SlideShare ist ein Scribd-Unternehmen logo
1 von 76
MASSAJA CHILDREN SUPPORT FOUNDATION BUDGET SUMMARY FOR PUTTING UP PRIMARY SCHOOL,
                     SECONDARY SCHOOL,   AND THE HEALTH CENTRE


                                ITEMISED BUDGET




 1.   PRIMARY SCHOOL COMPLETE WITH DOUBLE STREAMS ………………………{ $ 239,357 USD}




 2.   SECONDAYSCHOOL, COMPUTER    LAB, LIBRARY,……………………….. { $ 239,357 USD }




 3.   HEATH CENTRE FOR THE COMMUNITY,……. …………………….…….…         { $ 34,488 USD }




 4.   5 STANCE DRAINABLE PIT LATRINE FOR THE PRIMARY SCHOOL, SECONDARY SCHOOL, AND
      THE HEALTH CENTRE      R ESPCTIVELY………………………… X3           { $ 26,840 USD}




GRAND TOTAL         ………………………………………… $                           540,042 USD
ACCOUNTABILITY IN DETAIL THAT MAKES UP THE ABOVE AMOUNT



         The above budget is well detailed and accounted for below how it sums up to a grand total that
         you see above in US dollar.

         Below each item and material that will be used at the entire project is well detailed. The price is in
         local currency the {Ugandan Shilling} of which the



         Exchange rate is       ……………..       1 US dollar   =   2,467 Ugandan shillings




  ACCOUNTABILITY BUDGET FOR THE PRIMARY SCHOOL OF 16 BLOCK OF CLASSROOMS IN
                               LOCAL CURRENCY



Item Description                            Unit   Quantity Rate(Ushs)         Amount(Ugandan shillings)




             Element NO 1

          Substructure: (All Provisional)

            Site Preparation



1.01      Excavate oversite to remove

           top soil average 150mm thick and

                    remove from site.               SM      1504      @ 1000=         1;504,000=



1.02 Treat surface of subsoil or fillings

and Surroundings with approved

 Chemical ant termite
solution: provide ten year guarantee.         SM        1504         @ 1000=     1,504,000=



Excavation and Earthworks.

Note: Rates for excavation to

include for keeping excavations

free from water

and planking and strutting

to sides of excavations

1.03 Excavate to reduce levels and

Remove from site.                                  CM          216     @ 2000=          432,000



1.04 Excavate trenches for wall

Foundations: commencing from

Reduced levels: not

exceeding 1.5m deep .                              CM      248       @ 4000=         992,000=

1.05 Extra over excavation for excavating

in rock                                             CM         48      @ 30,000=        1,440,000=



Disposal of excavated material

1.06 Selected excavated material in filling

to foundation trenches : around walling :

placed in 200mm layers : watered and

Compacted to 95% MDD                                CM         176 2000=           352,000=



1.07 Remove surplus excavated

material from site                                  CM         128 4,000=          512,000=



Hardcore

1.08 150mm Filling : deposit, spread, level

and compact : 50mm selected quarry dust
blinding.                                      CM      752 10,000=     7,520,000=



Vibrated Insitu concrete grade 15 mix

(1:3:6 / 20mmaggregate) as described:-

1.09 Foundations in trenches                 CM     512 10,000=      5,120,000=



Vibrated reinforced concrete grade 20

Mix (1:2:4 / 20mm Aggregate) as

Described in:-

1.11 Ramp for the Disabled                   CM 128       @150,000=     19,200,000=

1.10 100mm thick ground floor slab           SM 9600      @ 10,000=     96,000,000=

1.12 Horizontal Ground beam                  CM 192        @ 250,000=    48,000,000=



High yield tensile steel bar reinforcement

To BS 4449 as described including

Cutting to lengths, bending, hoisting and

Fixing including all necessary tying

Wire and spacing blocks.

1.12 R8 bars for links                            KG     944     @ 3,000=   2,832,000=

1.13 Y12 bars.                                      KG    2280    @ 4,000= 9,120,000=



Total Carried to Collection                                          194,528,000=
Item        Description                Unit   Quantity       Rate(Ushs)    Amount(Ugandan shillings)

Reinforcement

1.12 Mesh reinforcement Ref No.

A98 size 200 x 200 mm weighing 1.54

kg per square metre: in floor slab:

including all necessary supports                  SM        840      @10,000=    8,400,000=



Sawn formwork as described to:

1.13 Vertical edges of surface bed :

over 75mm but not exceeding 150 mm high.          LM        368      @7,500=    2,760,000=



Brickwork in burnt clay bricks in cement and

sand mortar (1:4) mix; with and

including 25 x 3mm hoop iron strips

laid horizontally every alternate course.

1.14 230 mm thick plinth walling.                  SM        488     @40,000=    19,520,000=



Sundries

1.15 One layer 1000 gauge polythene sheet

damp proof membrane Under bed :

300mm laps.                                            SM          840   @9,500=    7,980,000=



1.16

Allow for " Dieldrex " or other approved

anti-termite treatment in sides and bottom

of foundation trenches and ground surface

below hard-core filling( SEE ITEM
No.1.02)                                               SM        1744      @ 8,000=      13,952,000=




Splash apron

1.17

75mm thick concrete (grade 20) splash apron on

75mm hardcore base well rammed and apron

finished with 25mm thick cement and

sand (1:3) screed trowelled smooth to gentle falls

with division strips every 2.00 metre length and

including 150mm thick clay bricks edge wall

average 500mm deep rendered on

and including 450mm x 150mm thick concrete

grade 15 foundation and all necessary excavations

and disposal of spoil and formwork to edge of apron

 Cement and Sand ( 1: 4 ) as described:-               SM    288         @36,000=       10 ,368,000=




1.18 20mm thick rendering to plinth walls

Prepare and apply two coats of bituminous paint on:-   SM    184            @8,000= 1,472,000=



1.19 Rendered plinth walls                                  SM     184      @ 8,000= 1,472,000=



Total Carried to Collection

Page E1- 1/                                                                         194,528,000=

Page E1- 2/                                                                          65,924,000=




Total Substructure To Summary                                                  260,452,000=
Item          Description                   Unit   Quantity Rate(Ushs) Amount (     Ugandan shillings)



Bill No. 2

Element No. 2

Super structure:

Vibrated Insitu reinforced concrete grade

20 mix (1:2:4 / 20mm Aggregate) as

Described:-

2.01 Ring beams                                      CM      24     @400,000=      9,600,000=



Mild steel reinforcement as described including

cutting to lengths, bending, hoisting and fixing

Including all necessary tying wire and

spacing blocks. hoisting and fixing including

all necessary tying wire and spacing blocks. .

2.02 8 mm diameter bar                                KG   944      @4,000=       3,776,000=



High yield tensile steel bar reinforcement to

BS 4449 as described including cutting to

Lengths, bending, hoisting and fixing including

all necessary tying wire and spacing blocks.

2.03 12 mm diameter bar                               KG    2,280   @ 4,000=      9,120,000=



Sawn formwork as described to:
2.04 Sides and soffites of beams                SM    192      @18,000=    3,456,000=



Damp proof courses : hessian based bituminous

felt: bedded in cement and

Sand (1:3) mortar: 300mm laps.

2.05 Horizontal : 230mm ditto                    LM     416    @ 2,500=     1,040,000=



Brickwork in burnt clay bricks in cement and

Sand mortar (1:4) mix; with and

Including 25 x 3mm hoop iron strips laid

Horizontally every alternate course.

2.06 230 mm thick below ring beam walling.      SM    776     @46,800=    36,316,800=



2.07 230mm Thick above ring beam and gable walling SM 272     @46,800= 12,729,600=



2.08 Labor and materials in eaves filling on

230mm wall for average height of 300mm            LM 368 @ 46,800= 17,222,400=



Permanent Vents

2.09 Permanent Vent filled in with Kajjansi

ventilation bricks or other equal and

approved; bat proof gauze and coffee tray

wire backing complete with necessary

timber framing and beading.

                                                      SM       8   @58,000=       464,000=




Total Super Structure To Summary                                           93,724,800=
Item         Description            Unit    Quantity Rat (Ushs)      Amount (Ugandan shillings)



Bill No. 2

Elemnt No.3

Roof:



Roof Construction

The followings 10nos. Timber trusses each

spanning 6.46M x 1.58M rise,

comprising of well treated members bolted

together to approval as described

and hoisted and fixed in position at about 3.30M

above floor level.

Sawn cypress pressure impregnated with

preservative:-

3.01 50 x 100mm Purlins                               LM    1400    @ 10,000= 14,000,000=

3.02 50 x 100mm Strut /tie                            LM      432   @10,000= 4,320,000=

3.03 50 x 150mm Ridge                                 LM      144   @ 12,000= 1,728,000=

3.04 50 x 150mm Tie beam                              LM      520   @12,000=   6240,000=

3.05 50 x 100mm Rafters                               LM      752   @10,000=   7,520,000=

3.06 75 x 100mm Wall Plate                             LM     264   @12,000=   3,168,000=

3.07 75 x 100mm overhangs                             LM      240   @12,000=   2,880,000=

Roof Covering



3.08 28 Gauge pre-painted iron roofing sheets

fixed with 1.5 side corrugation laps and

150mm end laps with and including approved
roofing nails or galvanized steel

drive screws with plastic washers and fller blocks to

    manufacturer's instructions.                            SM    1248      @ 38,000= 47,424,000=




3.09 28 Gauge plain (pre-coated) roll top ridge capping. LM 1368            @ 12,000= 16,416,000=




Eaves

3.10 25 x 225mm Wrot Cypress fascia board

and badge boards                                            LM     416     @ 10,000= 4,160,000

Painting Knot prime stop and apply three coats

    of gloss oil paint to timber surfaces.



.

3.11 Knot, prime, stop and apply three coats of gloss

oil paint to wood fascia 200-

300mm girth.                                                 SM     144    @ 10,000= 1,440,000=



Total Roof Carried To Summary                                                     103,696,000=




Item                     Description         Unit   Quantity Rate (Ushs)    Amount (Ugandan shillings)



Bill No.1
Element No.4

Doors and Windows:

Windows

Vibrated Precast concrete grade 20

mix (1:2:4 / 20mm aggregate) : units

reinforced as necessary and finished fair

face on all exposed sides as

described:-

4.01 75 x 285 mm sunk weathered and

throated window cill       Purpose made steel

casement windows manufactured from

standard W20

sections: manufacture, assemble and deliver

to site : Supply and fix

ironmongery comprising approved hinges

, pivoting mechanisms, stays,

fasteners to opening lights: plugged and screwed

or built into walling : one

coat red oxide primer before delivery. all to      LM   160   @3,000=   3,480,000=



Architects details Purpose made steel

casement windows manufactured

from standard W20

sections: manufacture, assemble and

deliver to site : Supply and fix

4.02 Window type W1 : Size 1200 x 1200mm

overall height:                                    NO   112     @ 250,000= 28,000,000=



Glass and Glazing

4.03 4mm thick clear sheet glass to metal
window with putty                                        SM      160                 @ 7 0,000=   11,200,000=



Prepare touch up primer and apply one

undercoat and two finishing coats of

gloss oil paint : on glazed metal surfaces

4.04 General Surfaces : windows                            SM   320           @3000=        960,000=



Total Carried to Collection                                                            43,640,000=




Item         Description                     Unit   Quantity Rate (Ushs)       Amount (Ugandan shillings)




Doors

Purpose made steel casement doors

manufactured from Standard W20

Sections complete as described to

Architects details

4 .05 Door size 900 x 2400mm with

permanent louvered vents 300mm

included : D1                                           NO           16    @300,000=      4800,000=



Prepare, knot prime, stop and apply

three coats of gloss oil paint: on

woodwork.

4.06 General surface of metal doors                   SM        72        @ 3,000=        216,000=
Supply and fix the following approved

ironmongeries complete with

marching screws, handles and keys

to hard wood.

4.07 Tower bolt complete with Pudlocks       NO   16   @ 100,000=    1,600,000=



4.08 25mm diameter rubber door stopper.      NO   16   @ 10,000=        160,000=

Total Carried to Collection

COLLECTION

Page E4- 4/                                                         43,640,000=

Page E4- 5/                                                          6,776,000=




Total Doors and Windows Carried To Summary                      50,416,000=
Item                  Description Unit         Quantity       Rate (Ushs) Amount     (Ugandan shillings)



Bill No. 2

Element No. 5

External Finishes:

Floor Finishes

Cement and sand (1:3) screeds and

pavings : one coat: steel trowell finish :

laid on concrete

5.01 30mm thick screed in the verandah              SM           160           @ 10,000 = 1,600,000=



5.02 25 x 200mm skirting with square top

edge and coved junction at bottom of paving.         LM            352              @ 10,000 =
3,520,000=



Cement and sand ( 1:4) render trowelled

smooth on concrete or masonry

5.03 15mm to walls.                                  SM          976           @ 10,000 =      9,760,000=



Two coats tyrolene rendering on masonry

5.04 Walls and concrete surfaces                     SM          544               @8.000=   4,352,000=



Painting: 'Sadolin Paints' or equal and approved.

5.05 Prepare and apply one undercoat

and two finishing coats weaher guard on

plastered surfaces.                                      SM      432           @10,000=      4,320,000=




5.06 Ditto to Tyrolean surfaces.                         SM      544           @ 10,000=      5,440,000=
Total External Walls Finishes Carried To Summary                             28,992,000=




Item         Description                Unit   Quantity   Rate (Ushs) Amount (Ugandan shillings)



Bill No. 2

Element No.6

Internal Finishes

Floor Finishes

Cement and sand (1:3) screeds and

pavings :

one coat: steel trowell finish :

laid on concrete

6.01 30mm thick screed                         SM     752    @10,000=    7,520,000=



6.02 25 x 100mm skirting with square top

edge and coved junction at bottom of paving. LM     424     @5000=      2,120,000=



Wall Finishes

Cement and sand ( 1:2:9) lime plaster

trowelled smooth on brick wall or
masonry

6.03 15mm thick cement and sand plaster :

steel trowell finish to walls.                  SM        1280      @10,000=   12,800,000=



Painting

6.04 Prepare and apply one undercoat

and three finishings coats of matt

vinyl paint to

plastered surfaces.                                 SM       1280    10,000= 12,800,000=



Black Board as described:-

6.05 Provide Black board, size:

4200mm long x 1200mm highx 20mm

thick complete

with chalk rails and painted in approved b/b paint NO       16    150,000= 2,400,000=

6.06 Provide3No pin boardsin each classroom,size:

1200mm x1200mm with hard wood

timber framing to approved section design              NO    48     150,000=   7,200,000=

Total Internal Finishes Carried To Summary                                      44,840,000=




Item         Description          Unit      Quantity     Rate (Ushs) Amount (Ushs) Ugandan shillings




Bill No. 2

Element No.7
Lightning Protection

Supply, install, connect and set to

work the following, all as described in the

Specifications and Drawings.

7 .01 Copper tape of Hard Drawn High

Conductivity copper plate 3mm x 25mm cross

section for Down Conductors, bonded to

the iron sheet roof complete with fixing

clips and all accessories as by FURSE or equal.

                                                    LM           28            @ 40,000 =
1,120,000=

7 .02 Air terminals complete with Tape

Adapter and all accessories as by FURSE or

equal.                                              NO           2             @150,000=    300,000=




7 .03 Test Blocks complete as by FURSE or equal.   NO            2             @100,000=    200,000=

7 .04 Earth electrodes made from Hard drawn

copper or copper weld 20mm diameter by

1200mm in two length screwed together

complete

with cap, earth clamp, manhole

and all accessories.

                                                        NO           2   120,000=   240,000=



7 .05 50mm diameter heavy duty P.V.C pipe          LM        4       10,000=    40,000=



TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY.                                       1,900,000=
Item         Description           Unit       Quantity     Rate (Ushs) Amount (Ushs) Ugandan shillings




Bill No. 2

Element No.8

Rain Water harvest

8 .01 P.V.C downpipes 110mm diameter

complete with all fittings

nessecary for erection

(refer to drawing)                                       LM      96      @6,000=      576,000=



8 .02 P.V.C gutters complete with gutter

brackets at 1000mm c/c including all fittings

nessecary for erection                                   LM      176     @20,000=     3,520,000=



8 .03 5,000 litre pvc tank placed on ground

concrete base (measured separetely),

complete with all accessories.                           NO      1        @300,000=     300,000=



8 .04 25mm gate valves as Peglar heavy duty

or equal approved.                                        NO        1     @40,000=       40,000=



8 .05 12mm Stand by pipe, complete with

12mm bib tap and all accessories                         Item   1         @ 37,000=       37,000=

Concrete Tank Base

9 .14 1.5m high Ground concrete water

tank base, made in masonry brickwork, well

compacted hardcore, with 150mm thick

slab on top as shown in drawing, for the
above water tank, complete.

                                            NO      2       @ 1.000,000=    2,000,000=



TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY                                6,473,000=




SUMMARY        FOR    PROPOSED CONSTRUCTION OF A PRIMARY SCHOOL AT IGEL




1 SUB-STRUCTURE                                  260,452,000=

2 SUPERSTRUCTURE                                  93,724,800=

3 ROOFING                                        103,696,000=

4 DOORS AND WINDOWS                               50,416,000=

5 EXTERNAL FINISHES                                 28,992,000=

6 INTERNAL FINISHES                                 44,840,000=

7 LIGHTNING PROTECTION                                  1,900,000=

8 RAIN WATER HARVEST                                    6,473,000=



GRAND TOTAL                                        590,493,800=
BUDGET FOR PUTTING UP A SECONDARY SCHOOL 16 BLOCK OF CLASSROOMS




Item Description                        Unit    Quantity Rate(Ushs) Amount(Ushs) Ugandan shillings




             Element NO 1

          Substructure: (All Provisional)

            Site Preparation

1.01      Excavate oversite to remove

           top soil average 150mm thick and

                    remove from site.              SM      1504        @ 1000=     1;504,000=



1.02 Treat surface of subsoil or fillings and

         surroundings with approved

          chemical antitermite

solution: provide ten year guarantee.             SM      1504         @ 1000=     1,504,000=



Excavation and Earthworks.

Note: Rates for excavation to

include for keeping excavations

free from water

and planking and strutting

to sides of excavations

1.03 Excavate to reduce levels and

remove from site.                                    CM          216     @ 2000=         432,000=
1.04 Excavate trenches for wall

foundations: commencing from

reduced levels : not

exceeding 1.5m deep .                         CM    248             @4000=            992,000=



1.05 Extra over excavation for excavating

in rock                                        CM        48   30,000=         1,440,000=



Disposal of excavated material

1.06 Selected excavated material in filling

to foundation trenches : around walling :

placed in 200mm layers : watered and

compacted to 95% MDD                           CM       176 2000=          352,000=



1.07 Remove surplus excavated

material from site                             CM       128 4,000=         512,000=



Hardcore

1.08 150mm Filling : deposit, spread, level

and compact : 50mm selected quarry dust

blinding.                                          CM     752 10,000=        7,520,000=



Vibrated Insitu concrete grade 15 mix

(1:3:6 / 20mmaggregate) as described:-

1.09 Foundations in trenches                   CM       512 10,000=      5,120,000=

Vibrated reinforced concrete grade 20

mix (1:2:4 / 20mm Aggregate) as

described in :-

1.11 Ramp for the Disabled                     CM 128 150,000=           19,200,000=

1.10 100mm thick ground floor slab             SM 9600 10,000=          96,000,000=
1.12 Horizontal Ground beam                             CM 192       250,000=    48,000,000=

High yield tensile steel bar reinforcement

to BS 4449 as described including

cutting to lengths, bending, hoisting and

fixing including all necessary tying

wire and spacing blocks.

1.12 R8 bars for links                                      KG    944       3,000=   2,832,000=

1.13 Y12 bars.                                               KG      2280    4,000= 9,120,000=

Total Carried to Collection                                                          194,528,000=




Item      / Description            Unit      Quantity   Rate(Ushs)    Amount (Ushs) Ugandan shillings




Reinforcement

1.12 Mesh reinforcement Ref No.

A98 size 200 x 200 mm weighing 1.54

kg per square metre: in floor slab:

including all necessary supports                   SM      840        @ 10,000= 8,400,000=



Sawn formwork as described to:

1.13 Vertical edges of surface bed :

over 75mm but not exceeding 150 mm high.          LM      368          @ 7,500=      2,760,000=
Brickwork in burnt clay bricks in cement and

sand mortar (1:4) mix; with and

including 25 x 3mm hoop iron strips

laid horizontally every alternate course.

1.14 230 mm thick plinth walling.                    SM        488          @ 40,000=   19,520,000=



Sundries

1.15 One layer 1000 gauge polythene sheet

damp proof membrane Under bed :

300mm laps.                                           SM         840         @9,500=    7,980,000=



1.16

Allow for " Dieldrex " or other approved

anti-termite treatment in sides and bottom

of foundation trenches and ground surface

below hard-core filling( SEE ITEM

No.1.02)                                                  SM         1744    @ 8,000=    13,952,000=




Splash apron

1.17

75mm thick concrete (grade 20) splash apron on

75mm hardcore base well rammed and apron

finished with 25mm thick cement and

sand (1:3) screed trowelled smooth to gentle falls

with division strips every 2.00 metre length and

including 150mm thick clay bricks edge wall

average 500mm deep rendered on

and including 450mm x 150mm thick concrete
grade 15 foundation and all necessary excavations

and disposal of spoil and formwork to edge of apron

  Cement and Sand ( 1: 4 ) as described:-              SM   288   @36,000=         10
,368,000=




1.18 20mm thick rendering to plinth walls

Prepare and apply two coats of bituminous paint on:-   SM   184   @ 8,000=
1,472,000=

1.19 Rendered plinth walls                             SM   184   @ 8,000=
1,472,000=

Total Carried to Collection

Page E1- 1/                                                        194,528,000=

Page E1- 2/                                                          65,924,000=




Total Substructure To Summary                                     260,452,000=
Item          Description          Unit     Quantity   Rate (Ushs) Amount (Ushs) Ugandan shillings




Bill No. 2

Element No. 2

Super structure:

Vibrated Insitu reinforced concrete grade

20 mix (1:2:4 / 20mm Aggregate) as

described:-

2.01 Ring beams                                        CM     24     @400,000=     9,600,000=



Mild steel reinforcement as described including

cutting to lengths, bending, hoisting and fixing

including all necessary tying wire and

spacing blocks. hoisting and fixing including

all necessary tying wire and spacing blocks. .

2.02 8 mm diameter bar                                 KG   944      @4,000 =        3,776,000=



High yield tensile steel bar reinforcement to

BS 4449 as described including cutting to

lengths, bending, hoisting and fixing including

all necessary tying wire and spacing blocks.

2.03 12 mm diameter bar                                KG    2,280     @4,000 =      9,120,000=



Sawn formwork as described to:

2.04 Sides and soffites of beams                       SM   192        @18,000 =      3,456,000=



Damp proof courses : hessian based bituminous

felt: bedded in cement and

sand (1:3) mortar : 300mm laps.
2.05 Horizontal : 230mm ditto                    LM     416       @2,500 = 1,040,000=



Brickwork in burnt clay bricks in cement and

sand mortar (1:4) mix;with and

including 25 x 3mm hoop iron strips laid

horizontally every alternate course.

2.06 230 mm thick below ring beam walling.      SM    776     46,800= 36,316,800=



2.07 230mm Thick above ring beam and gable walling SM 272   46,800= 12,729,600=



2.08 Labour and materials in eaves filling on

230mm wall for average height of 300mm            LM 368 46,800=      17,222,400=



Permanent Vents

2.09 Permanent Vent filled in with Kajjansi

ventilation bricks or other equal and

approved; bat proof gauze and coffee tray

wire backing complete with necessary

timber framing and beading.

                                                      SM       8 58,000=     464,000=




Total Super Structure To Summary                                           93,724,800=
Item         Description            Unit   Quantity     Rate (Ushs) Amount (Ushs) Ugandan shillings




Bill No. 2

Elemnt No.3

Roof:

Roof Construction

The followings 10nos. Timber trusses each

spanning 6.46M x 1.58M rise,

comprising of well treated members bolted

together to approval as described

and hoisted and fixed in position at about 3.30M

above floor level.

Sawn cypress pressure impregnated with

Preservative:-

3.01 50 x 100mm Purlins                                 LM      1400    @10,000 =     14,000,000=

3.02 50 x 100mm Strut /tie                              LM       432    @10,000 =     4,320,000=

3.03 50 x 150mm Ridge                                    LM      144     @12,000 =    1,728,000=

3.04 50 x 150mm Tie beam                                LM       520     @ 12,000 =   6240,000=

3.05 50 x 100mm Rafters                                 LM       752     @10,000 =    7,520,000=

3.06 75 x 100mm Wall Plate                              LM       264     @12,000 =    3,168,000=

3.07 75 x 100mm overhangs                                LM      240     @12,000 =    2,880,000=



Roof Covering

3.08 28 Gauge pre-painted iron roofing sheets

fixed with 1.5 side corrugation laps and

150mm end laps with and including approved

roofing nails or galvanized steel

drive screws with plastic washers and fller biocks to

manufacturer's instructions.                               SM    1248        @38,000= 47,424,000=
3.09 28 Gauge plain (pre-coated) roll top ridge capping.   LM 1368    @ 12,000= 16,416,000=




Eaves

3.10 25 x 225mm Wrot Cypress fascia board

and badge boards                                           LM   416   @ 10,000= 4,160,000

Painting Knot prime stop and apply three coats

    of gloss oil paint to timber surfaces.



.

3.11 Knot, prime, stop and apply three coats of gloss

oil paint to wood fascia 200-

300mm girth.                                               SM   144   @ 10,000=    1,440,000=




Total Roof Carried To Summary                                            103,696,000=
Item          Description        Unit       Quantity   Rate (Ushs)   Amount (Ushs) Ugandan shillings




Bill No.1

Element No.4

Doors and Windows:

Windows

Vibrated Precast concrete grade 20

mix (1:2:4 / 20mm aggregate) : units

reinforced as necessary and finished fair

face on all exposed sides as

described:-

4.01 75 x 285 mm sunk weathered and

throated window cill       Purpose made steel

casement windows manufactured from

standard W20

sections: manufacture, assemble and deliver

to site : Supply and fix

ironmongery comprising approved hinges

, pivoting mechanisms, stays,

fasteners to opening lights: plugged and screwed

or built into walling : one

coat red oxide primer before delivery. all to           LM     160     @3000      = 3,480,000=



Architects details Purpose made steel

casement windows manufactured

from standard W20

sections: manufacture, assemble and

deliver to site : Supply and fix

4.02 Window type W1 : Size 1200 x 1200mm
overall height:                              NO    112   @250,000    = 28,000,000=



Glass and Glazing

4.03 4mm thick clear sheet glass to metal

window with putty                            SM   160    70,000= 11,200,000=



Prepare touch up primer and apply one

undercoat and two finishing coats of

gloss oil paint : on glazed metal surfaces

4.04 General Surfaces : windows              SM   320    3000=      960,000=




Total Carried to Collection                                         43,640,000=
Item          Description            Unit   Quantity Rate (Ushs)      Amount (Ugandan shillings)




Doors

Purpose made steel casement doors

manufactured from Standard W20

Sections complete as described to

Architects details

4 .05 Door size 900 x 2400mm with

permanent louvered vents 300mm

included : D1                                         NO         16     @300,000    =   4,800,000=



Prepare, knot prime, stop and apply

three coats of gloss oil paint: on

woodwork.

4.06 General surface of metal doors                 SM      72          @ 3,000    =
216,000=



Supply and fix the following approved

ironmongeries complete with

marching screws, handles and keys

to hard wood.

4.07 Tower bolt complete with Padlocks                NO    16            @ 100,000 =
1,600,000=



4.08 25mm diameter rubber door stopper.               NO    16             @10,000=
160,000 =



Total Carried to Collection 0

COLLECTION

Page E4- 4/                                                                   43,640,000=
Page E4- 5/                                                                      6,776,000=



Total Doors and Windows Carried To Summary                                    50,416,000=




Item          Description             Unit     Quantity   Rate (Ushs) Amount (Ugandan shillings)




Bill No. 2

Element No. 5

External Finishes:

Floor Finishes

Cement and sand (1:3) screeds and

pavings : one coat: steel trowell finish :

laid on concrete

5.01 30mm thick screed in the verandah          SM        160      @ 10,000    = 1,600,000=



5.02 25 x 200mm skirting with square top

edge and coved junction at bottom of paving.    LM        352      @10,000     = 3,520,000=



Cement and sand ( 1:4) render trowelled

smooth on concrete or masonry

5.03 15mm to walls.                                  SM      976    @ 10,000     = 9,760,000=



Two coats tyrolene rendering on masonry

5.04 Walls and concrete surfaces                   SM       544     @ 8.000     =   4,352,000=
Painting : 'Sadolin Paints' or equal and approved.

5.05 Prepare and apply one undercoat

and two finishing coats weaher guard on

plastered surfaces.                                        SM         432     @ 10,000       =   4,320,000=



5.06 Ditto to tyrolean surfaces.                           SM         544     @ 10,000       =   5,440,000=



Total External Walls Finishes Carried To Summary                                          28,992,000=



Item         Description                Unit         Quantity     Rate (Ushs) Amount (Ugandan shillings)




Bill No. 2

Element No.6

Internal Finishes

Floor Finishes

Cement and sand (1:3) screeds and

pavings :

one coat: steel trowell finish :

laid on concrete

6.01 30mm thick screed                                SM        752         @10,000   =     7,520,000



6.02 25 x 100mm skirting with square top

edge and coved junction at bottom of paving.         LM         424           @5000   =     2,120,000



Wall Finishes

Cement and sand ( 1:2:9) lime plaster

trowelled smooth on brick wall or

masonry
6.03 15mm thick cement and sand plaster :

steel trowell finish to walls.                  SM        1280        @ 10,000    =       12,800,000



Painting

6.04 Prepare and apply one undercoat

and three finishings coats of matt

vinyl paint to

plastered surfaces.                                 SM     1280      @10,000     = 12,800,000=



Black Board as described:-

6.05 Provide Black board, size:

4200mm long x 1200mm highx 20mm

thick complete

with chalk rails and painted in approved b/b paint NO     16       @ 150,000    = 2,400,000=

6.06 Provide3No pin boardsin each classroom,size:

1200mm x1200mm with hard wood

timber framing to approved section design            NO     48    150,000=   7,200,000=




Total Internal Finishes Carried To Summary                                        44,840,000=




Item        Description              Unit   Quantity      Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2

Element No.7

Lightning Protection

Supply, install, connect and set to

work the following, all as described in the

Specifications and Drawings.

7 .01 Copper tape of Hard Drawn High

conductivity copper plate 3mm x 25mm cross

section for Down Conductors,bonded to

the iron sheet roof complete with fixing

clips and all accessories as by FURSE or equal.

                                                    LM           28      40,000=     1,120,000=

7 .02 Air terminals complete with Tape

Adapter and all accessories as by FURSE or

equal.                                              NO           2       150,000=    300,000=

7 .03 Test Blocks complete as by FURSE or equal.   NO        2       100,000=      200,000=

7 .04 Earth electrodes made from Hard drawn

copper or copper weld 20mm diameter by

1200mm in two length screwed together

complete

with cap, earth clamp, manhole

and all accessories.

                                                        NO           2    120,000=    240,000=

7 .05 50mm diameter heavy duty P.V.C pipe          LM        4       10,000=       40,000=




TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY.                                                1,900,000=
Item         Description           Unit         Quantity    Rate (Ushs)    Amount (Ugandan shillings)




Bill No. 2

Element No.8

Rain Water harvest

8 .01 P.V.C downpipes 110mm diameter

complete with all fittings

nessecary for erection

(refer to drawing)                                   LM        96         @ 6,000   =   576,000=



8 .02 P.V.C gutters complete with gutter

brackets at 1000mm c/c including all fittings

nessecary for erection                               LM        176        @20,000   =   3,520,000=



8 .03 5,000 litre pvc tank placed on ground

concrete base (measured separetely),

complete with all accessories.                       NO        1           @300,000=     300,000=



8 .04 25mm gate valves as Peglar heavy duty

or equal approved.                                     NO          1       @ 40,000=        40,000=
8 .05 12mm Stand by pipe, complete with

12mm bib tap and all accessories                Item        1                 @ 37,000=          37,000=

Concrete Tank Base

9 .14 1.5m high Ground concrete water

tank base, made in masonry brickwork, well

compacted hardcore, with 150mm thick

slab on top as shown in drawing, for the

above water tank, complete.

                                                       NO         2                @ 1000,000=
2,000,000=



TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY                                               6,473,000=




SUMMARY FOR           PROPOSED         CONSTRUCTION OF A SECONDARY SCHOOL AT IGEL




1 SUBSTRUCTURE                                              260,452,000=

2 SUPERSTRUCTURE                                                93,724,800=

3 ROOFING                                                   103,696,000=

4 DOORS AND WINDOWS                                             50,416,000=

5 EXTERNAL FINISHES                                              28,992,000=

6 INTERNAL FINISHES                                              44,840,000=

7 LIGHTNING PROTECTION                                                1,900,000=
8 RAIN WATER HARVEST                                        6,473,000=




GRAND TOTAL                                             590,493,800=




BUDGET FOR THE PROPOSED CONSTRUCTION OF 5 STANCE DRAINABLE PIT LATRINE
FOR BOTH THE PRIMARY ,HEALTH CENTRE AND SECONDARY SCHOOL AT IGEL KOLE
                                DISTRICT.



Item        Description        Unit    Quantity    Rate [Ushs) Amount [ Ugandan shillings)




BILL No 5

ELEMENT NO 1

SUBSTRUCTURE



(All Provisional)

Site Preparation

1.01 Excavate oversite

to remove top

soil average 150mm thick and

remove from site.                 SM              51            @ 1000 =     51,000=
1.02 Treat surface of subsoil or

fillings and surroundings with

approved chemical

anti-termite solution:

provide ten year guarantee.               SM         51                @300=      15,300=



Excavation and Earthworks.

Note: Rates for excavation to include

for keeping excavations free

from water and planking

and strutting to sides of excavations

1.03 Excavate to reduce levels

and remove from site.                          CM     15            @ 10,000=      150,000=



1.04 Excavate pit including all

earth work support and keeping

excavations free from water

and mud up to 1.5m                             CM         N/A

1.05 Ditto but up to 3m                        CM         22       @ 30,000=     660,000=



1.06 Ditto but up to 4m                        CM         N/A

1.07 Extra over excavation

for excavating in rock                          CM             5   @30,000=     150,000=



Disposal of excavated material

1.08 Selected excavated material

in filling to foundation trenches :

around walling : placed in 200mm layers

: watered and compacted to 95% MDD             CM         3        @30,000=     90,000=
1.09 Remove surplus excavated

material from site                               CM      43        @ 20,000=      860,000=



1.10 150mm Filling : deposit, spread,

level and compact : 50mm selected

quarry dust blinding.                              SM     22       @5,000=        110,000=



Insitu concrete grade 20

mix (1:2:4 / 20mm aggregate) as described:-

1.11 150mm thick pit floor bed using

mix 1:2:4 mass concrete                             CM        2       @200,000=     400,000=



1.12 230x 230mm columns and

beams mix 1:2:4/19mm                                CM        3       @400,000=     1,200,000=



1.13 100mm thick reinforced suspended floor

slab using mix 1:2:4 concrete.                      SM        13      @30,000=        390,000=



Total Carried to Collection                                                       4,476,300=




Item        Description                Unit   Quantity   Rate Ushs)    Amount Ugandan shillings)
Vibrated Insitu reinforced

concrete grade 20

mix (1:2:4 / 20mm aggregate)

as described:-

1.14 100mm thick slab in verandah    SM             12            @30,000=      360,000=



1.15 Ramp for the Disabled            CM                 1        @200,000=      200,000=



Reinforcement

1.16 Mesh reinforcement

Ref No. A98 size 200 x 200 mm

weighing 1.54 kg per square metre:

in floor slab:

including all necessary supports      SM            21            @20,000=       440,000=



Mild steel rod reinforcement

as described.

1.17 8 mm diameter bar                    KG         52            @3000=          156,000=



High yield tensile steel bar

reinforcement to

BS 4449 as described.

1.18 12 mm diameter bar                   KG         121           @ 4000=          484,000=

Sawn formwork as described to:

1.19 230x230mm columns: over

75mm but not exceeding 150

mm high.                                       LM            50      @10,000=         500,000=



1.20 Sides of the pit ringbeam

300mm wide: over 75mm but
not exceeding 150 mm high.               LM         8             @10,000=        80,000=

1.21 Soffit of 100mm thick slab:

over 75mm but not exceeding

150 mm high.                              SM         25        @ 20,000=       500,000=

1.22 Edge of slab 100mm high:

over 75mm but not

exceeding 150 mm high.                   LM         25         @10,000=       250,000=



Brickwork in burnt clay bricks

in cement and sand mortar (1:3) mix;

with and including 25 x

3mm hoop iron strips laid

horizontally every alternate course.

1.23 230 mm thick plinth walling.        SM         45        @46,800=       2,106,000=



1000 gauge vertical DPM SM 50 0

Finishes to the pit

1.24 15mm cement and sand

(1:4 mix) trawelled smooth and

hard using water resistant

cement additive.                              SM     53       10,000=         530,000=



1.25 25mm cement,sand screed finished

smooth to a gentle slope                      SM    23        10,000=        230,000=



Vent pipe

1.26 Supply and fix 3No 100mm diameter

uPVC vent pipes 3.5m long with

fly screen at the top complete

with mosquito wire netting.                    LM        11     10,000=      110,000=
Total Carried to Collection

Splash apron

1.27

75mm thick concrete (grade 20)

splash apron on 75mm hardcore

base well rammed and apron

finished with 25mm thick cement

and sand (1:3) screed trowelled

smooth to gentle falls with division

strips every 2.00 metre length and

including 150mm thick clay bricks edge

wall average 500mm deep

rendered on and including

450mm x 150mm thick concrete grade 15

foundation and all necessary

excavations and disposal of spoil and



formwork to edge of apron                SM   11   @ 30,000=    330,000=




Total Carried to Collection                                    6,276,000=
Item Description Unit Quantity Rate

(Ushs)

Amount

(Ushs)

COLLECTION

Page E1- 1/                                                4,476,300=

Page E1- 2/                                                 6,276,000=

TOTAL SUBSTRUCTURE CARRIED TO SUMMARY                          10,752,300=




 Item         Description             Unit   Quantity      Rate Ushs)    Amount Ugandan
shillings)




ELEMENT NO. 2

SUPER STRUCTURE

Vibrated Insitu reinforced

concrete grade 20 mix

(1:2:4 / 20mm Aggregate)

as described:-

2.01 Ring beams                        CM       1       @400,000=            400,000=



Mild steel reinforcement as

described including cutting to

lengths, bending, hoisting and
fixing including all necessary

tying wire and spacing blocks.

2.02 8 mm diameter bar                   KG        30        @ 3,000=    90,000=



High yield tensile steel bar

reinforcement to BS 4449 as

described including cutting to

lengths, bending, hoisting and

fixing including all necessary

tying wire and spacing blocks.

2.03 12 mm diameter bar                  KG        88        @4,000=     352,000=



Sawn formwork as described to:

2.04 Sides and soffites of beams         SM        14         @10,000=    140,000=



Damp proof courses : hessian based

bituminous felt: bedded in cement

and sand (1:3) mortar : 300mm laps.

2.05 Horizontal : 200mm ditto             LM            28   @ 2500=      70,000=



Brickwork in burnt clay bricks

in cement and sand mortar

(1:3) mix;with and including 25 x

3mm hoop iron strips laid horizontally

every alternate course.

2.06 230mm thick below

ring beam walling.                            SM        49    @46,800=   2,293,200=



2.07

Labour and materials in eaves
filling on 230mm wall for average

height of 300mm                            LM         32       @10,000=              320,000=



Permanent Vents

2.08 Permanent Vent filled in with

Kajjansi ventilation bricks or other

equal and approved; bat proof gauze

and coffee tray wire backing complete

with necessary timber

framing and beading.                       SM         1      @60,000=           60,000=

Disability Handrail

2.08 Provide handrials for the disabled

comprised of 35mm diameter

MS grip bars for the diasbled

complete installed to architects details   Item   1        150,000=       150,000=



TOTAL SUPER STRUCTURE CARRIED TO SUMMARY                                         3,875,200=

…………………………………………………………………………………………………………………
…………………………….
Item        Description          Unit   Quantity   Rate Ushs)     Amount Ugandan shillings)




ELEMENT NO. 3

ROOF

Roof Construction

The following in roof

construction including all

bolting, gusset plates, fixing

trusses to ring

beams with holding down bolts

and hoisting and fixing

approximately 3.0mm above ground

level.

Sawn cypress pressure impregnated

with preservative:-

3.01 50 x 100mm Purlins                 LM    20      @10,000=        200,000=

3.02 50 x 150mm Rafters                 LM    11      @12,000=        132,000=

3.03 75 x 100mm Wall Plate              LM    13      @ 12,000=       144,000=

Roof Covering

3.04 28 Gauge pre-painted iron

roofing sheets fixed with 1.5 side

corrugation laps and 150mm end laps

with and including approved

roofing nails or galvanized

steel drive screws with

plastic washers to

manufacturer's instructions.            SM    18    @ 38,000=       684,000=
Eaves

3.05 25 x 225mm Wrot

Cypress fascia board Painting                  LM   18   @15,000=   270,000=




Painting

Knot prime stop and apply three

coats of gloss oil paint to timber surfaces.

3.06 Knot, prime, stop and apply

three coats of gloss oil paint to

wood fascia 200-300mm girth.                   SM   9    @10,000=       90,000=




TOTAL ROOF CARRIED TO SUMMARY                                           1,520,000=
Item        Description           Unit    Quantity        Rate Ushs)      Amount Ugandan shillings)




ELEMENT NO. 4

DOORS

Doors

Purpose made steel casement

doors manufactured from

Standard W20

Sections complete as

described to Architects details

4.01 Door size 900 x 2400mm

with permanent louvered vents

300mm included.                          NO           6        200,000=     1,200,000=



Prepare, knot prime, stop

and apply three coats of

gloss oil paint: on metal

4.02 General Surfaces : doors            SM          23        3,000=         69,000=



Supply and fix the following

approved ironmongeries complete

with marching screws,

handles and keys to hard wood.

4.03 Tower bolt complete

with Pudlocks                                 NO          6   30,000=           180,000=




TOTAL DOORS AND WINDOWS CARRIED TO SUMMARY                                              1,449,000=
Item         Description         Unit        Quantity        Rate Ushs)   Amount Ugandan shillings)




ELEMENT NO. 5

EXTERNAL FINISHES

Floor Finishes

Cement and sand (1:3) screeds

and pavings : one coat:

steel trowell finish :

laid on concrete

5.01 30mm thick screed in

the verandah aand ramps                 SM         15         @10,000=          150,000=



5.02 25 x 200mm skirting with

square top edge and coved

junction at bottom of paving.           LM          6         @ 5000=            30,000=



Cement and sand ( 1:4) render

trowelled smooth on

concrete or masonry

5.03 15mm to walls.                          SM         56    @10,000=         560,000=



Two coats tyrolene rendering

on masonry

5.04 Walls and concrete surfaces         SM         56        @5000=          280,000=



Painting : 'Sadolin Paints' or
equal and approved.

5.05 Prepare and apply one

undercoat and two finishing coats

weather guard paint

on plastered surfaces.                 SM         15     @10,000=           150,000=

5.06 Ditto to tyrolean surfaces       Item       56     10,000=         560,000=

5.07 Supply and fix to position

standard engraved foundation

stones from approved product

from either

slates or marbles or terrazzo

to engineer's details.                Item        1     150,000=        150,000=




TOTAL EXTERNAL WALLS FINISHES CARRIED TO SUMMARY                               1,880,000=




Item          Description           Unit     Quantity   Rate Ushs)   Amount Ugandan shillings)




ELEMENT NO. 6

INTERNAL FINISHES

Floor Finishes

Cement and sand (1:3) screeds

and pavings : one coat:
steel trowell finish :

aid on concrete

6.01 30mm thick screed                SM        11        @10,000=     110,000=



6.02 25 x 200mm skirting with

square top edge and coved junction

at bottom of paving.                  LM        27        @ 5,000=      135,000=



Wall Finishes

6.03 15mm thick cement and

sand plaster : steel trowell finish

to walls.                                  SM        55    @ 10,000=         550,000=



Painting

6.04 Prepare and apply one

undercoat and three finishings

coats matt vinyl paint to

plastered surfaces.                    SM        55        @10,000=      550,000=




TOTAL INTERNAL FINISHES CARRIED TO SUMMARY                      1,345,000=      Ugandan shillings

…………………………………………………………………………………………………………………
……………………….
ELEMENT NO. 7

WATER SUPPLY

Supply, install, connect and

set to work the following,

all as described in the Specifications

and Drawings.

Water Supply

7.01 250 litre uPVC tank placed on

ground concrete base

(measured separately ) ,complete

with lockable

tap and washout approved                          NO        1       @500,000=     500,000=



7.03 Install 4"PVC pipe with approved

floor trap to urinal, including splash

apron for hand washing tanks                       NO       3        @50,000=     150,000=



7.04

1m high ground concrete water

tank base made in masonry brickwork,

well compacted with 150mm

thick slab on top as directed on site

for the tanks as above complete

with 1x1m spash apron,

concealed drain pipe and soakaway

complete

.(inc. metallic lockable burgler proffing metallic grills

engraved in concrete for protecting the tank)         NO        1     @500,000=   500,000=
7.05 Provive sock away pit size 1.5m

diameter and 1.2m depth complete

with drain pipe/floor trap from

urinal or wash room.                   Item   1   100,000=




TOTAL WATER SUPPLY CARRIED TO SUMMARY.                1,250,000=
BILL No 5




  SUMMARY FOR PROPOSED CONSTRUCTION OF1 BLOCK OF 5 STANCE VIP LATRINE IN
                      SCHOOL IN IGEL KOLE DISTRICT

1 SUBSTRUCTURE                                       10,752,300=

2 SUPERSTRUCTURE                                      3,875,200=

3 ROOFING                                             1,520,000=

4 DOORS                                               1,449,000=

5 EXTERNAL FINISHES                                     1,880,000=

6 INTERNAL FINISHES                                     1,345,000=

7 WATER SUPPLY                                         1,250,000=




FIVE STANCE VIP LATINE TOTAL TO SUMMARY FOR

PRIMARY HEALTH CENTRE AND SECONDARY WE MULTIPLY FUGURE X3
22,071,500= x 3
BUDGET FOR THE PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE
                                   DISTRICT.




Item       Description              Unit        Quantity     Rate [Ushs)   Amount [Ugandan shillings)




ELEMENT NO 1

SUBSTRUCTURE (All Provisional)

Site Preparation

1.01 Excavate over site to remove

Top soil average 150mm thick and

Remove from site.                      SM              324      @1,000=    324,000=



1.03 Treat surface of subsoil or

1.04 fillings and surroundings

1.05 with approved

1.06 chemical anti-termite

Solution: provide

Ten year guarantee.                        SM          324      @ 1,000=    324,000=



Excavation and Earthworks.

Note: Rates for excavation to
Include for keeping excavations

Free from water

And planking and strutting to

Sides of excavations

1.03 Excavate to reduce levels

And remove from site.                      CM         54        @5,000=          270,000=



1.04 Excavate trenches for wall

Foundations: commencing

From reduced levels: not

Exceeding 1.5m deep.                       CM         81        @ 5,000=            405,000=

1.05 Extra over excavation

For excavating in rock                      CM         5          @30,000=            150,000=



Disposal of excavated material

1.07 Selected excavated material

1.08 in filling to foundation trenches :

1.09 around walling :

Placed in 200mm layers: watered and

Compacted to 95% MDD                            CM         60         @ 5,000=          300,000=



1.07 Remove surplus excavated

material from site                          CM         11             @20,000=         220,000=



Hardcore

1.08 150mm Filling: deposit, spread,

Level and compact: 50mm selected

Quarry dust

Blinding.                                        SM             324     @ 5,000=        1,620,000=

Vibrated Insitu concrete grade 15
Mix (1:3:6 / 20mm aggregate) as described:-

1.09 Foundations in trenches                  CM          14       @200,000=       2,800,000=



Vibrated reinforced concrete grade 20

Mix (1:2:4) as described in :-

1.10 100mm thick ground floor slab            SM          105      @ 30,000=      3,150,000=



1.11 Ramp for the Disabled                     SM          9        @30,000=       270,000=



Total Carried to Collection                                                      9,833,000=




Item              Description        Unit      Quantity        Rate Ushs)      Amount Ushs)




Reinforcement

1.12 Mesh reinforcement

Ref No. A98 size 200 x 200 mm

weighing 1.54 kg per square

metre: in floor slab: including

all necessary supports                  SM           95         @11,500=    1,092,500=



Sawn formwork as described to:
1.13 Vertical edges of surface bed:

over 75mm but not exceeding

150 mm high.                          LM        44        @ 7,500=   330,000=



Brickwork in burnt clay bricks in

Cement and sand mortar (1:4) mix;

With and

Including 25 x 3mm hoop iron

strips laid horizontally

every alternate course.

1.14 230 mm thick plinth walling.     SM        88        @46,800=   4,118,400=



Sundries

1.15 One layer 1000 gauge

polythene sheet damp proof

membrane Under bed : 300mm

laps.                                      SM        95    @5,000=      475,000=



1.16

Allow for " Dieldrex " or other

approved anti-termite treatment

in sides and bottom

of foundation trenches and

ground surface below

hard-core filling(SEE ITEM

No.1.02)                                   SM    335       @300= 100,500=



Splash apron

1.17

75mm thick concrete (grade 20)
splash apron on 75mm

hardcore base well

rammed and apron finished

with 25mm thick cement

and sand (1:3) screed

trowelled smooth to gentle

falls with division strips every 2.00

metre length and

Including 150mm thick concrete

Block edge wall average 500mm

Deep rendered on

And including 450mm x 150mm thick

Concrete grade 15 foundation and all

necessary excavations and disposal

of spoil and formwork to edge of apron     SM        27    30,000=       810,000=



 Cement and Sand ( 1: 4 ) as described:-

1.18 Plinth Rendering                       SM            19    10,000=     190,000=



Prepare and apply two coats of

bituminous paint on:-

1.19 Rendered plinth walls                      SM    19       10,000=    190,000=



Total Carried to Collection                                                7,306,400=




COLLECTION

Page E1- 1/                                                                 9,833,000=

Page E1- 2/                                                                 7,306,400=
TOTAL SUBSTRUCTURE TO SUMMARY                                                   17,139,400=




ELEMENT       NO. 2

SUPER STRUCTURE

Insitu concrete grade 20 / 20mm:

Vibrated, reinforced as described

2.01 Ring beams                              CM     6        @400,000=      2,400,000=



Mild steel reinforcement as described

including cutting to lengths, bending,

hoisting and fixing including all

necessary tying wire and spacing blocks.

2.02 8 mm diameter bar                       KG    107        @ 3,000=        321,000=



High yield tensile steel bar reinforcement

to BS 4449 as described including

cutting to lengths, bending, hoisting and

fixing including all necessary tying

wire and spacing blocks.

2.03 12 mm diameter bar                      KG         263      @4,000=       1,052,000=



Sawn formwork as described to:

2.04 Sides and soffites of beams             SM         42     @ 10,000=       420,000=

Damp proof courses : hessian based

bituminous felt: bedded in cement and

sand (1:3) mortar : 300mm laps.

2.05 Horizontal : 200mm ditto                 LM         99      @ 2,500=        247,500=



Brickwork in burnt clay bricks in cement
and sand mortar (1:4) mix;with and

including 25 x 3mm hoop iron strips laid

horizontally every alternate course.

2.06 230 mm thick below ring beam walling.           SM        233    @46,800=       10,904,400=



2.07 230mm Thick above ring

beam and gable walling                                    SM     73       @46,800=     3,416,400=



2.08 Labour and materials in eaves filling

on 230mm wall for average height of 300mm             LM         77       @5,000=      385,000=

Permanent Vents

2.09

Permanent Vent filled in with Kajjansi ventilation

bricks or other equal and

approved; bat proof gauze and coffee tray

wire backing complete with necessary

timber framing and beading.

                                                                 SM   1      @ 60,000=       60,000=




TOTAL SUPER STRUCTURE TO SUMMARY                                                      19,206,300=
Ugandan shillings
Item          Description           Unit        Quantity    Rate Ushs)    Amount Ugandan shillings)




ELEMENT NO. 3

ROOF

Roof Construction

The followings 06nos. Timber

trusses each spanning

8.12M x 1.98M rise,

comprising of well treated

members bolted together to

approval as described

and hoisted and fixed in position

at about 3.30M above floor level.

Sawn cypress/ pine pressure

impregnated with preservative:-

3.01 50 x 100mm Purlins                    LM        145   @ 10,000=     1,450,000=

3.02 50 x 100mm Strut /tie             LM           130    @10,000=      1,300,000=

3.04 50 x 150mm Tie beam                   LM       155    @ 12,000=      1,860,000=

3.05 50 x 100mm Rafters                    LM       120    @10,000=       1,200,000=

3.06 75 x 100mm Wall Plate                 LM        55    @12,000=         144,000=



Roof Covering

3.07

28 Gauge pre-painted iron roofing

sheets fixed with 1 ½ side

corrugation laps and

150mm end laps with and including
filler blocks at the ridges, approved roofing

nails or galvanized steel drive screws

with plastic washers to manufacturer's

instructions.

                                                 SM    166       @38,000=    6,308,000=

3.08 28 Gauge plain (pre-coated)

roll top ridge capping.                         LM    22        @12,000=     264,000=



Eaves

3.09 25 x 225mm Wrot Cypress/ pine fascia

board                                            LM        61    @15,000=     915,000=



3.10 100 x 50 mm wrot cypress or pine

in fascia and badge board carriers              LM    61     @15,000=       915,000=



Painting

Knot prime stop and apply three coats

of gloss oil paint to timber surfaces.

3.11 Knot, prime, stop and apply three coats

of gloss oil paint to wood fascia 200-

300mm girth.                                     SM        26     @7500=      195,000=




TOTAL ROOF CARRIED TO SUMMARY                                                 14,551,000=
Ugandan shillings
Item           Description             Unit         Quantity   Rate Ushs)   Amount Ugandan shillings)




ELEMENT NO. 4

DOORS AND WINDOWS

Windows

Precast concrete grade 25 / 20mm

]aggregate : units reinforced

as necessary

and finished fair face on

all exposed sides.

4.01 75 x 285 mm sunk weathered

and throated window cill                      LM        11     @55,000=        605,000=



Purpose made steel casement

windows manufactured from

standard W20

sections: manufacture, assemble

and deliver to site : Supply and fix

ironmongery comprising

approved hinges, pivoting

mechanisms, stays,

fasteners to opening lights:

plugged and screwed or

built into walling : one

4.02 Window type W1 :

Size 1500 x 1500mm overall height:             NO         6    @300,000=      1,800,000=
4.04 Window type W3 :

Size 900 x 900mm overall height:             NO         2       200,000=            400,000=

Burglar proofing grille comprising

12mm square bars 150mm centres both

ways in cobweb pattern as described.

4.06 Window type W1 :

Size 1500 x 1500mm overall height:                NO        6       150,000=      900,000=



4.08 Window type W3 :

Size 900 x 900mm overall height:                  NO        2        100,000=      200,000=

Glass and Glazing

4.10 4mm thick clear sheet glass to metal

window with putty                                  SM           9        78,000     702,000=



4.11 Ditto but obscure glass                       SM           2        78,000    156,000=

Prepare touch up primer and apply one

undercoat and two finishing coats of

gloss oil paint : on glazed metal surfaces

4.12 General Surfaces : windows                    SM               24    3000=     72,000=

Total Carried to Collection                                                         4,835,000= Ugandan
shillings
Item           Description       Unit        Quantity       Rate Ushs)    ( Amount Ugandan shillings)




Doors

Wrot Mahogany : selected and

kept clean.

4.13

Supply and fix 1.5mm thick

metallic door frame (Jamb profile)

size:900 x2400mm

comprising 300mm high lourved

vent for full width.door

shutter size 800 x2100mm                NO          6       @ 200,000=        1,200,000=



all to Architects details

Purpose made steel casement

doors (including frames)

manufactured from

Standard W20 Sections

complete as described to

Architects details

4.15 Door size 1200 x 2400mm with

permanent louvered vents 300mm

included.(D1)                            NO             2     @500,000=          1,000,000=



4.16 Door size 900 x 2400mm with

permanent louvered vents
300mm included.(D2)                        NO             2           @400,000=       800,000=



Prepare, knot prime, stop and

apply three coats of gloss oil paint: on

woodwork.

4.17 General Surfaces : doors              SM             23           @ 3000=         69,000=



4.18 Ditto but general surface

of metal doors                              SM                9         @ 3000=         27,000=

Supply and fix the following approved

Ironmongeries complete with marching

screws, handles and keys to hard wood.

4.19 4 - Lever mortice lock as for Union

England ( or Italy ) specially

made for external Casement door.           NO             2           @200,000=      400,000=



4.20 3-lever mortise lock Code No. 2277     NO            8           @ 100,000=     800,000=

4.21 25mm diameter rubber door stopper. NO            8               @10,000=       80,000=

4.22 Supply and fix purpose made steel

door frames in jamb

profile 1.5mm thick all to

Architects detail                                NO               6     @ 200,000=     1,200,000=



Total Carried to Collection

COLLECTION

Page E4- 4/                                                                           4,835,000=

Page E4- 5/                                                                                 5,576,000=

TOTAL DOORS AND WINDOWS TO SUMMARY                                                     10,411,000=
Ugandan shillings
Item Description            Unit       Quantity         Rate Ushs)        Amount Ugandan shillings)




ELEMENT NO. 5



EXTERNAL FINISHES

Floor Finishes

Cement and sand (1:3) screeds

and pavings : one coat:

steel trowell finish :

laid on concrete

5.01 30mm thick screed in

the verandah                           SM         6         @ 10,000=      60,000=



5.02 25 x 200mm skirting with square

top edge and coved junction at

bottom of paving.                       LM        10         @5000=         50,000=



Cement and sand ( 1:4) render

trowelled smooth on

concrete or masonry

5.03 15mm to walls.                      SM           129      @10,000=      1,290,000=



Two coats tyrolene

rendering on masonry

5.04 Walls and concrete surfaces         SM           128       @10,000=     1,280,000=
Painting : 'Sadolin Paints' or

equal and approved.

5.05 Prepare and apply one undercoat

and two finishing coats

of weather guard on

plastered surfaces.                              SM      129    @ 10,000=   1,290,000=

5.06 Ditto to tyrolean surfaces                  SM      128     @10,000=   1,280,000=



TOTAL EXTERNAL FINISHESTO SUMMARY                                                  5,250,000=
Ugandan shillings




Item             Description      Unit        Quantity   Rate Ushs)   (Amount Ugandan shillings)




ELEMENT NO. 6

INTERNAL FINISHES

Floor Finishes

Cement and sand (1:3) screeds

and pavings : one coat: steel

trowell finish :

laid on concrete

6.01 30mm thick screed                   SM         78   @ 10,000=       780,000
6.02 25 x 200mm skirting with

square top edge and coved junction

at bottom of paving.                    LM              97      @ 5000=              485,000=



Wall Finishes

6.03 15mm thick cement and sand

plaster : steel trowell finish to walls. SM         270      @ 10,000=           2,700,000=



Painting

6.04 Prepare and apply one

undercoat and three finishings coats

of matt vinyl paint to

plastered surfaces.                           SM          270     @10,000=        2,700,000=



Ceiling Finishes

6.05 9 x 24 SWG galvanized expanded

metal lathing U-nailed to timber

branderings                                    SM            78         @5000=          780,000=



6.06 Cement and sand (1:4)

pricking course to metal lathing               SM               78        @10,000=        780,000=

6.07 12mm cement and sand plaster

to ceiling                                          SM            78     @ 10,000=       780,000=



6.08 Extra for 150 x 15mm thick

cement and sand cornice                            LM             120      @5,000=       600,000=

Pressure impregnated sawn Cypress

6.09 50 x 100mm branderings                        LM             140       @2000=        280,000=

6.10 50 x 100mm joists                              LM            153      @ 2000=       306,000=
Prepare and apply three coats of first

grade emulsion paint on:.

6.11 Plastered ceiling                            SM         78      @   10,000=    780,000=

6.12 Cornice : Over 100 but

not exceeding 200mm girth.                         LM        120      @ 2000=       240,000=



TOTAL INTERNAL FINISHES TO SUMMARY.                                                10,431,000=
Ugandan Shilling




Item            Description           Unit   Quantity   Rate Ushs)   { Amount in Ugandan shillings)




ELEMENT NO. 7

LIGHTNING PROTECTION

Supply, install, connect and set to

work the following, all as

described in the

Specifications and Drawings.

Lightning Protection.

7.01

Copper tape of Hard Drawn High

conductivity copper plate
3mm x 25mm cross

section for Down Conductors,

bonded to the iron sheet roof

complete with fixing

clips and all accessories as by

FURSE or equal.                     LM        21       @ 40,000=     840,000=



7 .02 Air terminals complete with

Tape Adapter and all

accessories as by FURSE or

equal.                               NO        2       @150,000=      300,000=



7 .03 Test Blocks complete

as by FURSE or equal.                NO        2       @100,000=     200,000=



7 .04

Earth electrodes made from Hard

drawn copper or copper weld 20mm

diameter by

1200mm in two length screwed

together complete with cap,

earth clamp, manhole

and all accessories.

                                         NO        2    @ 120,000=     240,000=



7.05 50 mmm diameter heavy

duty P.V.C pipe                          LM        4    @ 10,000=       40,000=
TOTAL ELECTRICAL INSTALLATION SUMMARY.                                 1,620,000= Ugandan Shilling




Item           Description                      Unit   Quantity Rate (Ushs) Amount(Ushs)




Bill No. 2

Element No.8

Rain Water harvest

8 .01 P.V.C downpipes 110mm diameter

complete with all fittings

nessecary for erection

(refer to drawing)                                LM       96    @6,000=      576,000=

8 .02 P.V.C gutters complete with gutter

brackets at 1000mm c/c including all fittings

nessecary for erection                            LM       176    @20,000=   3,520,000=



8 .03 5,000 litre pvc tank placed on ground



concrete base (measured separetely),
complete with all accessories.                NO     1           @ 300,000=   300,000=



8 .04 25mm gate valves as Peglar heavy duty

or equal approved.                            NO         1       @40,000=        40,000=



8 .05 12mm Stand by pipe, complete with

12mm bib tap and all accessories              Item   1           @ 37,000=       37,000=



Concrete Tank Base

8 .06 1.5m high Ground concrete water

tank base, made in masonry brickwork, well

compacted hardcore, with 150mm thick

slab on top as shown in drawing, for the

above water tank, complete.

                                                     NO      2     @ 1000,000=     2,000,000=




TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY                                        6,473,000=
Ugandan Shilling
Bill No.6



    SUMMARY OF PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE
                              DISTRICT




1 - SUB-STRUCTURE                                17,139,400=

2 -SUPERSTRUCTURE                               19,206,300=

3 -ROOFING                                      14,551,000=

4 -DOORS AND WINDOWS                            10,411,000=

5 -EXTERNAL FINISHES                               5,250,000=

6 - INTERNAL FINISHES                            10,431,000=

7 - LIGHTNING PROTECTION                           1,620,000=

8 - RAIN WATER HARVEST                             6,473,000=



GRAND TOTAL                                85,081,700   Ugandan Shilling

Weitere ähnliche Inhalte

Ähnlich wie McsfBudget

350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNAkshika Mahanama
 
Structural Design
Structural DesignStructural Design
Structural DesignVj NiroSh
 
Design ppt
Design pptDesign ppt
Design ppttishu001
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdfMutha Morgan
 
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkkskIntze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkkskKrish Bhavsar
 
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsMagdel Kotze
 
BSR - 2021 - Kiliinochchi - District
BSR - 2021 - Kiliinochchi - District BSR - 2021 - Kiliinochchi - District
BSR - 2021 - Kiliinochchi - District Vj NiroSh
 
BSR - 2021 - Mullaitivu - District
BSR - 2021 - Mullaitivu - District BSR - 2021 - Mullaitivu - District
BSR - 2021 - Mullaitivu - District Vj NiroSh
 
onw way slab design
onw way slab designonw way slab design
onw way slab designPalak Patel
 

Ähnlich wie McsfBudget (20)

footing design
footing designfooting design
footing design
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
RR Nagar
RR NagarRR Nagar
RR Nagar
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
 
Structural Design
Structural DesignStructural Design
Structural Design
 
Design ppt
Design pptDesign ppt
Design ppt
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdf
 
Intze Tank.ppt
Intze Tank.pptIntze Tank.ppt
Intze Tank.ppt
 
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkkskIntze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
 
Bo q for shelter
Bo q  for shelterBo q  for shelter
Bo q for shelter
 
Harshal
HarshalHarshal
Harshal
 
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
 
BSR - 2021 - Kiliinochchi - District
BSR - 2021 - Kiliinochchi - District BSR - 2021 - Kiliinochchi - District
BSR - 2021 - Kiliinochchi - District
 
BSR - 2021 - Mullaitivu - District
BSR - 2021 - Mullaitivu - District BSR - 2021 - Mullaitivu - District
BSR - 2021 - Mullaitivu - District
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
6.pptx
6.pptx6.pptx
6.pptx
 

Kürzlich hochgeladen

Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 

Kürzlich hochgeladen (20)

Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 

McsfBudget

  • 1. MASSAJA CHILDREN SUPPORT FOUNDATION BUDGET SUMMARY FOR PUTTING UP PRIMARY SCHOOL, SECONDARY SCHOOL, AND THE HEALTH CENTRE ITEMISED BUDGET 1. PRIMARY SCHOOL COMPLETE WITH DOUBLE STREAMS ………………………{ $ 239,357 USD} 2. SECONDAYSCHOOL, COMPUTER LAB, LIBRARY,……………………….. { $ 239,357 USD } 3. HEATH CENTRE FOR THE COMMUNITY,……. …………………….…….… { $ 34,488 USD } 4. 5 STANCE DRAINABLE PIT LATRINE FOR THE PRIMARY SCHOOL, SECONDARY SCHOOL, AND THE HEALTH CENTRE R ESPCTIVELY………………………… X3 { $ 26,840 USD} GRAND TOTAL ………………………………………… $ 540,042 USD
  • 2. ACCOUNTABILITY IN DETAIL THAT MAKES UP THE ABOVE AMOUNT The above budget is well detailed and accounted for below how it sums up to a grand total that you see above in US dollar. Below each item and material that will be used at the entire project is well detailed. The price is in local currency the {Ugandan Shilling} of which the Exchange rate is …………….. 1 US dollar = 2,467 Ugandan shillings ACCOUNTABILITY BUDGET FOR THE PRIMARY SCHOOL OF 16 BLOCK OF CLASSROOMS IN LOCAL CURRENCY Item Description Unit Quantity Rate(Ushs) Amount(Ugandan shillings) Element NO 1 Substructure: (All Provisional) Site Preparation 1.01 Excavate oversite to remove top soil average 150mm thick and remove from site. SM 1504 @ 1000= 1;504,000= 1.02 Treat surface of subsoil or fillings and Surroundings with approved Chemical ant termite
  • 3. solution: provide ten year guarantee. SM 1504 @ 1000= 1,504,000= Excavation and Earthworks. Note: Rates for excavation to include for keeping excavations free from water and planking and strutting to sides of excavations 1.03 Excavate to reduce levels and Remove from site. CM 216 @ 2000= 432,000 1.04 Excavate trenches for wall Foundations: commencing from Reduced levels: not exceeding 1.5m deep . CM 248 @ 4000= 992,000= 1.05 Extra over excavation for excavating in rock CM 48 @ 30,000= 1,440,000= Disposal of excavated material 1.06 Selected excavated material in filling to foundation trenches : around walling : placed in 200mm layers : watered and Compacted to 95% MDD CM 176 2000= 352,000= 1.07 Remove surplus excavated material from site CM 128 4,000= 512,000= Hardcore 1.08 150mm Filling : deposit, spread, level and compact : 50mm selected quarry dust
  • 4. blinding. CM 752 10,000= 7,520,000= Vibrated Insitu concrete grade 15 mix (1:3:6 / 20mmaggregate) as described:- 1.09 Foundations in trenches CM 512 10,000= 5,120,000= Vibrated reinforced concrete grade 20 Mix (1:2:4 / 20mm Aggregate) as Described in:- 1.11 Ramp for the Disabled CM 128 @150,000= 19,200,000= 1.10 100mm thick ground floor slab SM 9600 @ 10,000= 96,000,000= 1.12 Horizontal Ground beam CM 192 @ 250,000= 48,000,000= High yield tensile steel bar reinforcement To BS 4449 as described including Cutting to lengths, bending, hoisting and Fixing including all necessary tying Wire and spacing blocks. 1.12 R8 bars for links KG 944 @ 3,000= 2,832,000= 1.13 Y12 bars. KG 2280 @ 4,000= 9,120,000= Total Carried to Collection 194,528,000=
  • 5. Item Description Unit Quantity Rate(Ushs) Amount(Ugandan shillings) Reinforcement 1.12 Mesh reinforcement Ref No. A98 size 200 x 200 mm weighing 1.54 kg per square metre: in floor slab: including all necessary supports SM 840 @10,000= 8,400,000= Sawn formwork as described to: 1.13 Vertical edges of surface bed : over 75mm but not exceeding 150 mm high. LM 368 @7,500= 2,760,000= Brickwork in burnt clay bricks in cement and sand mortar (1:4) mix; with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 1.14 230 mm thick plinth walling. SM 488 @40,000= 19,520,000= Sundries 1.15 One layer 1000 gauge polythene sheet damp proof membrane Under bed : 300mm laps. SM 840 @9,500= 7,980,000= 1.16 Allow for " Dieldrex " or other approved anti-termite treatment in sides and bottom of foundation trenches and ground surface below hard-core filling( SEE ITEM
  • 6. No.1.02) SM 1744 @ 8,000= 13,952,000= Splash apron 1.17 75mm thick concrete (grade 20) splash apron on 75mm hardcore base well rammed and apron finished with 25mm thick cement and sand (1:3) screed trowelled smooth to gentle falls with division strips every 2.00 metre length and including 150mm thick clay bricks edge wall average 500mm deep rendered on and including 450mm x 150mm thick concrete grade 15 foundation and all necessary excavations and disposal of spoil and formwork to edge of apron Cement and Sand ( 1: 4 ) as described:- SM 288 @36,000= 10 ,368,000= 1.18 20mm thick rendering to plinth walls Prepare and apply two coats of bituminous paint on:- SM 184 @8,000= 1,472,000= 1.19 Rendered plinth walls SM 184 @ 8,000= 1,472,000= Total Carried to Collection Page E1- 1/ 194,528,000= Page E1- 2/ 65,924,000= Total Substructure To Summary 260,452,000=
  • 7. Item Description Unit Quantity Rate(Ushs) Amount ( Ugandan shillings) Bill No. 2 Element No. 2 Super structure: Vibrated Insitu reinforced concrete grade 20 mix (1:2:4 / 20mm Aggregate) as Described:- 2.01 Ring beams CM 24 @400,000= 9,600,000= Mild steel reinforcement as described including cutting to lengths, bending, hoisting and fixing Including all necessary tying wire and spacing blocks. hoisting and fixing including all necessary tying wire and spacing blocks. . 2.02 8 mm diameter bar KG 944 @4,000= 3,776,000= High yield tensile steel bar reinforcement to BS 4449 as described including cutting to Lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 2.03 12 mm diameter bar KG 2,280 @ 4,000= 9,120,000= Sawn formwork as described to:
  • 8. 2.04 Sides and soffites of beams SM 192 @18,000= 3,456,000= Damp proof courses : hessian based bituminous felt: bedded in cement and Sand (1:3) mortar: 300mm laps. 2.05 Horizontal : 230mm ditto LM 416 @ 2,500= 1,040,000= Brickwork in burnt clay bricks in cement and Sand mortar (1:4) mix; with and Including 25 x 3mm hoop iron strips laid Horizontally every alternate course. 2.06 230 mm thick below ring beam walling. SM 776 @46,800= 36,316,800= 2.07 230mm Thick above ring beam and gable walling SM 272 @46,800= 12,729,600= 2.08 Labor and materials in eaves filling on 230mm wall for average height of 300mm LM 368 @ 46,800= 17,222,400= Permanent Vents 2.09 Permanent Vent filled in with Kajjansi ventilation bricks or other equal and approved; bat proof gauze and coffee tray wire backing complete with necessary timber framing and beading. SM 8 @58,000= 464,000= Total Super Structure To Summary 93,724,800=
  • 9. Item Description Unit Quantity Rat (Ushs) Amount (Ugandan shillings) Bill No. 2 Elemnt No.3 Roof: Roof Construction The followings 10nos. Timber trusses each spanning 6.46M x 1.58M rise, comprising of well treated members bolted together to approval as described and hoisted and fixed in position at about 3.30M above floor level. Sawn cypress pressure impregnated with preservative:- 3.01 50 x 100mm Purlins LM 1400 @ 10,000= 14,000,000= 3.02 50 x 100mm Strut /tie LM 432 @10,000= 4,320,000= 3.03 50 x 150mm Ridge LM 144 @ 12,000= 1,728,000= 3.04 50 x 150mm Tie beam LM 520 @12,000= 6240,000= 3.05 50 x 100mm Rafters LM 752 @10,000= 7,520,000= 3.06 75 x 100mm Wall Plate LM 264 @12,000= 3,168,000= 3.07 75 x 100mm overhangs LM 240 @12,000= 2,880,000= Roof Covering 3.08 28 Gauge pre-painted iron roofing sheets fixed with 1.5 side corrugation laps and 150mm end laps with and including approved
  • 10. roofing nails or galvanized steel drive screws with plastic washers and fller blocks to manufacturer's instructions. SM 1248 @ 38,000= 47,424,000= 3.09 28 Gauge plain (pre-coated) roll top ridge capping. LM 1368 @ 12,000= 16,416,000= Eaves 3.10 25 x 225mm Wrot Cypress fascia board and badge boards LM 416 @ 10,000= 4,160,000 Painting Knot prime stop and apply three coats of gloss oil paint to timber surfaces. . 3.11 Knot, prime, stop and apply three coats of gloss oil paint to wood fascia 200- 300mm girth. SM 144 @ 10,000= 1,440,000= Total Roof Carried To Summary 103,696,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No.1
  • 11. Element No.4 Doors and Windows: Windows Vibrated Precast concrete grade 20 mix (1:2:4 / 20mm aggregate) : units reinforced as necessary and finished fair face on all exposed sides as described:- 4.01 75 x 285 mm sunk weathered and throated window cill Purpose made steel casement windows manufactured from standard W20 sections: manufacture, assemble and deliver to site : Supply and fix ironmongery comprising approved hinges , pivoting mechanisms, stays, fasteners to opening lights: plugged and screwed or built into walling : one coat red oxide primer before delivery. all to LM 160 @3,000= 3,480,000= Architects details Purpose made steel casement windows manufactured from standard W20 sections: manufacture, assemble and deliver to site : Supply and fix 4.02 Window type W1 : Size 1200 x 1200mm overall height: NO 112 @ 250,000= 28,000,000= Glass and Glazing 4.03 4mm thick clear sheet glass to metal
  • 12. window with putty SM 160 @ 7 0,000= 11,200,000= Prepare touch up primer and apply one undercoat and two finishing coats of gloss oil paint : on glazed metal surfaces 4.04 General Surfaces : windows SM 320 @3000= 960,000= Total Carried to Collection 43,640,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Doors Purpose made steel casement doors manufactured from Standard W20 Sections complete as described to Architects details 4 .05 Door size 900 x 2400mm with permanent louvered vents 300mm included : D1 NO 16 @300,000= 4800,000= Prepare, knot prime, stop and apply three coats of gloss oil paint: on woodwork. 4.06 General surface of metal doors SM 72 @ 3,000= 216,000=
  • 13. Supply and fix the following approved ironmongeries complete with marching screws, handles and keys to hard wood. 4.07 Tower bolt complete with Pudlocks NO 16 @ 100,000= 1,600,000= 4.08 25mm diameter rubber door stopper. NO 16 @ 10,000= 160,000= Total Carried to Collection COLLECTION Page E4- 4/ 43,640,000= Page E4- 5/ 6,776,000= Total Doors and Windows Carried To Summary 50,416,000=
  • 14. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No. 2 Element No. 5 External Finishes: Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 5.01 30mm thick screed in the verandah SM 160 @ 10,000 = 1,600,000= 5.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 352 @ 10,000 = 3,520,000= Cement and sand ( 1:4) render trowelled smooth on concrete or masonry 5.03 15mm to walls. SM 976 @ 10,000 = 9,760,000= Two coats tyrolene rendering on masonry 5.04 Walls and concrete surfaces SM 544 @8.000= 4,352,000= Painting: 'Sadolin Paints' or equal and approved. 5.05 Prepare and apply one undercoat and two finishing coats weaher guard on plastered surfaces. SM 432 @10,000= 4,320,000= 5.06 Ditto to Tyrolean surfaces. SM 544 @ 10,000= 5,440,000=
  • 15. Total External Walls Finishes Carried To Summary 28,992,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No. 2 Element No.6 Internal Finishes Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 6.01 30mm thick screed SM 752 @10,000= 7,520,000= 6.02 25 x 100mm skirting with square top edge and coved junction at bottom of paving. LM 424 @5000= 2,120,000= Wall Finishes Cement and sand ( 1:2:9) lime plaster trowelled smooth on brick wall or
  • 16. masonry 6.03 15mm thick cement and sand plaster : steel trowell finish to walls. SM 1280 @10,000= 12,800,000= Painting 6.04 Prepare and apply one undercoat and three finishings coats of matt vinyl paint to plastered surfaces. SM 1280 10,000= 12,800,000= Black Board as described:- 6.05 Provide Black board, size: 4200mm long x 1200mm highx 20mm thick complete with chalk rails and painted in approved b/b paint NO 16 150,000= 2,400,000= 6.06 Provide3No pin boardsin each classroom,size: 1200mm x1200mm with hard wood timber framing to approved section design NO 48 150,000= 7,200,000= Total Internal Finishes Carried To Summary 44,840,000= Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings Bill No. 2 Element No.7
  • 17. Lightning Protection Supply, install, connect and set to work the following, all as described in the Specifications and Drawings. 7 .01 Copper tape of Hard Drawn High Conductivity copper plate 3mm x 25mm cross section for Down Conductors, bonded to the iron sheet roof complete with fixing clips and all accessories as by FURSE or equal. LM 28 @ 40,000 = 1,120,000= 7 .02 Air terminals complete with Tape Adapter and all accessories as by FURSE or equal. NO 2 @150,000= 300,000= 7 .03 Test Blocks complete as by FURSE or equal. NO 2 @100,000= 200,000= 7 .04 Earth electrodes made from Hard drawn copper or copper weld 20mm diameter by 1200mm in two length screwed together complete with cap, earth clamp, manhole and all accessories. NO 2 120,000= 240,000= 7 .05 50mm diameter heavy duty P.V.C pipe LM 4 10,000= 40,000= TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY. 1,900,000=
  • 18. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings Bill No. 2 Element No.8 Rain Water harvest 8 .01 P.V.C downpipes 110mm diameter complete with all fittings nessecary for erection (refer to drawing) LM 96 @6,000= 576,000= 8 .02 P.V.C gutters complete with gutter brackets at 1000mm c/c including all fittings nessecary for erection LM 176 @20,000= 3,520,000= 8 .03 5,000 litre pvc tank placed on ground concrete base (measured separetely), complete with all accessories. NO 1 @300,000= 300,000= 8 .04 25mm gate valves as Peglar heavy duty or equal approved. NO 1 @40,000= 40,000= 8 .05 12mm Stand by pipe, complete with 12mm bib tap and all accessories Item 1 @ 37,000= 37,000= Concrete Tank Base 9 .14 1.5m high Ground concrete water tank base, made in masonry brickwork, well compacted hardcore, with 150mm thick slab on top as shown in drawing, for the
  • 19. above water tank, complete. NO 2 @ 1.000,000= 2,000,000= TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000= SUMMARY FOR PROPOSED CONSTRUCTION OF A PRIMARY SCHOOL AT IGEL 1 SUB-STRUCTURE 260,452,000= 2 SUPERSTRUCTURE 93,724,800= 3 ROOFING 103,696,000= 4 DOORS AND WINDOWS 50,416,000= 5 EXTERNAL FINISHES 28,992,000= 6 INTERNAL FINISHES 44,840,000= 7 LIGHTNING PROTECTION 1,900,000= 8 RAIN WATER HARVEST 6,473,000= GRAND TOTAL 590,493,800=
  • 20. BUDGET FOR PUTTING UP A SECONDARY SCHOOL 16 BLOCK OF CLASSROOMS Item Description Unit Quantity Rate(Ushs) Amount(Ushs) Ugandan shillings Element NO 1 Substructure: (All Provisional) Site Preparation 1.01 Excavate oversite to remove top soil average 150mm thick and remove from site. SM 1504 @ 1000= 1;504,000= 1.02 Treat surface of subsoil or fillings and surroundings with approved chemical antitermite solution: provide ten year guarantee. SM 1504 @ 1000= 1,504,000= Excavation and Earthworks. Note: Rates for excavation to include for keeping excavations free from water and planking and strutting to sides of excavations 1.03 Excavate to reduce levels and remove from site. CM 216 @ 2000= 432,000=
  • 21. 1.04 Excavate trenches for wall foundations: commencing from reduced levels : not exceeding 1.5m deep . CM 248 @4000= 992,000= 1.05 Extra over excavation for excavating in rock CM 48 30,000= 1,440,000= Disposal of excavated material 1.06 Selected excavated material in filling to foundation trenches : around walling : placed in 200mm layers : watered and compacted to 95% MDD CM 176 2000= 352,000= 1.07 Remove surplus excavated material from site CM 128 4,000= 512,000= Hardcore 1.08 150mm Filling : deposit, spread, level and compact : 50mm selected quarry dust blinding. CM 752 10,000= 7,520,000= Vibrated Insitu concrete grade 15 mix (1:3:6 / 20mmaggregate) as described:- 1.09 Foundations in trenches CM 512 10,000= 5,120,000= Vibrated reinforced concrete grade 20 mix (1:2:4 / 20mm Aggregate) as described in :- 1.11 Ramp for the Disabled CM 128 150,000= 19,200,000= 1.10 100mm thick ground floor slab SM 9600 10,000= 96,000,000=
  • 22. 1.12 Horizontal Ground beam CM 192 250,000= 48,000,000= High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 1.12 R8 bars for links KG 944 3,000= 2,832,000= 1.13 Y12 bars. KG 2280 4,000= 9,120,000= Total Carried to Collection 194,528,000= Item / Description Unit Quantity Rate(Ushs) Amount (Ushs) Ugandan shillings Reinforcement 1.12 Mesh reinforcement Ref No. A98 size 200 x 200 mm weighing 1.54 kg per square metre: in floor slab: including all necessary supports SM 840 @ 10,000= 8,400,000= Sawn formwork as described to: 1.13 Vertical edges of surface bed : over 75mm but not exceeding 150 mm high. LM 368 @ 7,500= 2,760,000=
  • 23. Brickwork in burnt clay bricks in cement and sand mortar (1:4) mix; with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 1.14 230 mm thick plinth walling. SM 488 @ 40,000= 19,520,000= Sundries 1.15 One layer 1000 gauge polythene sheet damp proof membrane Under bed : 300mm laps. SM 840 @9,500= 7,980,000= 1.16 Allow for " Dieldrex " or other approved anti-termite treatment in sides and bottom of foundation trenches and ground surface below hard-core filling( SEE ITEM No.1.02) SM 1744 @ 8,000= 13,952,000= Splash apron 1.17 75mm thick concrete (grade 20) splash apron on 75mm hardcore base well rammed and apron finished with 25mm thick cement and sand (1:3) screed trowelled smooth to gentle falls with division strips every 2.00 metre length and including 150mm thick clay bricks edge wall average 500mm deep rendered on and including 450mm x 150mm thick concrete
  • 24. grade 15 foundation and all necessary excavations and disposal of spoil and formwork to edge of apron Cement and Sand ( 1: 4 ) as described:- SM 288 @36,000= 10 ,368,000= 1.18 20mm thick rendering to plinth walls Prepare and apply two coats of bituminous paint on:- SM 184 @ 8,000= 1,472,000= 1.19 Rendered plinth walls SM 184 @ 8,000= 1,472,000= Total Carried to Collection Page E1- 1/ 194,528,000= Page E1- 2/ 65,924,000= Total Substructure To Summary 260,452,000=
  • 25. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings Bill No. 2 Element No. 2 Super structure: Vibrated Insitu reinforced concrete grade 20 mix (1:2:4 / 20mm Aggregate) as described:- 2.01 Ring beams CM 24 @400,000= 9,600,000= Mild steel reinforcement as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. hoisting and fixing including all necessary tying wire and spacing blocks. . 2.02 8 mm diameter bar KG 944 @4,000 = 3,776,000= High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 2.03 12 mm diameter bar KG 2,280 @4,000 = 9,120,000= Sawn formwork as described to: 2.04 Sides and soffites of beams SM 192 @18,000 = 3,456,000= Damp proof courses : hessian based bituminous felt: bedded in cement and sand (1:3) mortar : 300mm laps.
  • 26. 2.05 Horizontal : 230mm ditto LM 416 @2,500 = 1,040,000= Brickwork in burnt clay bricks in cement and sand mortar (1:4) mix;with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 2.06 230 mm thick below ring beam walling. SM 776 46,800= 36,316,800= 2.07 230mm Thick above ring beam and gable walling SM 272 46,800= 12,729,600= 2.08 Labour and materials in eaves filling on 230mm wall for average height of 300mm LM 368 46,800= 17,222,400= Permanent Vents 2.09 Permanent Vent filled in with Kajjansi ventilation bricks or other equal and approved; bat proof gauze and coffee tray wire backing complete with necessary timber framing and beading. SM 8 58,000= 464,000= Total Super Structure To Summary 93,724,800=
  • 27. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings Bill No. 2 Elemnt No.3 Roof: Roof Construction The followings 10nos. Timber trusses each spanning 6.46M x 1.58M rise, comprising of well treated members bolted together to approval as described and hoisted and fixed in position at about 3.30M above floor level. Sawn cypress pressure impregnated with Preservative:- 3.01 50 x 100mm Purlins LM 1400 @10,000 = 14,000,000= 3.02 50 x 100mm Strut /tie LM 432 @10,000 = 4,320,000= 3.03 50 x 150mm Ridge LM 144 @12,000 = 1,728,000= 3.04 50 x 150mm Tie beam LM 520 @ 12,000 = 6240,000= 3.05 50 x 100mm Rafters LM 752 @10,000 = 7,520,000= 3.06 75 x 100mm Wall Plate LM 264 @12,000 = 3,168,000= 3.07 75 x 100mm overhangs LM 240 @12,000 = 2,880,000= Roof Covering 3.08 28 Gauge pre-painted iron roofing sheets fixed with 1.5 side corrugation laps and 150mm end laps with and including approved roofing nails or galvanized steel drive screws with plastic washers and fller biocks to manufacturer's instructions. SM 1248 @38,000= 47,424,000=
  • 28. 3.09 28 Gauge plain (pre-coated) roll top ridge capping. LM 1368 @ 12,000= 16,416,000= Eaves 3.10 25 x 225mm Wrot Cypress fascia board and badge boards LM 416 @ 10,000= 4,160,000 Painting Knot prime stop and apply three coats of gloss oil paint to timber surfaces. . 3.11 Knot, prime, stop and apply three coats of gloss oil paint to wood fascia 200- 300mm girth. SM 144 @ 10,000= 1,440,000= Total Roof Carried To Summary 103,696,000=
  • 29. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings Bill No.1 Element No.4 Doors and Windows: Windows Vibrated Precast concrete grade 20 mix (1:2:4 / 20mm aggregate) : units reinforced as necessary and finished fair face on all exposed sides as described:- 4.01 75 x 285 mm sunk weathered and throated window cill Purpose made steel casement windows manufactured from standard W20 sections: manufacture, assemble and deliver to site : Supply and fix ironmongery comprising approved hinges , pivoting mechanisms, stays, fasteners to opening lights: plugged and screwed or built into walling : one coat red oxide primer before delivery. all to LM 160 @3000 = 3,480,000= Architects details Purpose made steel casement windows manufactured from standard W20 sections: manufacture, assemble and deliver to site : Supply and fix 4.02 Window type W1 : Size 1200 x 1200mm
  • 30. overall height: NO 112 @250,000 = 28,000,000= Glass and Glazing 4.03 4mm thick clear sheet glass to metal window with putty SM 160 70,000= 11,200,000= Prepare touch up primer and apply one undercoat and two finishing coats of gloss oil paint : on glazed metal surfaces 4.04 General Surfaces : windows SM 320 3000= 960,000= Total Carried to Collection 43,640,000=
  • 31. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Doors Purpose made steel casement doors manufactured from Standard W20 Sections complete as described to Architects details 4 .05 Door size 900 x 2400mm with permanent louvered vents 300mm included : D1 NO 16 @300,000 = 4,800,000= Prepare, knot prime, stop and apply three coats of gloss oil paint: on woodwork. 4.06 General surface of metal doors SM 72 @ 3,000 = 216,000= Supply and fix the following approved ironmongeries complete with marching screws, handles and keys to hard wood. 4.07 Tower bolt complete with Padlocks NO 16 @ 100,000 = 1,600,000= 4.08 25mm diameter rubber door stopper. NO 16 @10,000= 160,000 = Total Carried to Collection 0 COLLECTION Page E4- 4/ 43,640,000=
  • 32. Page E4- 5/ 6,776,000= Total Doors and Windows Carried To Summary 50,416,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No. 2 Element No. 5 External Finishes: Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 5.01 30mm thick screed in the verandah SM 160 @ 10,000 = 1,600,000= 5.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 352 @10,000 = 3,520,000= Cement and sand ( 1:4) render trowelled smooth on concrete or masonry 5.03 15mm to walls. SM 976 @ 10,000 = 9,760,000= Two coats tyrolene rendering on masonry 5.04 Walls and concrete surfaces SM 544 @ 8.000 = 4,352,000=
  • 33. Painting : 'Sadolin Paints' or equal and approved. 5.05 Prepare and apply one undercoat and two finishing coats weaher guard on plastered surfaces. SM 432 @ 10,000 = 4,320,000= 5.06 Ditto to tyrolean surfaces. SM 544 @ 10,000 = 5,440,000= Total External Walls Finishes Carried To Summary 28,992,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No. 2 Element No.6 Internal Finishes Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 6.01 30mm thick screed SM 752 @10,000 = 7,520,000 6.02 25 x 100mm skirting with square top edge and coved junction at bottom of paving. LM 424 @5000 = 2,120,000 Wall Finishes Cement and sand ( 1:2:9) lime plaster trowelled smooth on brick wall or masonry
  • 34. 6.03 15mm thick cement and sand plaster : steel trowell finish to walls. SM 1280 @ 10,000 = 12,800,000 Painting 6.04 Prepare and apply one undercoat and three finishings coats of matt vinyl paint to plastered surfaces. SM 1280 @10,000 = 12,800,000= Black Board as described:- 6.05 Provide Black board, size: 4200mm long x 1200mm highx 20mm thick complete with chalk rails and painted in approved b/b paint NO 16 @ 150,000 = 2,400,000= 6.06 Provide3No pin boardsin each classroom,size: 1200mm x1200mm with hard wood timber framing to approved section design NO 48 150,000= 7,200,000= Total Internal Finishes Carried To Summary 44,840,000= Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
  • 35. Bill No. 2 Element No.7 Lightning Protection Supply, install, connect and set to work the following, all as described in the Specifications and Drawings. 7 .01 Copper tape of Hard Drawn High conductivity copper plate 3mm x 25mm cross section for Down Conductors,bonded to the iron sheet roof complete with fixing clips and all accessories as by FURSE or equal. LM 28 40,000= 1,120,000= 7 .02 Air terminals complete with Tape Adapter and all accessories as by FURSE or equal. NO 2 150,000= 300,000= 7 .03 Test Blocks complete as by FURSE or equal. NO 2 100,000= 200,000= 7 .04 Earth electrodes made from Hard drawn copper or copper weld 20mm diameter by 1200mm in two length screwed together complete with cap, earth clamp, manhole and all accessories. NO 2 120,000= 240,000= 7 .05 50mm diameter heavy duty P.V.C pipe LM 4 10,000= 40,000= TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY. 1,900,000=
  • 36. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings) Bill No. 2 Element No.8 Rain Water harvest 8 .01 P.V.C downpipes 110mm diameter complete with all fittings nessecary for erection (refer to drawing) LM 96 @ 6,000 = 576,000= 8 .02 P.V.C gutters complete with gutter brackets at 1000mm c/c including all fittings nessecary for erection LM 176 @20,000 = 3,520,000= 8 .03 5,000 litre pvc tank placed on ground concrete base (measured separetely), complete with all accessories. NO 1 @300,000= 300,000= 8 .04 25mm gate valves as Peglar heavy duty or equal approved. NO 1 @ 40,000= 40,000=
  • 37. 8 .05 12mm Stand by pipe, complete with 12mm bib tap and all accessories Item 1 @ 37,000= 37,000= Concrete Tank Base 9 .14 1.5m high Ground concrete water tank base, made in masonry brickwork, well compacted hardcore, with 150mm thick slab on top as shown in drawing, for the above water tank, complete. NO 2 @ 1000,000= 2,000,000= TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000= SUMMARY FOR PROPOSED CONSTRUCTION OF A SECONDARY SCHOOL AT IGEL 1 SUBSTRUCTURE 260,452,000= 2 SUPERSTRUCTURE 93,724,800= 3 ROOFING 103,696,000= 4 DOORS AND WINDOWS 50,416,000= 5 EXTERNAL FINISHES 28,992,000= 6 INTERNAL FINISHES 44,840,000= 7 LIGHTNING PROTECTION 1,900,000=
  • 38. 8 RAIN WATER HARVEST 6,473,000= GRAND TOTAL 590,493,800= BUDGET FOR THE PROPOSED CONSTRUCTION OF 5 STANCE DRAINABLE PIT LATRINE FOR BOTH THE PRIMARY ,HEALTH CENTRE AND SECONDARY SCHOOL AT IGEL KOLE DISTRICT. Item Description Unit Quantity Rate [Ushs) Amount [ Ugandan shillings) BILL No 5 ELEMENT NO 1 SUBSTRUCTURE (All Provisional) Site Preparation 1.01 Excavate oversite to remove top soil average 150mm thick and remove from site. SM 51 @ 1000 = 51,000=
  • 39. 1.02 Treat surface of subsoil or fillings and surroundings with approved chemical anti-termite solution: provide ten year guarantee. SM 51 @300= 15,300= Excavation and Earthworks. Note: Rates for excavation to include for keeping excavations free from water and planking and strutting to sides of excavations 1.03 Excavate to reduce levels and remove from site. CM 15 @ 10,000= 150,000= 1.04 Excavate pit including all earth work support and keeping excavations free from water and mud up to 1.5m CM N/A 1.05 Ditto but up to 3m CM 22 @ 30,000= 660,000= 1.06 Ditto but up to 4m CM N/A 1.07 Extra over excavation for excavating in rock CM 5 @30,000= 150,000= Disposal of excavated material 1.08 Selected excavated material in filling to foundation trenches : around walling : placed in 200mm layers : watered and compacted to 95% MDD CM 3 @30,000= 90,000=
  • 40. 1.09 Remove surplus excavated material from site CM 43 @ 20,000= 860,000= 1.10 150mm Filling : deposit, spread, level and compact : 50mm selected quarry dust blinding. SM 22 @5,000= 110,000= Insitu concrete grade 20 mix (1:2:4 / 20mm aggregate) as described:- 1.11 150mm thick pit floor bed using mix 1:2:4 mass concrete CM 2 @200,000= 400,000= 1.12 230x 230mm columns and beams mix 1:2:4/19mm CM 3 @400,000= 1,200,000= 1.13 100mm thick reinforced suspended floor slab using mix 1:2:4 concrete. SM 13 @30,000= 390,000= Total Carried to Collection 4,476,300= Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
  • 41. Vibrated Insitu reinforced concrete grade 20 mix (1:2:4 / 20mm aggregate) as described:- 1.14 100mm thick slab in verandah SM 12 @30,000= 360,000= 1.15 Ramp for the Disabled CM 1 @200,000= 200,000= Reinforcement 1.16 Mesh reinforcement Ref No. A98 size 200 x 200 mm weighing 1.54 kg per square metre: in floor slab: including all necessary supports SM 21 @20,000= 440,000= Mild steel rod reinforcement as described. 1.17 8 mm diameter bar KG 52 @3000= 156,000= High yield tensile steel bar reinforcement to BS 4449 as described. 1.18 12 mm diameter bar KG 121 @ 4000= 484,000= Sawn formwork as described to: 1.19 230x230mm columns: over 75mm but not exceeding 150 mm high. LM 50 @10,000= 500,000= 1.20 Sides of the pit ringbeam 300mm wide: over 75mm but
  • 42. not exceeding 150 mm high. LM 8 @10,000= 80,000= 1.21 Soffit of 100mm thick slab: over 75mm but not exceeding 150 mm high. SM 25 @ 20,000= 500,000= 1.22 Edge of slab 100mm high: over 75mm but not exceeding 150 mm high. LM 25 @10,000= 250,000= Brickwork in burnt clay bricks in cement and sand mortar (1:3) mix; with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 1.23 230 mm thick plinth walling. SM 45 @46,800= 2,106,000= 1000 gauge vertical DPM SM 50 0 Finishes to the pit 1.24 15mm cement and sand (1:4 mix) trawelled smooth and hard using water resistant cement additive. SM 53 10,000= 530,000= 1.25 25mm cement,sand screed finished smooth to a gentle slope SM 23 10,000= 230,000= Vent pipe 1.26 Supply and fix 3No 100mm diameter uPVC vent pipes 3.5m long with fly screen at the top complete with mosquito wire netting. LM 11 10,000= 110,000=
  • 43. Total Carried to Collection Splash apron 1.27 75mm thick concrete (grade 20) splash apron on 75mm hardcore base well rammed and apron finished with 25mm thick cement and sand (1:3) screed trowelled smooth to gentle falls with division strips every 2.00 metre length and including 150mm thick clay bricks edge wall average 500mm deep rendered on and including 450mm x 150mm thick concrete grade 15 foundation and all necessary excavations and disposal of spoil and formwork to edge of apron SM 11 @ 30,000= 330,000= Total Carried to Collection 6,276,000=
  • 44. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) COLLECTION Page E1- 1/ 4,476,300= Page E1- 2/ 6,276,000= TOTAL SUBSTRUCTURE CARRIED TO SUMMARY 10,752,300= Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 2 SUPER STRUCTURE Vibrated Insitu reinforced concrete grade 20 mix (1:2:4 / 20mm Aggregate) as described:- 2.01 Ring beams CM 1 @400,000= 400,000= Mild steel reinforcement as described including cutting to lengths, bending, hoisting and
  • 45. fixing including all necessary tying wire and spacing blocks. 2.02 8 mm diameter bar KG 30 @ 3,000= 90,000= High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 2.03 12 mm diameter bar KG 88 @4,000= 352,000= Sawn formwork as described to: 2.04 Sides and soffites of beams SM 14 @10,000= 140,000= Damp proof courses : hessian based bituminous felt: bedded in cement and sand (1:3) mortar : 300mm laps. 2.05 Horizontal : 200mm ditto LM 28 @ 2500= 70,000= Brickwork in burnt clay bricks in cement and sand mortar (1:3) mix;with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 2.06 230mm thick below ring beam walling. SM 49 @46,800= 2,293,200= 2.07 Labour and materials in eaves
  • 46. filling on 230mm wall for average height of 300mm LM 32 @10,000= 320,000= Permanent Vents 2.08 Permanent Vent filled in with Kajjansi ventilation bricks or other equal and approved; bat proof gauze and coffee tray wire backing complete with necessary timber framing and beading. SM 1 @60,000= 60,000= Disability Handrail 2.08 Provide handrials for the disabled comprised of 35mm diameter MS grip bars for the diasbled complete installed to architects details Item 1 150,000= 150,000= TOTAL SUPER STRUCTURE CARRIED TO SUMMARY 3,875,200= ………………………………………………………………………………………………………………… …………………………….
  • 47. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 3 ROOF Roof Construction The following in roof construction including all bolting, gusset plates, fixing trusses to ring beams with holding down bolts and hoisting and fixing approximately 3.0mm above ground level. Sawn cypress pressure impregnated with preservative:- 3.01 50 x 100mm Purlins LM 20 @10,000= 200,000= 3.02 50 x 150mm Rafters LM 11 @12,000= 132,000= 3.03 75 x 100mm Wall Plate LM 13 @ 12,000= 144,000= Roof Covering 3.04 28 Gauge pre-painted iron roofing sheets fixed with 1.5 side corrugation laps and 150mm end laps with and including approved roofing nails or galvanized steel drive screws with plastic washers to manufacturer's instructions. SM 18 @ 38,000= 684,000=
  • 48. Eaves 3.05 25 x 225mm Wrot Cypress fascia board Painting LM 18 @15,000= 270,000= Painting Knot prime stop and apply three coats of gloss oil paint to timber surfaces. 3.06 Knot, prime, stop and apply three coats of gloss oil paint to wood fascia 200-300mm girth. SM 9 @10,000= 90,000= TOTAL ROOF CARRIED TO SUMMARY 1,520,000=
  • 49. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 4 DOORS Doors Purpose made steel casement doors manufactured from Standard W20 Sections complete as described to Architects details 4.01 Door size 900 x 2400mm with permanent louvered vents 300mm included. NO 6 200,000= 1,200,000= Prepare, knot prime, stop and apply three coats of gloss oil paint: on metal 4.02 General Surfaces : doors SM 23 3,000= 69,000= Supply and fix the following approved ironmongeries complete with marching screws, handles and keys to hard wood. 4.03 Tower bolt complete with Pudlocks NO 6 30,000= 180,000= TOTAL DOORS AND WINDOWS CARRIED TO SUMMARY 1,449,000=
  • 50. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 5 EXTERNAL FINISHES Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 5.01 30mm thick screed in the verandah aand ramps SM 15 @10,000= 150,000= 5.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 6 @ 5000= 30,000= Cement and sand ( 1:4) render trowelled smooth on concrete or masonry 5.03 15mm to walls. SM 56 @10,000= 560,000= Two coats tyrolene rendering on masonry 5.04 Walls and concrete surfaces SM 56 @5000= 280,000= Painting : 'Sadolin Paints' or
  • 51. equal and approved. 5.05 Prepare and apply one undercoat and two finishing coats weather guard paint on plastered surfaces. SM 15 @10,000= 150,000= 5.06 Ditto to tyrolean surfaces Item 56 10,000= 560,000= 5.07 Supply and fix to position standard engraved foundation stones from approved product from either slates or marbles or terrazzo to engineer's details. Item 1 150,000= 150,000= TOTAL EXTERNAL WALLS FINISHES CARRIED TO SUMMARY 1,880,000= Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 6 INTERNAL FINISHES Floor Finishes Cement and sand (1:3) screeds and pavings : one coat:
  • 52. steel trowell finish : aid on concrete 6.01 30mm thick screed SM 11 @10,000= 110,000= 6.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 27 @ 5,000= 135,000= Wall Finishes 6.03 15mm thick cement and sand plaster : steel trowell finish to walls. SM 55 @ 10,000= 550,000= Painting 6.04 Prepare and apply one undercoat and three finishings coats matt vinyl paint to plastered surfaces. SM 55 @10,000= 550,000= TOTAL INTERNAL FINISHES CARRIED TO SUMMARY 1,345,000= Ugandan shillings ………………………………………………………………………………………………………………… ……………………….
  • 53. ELEMENT NO. 7 WATER SUPPLY Supply, install, connect and set to work the following, all as described in the Specifications and Drawings. Water Supply 7.01 250 litre uPVC tank placed on ground concrete base (measured separately ) ,complete with lockable tap and washout approved NO 1 @500,000= 500,000= 7.03 Install 4"PVC pipe with approved floor trap to urinal, including splash apron for hand washing tanks NO 3 @50,000= 150,000= 7.04 1m high ground concrete water tank base made in masonry brickwork, well compacted with 150mm thick slab on top as directed on site for the tanks as above complete with 1x1m spash apron, concealed drain pipe and soakaway complete .(inc. metallic lockable burgler proffing metallic grills engraved in concrete for protecting the tank) NO 1 @500,000= 500,000=
  • 54. 7.05 Provive sock away pit size 1.5m diameter and 1.2m depth complete with drain pipe/floor trap from urinal or wash room. Item 1 100,000= TOTAL WATER SUPPLY CARRIED TO SUMMARY. 1,250,000=
  • 55. BILL No 5 SUMMARY FOR PROPOSED CONSTRUCTION OF1 BLOCK OF 5 STANCE VIP LATRINE IN SCHOOL IN IGEL KOLE DISTRICT 1 SUBSTRUCTURE 10,752,300= 2 SUPERSTRUCTURE 3,875,200= 3 ROOFING 1,520,000= 4 DOORS 1,449,000= 5 EXTERNAL FINISHES 1,880,000= 6 INTERNAL FINISHES 1,345,000= 7 WATER SUPPLY 1,250,000= FIVE STANCE VIP LATINE TOTAL TO SUMMARY FOR PRIMARY HEALTH CENTRE AND SECONDARY WE MULTIPLY FUGURE X3 22,071,500= x 3
  • 56. BUDGET FOR THE PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE DISTRICT. Item Description Unit Quantity Rate [Ushs) Amount [Ugandan shillings) ELEMENT NO 1 SUBSTRUCTURE (All Provisional) Site Preparation 1.01 Excavate over site to remove Top soil average 150mm thick and Remove from site. SM 324 @1,000= 324,000= 1.03 Treat surface of subsoil or 1.04 fillings and surroundings 1.05 with approved 1.06 chemical anti-termite Solution: provide Ten year guarantee. SM 324 @ 1,000= 324,000= Excavation and Earthworks. Note: Rates for excavation to
  • 57. Include for keeping excavations Free from water And planking and strutting to Sides of excavations 1.03 Excavate to reduce levels And remove from site. CM 54 @5,000= 270,000= 1.04 Excavate trenches for wall Foundations: commencing From reduced levels: not Exceeding 1.5m deep. CM 81 @ 5,000= 405,000= 1.05 Extra over excavation For excavating in rock CM 5 @30,000= 150,000= Disposal of excavated material 1.07 Selected excavated material 1.08 in filling to foundation trenches : 1.09 around walling : Placed in 200mm layers: watered and Compacted to 95% MDD CM 60 @ 5,000= 300,000= 1.07 Remove surplus excavated material from site CM 11 @20,000= 220,000= Hardcore 1.08 150mm Filling: deposit, spread, Level and compact: 50mm selected Quarry dust Blinding. SM 324 @ 5,000= 1,620,000= Vibrated Insitu concrete grade 15
  • 58. Mix (1:3:6 / 20mm aggregate) as described:- 1.09 Foundations in trenches CM 14 @200,000= 2,800,000= Vibrated reinforced concrete grade 20 Mix (1:2:4) as described in :- 1.10 100mm thick ground floor slab SM 105 @ 30,000= 3,150,000= 1.11 Ramp for the Disabled SM 9 @30,000= 270,000= Total Carried to Collection 9,833,000= Item Description Unit Quantity Rate Ushs) Amount Ushs) Reinforcement 1.12 Mesh reinforcement Ref No. A98 size 200 x 200 mm weighing 1.54 kg per square metre: in floor slab: including all necessary supports SM 95 @11,500= 1,092,500= Sawn formwork as described to:
  • 59. 1.13 Vertical edges of surface bed: over 75mm but not exceeding 150 mm high. LM 44 @ 7,500= 330,000= Brickwork in burnt clay bricks in Cement and sand mortar (1:4) mix; With and Including 25 x 3mm hoop iron strips laid horizontally every alternate course. 1.14 230 mm thick plinth walling. SM 88 @46,800= 4,118,400= Sundries 1.15 One layer 1000 gauge polythene sheet damp proof membrane Under bed : 300mm laps. SM 95 @5,000= 475,000= 1.16 Allow for " Dieldrex " or other approved anti-termite treatment in sides and bottom of foundation trenches and ground surface below hard-core filling(SEE ITEM No.1.02) SM 335 @300= 100,500= Splash apron 1.17 75mm thick concrete (grade 20)
  • 60. splash apron on 75mm hardcore base well rammed and apron finished with 25mm thick cement and sand (1:3) screed trowelled smooth to gentle falls with division strips every 2.00 metre length and Including 150mm thick concrete Block edge wall average 500mm Deep rendered on And including 450mm x 150mm thick Concrete grade 15 foundation and all necessary excavations and disposal of spoil and formwork to edge of apron SM 27 30,000= 810,000= Cement and Sand ( 1: 4 ) as described:- 1.18 Plinth Rendering SM 19 10,000= 190,000= Prepare and apply two coats of bituminous paint on:- 1.19 Rendered plinth walls SM 19 10,000= 190,000= Total Carried to Collection 7,306,400= COLLECTION Page E1- 1/ 9,833,000= Page E1- 2/ 7,306,400=
  • 61. TOTAL SUBSTRUCTURE TO SUMMARY 17,139,400= ELEMENT NO. 2 SUPER STRUCTURE Insitu concrete grade 20 / 20mm: Vibrated, reinforced as described 2.01 Ring beams CM 6 @400,000= 2,400,000= Mild steel reinforcement as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 2.02 8 mm diameter bar KG 107 @ 3,000= 321,000= High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing blocks. 2.03 12 mm diameter bar KG 263 @4,000= 1,052,000= Sawn formwork as described to: 2.04 Sides and soffites of beams SM 42 @ 10,000= 420,000= Damp proof courses : hessian based bituminous felt: bedded in cement and sand (1:3) mortar : 300mm laps. 2.05 Horizontal : 200mm ditto LM 99 @ 2,500= 247,500= Brickwork in burnt clay bricks in cement
  • 62. and sand mortar (1:4) mix;with and including 25 x 3mm hoop iron strips laid horizontally every alternate course. 2.06 230 mm thick below ring beam walling. SM 233 @46,800= 10,904,400= 2.07 230mm Thick above ring beam and gable walling SM 73 @46,800= 3,416,400= 2.08 Labour and materials in eaves filling on 230mm wall for average height of 300mm LM 77 @5,000= 385,000= Permanent Vents 2.09 Permanent Vent filled in with Kajjansi ventilation bricks or other equal and approved; bat proof gauze and coffee tray wire backing complete with necessary timber framing and beading. SM 1 @ 60,000= 60,000= TOTAL SUPER STRUCTURE TO SUMMARY 19,206,300= Ugandan shillings
  • 63. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 3 ROOF Roof Construction The followings 06nos. Timber trusses each spanning 8.12M x 1.98M rise, comprising of well treated members bolted together to approval as described and hoisted and fixed in position at about 3.30M above floor level. Sawn cypress/ pine pressure impregnated with preservative:- 3.01 50 x 100mm Purlins LM 145 @ 10,000= 1,450,000= 3.02 50 x 100mm Strut /tie LM 130 @10,000= 1,300,000= 3.04 50 x 150mm Tie beam LM 155 @ 12,000= 1,860,000= 3.05 50 x 100mm Rafters LM 120 @10,000= 1,200,000= 3.06 75 x 100mm Wall Plate LM 55 @12,000= 144,000= Roof Covering 3.07 28 Gauge pre-painted iron roofing sheets fixed with 1 ½ side corrugation laps and 150mm end laps with and including
  • 64. filler blocks at the ridges, approved roofing nails or galvanized steel drive screws with plastic washers to manufacturer's instructions. SM 166 @38,000= 6,308,000= 3.08 28 Gauge plain (pre-coated) roll top ridge capping. LM 22 @12,000= 264,000= Eaves 3.09 25 x 225mm Wrot Cypress/ pine fascia board LM 61 @15,000= 915,000= 3.10 100 x 50 mm wrot cypress or pine in fascia and badge board carriers LM 61 @15,000= 915,000= Painting Knot prime stop and apply three coats of gloss oil paint to timber surfaces. 3.11 Knot, prime, stop and apply three coats of gloss oil paint to wood fascia 200- 300mm girth. SM 26 @7500= 195,000= TOTAL ROOF CARRIED TO SUMMARY 14,551,000= Ugandan shillings
  • 65. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 4 DOORS AND WINDOWS Windows Precast concrete grade 25 / 20mm ]aggregate : units reinforced as necessary and finished fair face on all exposed sides. 4.01 75 x 285 mm sunk weathered and throated window cill LM 11 @55,000= 605,000= Purpose made steel casement windows manufactured from standard W20 sections: manufacture, assemble and deliver to site : Supply and fix ironmongery comprising approved hinges, pivoting mechanisms, stays, fasteners to opening lights: plugged and screwed or built into walling : one 4.02 Window type W1 : Size 1500 x 1500mm overall height: NO 6 @300,000= 1,800,000=
  • 66. 4.04 Window type W3 : Size 900 x 900mm overall height: NO 2 200,000= 400,000= Burglar proofing grille comprising 12mm square bars 150mm centres both ways in cobweb pattern as described. 4.06 Window type W1 : Size 1500 x 1500mm overall height: NO 6 150,000= 900,000= 4.08 Window type W3 : Size 900 x 900mm overall height: NO 2 100,000= 200,000= Glass and Glazing 4.10 4mm thick clear sheet glass to metal window with putty SM 9 78,000 702,000= 4.11 Ditto but obscure glass SM 2 78,000 156,000= Prepare touch up primer and apply one undercoat and two finishing coats of gloss oil paint : on glazed metal surfaces 4.12 General Surfaces : windows SM 24 3000= 72,000= Total Carried to Collection 4,835,000= Ugandan shillings
  • 67. Item Description Unit Quantity Rate Ushs) ( Amount Ugandan shillings) Doors Wrot Mahogany : selected and kept clean. 4.13 Supply and fix 1.5mm thick metallic door frame (Jamb profile) size:900 x2400mm comprising 300mm high lourved vent for full width.door shutter size 800 x2100mm NO 6 @ 200,000= 1,200,000= all to Architects details Purpose made steel casement doors (including frames) manufactured from Standard W20 Sections complete as described to Architects details 4.15 Door size 1200 x 2400mm with permanent louvered vents 300mm included.(D1) NO 2 @500,000= 1,000,000= 4.16 Door size 900 x 2400mm with permanent louvered vents
  • 68. 300mm included.(D2) NO 2 @400,000= 800,000= Prepare, knot prime, stop and apply three coats of gloss oil paint: on woodwork. 4.17 General Surfaces : doors SM 23 @ 3000= 69,000= 4.18 Ditto but general surface of metal doors SM 9 @ 3000= 27,000= Supply and fix the following approved Ironmongeries complete with marching screws, handles and keys to hard wood. 4.19 4 - Lever mortice lock as for Union England ( or Italy ) specially made for external Casement door. NO 2 @200,000= 400,000= 4.20 3-lever mortise lock Code No. 2277 NO 8 @ 100,000= 800,000= 4.21 25mm diameter rubber door stopper. NO 8 @10,000= 80,000= 4.22 Supply and fix purpose made steel door frames in jamb profile 1.5mm thick all to Architects detail NO 6 @ 200,000= 1,200,000= Total Carried to Collection COLLECTION Page E4- 4/ 4,835,000= Page E4- 5/ 5,576,000= TOTAL DOORS AND WINDOWS TO SUMMARY 10,411,000= Ugandan shillings
  • 69. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings) ELEMENT NO. 5 EXTERNAL FINISHES Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 5.01 30mm thick screed in the verandah SM 6 @ 10,000= 60,000= 5.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 10 @5000= 50,000= Cement and sand ( 1:4) render trowelled smooth on concrete or masonry 5.03 15mm to walls. SM 129 @10,000= 1,290,000= Two coats tyrolene rendering on masonry 5.04 Walls and concrete surfaces SM 128 @10,000= 1,280,000=
  • 70. Painting : 'Sadolin Paints' or equal and approved. 5.05 Prepare and apply one undercoat and two finishing coats of weather guard on plastered surfaces. SM 129 @ 10,000= 1,290,000= 5.06 Ditto to tyrolean surfaces SM 128 @10,000= 1,280,000= TOTAL EXTERNAL FINISHESTO SUMMARY 5,250,000= Ugandan shillings Item Description Unit Quantity Rate Ushs) (Amount Ugandan shillings) ELEMENT NO. 6 INTERNAL FINISHES Floor Finishes Cement and sand (1:3) screeds and pavings : one coat: steel trowell finish : laid on concrete 6.01 30mm thick screed SM 78 @ 10,000= 780,000
  • 71. 6.02 25 x 200mm skirting with square top edge and coved junction at bottom of paving. LM 97 @ 5000= 485,000= Wall Finishes 6.03 15mm thick cement and sand plaster : steel trowell finish to walls. SM 270 @ 10,000= 2,700,000= Painting 6.04 Prepare and apply one undercoat and three finishings coats of matt vinyl paint to plastered surfaces. SM 270 @10,000= 2,700,000= Ceiling Finishes 6.05 9 x 24 SWG galvanized expanded metal lathing U-nailed to timber branderings SM 78 @5000= 780,000= 6.06 Cement and sand (1:4) pricking course to metal lathing SM 78 @10,000= 780,000= 6.07 12mm cement and sand plaster to ceiling SM 78 @ 10,000= 780,000= 6.08 Extra for 150 x 15mm thick cement and sand cornice LM 120 @5,000= 600,000= Pressure impregnated sawn Cypress 6.09 50 x 100mm branderings LM 140 @2000= 280,000= 6.10 50 x 100mm joists LM 153 @ 2000= 306,000=
  • 72. Prepare and apply three coats of first grade emulsion paint on:. 6.11 Plastered ceiling SM 78 @ 10,000= 780,000= 6.12 Cornice : Over 100 but not exceeding 200mm girth. LM 120 @ 2000= 240,000= TOTAL INTERNAL FINISHES TO SUMMARY. 10,431,000= Ugandan Shilling Item Description Unit Quantity Rate Ushs) { Amount in Ugandan shillings) ELEMENT NO. 7 LIGHTNING PROTECTION Supply, install, connect and set to work the following, all as described in the Specifications and Drawings. Lightning Protection. 7.01 Copper tape of Hard Drawn High conductivity copper plate
  • 73. 3mm x 25mm cross section for Down Conductors, bonded to the iron sheet roof complete with fixing clips and all accessories as by FURSE or equal. LM 21 @ 40,000= 840,000= 7 .02 Air terminals complete with Tape Adapter and all accessories as by FURSE or equal. NO 2 @150,000= 300,000= 7 .03 Test Blocks complete as by FURSE or equal. NO 2 @100,000= 200,000= 7 .04 Earth electrodes made from Hard drawn copper or copper weld 20mm diameter by 1200mm in two length screwed together complete with cap, earth clamp, manhole and all accessories. NO 2 @ 120,000= 240,000= 7.05 50 mmm diameter heavy duty P.V.C pipe LM 4 @ 10,000= 40,000=
  • 74. TOTAL ELECTRICAL INSTALLATION SUMMARY. 1,620,000= Ugandan Shilling Item Description Unit Quantity Rate (Ushs) Amount(Ushs) Bill No. 2 Element No.8 Rain Water harvest 8 .01 P.V.C downpipes 110mm diameter complete with all fittings nessecary for erection (refer to drawing) LM 96 @6,000= 576,000= 8 .02 P.V.C gutters complete with gutter brackets at 1000mm c/c including all fittings nessecary for erection LM 176 @20,000= 3,520,000= 8 .03 5,000 litre pvc tank placed on ground concrete base (measured separetely),
  • 75. complete with all accessories. NO 1 @ 300,000= 300,000= 8 .04 25mm gate valves as Peglar heavy duty or equal approved. NO 1 @40,000= 40,000= 8 .05 12mm Stand by pipe, complete with 12mm bib tap and all accessories Item 1 @ 37,000= 37,000= Concrete Tank Base 8 .06 1.5m high Ground concrete water tank base, made in masonry brickwork, well compacted hardcore, with 150mm thick slab on top as shown in drawing, for the above water tank, complete. NO 2 @ 1000,000= 2,000,000= TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000= Ugandan Shilling
  • 76. Bill No.6 SUMMARY OF PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE DISTRICT 1 - SUB-STRUCTURE 17,139,400= 2 -SUPERSTRUCTURE 19,206,300= 3 -ROOFING 14,551,000= 4 -DOORS AND WINDOWS 10,411,000= 5 -EXTERNAL FINISHES 5,250,000= 6 - INTERNAL FINISHES 10,431,000= 7 - LIGHTNING PROTECTION 1,620,000= 8 - RAIN WATER HARVEST 6,473,000= GRAND TOTAL 85,081,700 Ugandan Shilling