Jim Waite
                                                                              OM 380
                                                                              10/14/2004

                                   x bar and R Charts

       Statistical process control is an effective method for improving a firm’s quality

and productivity. There has been an increased interest in their effective implementation in

American industry, brought about by increased competition and improvements in quality

in foreign-made products. Many tools may be utilized to gain the desired information on

a firm’s quality and productivity. Some of the more commonly used tools are control

charts, which are useful in determining any changes in process performance. These

include a variety of charts such as p charts, c charts and x bar and R charts. In this paper,

I will be focusing on the latter two mentioned.

X bar Charts defined

       An x bar chart is used to monitor the average value, or mean, of a process over

time. For each subgroup, the x bar value is plotted. The upper and lower control limits

define the range of inherent variation in the subgroup means when the process is in

control.

R Chart defined

       An R Chart is a control chart that is used to monitor process variation when the

variable of interest is a quantitative measure. Now, what does all this mean? These

charts will allow us to see any deviations from desired limits within the quality process

and, in effect, allow the firm to make necessary adjustments to improve quality.

The Chart Construction Process

       In order to construct x bar and R charts, we must first find our upper- and lower-

control limits. This is done by utilizing the following formulae:
UCL = µ+ 3σ
                 √n

        LCL = µ - 3σ
                  √n


        While theoretically possible, since we do not know either the population process

mean or standard deviation, these formulas cannot be used directly and both must be

estimated from the process itself. First, the R chart is constructed. If the R chart validates

that the process variation is in statistical control, the x bar chart is constructed.

Steps in Constructing an R chart


1. Select k successive subgroups where k is at least 20, in which there are n
   measurements in each subgroup. Typically n is between 1 and 9. 3, 4, or 5
   measurements per subgroup is quite common.
2. Find the range of each subgroup R(i) where R(i)=biggest value - smallest value for
   each subgroup i.
3. Find the centerline for the R chart, denoted by




4. Find the UCL and LCL with the following formulas: UCL= D(4)RBAR and
   LCL=D(3)RBAR with D(3) and D(4) can be found in the following table:

        Table of D(3) and D(4)
        n D(3) D(4)        n D(3) D(4)
        2 0      3.267    6 0    2.004
        3 0      2.574    7 .076 1.924
        4 0      2.282    8 .136 1.864
        5 0      2.114    9 .184 1.816

5. Plot the subgroup data and determine if the process is in statistical control. If not,
   determine the reason for the assignable cause, eliminate it, and the subgroup(s) and
   repeat the previous 3 steps. Do NOT eliminate subgroups with points out of range for
   which assignable causes cannot be found.
6. Once the R chart is in a state of statistical control and the centerline RBAR can be
   considered a reliable estimate of the range, the process standard deviation can be
   estimated using:
d(2) can be found in the following table:

      n    d(2) n    d(2)
      2    1.128 6    2.534
      3    1.693 7    2.704
      4    2.059 8    2.847
      5    2.326 9    2.970


Steps in Constructing the XBAR Chart

   1. Find the mean of each subgroup XBAR(1), XBAR(2), XBAR(3)... XBAR(k) and
      the grand mean of all subgroups using:




   2. Find the UCL and LCL using the following equations:




      A(2) can be found in the following table:
      n   A(2)     n   A(2)
      2   1.880    6   .483
      3   1.023    7   .419
      4    .729    8   .373
      5    .577    9   .337

   3. Plot the LCL, UCL, centerline, and subgroup means
   4. Interpret the data using the following guidelines to determine if the process is in
      control:

      a.  one point outside the 3 sigma control limits
      b.  eight successive points on the same side of the centerline
      c.  six successive points that increase or decrease
      d.  two out of three points that are on the same side of the centerline,
         both at a distance exceeding 2 sigma’s from the centerline
      e. four out of five points that are on the same side of the centerline,
         four at a distance exceeding 1 sigma from the centerline
      f. using an average run length (ARL) for determining process anomalies
Example:

The following data consists of 20 sets of three measurements of the diameter of an engine

shaft.

n    meas#1 meas#2 meas#3       Range XBAR
1    2.0000 1.9998 2.0002    0.0004 2.0000
2    1.9998 2.0003 2.0002    0.0005 2.0001
3    1.9998 2.0001 2.0005    0.0007 2.0001
4    1.9997 2.0000 2.0004    0.0007 2.0000
5    2.0003 2.0003 2.0002    0.0001 2.0003
6    2.0004 2.0003 2.0000    0.0004 2.0002
7    1.9998 1.9998 1.9998    0.0000 1.9998
8    2.0000 2.0001 2.0001    0.0001 2.0001
9    2.0005 2.0000 1.9999    0.0006 2.0001
10   1.9995 1.9998 2.0001    0.0006 1.9998
11   2.0002 1.9999 2.0001    0.0003 2.0001
12   2.0002 1.9998 2.0005    0.0007 2.0002
13   2.0000 2.0001 1.9998    0.0003 2.0000
14   2.0000 2.0002 2.0004    0.0004 2.0002
15   1.9994 2.0001 1.9996    0.0007 1.9997
16   1.9999 2.0003 1.9993    0.0010 1.9998
17   2.0002 1.9998 2.0004    0.0006 2.0001
18   2.0000 2.0001 2.0001    0.0001 2.0001
19   1.9997 1.9994 1.9998    0.0004 1.9996
20   2.0003 2.0007 1.9999    0.0008 2.0003

RBAR CHART LIMITS:

RBAR = 0.0005

UCL=D(4)*RBAR = 2.574 * .0005 = 0.001287
LCL=D(3)*RBAR = 0.000 * .0005 = 0.000


XBAR CHART LIMITS:

XDBLBAR = 2.0000

UCL = XDBLBAR + A(2)*RBAR = 2.000+1.023*.0005 = 2.0005115
LCL = XDBLBAR - A(2)*RBAR = 2.000-1.023*.0005 = 1.9994885
R - Chart:




XBAR - Chart:
Works Cited

Erwin M. Saniga, Economic Statistical Control-Chart Designs With an Application to
      Xbar and R Charts (University of Delaware, Department of Business
      Administration, Newark DE, 1989)

Richard L. Marcellus, Operating characteristics of X-bar charts with asymmetric control
       limits (Department of Industrial Engineering, Northern Illinois University,
       DeKalb IL, 1998)

W. H. Woodall, “The Statistical Design of Quality Control Charts,” The Statistician, 34,
      155-160.

Business Statistics: A Decision-Making Approach, Groebner, David F., Shannon, Patrick
W., Fry, Phillip C., and Smith, Kent D.; Prentice Hall, UpperSaddle River, NJ, 2001.

Paul A. Keller, “When to use and X-bar/R Chart,” Internet
       http://www.qualityamerica.com/knowledgecente/knowctrWhen_to_Use_an__Xba
       r__R_Chart.htm (10/13/2004)

Weitere ähnliche Inhalte

Was ist angesagt?

Statistical Quality Control
Statistical Quality ControlStatistical Quality Control
Statistical Quality Control
Dr. Rana Singh
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentation
vivekissar
 
Statistical process control
Statistical process controlStatistical process control
Statistical process control
ANOOPA NARAYANAN
 

Was ist angesagt? (20)

Statistical Quality Control.
Statistical Quality Control.Statistical Quality Control.
Statistical Quality Control.
 
Quality Control Chart
 Quality Control Chart Quality Control Chart
Quality Control Chart
 
Chapter 1 spc
Chapter 1   spcChapter 1   spc
Chapter 1 spc
 
Statistical Quality Control
Statistical Quality ControlStatistical Quality Control
Statistical Quality Control
 
Statistical quality control
Statistical quality controlStatistical quality control
Statistical quality control
 
Spc training
Spc training Spc training
Spc training
 
X, s chart and shewart control chart
X, s chart and shewart control chartX, s chart and shewart control chart
X, s chart and shewart control chart
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentation
 
Statistical Process control
Statistical Process controlStatistical Process control
Statistical Process control
 
Spc la
Spc laSpc la
Spc la
 
5. spc control charts
5. spc   control charts5. spc   control charts
5. spc control charts
 
Control charts (p np c u)
Control charts (p np c u)Control charts (p np c u)
Control charts (p np c u)
 
Statistical process control
Statistical process controlStatistical process control
Statistical process control
 
Statistical control chart
Statistical control chartStatistical control chart
Statistical control chart
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Mark Harrison SPC Implementation
Mark Harrison   SPC ImplementationMark Harrison   SPC Implementation
Mark Harrison SPC Implementation
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Meaning &significance of spc
Meaning &significance of spcMeaning &significance of spc
Meaning &significance of spc
 
Ppc
PpcPpc
Ppc
 
DMAIC Model
DMAIC ModelDMAIC Model
DMAIC Model
 

Andere mochten auch

P chart & c-chart
P chart & c-chartP chart & c-chart
P chart & c-chart
prinku k
 
Binomial probability distribution
Binomial probability distributionBinomial probability distribution
Binomial probability distribution
Muhammad Yahaya
 
Variance and standard deviation
Variance and standard deviationVariance and standard deviation
Variance and standard deviation
Amrit Swaroop
 

Andere mochten auch (20)

Control charts
Control charts Control charts
Control charts
 
CONTROL CHARTS
CONTROL CHARTSCONTROL CHARTS
CONTROL CHARTS
 
Control charts
Control chartsControl charts
Control charts
 
P chart & c-chart
P chart & c-chartP chart & c-chart
P chart & c-chart
 
X Bar R Charts
X Bar R ChartsX Bar R Charts
X Bar R Charts
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Statistical Process...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Statistical Process...Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Statistical Process...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Statistical Process...
 
P Charts
P ChartsP Charts
P Charts
 
X Bar And S Charts Mini Tutorial
X Bar And S Charts Mini TutorialX Bar And S Charts Mini Tutorial
X Bar And S Charts Mini Tutorial
 
حلقات ضبط الجودة
حلقات ضبط الجودةحلقات ضبط الجودة
حلقات ضبط الجودة
 
Control Charts[1]
Control Charts[1]Control Charts[1]
Control Charts[1]
 
P Chart Tutorial
P Chart TutorialP Chart Tutorial
P Chart Tutorial
 
Control chart
Control chartControl chart
Control chart
 
Xbar theory
Xbar theoryXbar theory
Xbar theory
 
X bar theory
X bar theoryX bar theory
X bar theory
 
What is deficit financing
What is deficit financingWhat is deficit financing
What is deficit financing
 
Step By Step Guide to Learn R
Step By Step Guide to Learn RStep By Step Guide to Learn R
Step By Step Guide to Learn R
 
Process Capability[1]
Process Capability[1]Process Capability[1]
Process Capability[1]
 
Binomial probability distribution
Binomial probability distributionBinomial probability distribution
Binomial probability distribution
 
Variance and standard deviation
Variance and standard deviationVariance and standard deviation
Variance and standard deviation
 
Quality management system
Quality management system Quality management system
Quality management system
 

Ähnlich wie X Bar R Charts

Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
CSCJournals
 

Ähnlich wie X Bar R Charts (20)

JF608: Quality Control - Unit 3
JF608: Quality Control - Unit 3JF608: Quality Control - Unit 3
JF608: Quality Control - Unit 3
 
Control Charts in Lab and Trend Analysis
Control Charts in Lab and Trend AnalysisControl Charts in Lab and Trend Analysis
Control Charts in Lab and Trend Analysis
 
Six sigma pedagogy
Six sigma pedagogySix sigma pedagogy
Six sigma pedagogy
 
Six sigma
Six sigma Six sigma
Six sigma
 
Use of control charts in laboratory as per ISO 17025:2017
Use of control charts in laboratory as per ISO 17025:2017Use of control charts in laboratory as per ISO 17025:2017
Use of control charts in laboratory as per ISO 17025:2017
 
Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
Use Fuzzy Midrange Transformation Method to Construction Fuzzy Control Charts...
 
Statirstical Process Control in manufacturing
Statirstical Process Control in manufacturingStatirstical Process Control in manufacturing
Statirstical Process Control in manufacturing
 
Introduction to Six Sigma
Introduction to Six SigmaIntroduction to Six Sigma
Introduction to Six Sigma
 
Lwrb ms
Lwrb msLwrb ms
Lwrb ms
 
Statistical process control
Statistical process control Statistical process control
Statistical process control
 
control charts
control chartscontrol charts
control charts
 
Statistics
StatisticsStatistics
Statistics
 
CONTROL CHART V.VIGNESHWARAN 2023HT79026.pdf
CONTROL CHART V.VIGNESHWARAN   2023HT79026.pdfCONTROL CHART V.VIGNESHWARAN   2023HT79026.pdf
CONTROL CHART V.VIGNESHWARAN 2023HT79026.pdf
 
TQM control charts for variables and attributes
TQM control charts for variables and attributesTQM control charts for variables and attributes
TQM control charts for variables and attributes
 
6 statistical quality control
6   statistical quality control6   statistical quality control
6 statistical quality control
 
Statistical Process Control
Statistical Process ControlStatistical Process Control
Statistical Process Control
 
Cluto presentation
Cluto presentationCluto presentation
Cluto presentation
 
Shewhart Charts for Variables
Shewhart Charts for VariablesShewhart Charts for Variables
Shewhart Charts for Variables
 
Control charts
Control chartsControl charts
Control charts
 
Statisticalqualitycontrol
StatisticalqualitycontrolStatisticalqualitycontrol
Statisticalqualitycontrol
 

Mehr von ahmad bassiouny (20)

Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 
Work Study
Work StudyWork Study
Work Study
 
Motion And Time Study
Motion And Time StudyMotion And Time Study
Motion And Time Study
 
Motion Study
Motion StudyMotion Study
Motion Study
 
The Christmas Story
The Christmas StoryThe Christmas Story
The Christmas Story
 
Turkey Photos
Turkey PhotosTurkey Photos
Turkey Photos
 
Mission Bo Kv3
Mission Bo Kv3Mission Bo Kv3
Mission Bo Kv3
 
Miramar
MiramarMiramar
Miramar
 
Mom
MomMom
Mom
 
Linearization
LinearizationLinearization
Linearization
 
Kblmt B000 Intro Kaizen Based Lean Manufacturing
Kblmt B000 Intro Kaizen Based Lean ManufacturingKblmt B000 Intro Kaizen Based Lean Manufacturing
Kblmt B000 Intro Kaizen Based Lean Manufacturing
 
How To Survive
How To SurviveHow To Survive
How To Survive
 
Dad
DadDad
Dad
 
Ancient Hieroglyphics
Ancient HieroglyphicsAncient Hieroglyphics
Ancient Hieroglyphics
 
Dubai In 2009
Dubai In 2009Dubai In 2009
Dubai In 2009
 
DesignPeopleSystem
DesignPeopleSystemDesignPeopleSystem
DesignPeopleSystem
 
Organizational Behavior
Organizational BehaviorOrganizational Behavior
Organizational Behavior
 
Work Study Workshop
Work Study WorkshopWork Study Workshop
Work Study Workshop
 
Workstudy
WorkstudyWorkstudy
Workstudy
 
Time And Motion Study
Time And  Motion  StudyTime And  Motion  Study
Time And Motion Study
 

Kürzlich hochgeladen

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 

Kürzlich hochgeladen (20)

Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 

X Bar R Charts

  • 1. Jim Waite OM 380 10/14/2004 x bar and R Charts Statistical process control is an effective method for improving a firm’s quality and productivity. There has been an increased interest in their effective implementation in American industry, brought about by increased competition and improvements in quality in foreign-made products. Many tools may be utilized to gain the desired information on a firm’s quality and productivity. Some of the more commonly used tools are control charts, which are useful in determining any changes in process performance. These include a variety of charts such as p charts, c charts and x bar and R charts. In this paper, I will be focusing on the latter two mentioned. X bar Charts defined An x bar chart is used to monitor the average value, or mean, of a process over time. For each subgroup, the x bar value is plotted. The upper and lower control limits define the range of inherent variation in the subgroup means when the process is in control. R Chart defined An R Chart is a control chart that is used to monitor process variation when the variable of interest is a quantitative measure. Now, what does all this mean? These charts will allow us to see any deviations from desired limits within the quality process and, in effect, allow the firm to make necessary adjustments to improve quality. The Chart Construction Process In order to construct x bar and R charts, we must first find our upper- and lower- control limits. This is done by utilizing the following formulae:
  • 2. UCL = µ+ 3σ √n LCL = µ - 3σ √n While theoretically possible, since we do not know either the population process mean or standard deviation, these formulas cannot be used directly and both must be estimated from the process itself. First, the R chart is constructed. If the R chart validates that the process variation is in statistical control, the x bar chart is constructed. Steps in Constructing an R chart 1. Select k successive subgroups where k is at least 20, in which there are n measurements in each subgroup. Typically n is between 1 and 9. 3, 4, or 5 measurements per subgroup is quite common. 2. Find the range of each subgroup R(i) where R(i)=biggest value - smallest value for each subgroup i. 3. Find the centerline for the R chart, denoted by 4. Find the UCL and LCL with the following formulas: UCL= D(4)RBAR and LCL=D(3)RBAR with D(3) and D(4) can be found in the following table: Table of D(3) and D(4) n D(3) D(4) n D(3) D(4) 2 0 3.267 6 0 2.004 3 0 2.574 7 .076 1.924 4 0 2.282 8 .136 1.864 5 0 2.114 9 .184 1.816 5. Plot the subgroup data and determine if the process is in statistical control. If not, determine the reason for the assignable cause, eliminate it, and the subgroup(s) and repeat the previous 3 steps. Do NOT eliminate subgroups with points out of range for which assignable causes cannot be found. 6. Once the R chart is in a state of statistical control and the centerline RBAR can be considered a reliable estimate of the range, the process standard deviation can be estimated using:
  • 3. d(2) can be found in the following table: n d(2) n d(2) 2 1.128 6 2.534 3 1.693 7 2.704 4 2.059 8 2.847 5 2.326 9 2.970 Steps in Constructing the XBAR Chart 1. Find the mean of each subgroup XBAR(1), XBAR(2), XBAR(3)... XBAR(k) and the grand mean of all subgroups using: 2. Find the UCL and LCL using the following equations: A(2) can be found in the following table: n A(2) n A(2) 2 1.880 6 .483 3 1.023 7 .419 4 .729 8 .373 5 .577 9 .337 3. Plot the LCL, UCL, centerline, and subgroup means 4. Interpret the data using the following guidelines to determine if the process is in control: a. one point outside the 3 sigma control limits b. eight successive points on the same side of the centerline c. six successive points that increase or decrease d. two out of three points that are on the same side of the centerline, both at a distance exceeding 2 sigma’s from the centerline e. four out of five points that are on the same side of the centerline, four at a distance exceeding 1 sigma from the centerline f. using an average run length (ARL) for determining process anomalies
  • 4. Example: The following data consists of 20 sets of three measurements of the diameter of an engine shaft. n meas#1 meas#2 meas#3 Range XBAR 1 2.0000 1.9998 2.0002 0.0004 2.0000 2 1.9998 2.0003 2.0002 0.0005 2.0001 3 1.9998 2.0001 2.0005 0.0007 2.0001 4 1.9997 2.0000 2.0004 0.0007 2.0000 5 2.0003 2.0003 2.0002 0.0001 2.0003 6 2.0004 2.0003 2.0000 0.0004 2.0002 7 1.9998 1.9998 1.9998 0.0000 1.9998 8 2.0000 2.0001 2.0001 0.0001 2.0001 9 2.0005 2.0000 1.9999 0.0006 2.0001 10 1.9995 1.9998 2.0001 0.0006 1.9998 11 2.0002 1.9999 2.0001 0.0003 2.0001 12 2.0002 1.9998 2.0005 0.0007 2.0002 13 2.0000 2.0001 1.9998 0.0003 2.0000 14 2.0000 2.0002 2.0004 0.0004 2.0002 15 1.9994 2.0001 1.9996 0.0007 1.9997 16 1.9999 2.0003 1.9993 0.0010 1.9998 17 2.0002 1.9998 2.0004 0.0006 2.0001 18 2.0000 2.0001 2.0001 0.0001 2.0001 19 1.9997 1.9994 1.9998 0.0004 1.9996 20 2.0003 2.0007 1.9999 0.0008 2.0003 RBAR CHART LIMITS: RBAR = 0.0005 UCL=D(4)*RBAR = 2.574 * .0005 = 0.001287 LCL=D(3)*RBAR = 0.000 * .0005 = 0.000 XBAR CHART LIMITS: XDBLBAR = 2.0000 UCL = XDBLBAR + A(2)*RBAR = 2.000+1.023*.0005 = 2.0005115 LCL = XDBLBAR - A(2)*RBAR = 2.000-1.023*.0005 = 1.9994885
  • 5. R - Chart: XBAR - Chart:
  • 6. Works Cited Erwin M. Saniga, Economic Statistical Control-Chart Designs With an Application to Xbar and R Charts (University of Delaware, Department of Business Administration, Newark DE, 1989) Richard L. Marcellus, Operating characteristics of X-bar charts with asymmetric control limits (Department of Industrial Engineering, Northern Illinois University, DeKalb IL, 1998) W. H. Woodall, “The Statistical Design of Quality Control Charts,” The Statistician, 34, 155-160. Business Statistics: A Decision-Making Approach, Groebner, David F., Shannon, Patrick W., Fry, Phillip C., and Smith, Kent D.; Prentice Hall, UpperSaddle River, NJ, 2001. Paul A. Keller, “When to use and X-bar/R Chart,” Internet http://www.qualityamerica.com/knowledgecente/knowctrWhen_to_Use_an__Xba r__R_Chart.htm (10/13/2004)