No. 123, Jalan SS19/6A, Petaling Jaya, Selangor. 3.0 PROJECT MANAGEMENT
  • 9. Stages Type of Risks Likelihood Severity Impact Strategy Contingency PRE-DESIGN Change of program 3 4 Time and effort wasted in preparing the previous proposal Prepare new proposal for the new program Regular meetings and discussions with the client Misunderstanding of project brief 2 4 Inappropriate design proposal Understand the project scope and follow the schedule planned Regular meetings and discussions with the client Reduction of budget 2 4 Team being underpaid To convince the client Reduce the scope of project Design that is beyond client’s expectation Cancellation of project 1 5 Losing the project To convince the client Design that is beyond client’s expectation. DESIGN Internal conflict 3 4 Poor performance Project manager to resolve the conflict. Project manager to build up the teamwork. Miscommunication between client and team 2 4 Not meeting client’s requirement Discussions with client for clarification of project Update the result of discussion consistently Costing error 3 3 Resulting in over budgeting Considering reducing budget in materials (replaced with recycled materials) Detail drawings to be supervised. Untallied drawings 2 3 Inconsistency in project presentation Technical meetings within the team to ensure the consistency before presentation Regular meetings and discussions with the client POST DESIGN Late approval by local authority 2 4 Delay in project Changes for submission requirements To check with the local authority before finalizing design 3.3 RISK ANALYSIS 3.0 PROJECT MANAGEMENT
  • 10. Exceeds customer’s expectation by completing the project within three constraints: deadline, budget and quality. KEY SUCCESS INDICATORS 1. Project efficiency - Meeting schedule - Completing within budget 2. Impact on the customer - Fulfilling customer’s needs - Meeting functional performance 3. Direct and business success - Immediate revenue and profit enhanced - Larger market share generated 4. Preparing for the future - Create new opportunity - Increase capability and competency A success project is with the help of proper management and planning. Meeting the objective of the project shows the understanding in business drivers and brings satisfaction to the client. Project manager is able to keep track with the objective and improve the whole performance through these measurable regulators. 3.4 SUCCESS CRITERIA A successful project is the one being delivered on time, within budget and meet scope specifications. 1. Understanding the project scope - Redesigning compact living within a budget of RM100,000 2. Starting the project with a plan ahead - Gives direction to the team with each responsibilities 3. Good communication - Meeting for discussion in regular basis to update the each progress and ensure everyone is on the same path 4. Widen resources, skills and knowledge - Research and development in skills for each role in order to produce qualitative outcome 5. Well management & control of project - Following the management framework in an ongoing project to ensure success 6. Learn from the past mistakes - Improvise and rework from the error 3.0 PROJECT MANAGEMENT TIME SCOPECOST QUALITY SATISFACTION SCHEDULE BUDGET VOLUME QUALITY
  • 11. 3.5 MAINTENANCE PROPOSAL As the design approach is to redesign the house into a compact living and sell it off instead of renting, a lower maintenance is required compared to rental basis as it will be the buyer’s responsibility to take care of the house. Therefore, much precautions should be taken before handing the house to the client. Management A structured working schedule should be planned in the early stage of the preparation for the project so that each team member will be guided to work according to the flow. Besides, the working environment should be inspiring to boost the member’s productivity during the project. Architect The architect has to make sure that the house is practical and promising up to the client’s requirement. Besides, he will have to ensure that the extension of the building is according to by-law and did not break any rules and regulations set by the local authority. C&S Engineer As the building is extended with a new roof structure, the engineer has to make sure that the building structure can withstand the load from the new added elements. Besides, the engineer has to enhance the existing structure due to lack of maintenance from the previous tenant. M&E Engineer Mostly all the existing system will be renewed for further usage hence the engineer has to make the renewal is done appropriately to avoid accident or leakage. Besides, proposing system that is energy saving could enhance the sale of the house. 3.0 PROJECT MANAGEMENT Interior Designer As the client wanted an easy maintain and minimal look new interior, the designer will have to make sure that the selected design concept is meeting the requirement which is simple yet practical. Besides, as a lot of openings are being proposed to enhance the lighting in the house, privacy of the owner of the house is one of the issues that should be taken care of. Landscape Architect The landscape designer will have to ensure that the proposed landscape is not only nice to view at, but also easy maintained. The outdoor furniture has to be durable and weather resistance so that it can last long. Quantity Surveyor Costing is one of the major factor in the project hence it should be calculated as precise as possible according to the constraints set by the client. Furthermore, the surveyor has to make sure that each of the team member is paid accordingly and sufficiently from the project.
  • 12. 4.0 DESIGN DEVELOPMENT 4.1 ARCHITECTURE 4.1.1 PLANS
  • 13. 4.0 DESIGN DEVELOPMENT 4.1 ARCHITECTURE 4.1.2 ELEVATIONS
  • 14. 4.0 DESIGN DEVELOPMENT 4.1 ARCHITECTURE 4.1.3 ELEVATIONS (COLOR SELECTION)
  • 15. 4.0 DESIGN DEVELOPMENT 4.1 ARCHITECTURE 4.1.4 SECTIONS
  • 16. 4.0 DESIGN DEVELOPMENT 4.1 ARCHITECTURE 4.1.5 SITE ELEVATIONS
  • 17. Existing structural planNew structural plan 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.1 GROUND FLOOR STRUCTURAL PLAN
  • 18. Existing structural planNew structural plan 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.2 FIRST FLOOR STRUCTURAL PLAN
  • 19. Existing structural planNew structural plan 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.3 ROOF LEVEL STRUCTURAL PLAN
  • 20. Structural model (Front perspective) Structural model (Rear perspective) New structural members Existing structural members 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.4 STRUCTURAL MODEL
  • 21. Column B1, 1 Dead load: Roof = 45.55 kN First floor = 96.78 kN Live load: Roof = 6.37 kN First floor = 9.56 kN Column C1, 1 Dead load: Roof = 18.97 kN First floor = 62.82 kN Live load: Roof = 3.21 kN First floor = 6.45 kN Column C, 1 Dead load: Ground floor = 56.11 kN Live load: Ground floor = 8.33 kN Ultimate Load of column C, 1 Total dead load x 1.4 = 392.3 kN Total live load x 1.6 = 54.28 kN Ultimate load = 392.3 + 54.28 = 446.58 kN Assumption Fcu = 30N/mm² (concrete strength) Fy = 460N/mm ² (yield strength of reinforcement) Ac = 120mm x 250mm =30000mm ² (Column section area) Asc = 30000 x 2% = 540mm ² N, capacity of concrete = 0.4 x Fcu x Ac + 0.8 x 540 x 460 = 0.4 x 30 x 30000 + 0.8 x 540 x 460 = 558.72 kN Original column size of 120mm x 225mm is sufficient to sustain the new ultimate load. Transfer of load from the roof to the ground along column B1,1, column C1, 1 and column C,1. 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.5 CALCULATION OF COLUMN LOADS AND FEASIBILITY
  • 22. Small cracks restoration & Reinforcing weak walls Jointing new walls Small cracks found within the existing structure can be restored to its original tensile strength by pressure injection of grout or epoxy into the cracks of the wall. The old structure may require reinforcement for weak walls, in which the same technique is applied through making injection holes on the wall which is to be reinforced. Construction of a new lateral structure to reinforce existing walls. Connection steels are grouted in drilled holes to create the jointing between the existing structure and the new structure. 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.6 REINFORCEMENT OF EXISTING STRUCTURE
  • 23. Cable turnbuckle suspension cable Cable turnbuckle hinge Tension cable Stainless steel U plate welded to tread and wall Steel pin bolted to tread and wall Bolt and washer securing the U plate Open riser tread Threaded washer and bolt support at cable end Suspension bolt Bolt securing and attached Chrome washer Bolt Cable end Cable anchor that attaches to to tension cable steel plate bolted to underside of beam Cable suspended open riser staircase Normal staircase supported by masonry wall below The design of the staircase includes that of a standard concrete stairs with timber finishing and also steps that are cable suspended and mounted to the wall. The structure is constructed above the masonry walls of the storeroom space beneath the staircase. The cable suspended staircase is securely anchored to the First floor beams as well as the wall. U-plates grip and supports the tread as they are welded & bolted to the wall. Tension cables support the other side of the treads which also forms the balustrade for the whole staircase. 4.0 DESIGN DEVELOPMENT 4.2 CIVIL AND STRUCTURAL 4.2.7 STAIRCASE DETAILS
  • 24. 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.1 ELECTRICAL SYSTEM
  • 25. 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.1 ELECTRICAL SYSTEM
  • 26. Note: COP 28, Cables installed behind walls (MS 1979:2007) Where cables are installed buried behind walls, they shall be installed horizontally or vertically. i.e. parallel to the edges of the room. Subject to the dimensions of the columns and beams, they shall be within 150 mm from the top of the walls and 150 mm from the edge of the wall 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.1 ELECTRICAL SYSTEM Electrical Schematic Layout
  • 27. Water Heater Features: - Sleek and Stylish In-Mould Casing Technology - Stepless Electronic Power Control - IP25 Splash Proof Protection - 1 Touch Shower On / Off Safety Switch Technology - Reinforced 3 Layer Flexi-Hose Volume : 1000 liters Dimensions : 240 X 360 X 70 mm Inlet/ Outlet Connection : ø15mm (1/2” BSP) – Single Point System Min. Water Pressure :10 kPa Max. Water Pressure: 380 kPa Min. Water Flow : 2 litres per minute Max. Water Flow : 8 litres per minute Hot and Cold Water Supply System Schematic Layout 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.2 HOT & COLD WATER SUPPLY Total Water Heater: 3 Total Cost : RM 770 x 3 units = RM2310
  • 28. Sanitary System Schematic Layout 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.3 SANITARY SYSTEM
  • 29. 80 Gallon Rainwater Harvesting Tank The Minister of Housing and Local Government on 7 May 1998 has expressed the Government’s interest for houses to be designed for collecting rainwater. In 1999, the Ministry of Housing and Local Government has produced a Guideline on Installing a Rainwater Collection and Utilization System. Rainwater is collected from roof of the and filtered before entering below ground rainwater harvesting tank. The water can then either be pumped either directly to WCs and vehicle jet washes, or to a high level break tank within the house which will then service the non- potable appliances as per normal. Potential Rainwater From Roof Roof Yield = Roof Area x Average Annual Rainfall = (32.3+26.7) X 2400mm = 141,600 litres per year Features: - Made from 100% pre-consumer waste - UV-resistant LLDPE polyethylene - 45% more water than a 55 gallon container - No bisphenol A in our plastic! - Unlimited number of units can be connected in series - Assembly Required - Built-in store/divert diverter valve - Garden hose shut off valve included - Child safe design - The bottom of the diverter box is designed to accept 4 inch landscape pipe. Capacity : 80 Galloons (302.8 litres) Dimensions : 711.2 X 711.2 X 1320.8 mm Inlet/ Outlet Connection : ø101.6mm diameter (4”) Cost for tank : RM 764.6100 Cost for drain pipe : RM 69.81 80-gallon Molded Plastic Rain Water Harvesting Tank Schematic Section Rainwater Harvesting System Schematic Design 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.4 RAINWATER HARVESTING SYSTEM
  • 30. Rainwater Harvesting System Layout 4.0 DESIGN DEVELOPMENT 4.3 MECHANICAL & ELECTRICAL 4.3.4 RAINWATER HARVESTING SYSTEM
  • 31. Location: Taman Tun Dr Ismail, Kuala Lumpur, Federal Territory of Kuala Lumpur, Malaysia Terrace 23 GROUND FLOOR PLAN FIRST FLOOR PLAN Case Study 1 • Linear and narrow layout. • Double-story unit. • Family living of design layout. • Contemporary interior design with simple, raw finishes to outline a clean visual layout, giving an illusion of “enlargement” in space. HIGHLIGHTS: • Green building feature – Roof Garden 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.1 CASE STUDIES
  • 32. GROUND FLOOR PLAN FIRST FLOOR PLAN Case Study 2 Location: Jalan Kaloi, 59100 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur. L 45 – Community Library & Student Housing • Narrow rooms/ limited spaces. • Double-story unit. • Student dormitory interior design layout. • Industrial interior design furniture and fixtures. • Easy cleaning and maintenance. HIGHLIGHTS: 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.1 CASE STUDIES
  • 33. • Living Area • Dining Area • Kitchen • Bathroom • Staircase MOOD BOARD 1 – Ground Floor: • Bedroom 1 • Bedroom 2 • Bathroom • Master Bedroom • Master Bathroom MOOD BOARD 2 – First Floor: Design Style - Industrial • CLEAN LINES • FORM FOLLOW FUNCTION • LOWER SITTING FURNITURE • EMPHASIZE NEGATIVE SPACES • HELP SMALL SPACES APPEAR LARGER • NEUTRAL COLOURS • 20 YEARS IN THE FUTURE – “RETRO” | CONTEMPORARY | ADVANTAGES | MINIMALIST • NATURAL LIGHTS TO HIGHLIGHT SPACES & SHAPES • BARE MINIMUM OF FURNITURE • HIDEEN STORAGE (CABINETS BLEND INTO WALL) • SIMPLE & TIDY • VISUALLY ENLARGE SMALL SPACES • EASY MAINTENANCE 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.2 PROPOSALS OF INTERIOR DESIGN STYLE
  • 34. First Floor Plan 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.3 FURNITURE LAYOUT PLANS Ground Floor Plan
  • 35. Wall Finishes Floor Finishes TIMBER STAIR STEPS - Give contrast and warm-up the cold tone of industrial design. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.4 FINISHES SELECTION Industrial Cold Series
  • 36. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.5 INTERIOR SPACES OVERVIEW Ground Floor Plan
  • 37. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.5 INTERIOR SPACES OVERVIEW First Floor Plan
  • 38. Large openings are selected to allow more natural light penetration and natural wind to flow into the narrow spaces, it celebrates the realm of industrial design, meantime creating lively and brighter ambience in the house. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.6 INTERIOR OPENINGS Ground Floor Plan
  • 39. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.6 INTERIOR OPENINGS First Floor Plan
  • 40. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.7 INTERIOR FITTINGS Ground Floor Plan
  • 41. 4.0 DESIGN DEVELOPMENT 4.4 INTERIOR DESIGN 4.4.7 INTERIOR FITTINGS First Floor Plan
  • 42. • Ornamental grass • Water feature • Grass • Gravels LANDSCAPING 4.0 DESIGN DEVELOPMENT 4.5 LANDSCAPE DESIGN 4.5.1 CONCEPT
  • 43. 4.0 DESIGN DEVELOPMENT 4.5 LANDSCAPE DESIGN 4.5.2 CONCEPTUAL VISUAL 3D RENDERINGS Ground Floor Plan
  • 44. CAR PORCH LANDSCAPE 4.0 DESIGN DEVELOPMENT 4.5 LANDSCAPE DESIGN 4.5.3 PROPOSED LANDSCAPING Minimalist Gate • Simple design • Complementing the design approach of industrial design • Not overpowering the façade • Can be constructed from construction waste Concrete Tiles • Non-slip tiles • Suitable for outdoor purposes • Easy maintenance • Complementing the design approach of industrial design
  • 45. Bamboo Palm • Plant type: House Plant • Height: Ranging from 1.7 m to 3m • Leaf Colour: Green • Growth Rate: Average Water Feature • 1.7 m in height • Gives a strong sense of nature to compliment the small area of the landscape • Provide the sound of nature • Gives a strong aesthetic value • Gives a calm effect through the sense of hearing Fake Grass • Wide range of grass colour shade selection • Comes in role or tiles; for easier customization of size needed • Offer a real aesthetic value with a real grass • Very easy maintenance as watering and trimming is not needed 4.0 DESIGN DEVELOPMENT 4.5 LANDSCAPE DESIGN 4.5.3 PROPOSED LANDSCAPING
  • 46. SELL Property Gains = Selling Price – Acquisition Price Selling Price = (Acquisition Price + Renovation Cost) x 20% Capital Gain = (RM420,000 + RM100,000) x 20% Capital Gain = RM624,000 Property Gains = RM624,000 – RM420,000 = RM204,000 Net Property Gains = Property Gains – Property Gain Tax of 30% – Agency Fee of 2% – Legal Fee of 1% & 0.7% = RM204,000 – (RM204,000 x 30%) – (RM624,000 x 2%) – (RM150,000 x 1% + RM474,000 x 0.7%) = RM204,000 – RM61,200 – RM12,480 – RM4818 = RM125,502 Selling of property would obtain a net property gain of RM125,502 at its minimum. Depending on which year the property is being sold, the longer it takes to sell the property, the lower the percentage of property gain tax. Thus, selling of property is viable for this project. 4.0 DESIGN DEVELOPMENT 4.6 QUANTITY SURVEYING 4.6.1 RETURN OF INVESTMENT
  • 47. Rent For Short Stay Rental Yield Per Annum = [(Rental Per Year – Maintenance Fee of 10%) / (Acquisition Price + Renovation Cost)] x 100% According to rental yield per annum of 6.5%, Rental Per Year = [(6.5 /100) x (RM420,000 + RM100,000) x 110%] = [RM33,800 x 110%] = RM37,180 Occupied Period = Rental Per Year After Renovation / Rental Per Night = RM37,180 / RM300 = 124 days = 1/3 of a year In order to obtain a rental yield per annum of 6.5% for short stay, the rental per year ought to be at the value of RM37,180 and the occupied period per year is 124 days, which is equivalent to 1/3 of a year. The number of short or long holidays per year is only about 7 times. It means that the probability of the house being rented for short stay would only be about 7 times per year. 7 times x Average of 3-day stay= 7 times x 3 days x RM300 = RM6,300 Thus, renting the house for short stay is not viable for the project. Rent For Long Term Rental Yield Per Annum = [(Rental Per Year – Maintenance Fee of 10%) / (Acquisition Price + Renovation Cost)] x 100% According to rental after renovation of RM1500 per month, Rental Per Year = RM1500 x 12 months = RM18,000 Rental Yield Per Annum = [(RM18,000 – RM1800) / (RM420,000 + RM100,000)] x 100% = 3.1% According to rental yield per annum of 3.5%, Rental Per Month = [(3.5 /100) x (RM420,000 + RM100,000) x 110%] / 12 = [RM18,200 x 110%] / 12 = RM20020 / 12 = RM1668 In order to obtain rental yield per annum of 3.5% for long term stay, the monthly rental ought to be at the value of RM1668. As compared to the current rental value of RM1500, the difference is only RM168. Thus, renting the house for long term is viable for this project. 4.0 DESIGN DEVELOPMENT 4.6 QUANTITY SURVEYING 4.6.1 RETURN OF INVESTMENT
  • 48. 4.0 DESIGN DEVELOPMENT 4.6 QUANTITY SURVEYING 4.6.2 BREAKDOWN OF RENOVATION COST
  • 49. 4.0 DESIGN DEVELOPMENT 4.6 QUANTITY SURVEYING 4.6.2 BREAKDOWN OF RENOVATION COST
  • 50. Superstructure 19% Interior 18% Mechanical and Electrical 11% Water Supply 2% Sanitary System 12% Landscape 4% Other 11% Consultant Fees 23% The total renovation cost for this project is RM142,651.10, inclusive of furniture and fixture. Excluding furniture and fixture, the total renovation cost would be RM130,651.10. Renovation Cost 4.0 DESIGN DEVELOPMENT 4.6 QUANTITY SURVEYING 4.6.2 BREAKDOWN OF RENOVATION COST
  • 51. 5.0 REFERENCES Arya, Anand S. Guidelines For Earthquake Resistant Non-Engineered Construction. Tokyo, Japan: International Association for Earthquake Engineering, 1986. Print Aquabarrel. (n.d.). Overview of ALL Complete Rain Containment Kits. Retrieved October 11, 2015, from http://www.aquabarrel.com/product_rain_barrel_complete.php Board of Engineers. (2005, July 19). A Guide to Engineering Practice for M&E Engineers. Retrieved September 14, 2015, from http://www.bem.org.my/v3/pdf/circulars/Guide%20M&E.pdf Cawangan Kejuruteraan Mekanikal, JKR. (2011). Mechanical System Design and Installation Guidelines for Architects and Engineers. Retrieved October 10, 2015, from https://www.jkr.gov.my/cawmekanikal/Dokumentasi/Garis%20Panduan/Garispanduan%20Arkitek%20dan%20Jurutera.pdf Joven. (n.d.). Instant Water Heater- i-Series. Retrieved October 10, 2015, from http://www.jovenelectric.com/product_details.php?p_id=81&category_id=2&series_id=5 Rainharvesting Systems. (2005, March 31). Rainharvesting Systems. Retrieved October 10, 2015, from http://rainharvesting.co.uk/pdfs/Domestic%20Indirect%20system.pdf Rosly, B. (2014, September 23). Real Property Gains Tax in Malaysia. Retrieved from Ringgit Plus: https://ringgitplus.com/en/blog/Personal-Finance- News/Real-Property-Gains-Tax-in-Malaysia-What-Who-Where-and-How-Much.html Unknown. (2014, November 17). Calculating Rental Yield and ROI. Retrieved from Property Guru: http://www.propertyguru.com.my/resources/for- rent-guide/calculating-rental-yield-and-roi?gclid=Cj0KEQjw-b2wBRDcrKerwe-S5c4BEiQABprW- L4821cuEcatzTzqLeRIPRS8pknUi02zHPupKvfdGMsaApOb8P8HAQ Unknown. (2015, September 25). Building Materials Price. Retrieved from CIDB Malaysia: http://www.cidb.gov.my/cidbv4/index.php?option=com_content&view=article&id=184&Itemid=328&lang=en Unknown. (2015, October 2). Calculation Method (Legal Fees). Retrieved from eLawyer: http://www.elawyer.com.my/legal_calculator_info.php Unknown. (2015, September 20). Preliminaries Rates. Retrieved from Quantity Surveyor Online: http://quantitysurveyoronline.com.my/preliminaries- rates.html Unit Perancang Ekonomi, Jabatan Perdana Menteri Malaysia. (2005). Garis Panduan Dan Peraturan Bagi Perancangan Bangunan Oleh Jawatankuasa Kecil Piawaian Dan Kos Bagi Jppn Jabatan Perdana Menteri. Retrieved September 14, 2015, from http://www.jpph.gov.my/V2/pdf/GarisPanduanBangunan.pdf
  • 54. 6.0 APPENDIX 6.1 ATTENDANCE RECORDS 6.2 MEETING AGENDA
  • 55. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 1
  • 56. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 2
  • 57. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 2
  • 58. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 3
  • 59. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 3
  • 60. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 4
  • 61. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 4
  • 62. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 5
  • 63. 6.0 APPENDIX 6.3 MEETING MINUTES CLIENT-CONSULTANT MEETING 5