SlideShare ist ein Scribd-Unternehmen logo
1 von 2
Downloaden Sie, um offline zu lesen
PMBOK 4th Edition                  PMI-CCVC Time managment CAPM Prep                                     6/21/2011




                                           Progressive elaboration where near term work is planned in detail and
  1       Define Activities            a
                                           future work is planned at a higher level of the WBS.
                               v
                                           The process of estimating the type and quantities of material, people,
  2     Sequence Activities           b
                                           equipment, or supplies required to perform each activity.
                               e
         Estimate Activity                 The process of monitoring the status of the project to update project
  3                                    c
             Resources                     progress and managing changes to the schedule baseline.
                               b
         Estimate Activity                 Specify when and how long identified project resources are available.
  4                                   d
             Durations                     This includes resource skill level and geographical locations of orgin.
                               s
                                           The process of identifying and documenting relationships among the
  5      Develop Schedule              e
                               t           project activities.
                                           Preferred logic, preferential logic, or soft logic. When fast tracking
  6      Control Schedule              f   techniques are used, these should be reviewed and considered for
                               c           modification or removal.
                                           A project schedule developed from the schedule network analysis. It is
      Finalized and Approved               accepted and approved by the project management team as the
  7                                    g
              Schedule                     schedule with start and finish dates. It is a component of the project
                               l           management plan.
                                           Uses Most likely, Optimistic and Pessimistic values for Three-Point
  8       Decomposition               h
                               m           Estimates.
                                           Resource need is estimated and the quantities are totaled for each
  9    Rolling Wave Planning           i
                               a           activitiy's resources.
                                           Uses parameters such as duration, budget, size, weight and complexity
 10      Activity Attributes           j   from a previous project as the basis for estimating the same parameter
                          k                for a future project.
            Precedence
                                           Used for schedule development and for selecting, ordering, and sorting
 11    Diagramming Method              k
                                           the planned activities in reports.
              (PDM)       n
           Discretionary
 12                                    l   The baseline that is used in the Control Schedule process.
           dependencies   f
                                           Subdividing the project work packages into smaller, more manageable
 13     Resource Calendars            m
                               d           compoents called activities.
                                           Uses boxes, referred to as nodes, to represent activities, and connects
 14    Bottom-Up Estimating           n    them with arrows that show the logical relationships that exist
                                           between them. This technique is also called Activity-On-Node (AON).
                               i
       Resource Breakdown                  A structure of identified resources by resource category and resource
 15                                   o
            Structure          o           type.

                                           A schedule network analysis technique applied to a schedule that has
 16    Analogous Estimating           p    been analysised by critical path method. Can be used when shared
                                           resources are only available at certain times or limited quantities.
                             j
      Program Evaluation and
                                           Schedule performance measurements (SV, SPI) are used to assess the
 17      Review Technique             q
                                           changes from the original schedule baseline.
              (PERT)         h

                                                Page 1 of 2
PMBOK 4th Edition                PMI-CCVC Time managment CAPM Prep                                      6/21/2011


         Schedule Network                Uses analytical techniques such as critical path method, critical chain
 18                                  r
             Analysis                    method and resource leveling for generating a project schedule.
                             r
                                         The process of approximating the number of work periods needed to
 19      Resource Leveling           s
                                         complete individual activities with estimated resources.
                             p
                                         The process of analyzing activity sequences, durations, resource
 20      Schedule Baseline           t
                                         requirements, and schedule constraints to create the project schedule.
                             g
                                         The process of identifying the specific actions to be performed to
 21      Variance Analysis           v
                             q           produce the project deliverables.




                                              Page 2 of 2

Weitere ähnliche Inhalte

Was ist angesagt?

Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llNASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Blythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalBlythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalNASAPMC
 
Ken poole
Ken pooleKen poole
Ken pooleNASAPMC
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hallNASAPMC
 
Nichols.david
Nichols.davidNichols.david
Nichols.davidNASAPMC
 
Corcoran webster
Corcoran websterCorcoran webster
Corcoran websterNASAPMC
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevinNASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.edNASAPMC
 
Fujieh.maura
Fujieh.mauraFujieh.maura
Fujieh.mauraNASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey NASAPMC
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity ResourcesDavidMcLachlan1
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1NASAPMC
 
Linda maleki
Linda malekiLinda maleki
Linda malekiNASAPMC
 
Semancik.susan
Semancik.susanSemancik.susan
Semancik.susanNASAPMC
 

Was ist angesagt? (20)

Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Blythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 finalBlythe ortiz7120 5e handbooks 2 15-2012 final
Blythe ortiz7120 5e handbooks 2 15-2012 final
 
Ken poole
Ken pooleKen poole
Ken poole
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Phillip.hall
Phillip.hallPhillip.hall
Phillip.hall
 
Nichols.david
Nichols.davidNichols.david
Nichols.david
 
Corcoran webster
Corcoran websterCorcoran webster
Corcoran webster
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Carmichael.kevin
Carmichael.kevinCarmichael.kevin
Carmichael.kevin
 
Pmbok6
Pmbok6Pmbok6
Pmbok6
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
 
Fujieh.maura
Fujieh.mauraFujieh.maura
Fujieh.maura
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
 
Linda maleki
Linda malekiLinda maleki
Linda maleki
 
Semancik.susan
Semancik.susanSemancik.susan
Semancik.susan
 

Andere mochten auch

Online PMP Training, Nigeria: Introduction to Projects and Project Management
Online PMP Training, Nigeria: Introduction to Projects and Project ManagementOnline PMP Training, Nigeria: Introduction to Projects and Project Management
Online PMP Training, Nigeria: Introduction to Projects and Project ManagementProTrainingCentre
 
Improving your Project Communications
Improving your Project CommunicationsImproving your Project Communications
Improving your Project CommunicationsArt Gelwicks
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Amr Miqdadi
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!Edureka!
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinasPedro Arcas
 
Fast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcFast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcDux Raymond Sy
 
Final exam review_questions
Final exam review_questionsFinal exam review_questions
Final exam review_questionsCarmenLamdegil
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)May Wong, PMP
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas SummaryAmr Miqdadi
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)May Wong, PMP
 

Andere mochten auch (20)

Online PMP Training, Nigeria: Introduction to Projects and Project Management
Online PMP Training, Nigeria: Introduction to Projects and Project ManagementOnline PMP Training, Nigeria: Introduction to Projects and Project Management
Online PMP Training, Nigeria: Introduction to Projects and Project Management
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
Improving your Project Communications
Improving your Project CommunicationsImproving your Project Communications
Improving your Project Communications
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
 
PMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration managementPMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration management
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1
 
Path to PMP!
Path to PMP!Path to PMP!
Path to PMP!
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinas
 
Fast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdcFast Track Project Management Success w/ Project Online #pmiwdc
Fast Track Project Management Success w/ Project Online #pmiwdc
 
T344 Web
T344 WebT344 Web
T344 Web
 
Cheatsheet
CheatsheetCheatsheet
Cheatsheet
 
PMP Exam-Prep
PMP Exam-PrepPMP Exam-Prep
PMP Exam-Prep
 
Final exam review_questions
Final exam review_questionsFinal exam review_questions
Final exam review_questions
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 Part 2 (CONSTRAINTS)
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas Summary
 
Ch1 ch2
Ch1 ch2Ch1 ch2
Ch1 ch2
 
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
Taking smaller bites with PMP-Bite series - PMP Chapter 1 (the 4Ps)
 
Typing An Official Letter
Typing An Official LetterTyping An Official Letter
Typing An Official Letter
 

Ähnlich wie Dah time mgmt matching exercise answers

Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach Matilda Barbayanni
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach Matilda Barbayanni
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 

Ähnlich wie Dah time mgmt matching exercise answers (20)

Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Cps print
Cps printCps print
Cps print
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
SAP cProjects
SAP cProjectsSAP cProjects
SAP cProjects
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 

Mehr von University High School - Fresno (11)

Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm process cheat sheet
Capm process cheat sheetCapm process cheat sheet
Capm process cheat sheet
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Dah time mgmt matching exercise answers

  • 1. PMBOK 4th Edition PMI-CCVC Time managment CAPM Prep 6/21/2011 Progressive elaboration where near term work is planned in detail and 1 Define Activities a future work is planned at a higher level of the WBS. v The process of estimating the type and quantities of material, people, 2 Sequence Activities b equipment, or supplies required to perform each activity. e Estimate Activity The process of monitoring the status of the project to update project 3 c Resources progress and managing changes to the schedule baseline. b Estimate Activity Specify when and how long identified project resources are available. 4 d Durations This includes resource skill level and geographical locations of orgin. s The process of identifying and documenting relationships among the 5 Develop Schedule e t project activities. Preferred logic, preferential logic, or soft logic. When fast tracking 6 Control Schedule f techniques are used, these should be reviewed and considered for c modification or removal. A project schedule developed from the schedule network analysis. It is Finalized and Approved accepted and approved by the project management team as the 7 g Schedule schedule with start and finish dates. It is a component of the project l management plan. Uses Most likely, Optimistic and Pessimistic values for Three-Point 8 Decomposition h m Estimates. Resource need is estimated and the quantities are totaled for each 9 Rolling Wave Planning i a activitiy's resources. Uses parameters such as duration, budget, size, weight and complexity 10 Activity Attributes j from a previous project as the basis for estimating the same parameter k for a future project. Precedence Used for schedule development and for selecting, ordering, and sorting 11 Diagramming Method k the planned activities in reports. (PDM) n Discretionary 12 l The baseline that is used in the Control Schedule process. dependencies f Subdividing the project work packages into smaller, more manageable 13 Resource Calendars m d compoents called activities. Uses boxes, referred to as nodes, to represent activities, and connects 14 Bottom-Up Estimating n them with arrows that show the logical relationships that exist between them. This technique is also called Activity-On-Node (AON). i Resource Breakdown A structure of identified resources by resource category and resource 15 o Structure o type. A schedule network analysis technique applied to a schedule that has 16 Analogous Estimating p been analysised by critical path method. Can be used when shared resources are only available at certain times or limited quantities. j Program Evaluation and Schedule performance measurements (SV, SPI) are used to assess the 17 Review Technique q changes from the original schedule baseline. (PERT) h Page 1 of 2
  • 2. PMBOK 4th Edition PMI-CCVC Time managment CAPM Prep 6/21/2011 Schedule Network Uses analytical techniques such as critical path method, critical chain 18 r Analysis method and resource leveling for generating a project schedule. r The process of approximating the number of work periods needed to 19 Resource Leveling s complete individual activities with estimated resources. p The process of analyzing activity sequences, durations, resource 20 Schedule Baseline t requirements, and schedule constraints to create the project schedule. g The process of identifying the specific actions to be performed to 21 Variance Analysis v q produce the project deliverables. Page 2 of 2