SlideShare ist ein Scribd-Unternehmen logo
1 von 2
Downloaden Sie, um offline zu lesen
Chemical weapons facility completes major
                          structural steel on main processing building
                          February 14, 2013                                                 CONTACT: Stephanie Parrett
FOR MORE
INFORMATION               FOR IMMEDIATE RELEASE                                                      t: 859-624-6326
CONTACT:                                                                                             c: 859-661-2203
Blue Grass
Chemical Stockpile
Outreach Office           RICHMOND, Ky. – Construction crews at the Blue Grass Chemical Agent-Destruction Pilot Plant
1000 Commercial           (BGCAPP) achieved another milestone this month, safely installing the final pieces of major
Drive, Suite 2
Richmond, KY40475         structural steel into the plant’s Munitions Demilitarization Building (MDB) at the Blue Grass Army
(859) 626-8944            Depot.
bgoutreach@iem.com

Blue Grass Chemical       The milestone represents the successful completion of a 10-year design and construction effort, as
Agent-Destruction         the 143,000 square-foot facility contains more than 3,650 tons of structural steel. The MDB is the
Pilot Plant Public
Affairs
                          largest and most complex facility at BGCAPP with a footprint about the size of two adjacent football
(859) 624-6326            fields. During plant operations, the MDB is where an automated process will remove the weapons’
                          energetics and chemical agents for destruction in separate processes. A small portion of the
Blue Grass Army
Depot Public Affairs      structural steel remains to be installed to allow workers space to set more process equipment.
Office
(859) 779-6221            “Completing this work allows for more progress, as we now move forward to enclose the facility with
Blue Grass Chemical       exterior siding,” said Gil Drexel, construction manager for BGCAPP systems contractor Bechtel
Activity Public Affairs   Parsons Blue Grass. “This accomplishment was made possible by our entire workforce that includes
Office
(859) 779-6897
                          skilled local ironworkers from the Central Kentucky Building and Construction Trades Council.”

                          Design of the plant began in 2003. Since breaking ground in 2006, workers have completed the
                          building’s concrete foundation and blast-proof rooms, and installed large neutralization process
                          equipment. Now that the facility’s major structural steel is also complete, work will shift to installing
                          piping and wiring, along with specially-designed and fabricated munitions reverse assembly
                          equipment.

                          “Completing major structural steel work is another example of everyone’s commitment to progress
                          and getting the job done right,” explained Jeff Brubaker, the Army’s site project manager. “This
                          milestone is a reflection of the entire BGCAPP team’s collaboration and rigorous support for a
                          common mission and goal.”

                          Tom McKinney, Bechtel Parsons project manager, agreed. “Milestones are worthy of recognition
                          when they are completed safely and with the highest of quality standards. From design to
                          procurement to construction, every step is important. Designing and reviewing the steel, finding
                          high-quality U.S. fabricators, and safely erecting the facility were all critical.”

                          BGCAPP is being built to safely and efficiently destroy a stockpile of 523 tons of blister and nerve
                          agents in projectiles and rockets currently in storage at the Blue Grass Army Depot. Currently,
                          construction is more than 64 percent complete, systemization is more than 9 percent complete and
                          work is progressing on a variety of facilities that will support chemical demilitarization operations.

                          For more information on the project, please visit the Assembled Chemical Weapons Alternatives
                          website at www.peoacwa.army.mil.




                                                                                                                     14 February 2013
Major structural steel finished at main chemical weapons destruction facility (continued)




Central Kentucky Building and Construction Trades Council local ironworkers (above) safely install
structural steel inside the Blue Grass Chemical Agent-Destruction Pilot Plant’s (BGCAPP)
Munitions Demilitarization Building (MDB). Workers recently completed major structural steel
installation at the MDB, a construction milestone for BGCAPP’s largest and most complex facility.




Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) (above) construction is more than
64 percent complete. BGCAPP workers recently achieved a project milestone as they safely installed
the final pieces of major structural steel into the pilot plant’s Munitions Demilitarization Building
(MDB). During plant operations, the MDB is where an automated process will remove the weapons’
energetics and chemical agents for destruction in separate processes.




                                                                                        14 February 2013

Weitere ähnliche Inhalte

Mehr von Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

Mehr von Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 
Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012
 
Explosive Destruction Technologies Summary 23 October 2013
Explosive Destruction Technologies Summary 23 October 2013Explosive Destruction Technologies Summary 23 October 2013
Explosive Destruction Technologies Summary 23 October 2013
 
Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update ...
Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update...Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update...
Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
 

News Release: Chemical weapons facility completes major structural steel on main processing building

  • 1. Chemical weapons facility completes major structural steel on main processing building February 14, 2013 CONTACT: Stephanie Parrett FOR MORE INFORMATION FOR IMMEDIATE RELEASE t: 859-624-6326 CONTACT: c: 859-661-2203 Blue Grass Chemical Stockpile Outreach Office RICHMOND, Ky. – Construction crews at the Blue Grass Chemical Agent-Destruction Pilot Plant 1000 Commercial (BGCAPP) achieved another milestone this month, safely installing the final pieces of major Drive, Suite 2 Richmond, KY40475 structural steel into the plant’s Munitions Demilitarization Building (MDB) at the Blue Grass Army (859) 626-8944 Depot. bgoutreach@iem.com Blue Grass Chemical The milestone represents the successful completion of a 10-year design and construction effort, as Agent-Destruction the 143,000 square-foot facility contains more than 3,650 tons of structural steel. The MDB is the Pilot Plant Public Affairs largest and most complex facility at BGCAPP with a footprint about the size of two adjacent football (859) 624-6326 fields. During plant operations, the MDB is where an automated process will remove the weapons’ energetics and chemical agents for destruction in separate processes. A small portion of the Blue Grass Army Depot Public Affairs structural steel remains to be installed to allow workers space to set more process equipment. Office (859) 779-6221 “Completing this work allows for more progress, as we now move forward to enclose the facility with Blue Grass Chemical exterior siding,” said Gil Drexel, construction manager for BGCAPP systems contractor Bechtel Activity Public Affairs Parsons Blue Grass. “This accomplishment was made possible by our entire workforce that includes Office (859) 779-6897 skilled local ironworkers from the Central Kentucky Building and Construction Trades Council.” Design of the plant began in 2003. Since breaking ground in 2006, workers have completed the building’s concrete foundation and blast-proof rooms, and installed large neutralization process equipment. Now that the facility’s major structural steel is also complete, work will shift to installing piping and wiring, along with specially-designed and fabricated munitions reverse assembly equipment. “Completing major structural steel work is another example of everyone’s commitment to progress and getting the job done right,” explained Jeff Brubaker, the Army’s site project manager. “This milestone is a reflection of the entire BGCAPP team’s collaboration and rigorous support for a common mission and goal.” Tom McKinney, Bechtel Parsons project manager, agreed. “Milestones are worthy of recognition when they are completed safely and with the highest of quality standards. From design to procurement to construction, every step is important. Designing and reviewing the steel, finding high-quality U.S. fabricators, and safely erecting the facility were all critical.” BGCAPP is being built to safely and efficiently destroy a stockpile of 523 tons of blister and nerve agents in projectiles and rockets currently in storage at the Blue Grass Army Depot. Currently, construction is more than 64 percent complete, systemization is more than 9 percent complete and work is progressing on a variety of facilities that will support chemical demilitarization operations. For more information on the project, please visit the Assembled Chemical Weapons Alternatives website at www.peoacwa.army.mil. 14 February 2013
  • 2. Major structural steel finished at main chemical weapons destruction facility (continued) Central Kentucky Building and Construction Trades Council local ironworkers (above) safely install structural steel inside the Blue Grass Chemical Agent-Destruction Pilot Plant’s (BGCAPP) Munitions Demilitarization Building (MDB). Workers recently completed major structural steel installation at the MDB, a construction milestone for BGCAPP’s largest and most complex facility. Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) (above) construction is more than 64 percent complete. BGCAPP workers recently achieved a project milestone as they safely installed the final pieces of major structural steel into the pilot plant’s Munitions Demilitarization Building (MDB). During plant operations, the MDB is where an automated process will remove the weapons’ energetics and chemical agents for destruction in separate processes. 14 February 2013