SlideShare ist ein Scribd-Unternehmen logo
1 von 59
What will you gain from this
presentation?
•
•
•
•
•

Gain insight into the construction process activities for a structural
steel frame of a case study office building. Slides are presented
from a technical point of view.
Get acquainted with tools, equipment and techniques used in this
project.
Develop an understanding of the sequence of activities that are part
of the structural steel construction process of the case study.
Learn about different structural steel elements used in this project.
Observe how the structural steel frame was erected through
photographs and animations.
Introduction
This presentation was developed as a teaching aid with the support of the
American Institute of Steel Construction. Its objective is to introduce the user
to the construction process of the structural steel frame for a common
building type, a four story office building.
The presentation documents the construction of the steel frame for a case
study building. Photographs were taken throughout the construction process
of the structural steel frame including detailing, fabrication and erection. Data
from the project was also compiled including plans, schedules, specifications
and other details. This information was brought together to create the
following presentation.
This slide show is presented from a technical perspective. In this sense, it
contains information on detailing procedures, structural elements, surveying
procedures, erection processes, tools and equipment.
Case Study Project

Description of the structural steel frame:
• Office building use
• 4 Stories
• 80,000 square feet of building
construction area
• Approximately 400 tons of structural
steel or 10 pounds per square foot

• Approximate fabrication and erection
cost 9 dollars per square foot
• Standard bay size of 30ft by 30ft
• 3 by 7 bays
• 964 pieces of structural steel
Structural Steel Construction Phase
Schedule

As seen on the schedule, material procurement occurs early in the process, even
before shop drawings are generated. This is done so that a steel mill has enough
time to produce the required steel. Material procurement includes: quantity
surveying, placing the mill order, delivery of steel from the mill and storage of the
steel in the fabrication shop. Detailing includes the creation of shop drawings of
every piece in the structural frame. Shop drawings are submitted to the contractor
and structural engineer to ensure that they comply with the engineer’s design.
Upon approval of shop drawings and arrival of steel from the mill, steel pieces are
precisely fabricated. Once structural steel members are fabricated they are taken
to the yard, loaded on trucks and transported to the job site for erection.
Detailing Process

To start the detailing process, the fabricator used specialized detailing software
referred to as SDS/2, to create a three dimensional model of the steel frame
based on the design prepared by the structural engineer. This model can be
created from data input by the detailer or from data imported from the designer’s
design software. The model assisted the detailer to visualize connections during
development of shop drawings.
Shop Drawings

During the detailing process, shop drawings are developed by the fabricator’s
detailer to convey precise information about how to fabricate each steel member in
the structure. Each member is assigned a unique piece mark for identification and
tracking. The detailer also prepares a list with a description of the structural steel
members. Shop drawings for beams 22B1, 22B2, 22B4 and 22B5 for the case
study are shown above. For this project, all wide flange material conformed to
ASTM A992 which has a yield strength of 50 ksi.
Fabrication

Structural steel members are fabricated by precisely cutting, shearing,
punching, drilling, fitting and welding in order to produce the
configurations detailed in the shop drawings. Each member is labeled
with a piece mark, length, and job number for identification.
Cambering

Cambering is an effective method used on some buildings to
offset deflections of steel floor beams and girders under the
weight of concrete floors. With cambering, the depth of floor
concrete must be varied to achieve level floors. Cambering is
done during the fabrication process by the fabricator and
introduces slight arching in the beams. Cambering was
specified for most of beams of the case study project (top
plan). C=3/4 means that the beams should be cambered ¾
inch in the center. Cambering can be achieved by applying
temperature to certain points of the beam or by mechanically
applying pressure to the beam using specialized machinery.
Piece Mark

Once fabricated, each finished structural steel member was labeled. In this
case the fabricator labeled each steel member with its piece mark, sequence
number, and the last two digits of the job number. Specific labeling practices
may vary by fabricator. Labeling of the steel pieces is crucial because it will
help identify members on the job site.
Anchor Rod Plan

One of the first drawings prepared by the detailer is the anchor rod plan. This plan
guides the foundation subcontractor in the placement of anchor rods. It contains
horizontal and vertical information for placement of anchor rods, as well as
dimensions and elevations of leveling plates (if used). Three different leveling plates
and anchor rods configurations were used in this project and can be seen in blue,
red, and green color in the plan.
Anchor Rod Details

The drawing above shows three anchor rod details from the case study. Details A
and B show anchor rods embedded in concrete when the concrete was poured.
Detail C shows anchor rods set in concrete using high strength epoxy gel. For this
project, anchor rods were required to extend at least one foot into the concrete.
The space below leveling plates was detailed to be packed solid with 1 ¾ inch of
non-shrink grout.
Leveling Plates

A leveling plate is a steel plate fixed on top of a foundation on which a
structural column can be placed. Leveling plates for the case study project
have a thickness of ¼ inch and conform to ASTM A36. They were placed
after the anchor rods were set.
Leveling Plates & Anchor Rods

These are the three leveling plate
and anchor rod configurations
used in the project: A (upper left),
B (upper right) and C (lower left).
The leveling plates were leveled
and grouted prior to installation of
the columns. This is one method
for setting columns, however
practices may vary with other
erectors.
Anchor Rod Survey

Before the erection process started, anchor rods and leveling plates were
surveyed by the erector’s surveyor to check if they were correctly positioned. If
anchor rods are improperly located, they must be corrected by the foundation
subcontractor before the erection process may start.
Surveying Equipment

The surveyor used a total station (center) and prisms (left and right) to verify the
horizontal and vertical location of each leveling plate and anchor rod.
Survey Results

The survey provided information about any deviations of anchor rods and
leveling plates from the plans. Tolerances for location of anchor rods and
leveling plates are specified in the AISC Code of Standard Practice.
Hoisting Sequences

During detailing, the steel frame was divided into 6 sequences illustrated on the
erection drawings. Sequences represent the order in which a zone or section of the
frame will be erected. They are designed to improve efficiency of the erection
process. Planning the sequences allowed for parallel construction operations to take
place. For example, while the erection crew erected sequence 2, the decking crew
placed metal deck at the previously placed sequence 1. In this way the deck placed
at sequence 1 formed a work platform and reduced the potential fall distance when
the steel contractor erected sequence 3 which was above sequence 1.
STRUCTURAL STEEL ERECTION BY
SEQUENCE

The following is an animation of the structural steel erection process by
sequence. The six sequences will slowly appear along with the working day in
which hoisting of each sequence was completed. The last images to appear
are of the masonry stair and elevator shafts. They were built after the frame
was erected. The steel frame was connected to the vertical shafts to provide
permanent lateral stability of the frame.
Erection Crew

Seven people formed the erection crew used for this project. The crew
consisted of one foreman, two ironworkers hooking steel (upper left), two
ironworkers connecting steel (upper right), a crane operator (lower left), and
an oiler (lower right).
Tools of the Trade

Common tools used by ironworkers include spud wrenches, pins and
correction bars of various sizes. These tools are used to align steel
members. Spud wrenches are also used to tighten bolts.
Crane

The crane used for the project was a 100 ton crawler mounted crane with a 160
foot boom and a 40 foot jib. The boom (upper right) is the main projecting structure
of the crane and the jib (lower right) is the smaller structure attached to the boom.
There are many configurations and sizes of cranes available. Cranes are selected
on the basis of cost, availability, speed, reach and capacity.
Unloading

Upon delivery to the job site,
fabricated steel was unloaded
and placed on wood or steel
blocking. The blocking allowed
for chokers to be attached to
each member for subsequent
hoisting and erection.
Shakeout

Shakeout of structural steel took place after unloading. Shakeout is the
process of sorting steel pieces on site so that they can be efficiently erected.
It involves organizing and spacing the steel members.
Erection Drawings

This is the erection drawing (e-drawing or e-sheet) of the first floor framing for the
project. The numbers one and two inside the red hexagons on each side of the red
line indicate the sequence number for each part of the structure. The piece marks
on the drawing match those on the beams, girders and columns and are used to
locate and orient each member during erection.
Erection Order

The erection crew foreman used the erection drawings to determine the exact
order in which structural steel members were to be erected. The first pieces
hoisted during this project were the columns in sequence 1 (right sheet), then
girders and beams (left and center sheets).
Erection of Sequence 1

The following is an animation of the structural steel erection process of
sequence 1 for the project. Starting on the lower left corner, each structural
steel member will become red in the same order each piece was erected on
site.
Special Column Hoisting Device

This is a special column hoisting device used on the case study project. It
has a release attached to a rope to facilitate its detachment from a
column. After the column is secured with the required bolts, an ironworker
actuates the release directly from the ground to disengage the hoisting
cable.
First Column

This is the first column being hoisted into position. Using ladders,
ironworkers temporarily bolted the column. Prior to erection, the erector must
consider column stability in accordance with safety standards and the AISC
Code of Standard Practice.
Sequence 1 Columns

The first structural steel members hoisted were the columns. This is a
view of sequence 1 after the columns were set. Notice that all columns
have a splice on the top.
Column Splice

The case study project columns were
spliced at elevation 131’-3” (between the
third and fourth floors). A column splice is
used to connect two columns together
vertically. The column splices consisted
of two shop bolted steel plates attached
to the column flanges. The bolts were
loosened before hoisting the upper
column in place to facilitate the
connection.
Column Base Plates

Base plates were welded to the columns during fabrication. Welds were
sized to carry structural loads and to meet or exceed code minimums.
Column Base Plates

These are views of the three
different column base plates
used for the project. Leveling
plates were detailed slightly
larger than the column base
plates to ensure complete
support of the base. This
practice may vary by fabricator.
Chokers

A choker is a rigging assembly used to attach a load to a hoisting device. It
is usually made of wire rope or synthetic fiber. Chokers are used to hoist
beams into position. They are positioned at the center of gravity of the
beam so that the beam remains level when hoisted.
Multiple Lift Rigging

Multiple lift rigging is a process used to hoist several pieces of steel
simultaneously. This is accomplished by utilizing a rigging assembly that
facilitates the attachment of up to five independent loads to the hoist
rigging of a crane. In this project up to four beams were hoisted at a time.
Multiple lift rigging speeds the lifting process by reducing the total number
of lifts required for the frame.
Preliminary Bolting

The connector uses pins to align the holes between structural steel members
being connected. Then he places several bolts and temporarily tightens them
with his spud wrench. At least two bolts per connection are used to
temporarily fasten each connection.
Beams

Main girders are hoisted after the columns. Beams are then hoisted
and connected to the girders. On the left is a photograph of the first
bay to be hoisted. On the right is a photograph of the first three bays
in place.
Double Connections

During the erection process special attention should be given to double
connections. A double connection is an attachment method where the
connection point is intended for two pieces of steel which share common
bolts on either side of a central piece. When two structural members on
opposite sides of a column or beam web are connected sharing common
connection holes, at least one bolt with its wrench-tight nut should remain
connected to the first member, unless a shop-attached or field-attached
seat or equivalent connection device is supplied with the member to
secure the first member and prevent the column from being displaced.
Sequence 1

Sequence 2

This is a view of the completed hoisting activity for sequences 1 (left)
and 2 (right). It took approximately 5 days to hoist the 166 pieces of
steel that are part of the two sequences.
Metal Decking

Metal deck was placed and attached with a series of welds. Controlled deck zones
were used during installation. A controlled deck zone is an area in which initial
installation and placement of metal decking may take place without the use of
guardrail systems, personal fall arrest systems, fall restraint systems, or safety net
systems and where access to the zone is controlled.
Perimeter Safety Cables

On multi-story structures, perimeter safety
cables are installed at the interior and exterior
perimeters of floors and openings as soon as
the metal decking has been installed.
Shear Studs

These are shear studs. The white rings are ceramic ferrules. The ceramic
ferrule constrains the molten metal into which the stud is thrust automatically
and a high quality fusion weld is accomplished where the weld is stronger
than the stud itself.
Welding Shear Studs

Snow was removed from the locations where shear
studs were to be placed (upper left). Using a studwelding gun (an automatic welding device) the shear
studs were then welded to the structural members below
the metal decking. Shear studs are used to ensure a
composite action between the concrete slab and
structural steel beams (upper right). Whether shear
studs are used is a function of the structural engineer’s
design.
Shear Studs

This is a view of the welded studs. Shear studs were tested to ensure that they
were correctly welded to the structural steel members in compliance with the bend
test of the AWS D 1.1 Structural Welding Code.
Sequence 3

Sequence 4

This is a view of the completed hoisting activity for sequences 3 and 4.
Hoisting these two sequences took approximately 9 days in contrast
with the five days it took to hoist sequences 1 and 2, because
sequences 3 and 4 consisted of two floors (365 pieces of steel) and
sequences 1 and 2 consisted of one floor (166 pieces of steel).
Temporary Bracing

Temporary bracing was placed before
plumbing up the structural frame.
Temporary bracing is used to provide
temporary lateral stability to the structure
and to plumb up the frame. The temporary
bracing was removed by the erector once
the structural steel frame was secured to
the vertical masonry elevator and stair
shafts, which were installed after
completion of the steel frame.
Plumbing Up

Plumbing up refers to the vertical alignment of the structure in
accordance with the AISC Code of Standard Practice. A theodolite
was used to verify the alignment of columns in the perimeter of the
building. The foreman directed ironworkers on the structure to shift
the frame using the temporary bracing.
Plumbing Up

Turnbuckles (lower left) are a common part of
the bracing system. A turnbuckle is a device
that usually consists of a link with screw
threads at both ends that is turned to bring
the ends closer together. Using several
turnbuckles connected to the temporary
bracing, the steel frame was shifted until it
was vertically aligned.
Final Bolt-up

After a section of the structural frame was assembled and vertically
aligned, ironworkers permanently fastened the structural steel members
with additional bolts and welds. Tension controlled bolts (F1852) were
used. Final bolt-up was performed using a torque wrench. The wrench
stops automatically when the bolt shears at a tension control groove
indicating that the required tension is reached.
Sequence 5

Sequence 6

This is a view of the completed hoisting activity for sequences 5 (left) and
6 (right). It took approximately 9 days to hoist both sequences, similar to
sequences 3 and 4.
Lateral Stability

One of the last activities of the steel erection process was to secure the structural
steel frame to the elevator and stair masonry shafts. On the left is a plan view of a
stair shaft as seen in the 1st floor framing plan. The middle image shows a detail
drawing of section 2 on sheet E11. This detail illustrates how perimeter beams
were attached to the masonry. Angles were connected to the masonry shaft using
¾” diameter bolts every 8”, which were set by the mason. The angles were then
welded to the steel beams.
Lateral Stability

The elevator shafts provide lateral stability to the structural steel frame
of the building.
Slabs

Floor slabs were poured (upper right)
after the structural steel frame was
secured to the vertical masonry shafts.
After reinforcing steel (upper left) and
concrete were placed, the slab was
leveled and finished (lower left).
Slabs

This is a view of the finished slab. At this point the structural
frame of the building is complete.
Inspection

The structural steel frame was inspected upon completion by the local
jurisdiction and work could proceed accordingly. Depending on frame
complexity, additional periodic inspection and testing may also be required
by the local jurisdiction. The design engineer also conducts contract
administration and field observation activities which help ensure quality.
Fireproofing

Structural steel has to be protected from fire. Steel will not burn, but it
may become soft and weak when exposed to intense heat. Building
codes regulate the need for fire protection and its required locations.
There are several methods for fire protection. The method utilized for
this project was spray-on fire protection. Spray-on material may be
portland cement or a gypsum-based product and can be applied directly
to structural steel members.
Finished Building

This is how the building will look after it is completed. The structural steel frame is
one of the most important parts of the building. Building with steel has several
advantages over other building materials. Steel can be erected year round. It is
light yet strong when compared with other structural frame materials. Steel can
also be adapted to almost any imaginable shape. One of the biggest advantages
is that it can be erected very fast.

Weitere ähnliche Inhalte

Was ist angesagt?

4830 vulcraft steel deck
4830 vulcraft steel deck4830 vulcraft steel deck
4830 vulcraft steel deckcacostae111
 
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedComposite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedAIT Solutions
 
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...AIT Solutions
 
50727481 checklist-for-site-works
50727481 checklist-for-site-works50727481 checklist-for-site-works
50727481 checklist-for-site-worksimaduddin91
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxmrujjavalsinghvarana
 
Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...suchit03
 
Design of Steel Structures.pptx
Design of Steel Structures.pptxDesign of Steel Structures.pptx
Design of Steel Structures.pptxShuchiGupta39
 
Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )Hossam Shafiq I
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildingshlksd
 
Reinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing ModuleReinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing ModuleBahzad5
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel StructureGaurang Kakadiya
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''Nabeel Rajpoot
 
Column base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayColumn base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayAlberto Rosado
 

Was ist angesagt? (20)

4830 vulcraft steel deck
4830 vulcraft steel deck4830 vulcraft steel deck
4830 vulcraft steel deck
 
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. NaveedComposite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
Composite Concrete-Steel Construction in Tall Buildings by Dr. Naveed
 
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...
Integrated Performance Based Design of Tall Buildings for Wind and Earthquake...
 
50727481 checklist-for-site-works
50727481 checklist-for-site-works50727481 checklist-for-site-works
50727481 checklist-for-site-works
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
 
Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...
 
Steel structures
Steel structuresSteel structures
Steel structures
 
What is rebar
What is rebarWhat is rebar
What is rebar
 
composite structure.pptx
composite structure.pptxcomposite structure.pptx
composite structure.pptx
 
9 design-of-flat-slabs
9 design-of-flat-slabs9 design-of-flat-slabs
9 design-of-flat-slabs
 
Peb ss
Peb ssPeb ss
Peb ss
 
Design of Steel Structures.pptx
Design of Steel Structures.pptxDesign of Steel Structures.pptx
Design of Steel Structures.pptx
 
Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )Cold-Formed-Steel Design And Construction ( Steel Structure )
Cold-Formed-Steel Design And Construction ( Steel Structure )
 
115659118 pre-engineered-buildings
115659118 pre-engineered-buildings115659118 pre-engineered-buildings
115659118 pre-engineered-buildings
 
Reinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing ModuleReinforced Concrete Structure and Detailing Module
Reinforced Concrete Structure and Detailing Module
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
Column base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayColumn base plates_prof_thomas_murray
Column base plates_prof_thomas_murray
 
Shear wall
Shear wallShear wall
Shear wall
 
Formwork
FormworkFormwork
Formwork
 

Ähnlich wie Technical

ConstructionManagement.ppt
ConstructionManagement.pptConstructionManagement.ppt
ConstructionManagement.pptHendyWijaya17
 
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptyokeceg852
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for studentssomeoneslife167
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Steel framed building Shrilkant
Steel framed building  ShrilkantSteel framed building  Shrilkant
Steel framed building ShrilkantShriKant49
 
111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451AnhKSLT
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxanik7nziza
 
Curved steel-a-reference-for-architects-and-engineers
Curved steel-a-reference-for-architects-and-engineersCurved steel-a-reference-for-architects-and-engineers
Curved steel-a-reference-for-architects-and-engineerstecnidibujos
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
aisc-bolting-and-welding
aisc-bolting-and-weldingaisc-bolting-and-welding
aisc-bolting-and-weldingtecnidibujos
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET Journal
 
AISCBoltingWelding1.ppt
AISCBoltingWelding1.pptAISCBoltingWelding1.ppt
AISCBoltingWelding1.pptZarnaModi1
 
Steel building construction
Steel building constructionSteel building construction
Steel building constructionprices89b
 
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...IRJET Journal
 

Ähnlich wie Technical (20)

ConstructionManagement.ppt
ConstructionManagement.pptConstructionManagement.ppt
ConstructionManagement.ppt
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
 
STRUCTURAL STEEL DETAILING SERVICES.pptx
STRUCTURAL STEEL DETAILING SERVICES.pptxSTRUCTURAL STEEL DETAILING SERVICES.pptx
STRUCTURAL STEEL DETAILING SERVICES.pptx
 
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.ppt
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for students
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Steel framed building Shrilkant
Steel framed building  ShrilkantSteel framed building  Shrilkant
Steel framed building Shrilkant
 
ALL ABOUT ERECTION
ALL ABOUT ERECTIONALL ABOUT ERECTION
ALL ABOUT ERECTION
 
111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451111562940 aisc-bolting-and-welding-190606215451
111562940 aisc-bolting-and-welding-190606215451
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptx
 
Curved steel-a-reference-for-architects-and-engineers
Curved steel-a-reference-for-architects-and-engineersCurved steel-a-reference-for-architects-and-engineers
Curved steel-a-reference-for-architects-and-engineers
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
aisc-bolting-and-welding
aisc-bolting-and-weldingaisc-bolting-and-welding
aisc-bolting-and-welding
 
Design of casting.pptx
Design of casting.pptxDesign of casting.pptx
Design of casting.pptx
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
 
AISCBoltingWelding1.ppt
AISCBoltingWelding1.pptAISCBoltingWelding1.ppt
AISCBoltingWelding1.ppt
 
7344574 bolting-welding-1
7344574 bolting-welding-17344574 bolting-welding-1
7344574 bolting-welding-1
 
Steel building construction
Steel building constructionSteel building construction
Steel building construction
 
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...
IRJET- Study on Effective Seismic Retrofitting for High Rise Steel Frame with...
 
Company profile
Company profileCompany profile
Company profile
 

Kürzlich hochgeladen

4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 

Kürzlich hochgeladen (20)

4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 

Technical

  • 1.
  • 2. What will you gain from this presentation? • • • • • Gain insight into the construction process activities for a structural steel frame of a case study office building. Slides are presented from a technical point of view. Get acquainted with tools, equipment and techniques used in this project. Develop an understanding of the sequence of activities that are part of the structural steel construction process of the case study. Learn about different structural steel elements used in this project. Observe how the structural steel frame was erected through photographs and animations.
  • 3. Introduction This presentation was developed as a teaching aid with the support of the American Institute of Steel Construction. Its objective is to introduce the user to the construction process of the structural steel frame for a common building type, a four story office building. The presentation documents the construction of the steel frame for a case study building. Photographs were taken throughout the construction process of the structural steel frame including detailing, fabrication and erection. Data from the project was also compiled including plans, schedules, specifications and other details. This information was brought together to create the following presentation. This slide show is presented from a technical perspective. In this sense, it contains information on detailing procedures, structural elements, surveying procedures, erection processes, tools and equipment.
  • 4. Case Study Project Description of the structural steel frame: • Office building use • 4 Stories • 80,000 square feet of building construction area • Approximately 400 tons of structural steel or 10 pounds per square foot • Approximate fabrication and erection cost 9 dollars per square foot • Standard bay size of 30ft by 30ft • 3 by 7 bays • 964 pieces of structural steel
  • 5. Structural Steel Construction Phase Schedule As seen on the schedule, material procurement occurs early in the process, even before shop drawings are generated. This is done so that a steel mill has enough time to produce the required steel. Material procurement includes: quantity surveying, placing the mill order, delivery of steel from the mill and storage of the steel in the fabrication shop. Detailing includes the creation of shop drawings of every piece in the structural frame. Shop drawings are submitted to the contractor and structural engineer to ensure that they comply with the engineer’s design. Upon approval of shop drawings and arrival of steel from the mill, steel pieces are precisely fabricated. Once structural steel members are fabricated they are taken to the yard, loaded on trucks and transported to the job site for erection.
  • 6. Detailing Process To start the detailing process, the fabricator used specialized detailing software referred to as SDS/2, to create a three dimensional model of the steel frame based on the design prepared by the structural engineer. This model can be created from data input by the detailer or from data imported from the designer’s design software. The model assisted the detailer to visualize connections during development of shop drawings.
  • 7. Shop Drawings During the detailing process, shop drawings are developed by the fabricator’s detailer to convey precise information about how to fabricate each steel member in the structure. Each member is assigned a unique piece mark for identification and tracking. The detailer also prepares a list with a description of the structural steel members. Shop drawings for beams 22B1, 22B2, 22B4 and 22B5 for the case study are shown above. For this project, all wide flange material conformed to ASTM A992 which has a yield strength of 50 ksi.
  • 8. Fabrication Structural steel members are fabricated by precisely cutting, shearing, punching, drilling, fitting and welding in order to produce the configurations detailed in the shop drawings. Each member is labeled with a piece mark, length, and job number for identification.
  • 9. Cambering Cambering is an effective method used on some buildings to offset deflections of steel floor beams and girders under the weight of concrete floors. With cambering, the depth of floor concrete must be varied to achieve level floors. Cambering is done during the fabrication process by the fabricator and introduces slight arching in the beams. Cambering was specified for most of beams of the case study project (top plan). C=3/4 means that the beams should be cambered ¾ inch in the center. Cambering can be achieved by applying temperature to certain points of the beam or by mechanically applying pressure to the beam using specialized machinery.
  • 10. Piece Mark Once fabricated, each finished structural steel member was labeled. In this case the fabricator labeled each steel member with its piece mark, sequence number, and the last two digits of the job number. Specific labeling practices may vary by fabricator. Labeling of the steel pieces is crucial because it will help identify members on the job site.
  • 11. Anchor Rod Plan One of the first drawings prepared by the detailer is the anchor rod plan. This plan guides the foundation subcontractor in the placement of anchor rods. It contains horizontal and vertical information for placement of anchor rods, as well as dimensions and elevations of leveling plates (if used). Three different leveling plates and anchor rods configurations were used in this project and can be seen in blue, red, and green color in the plan.
  • 12. Anchor Rod Details The drawing above shows three anchor rod details from the case study. Details A and B show anchor rods embedded in concrete when the concrete was poured. Detail C shows anchor rods set in concrete using high strength epoxy gel. For this project, anchor rods were required to extend at least one foot into the concrete. The space below leveling plates was detailed to be packed solid with 1 ¾ inch of non-shrink grout.
  • 13. Leveling Plates A leveling plate is a steel plate fixed on top of a foundation on which a structural column can be placed. Leveling plates for the case study project have a thickness of ¼ inch and conform to ASTM A36. They were placed after the anchor rods were set.
  • 14. Leveling Plates & Anchor Rods These are the three leveling plate and anchor rod configurations used in the project: A (upper left), B (upper right) and C (lower left). The leveling plates were leveled and grouted prior to installation of the columns. This is one method for setting columns, however practices may vary with other erectors.
  • 15. Anchor Rod Survey Before the erection process started, anchor rods and leveling plates were surveyed by the erector’s surveyor to check if they were correctly positioned. If anchor rods are improperly located, they must be corrected by the foundation subcontractor before the erection process may start.
  • 16. Surveying Equipment The surveyor used a total station (center) and prisms (left and right) to verify the horizontal and vertical location of each leveling plate and anchor rod.
  • 17. Survey Results The survey provided information about any deviations of anchor rods and leveling plates from the plans. Tolerances for location of anchor rods and leveling plates are specified in the AISC Code of Standard Practice.
  • 18. Hoisting Sequences During detailing, the steel frame was divided into 6 sequences illustrated on the erection drawings. Sequences represent the order in which a zone or section of the frame will be erected. They are designed to improve efficiency of the erection process. Planning the sequences allowed for parallel construction operations to take place. For example, while the erection crew erected sequence 2, the decking crew placed metal deck at the previously placed sequence 1. In this way the deck placed at sequence 1 formed a work platform and reduced the potential fall distance when the steel contractor erected sequence 3 which was above sequence 1.
  • 19. STRUCTURAL STEEL ERECTION BY SEQUENCE The following is an animation of the structural steel erection process by sequence. The six sequences will slowly appear along with the working day in which hoisting of each sequence was completed. The last images to appear are of the masonry stair and elevator shafts. They were built after the frame was erected. The steel frame was connected to the vertical shafts to provide permanent lateral stability of the frame.
  • 20.
  • 21. Erection Crew Seven people formed the erection crew used for this project. The crew consisted of one foreman, two ironworkers hooking steel (upper left), two ironworkers connecting steel (upper right), a crane operator (lower left), and an oiler (lower right).
  • 22. Tools of the Trade Common tools used by ironworkers include spud wrenches, pins and correction bars of various sizes. These tools are used to align steel members. Spud wrenches are also used to tighten bolts.
  • 23. Crane The crane used for the project was a 100 ton crawler mounted crane with a 160 foot boom and a 40 foot jib. The boom (upper right) is the main projecting structure of the crane and the jib (lower right) is the smaller structure attached to the boom. There are many configurations and sizes of cranes available. Cranes are selected on the basis of cost, availability, speed, reach and capacity.
  • 24. Unloading Upon delivery to the job site, fabricated steel was unloaded and placed on wood or steel blocking. The blocking allowed for chokers to be attached to each member for subsequent hoisting and erection.
  • 25. Shakeout Shakeout of structural steel took place after unloading. Shakeout is the process of sorting steel pieces on site so that they can be efficiently erected. It involves organizing and spacing the steel members.
  • 26. Erection Drawings This is the erection drawing (e-drawing or e-sheet) of the first floor framing for the project. The numbers one and two inside the red hexagons on each side of the red line indicate the sequence number for each part of the structure. The piece marks on the drawing match those on the beams, girders and columns and are used to locate and orient each member during erection.
  • 27. Erection Order The erection crew foreman used the erection drawings to determine the exact order in which structural steel members were to be erected. The first pieces hoisted during this project were the columns in sequence 1 (right sheet), then girders and beams (left and center sheets).
  • 28. Erection of Sequence 1 The following is an animation of the structural steel erection process of sequence 1 for the project. Starting on the lower left corner, each structural steel member will become red in the same order each piece was erected on site.
  • 29.
  • 30. Special Column Hoisting Device This is a special column hoisting device used on the case study project. It has a release attached to a rope to facilitate its detachment from a column. After the column is secured with the required bolts, an ironworker actuates the release directly from the ground to disengage the hoisting cable.
  • 31. First Column This is the first column being hoisted into position. Using ladders, ironworkers temporarily bolted the column. Prior to erection, the erector must consider column stability in accordance with safety standards and the AISC Code of Standard Practice.
  • 32. Sequence 1 Columns The first structural steel members hoisted were the columns. This is a view of sequence 1 after the columns were set. Notice that all columns have a splice on the top.
  • 33. Column Splice The case study project columns were spliced at elevation 131’-3” (between the third and fourth floors). A column splice is used to connect two columns together vertically. The column splices consisted of two shop bolted steel plates attached to the column flanges. The bolts were loosened before hoisting the upper column in place to facilitate the connection.
  • 34. Column Base Plates Base plates were welded to the columns during fabrication. Welds were sized to carry structural loads and to meet or exceed code minimums.
  • 35. Column Base Plates These are views of the three different column base plates used for the project. Leveling plates were detailed slightly larger than the column base plates to ensure complete support of the base. This practice may vary by fabricator.
  • 36. Chokers A choker is a rigging assembly used to attach a load to a hoisting device. It is usually made of wire rope or synthetic fiber. Chokers are used to hoist beams into position. They are positioned at the center of gravity of the beam so that the beam remains level when hoisted.
  • 37. Multiple Lift Rigging Multiple lift rigging is a process used to hoist several pieces of steel simultaneously. This is accomplished by utilizing a rigging assembly that facilitates the attachment of up to five independent loads to the hoist rigging of a crane. In this project up to four beams were hoisted at a time. Multiple lift rigging speeds the lifting process by reducing the total number of lifts required for the frame.
  • 38. Preliminary Bolting The connector uses pins to align the holes between structural steel members being connected. Then he places several bolts and temporarily tightens them with his spud wrench. At least two bolts per connection are used to temporarily fasten each connection.
  • 39. Beams Main girders are hoisted after the columns. Beams are then hoisted and connected to the girders. On the left is a photograph of the first bay to be hoisted. On the right is a photograph of the first three bays in place.
  • 40. Double Connections During the erection process special attention should be given to double connections. A double connection is an attachment method where the connection point is intended for two pieces of steel which share common bolts on either side of a central piece. When two structural members on opposite sides of a column or beam web are connected sharing common connection holes, at least one bolt with its wrench-tight nut should remain connected to the first member, unless a shop-attached or field-attached seat or equivalent connection device is supplied with the member to secure the first member and prevent the column from being displaced.
  • 41. Sequence 1 Sequence 2 This is a view of the completed hoisting activity for sequences 1 (left) and 2 (right). It took approximately 5 days to hoist the 166 pieces of steel that are part of the two sequences.
  • 42. Metal Decking Metal deck was placed and attached with a series of welds. Controlled deck zones were used during installation. A controlled deck zone is an area in which initial installation and placement of metal decking may take place without the use of guardrail systems, personal fall arrest systems, fall restraint systems, or safety net systems and where access to the zone is controlled.
  • 43. Perimeter Safety Cables On multi-story structures, perimeter safety cables are installed at the interior and exterior perimeters of floors and openings as soon as the metal decking has been installed.
  • 44. Shear Studs These are shear studs. The white rings are ceramic ferrules. The ceramic ferrule constrains the molten metal into which the stud is thrust automatically and a high quality fusion weld is accomplished where the weld is stronger than the stud itself.
  • 45. Welding Shear Studs Snow was removed from the locations where shear studs were to be placed (upper left). Using a studwelding gun (an automatic welding device) the shear studs were then welded to the structural members below the metal decking. Shear studs are used to ensure a composite action between the concrete slab and structural steel beams (upper right). Whether shear studs are used is a function of the structural engineer’s design.
  • 46. Shear Studs This is a view of the welded studs. Shear studs were tested to ensure that they were correctly welded to the structural steel members in compliance with the bend test of the AWS D 1.1 Structural Welding Code.
  • 47. Sequence 3 Sequence 4 This is a view of the completed hoisting activity for sequences 3 and 4. Hoisting these two sequences took approximately 9 days in contrast with the five days it took to hoist sequences 1 and 2, because sequences 3 and 4 consisted of two floors (365 pieces of steel) and sequences 1 and 2 consisted of one floor (166 pieces of steel).
  • 48. Temporary Bracing Temporary bracing was placed before plumbing up the structural frame. Temporary bracing is used to provide temporary lateral stability to the structure and to plumb up the frame. The temporary bracing was removed by the erector once the structural steel frame was secured to the vertical masonry elevator and stair shafts, which were installed after completion of the steel frame.
  • 49. Plumbing Up Plumbing up refers to the vertical alignment of the structure in accordance with the AISC Code of Standard Practice. A theodolite was used to verify the alignment of columns in the perimeter of the building. The foreman directed ironworkers on the structure to shift the frame using the temporary bracing.
  • 50. Plumbing Up Turnbuckles (lower left) are a common part of the bracing system. A turnbuckle is a device that usually consists of a link with screw threads at both ends that is turned to bring the ends closer together. Using several turnbuckles connected to the temporary bracing, the steel frame was shifted until it was vertically aligned.
  • 51. Final Bolt-up After a section of the structural frame was assembled and vertically aligned, ironworkers permanently fastened the structural steel members with additional bolts and welds. Tension controlled bolts (F1852) were used. Final bolt-up was performed using a torque wrench. The wrench stops automatically when the bolt shears at a tension control groove indicating that the required tension is reached.
  • 52. Sequence 5 Sequence 6 This is a view of the completed hoisting activity for sequences 5 (left) and 6 (right). It took approximately 9 days to hoist both sequences, similar to sequences 3 and 4.
  • 53. Lateral Stability One of the last activities of the steel erection process was to secure the structural steel frame to the elevator and stair masonry shafts. On the left is a plan view of a stair shaft as seen in the 1st floor framing plan. The middle image shows a detail drawing of section 2 on sheet E11. This detail illustrates how perimeter beams were attached to the masonry. Angles were connected to the masonry shaft using ¾” diameter bolts every 8”, which were set by the mason. The angles were then welded to the steel beams.
  • 54. Lateral Stability The elevator shafts provide lateral stability to the structural steel frame of the building.
  • 55. Slabs Floor slabs were poured (upper right) after the structural steel frame was secured to the vertical masonry shafts. After reinforcing steel (upper left) and concrete were placed, the slab was leveled and finished (lower left).
  • 56. Slabs This is a view of the finished slab. At this point the structural frame of the building is complete.
  • 57. Inspection The structural steel frame was inspected upon completion by the local jurisdiction and work could proceed accordingly. Depending on frame complexity, additional periodic inspection and testing may also be required by the local jurisdiction. The design engineer also conducts contract administration and field observation activities which help ensure quality.
  • 58. Fireproofing Structural steel has to be protected from fire. Steel will not burn, but it may become soft and weak when exposed to intense heat. Building codes regulate the need for fire protection and its required locations. There are several methods for fire protection. The method utilized for this project was spray-on fire protection. Spray-on material may be portland cement or a gypsum-based product and can be applied directly to structural steel members.
  • 59. Finished Building This is how the building will look after it is completed. The structural steel frame is one of the most important parts of the building. Building with steel has several advantages over other building materials. Steel can be erected year round. It is light yet strong when compared with other structural frame materials. Steel can also be adapted to almost any imaginable shape. One of the biggest advantages is that it can be erected very fast.