Guide Complete Set of Residential Architectural Drawings PDF
McsfBudget
1. MASSAJA CHILDREN SUPPORT FOUNDATION BUDGET SUMMARY FOR PUTTING UP PRIMARY SCHOOL,
SECONDARY SCHOOL, AND THE HEALTH CENTRE
ITEMISED BUDGET
1. PRIMARY SCHOOL COMPLETE WITH DOUBLE STREAMS ………………………{ $ 239,357 USD}
2. SECONDAYSCHOOL, COMPUTER LAB, LIBRARY,……………………….. { $ 239,357 USD }
3. HEATH CENTRE FOR THE COMMUNITY,……. …………………….…….… { $ 34,488 USD }
4. 5 STANCE DRAINABLE PIT LATRINE FOR THE PRIMARY SCHOOL, SECONDARY SCHOOL, AND
THE HEALTH CENTRE R ESPCTIVELY………………………… X3 { $ 26,840 USD}
GRAND TOTAL ………………………………………… $ 540,042 USD
2. ACCOUNTABILITY IN DETAIL THAT MAKES UP THE ABOVE AMOUNT
The above budget is well detailed and accounted for below how it sums up to a grand total that
you see above in US dollar.
Below each item and material that will be used at the entire project is well detailed. The price is in
local currency the {Ugandan Shilling} of which the
Exchange rate is …………….. 1 US dollar = 2,467 Ugandan shillings
ACCOUNTABILITY BUDGET FOR THE PRIMARY SCHOOL OF 16 BLOCK OF CLASSROOMS IN
LOCAL CURRENCY
Item Description Unit Quantity Rate(Ushs) Amount(Ugandan shillings)
Element NO 1
Substructure: (All Provisional)
Site Preparation
1.01 Excavate oversite to remove
top soil average 150mm thick and
remove from site. SM 1504 @ 1000= 1;504,000=
1.02 Treat surface of subsoil or fillings
and Surroundings with approved
Chemical ant termite
3. solution: provide ten year guarantee. SM 1504 @ 1000= 1,504,000=
Excavation and Earthworks.
Note: Rates for excavation to
include for keeping excavations
free from water
and planking and strutting
to sides of excavations
1.03 Excavate to reduce levels and
Remove from site. CM 216 @ 2000= 432,000
1.04 Excavate trenches for wall
Foundations: commencing from
Reduced levels: not
exceeding 1.5m deep . CM 248 @ 4000= 992,000=
1.05 Extra over excavation for excavating
in rock CM 48 @ 30,000= 1,440,000=
Disposal of excavated material
1.06 Selected excavated material in filling
to foundation trenches : around walling :
placed in 200mm layers : watered and
Compacted to 95% MDD CM 176 2000= 352,000=
1.07 Remove surplus excavated
material from site CM 128 4,000= 512,000=
Hardcore
1.08 150mm Filling : deposit, spread, level
and compact : 50mm selected quarry dust
4. blinding. CM 752 10,000= 7,520,000=
Vibrated Insitu concrete grade 15 mix
(1:3:6 / 20mmaggregate) as described:-
1.09 Foundations in trenches CM 512 10,000= 5,120,000=
Vibrated reinforced concrete grade 20
Mix (1:2:4 / 20mm Aggregate) as
Described in:-
1.11 Ramp for the Disabled CM 128 @150,000= 19,200,000=
1.10 100mm thick ground floor slab SM 9600 @ 10,000= 96,000,000=
1.12 Horizontal Ground beam CM 192 @ 250,000= 48,000,000=
High yield tensile steel bar reinforcement
To BS 4449 as described including
Cutting to lengths, bending, hoisting and
Fixing including all necessary tying
Wire and spacing blocks.
1.12 R8 bars for links KG 944 @ 3,000= 2,832,000=
1.13 Y12 bars. KG 2280 @ 4,000= 9,120,000=
Total Carried to Collection 194,528,000=
5. Item Description Unit Quantity Rate(Ushs) Amount(Ugandan shillings)
Reinforcement
1.12 Mesh reinforcement Ref No.
A98 size 200 x 200 mm weighing 1.54
kg per square metre: in floor slab:
including all necessary supports SM 840 @10,000= 8,400,000=
Sawn formwork as described to:
1.13 Vertical edges of surface bed :
over 75mm but not exceeding 150 mm high. LM 368 @7,500= 2,760,000=
Brickwork in burnt clay bricks in cement and
sand mortar (1:4) mix; with and
including 25 x 3mm hoop iron strips
laid horizontally every alternate course.
1.14 230 mm thick plinth walling. SM 488 @40,000= 19,520,000=
Sundries
1.15 One layer 1000 gauge polythene sheet
damp proof membrane Under bed :
300mm laps. SM 840 @9,500= 7,980,000=
1.16
Allow for " Dieldrex " or other approved
anti-termite treatment in sides and bottom
of foundation trenches and ground surface
below hard-core filling( SEE ITEM
6. No.1.02) SM 1744 @ 8,000= 13,952,000=
Splash apron
1.17
75mm thick concrete (grade 20) splash apron on
75mm hardcore base well rammed and apron
finished with 25mm thick cement and
sand (1:3) screed trowelled smooth to gentle falls
with division strips every 2.00 metre length and
including 150mm thick clay bricks edge wall
average 500mm deep rendered on
and including 450mm x 150mm thick concrete
grade 15 foundation and all necessary excavations
and disposal of spoil and formwork to edge of apron
Cement and Sand ( 1: 4 ) as described:- SM 288 @36,000= 10 ,368,000=
1.18 20mm thick rendering to plinth walls
Prepare and apply two coats of bituminous paint on:- SM 184 @8,000= 1,472,000=
1.19 Rendered plinth walls SM 184 @ 8,000= 1,472,000=
Total Carried to Collection
Page E1- 1/ 194,528,000=
Page E1- 2/ 65,924,000=
Total Substructure To Summary 260,452,000=
7. Item Description Unit Quantity Rate(Ushs) Amount ( Ugandan shillings)
Bill No. 2
Element No. 2
Super structure:
Vibrated Insitu reinforced concrete grade
20 mix (1:2:4 / 20mm Aggregate) as
Described:-
2.01 Ring beams CM 24 @400,000= 9,600,000=
Mild steel reinforcement as described including
cutting to lengths, bending, hoisting and fixing
Including all necessary tying wire and
spacing blocks. hoisting and fixing including
all necessary tying wire and spacing blocks. .
2.02 8 mm diameter bar KG 944 @4,000= 3,776,000=
High yield tensile steel bar reinforcement to
BS 4449 as described including cutting to
Lengths, bending, hoisting and fixing including
all necessary tying wire and spacing blocks.
2.03 12 mm diameter bar KG 2,280 @ 4,000= 9,120,000=
Sawn formwork as described to:
8. 2.04 Sides and soffites of beams SM 192 @18,000= 3,456,000=
Damp proof courses : hessian based bituminous
felt: bedded in cement and
Sand (1:3) mortar: 300mm laps.
2.05 Horizontal : 230mm ditto LM 416 @ 2,500= 1,040,000=
Brickwork in burnt clay bricks in cement and
Sand mortar (1:4) mix; with and
Including 25 x 3mm hoop iron strips laid
Horizontally every alternate course.
2.06 230 mm thick below ring beam walling. SM 776 @46,800= 36,316,800=
2.07 230mm Thick above ring beam and gable walling SM 272 @46,800= 12,729,600=
2.08 Labor and materials in eaves filling on
230mm wall for average height of 300mm LM 368 @ 46,800= 17,222,400=
Permanent Vents
2.09 Permanent Vent filled in with Kajjansi
ventilation bricks or other equal and
approved; bat proof gauze and coffee tray
wire backing complete with necessary
timber framing and beading.
SM 8 @58,000= 464,000=
Total Super Structure To Summary 93,724,800=
9. Item Description Unit Quantity Rat (Ushs) Amount (Ugandan shillings)
Bill No. 2
Elemnt No.3
Roof:
Roof Construction
The followings 10nos. Timber trusses each
spanning 6.46M x 1.58M rise,
comprising of well treated members bolted
together to approval as described
and hoisted and fixed in position at about 3.30M
above floor level.
Sawn cypress pressure impregnated with
preservative:-
3.01 50 x 100mm Purlins LM 1400 @ 10,000= 14,000,000=
3.02 50 x 100mm Strut /tie LM 432 @10,000= 4,320,000=
3.03 50 x 150mm Ridge LM 144 @ 12,000= 1,728,000=
3.04 50 x 150mm Tie beam LM 520 @12,000= 6240,000=
3.05 50 x 100mm Rafters LM 752 @10,000= 7,520,000=
3.06 75 x 100mm Wall Plate LM 264 @12,000= 3,168,000=
3.07 75 x 100mm overhangs LM 240 @12,000= 2,880,000=
Roof Covering
3.08 28 Gauge pre-painted iron roofing sheets
fixed with 1.5 side corrugation laps and
150mm end laps with and including approved
10. roofing nails or galvanized steel
drive screws with plastic washers and fller blocks to
manufacturer's instructions. SM 1248 @ 38,000= 47,424,000=
3.09 28 Gauge plain (pre-coated) roll top ridge capping. LM 1368 @ 12,000= 16,416,000=
Eaves
3.10 25 x 225mm Wrot Cypress fascia board
and badge boards LM 416 @ 10,000= 4,160,000
Painting Knot prime stop and apply three coats
of gloss oil paint to timber surfaces.
.
3.11 Knot, prime, stop and apply three coats of gloss
oil paint to wood fascia 200-
300mm girth. SM 144 @ 10,000= 1,440,000=
Total Roof Carried To Summary 103,696,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No.1
11. Element No.4
Doors and Windows:
Windows
Vibrated Precast concrete grade 20
mix (1:2:4 / 20mm aggregate) : units
reinforced as necessary and finished fair
face on all exposed sides as
described:-
4.01 75 x 285 mm sunk weathered and
throated window cill Purpose made steel
casement windows manufactured from
standard W20
sections: manufacture, assemble and deliver
to site : Supply and fix
ironmongery comprising approved hinges
, pivoting mechanisms, stays,
fasteners to opening lights: plugged and screwed
or built into walling : one
coat red oxide primer before delivery. all to LM 160 @3,000= 3,480,000=
Architects details Purpose made steel
casement windows manufactured
from standard W20
sections: manufacture, assemble and
deliver to site : Supply and fix
4.02 Window type W1 : Size 1200 x 1200mm
overall height: NO 112 @ 250,000= 28,000,000=
Glass and Glazing
4.03 4mm thick clear sheet glass to metal
12. window with putty SM 160 @ 7 0,000= 11,200,000=
Prepare touch up primer and apply one
undercoat and two finishing coats of
gloss oil paint : on glazed metal surfaces
4.04 General Surfaces : windows SM 320 @3000= 960,000=
Total Carried to Collection 43,640,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Doors
Purpose made steel casement doors
manufactured from Standard W20
Sections complete as described to
Architects details
4 .05 Door size 900 x 2400mm with
permanent louvered vents 300mm
included : D1 NO 16 @300,000= 4800,000=
Prepare, knot prime, stop and apply
three coats of gloss oil paint: on
woodwork.
4.06 General surface of metal doors SM 72 @ 3,000= 216,000=
13. Supply and fix the following approved
ironmongeries complete with
marching screws, handles and keys
to hard wood.
4.07 Tower bolt complete with Pudlocks NO 16 @ 100,000= 1,600,000=
4.08 25mm diameter rubber door stopper. NO 16 @ 10,000= 160,000=
Total Carried to Collection
COLLECTION
Page E4- 4/ 43,640,000=
Page E4- 5/ 6,776,000=
Total Doors and Windows Carried To Summary 50,416,000=
14. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2
Element No. 5
External Finishes:
Floor Finishes
Cement and sand (1:3) screeds and
pavings : one coat: steel trowell finish :
laid on concrete
5.01 30mm thick screed in the verandah SM 160 @ 10,000 = 1,600,000=
5.02 25 x 200mm skirting with square top
edge and coved junction at bottom of paving. LM 352 @ 10,000 =
3,520,000=
Cement and sand ( 1:4) render trowelled
smooth on concrete or masonry
5.03 15mm to walls. SM 976 @ 10,000 = 9,760,000=
Two coats tyrolene rendering on masonry
5.04 Walls and concrete surfaces SM 544 @8.000= 4,352,000=
Painting: 'Sadolin Paints' or equal and approved.
5.05 Prepare and apply one undercoat
and two finishing coats weaher guard on
plastered surfaces. SM 432 @10,000= 4,320,000=
5.06 Ditto to Tyrolean surfaces. SM 544 @ 10,000= 5,440,000=
15. Total External Walls Finishes Carried To Summary 28,992,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2
Element No.6
Internal Finishes
Floor Finishes
Cement and sand (1:3) screeds and
pavings :
one coat: steel trowell finish :
laid on concrete
6.01 30mm thick screed SM 752 @10,000= 7,520,000=
6.02 25 x 100mm skirting with square top
edge and coved junction at bottom of paving. LM 424 @5000= 2,120,000=
Wall Finishes
Cement and sand ( 1:2:9) lime plaster
trowelled smooth on brick wall or
16. masonry
6.03 15mm thick cement and sand plaster :
steel trowell finish to walls. SM 1280 @10,000= 12,800,000=
Painting
6.04 Prepare and apply one undercoat
and three finishings coats of matt
vinyl paint to
plastered surfaces. SM 1280 10,000= 12,800,000=
Black Board as described:-
6.05 Provide Black board, size:
4200mm long x 1200mm highx 20mm
thick complete
with chalk rails and painted in approved b/b paint NO 16 150,000= 2,400,000=
6.06 Provide3No pin boardsin each classroom,size:
1200mm x1200mm with hard wood
timber framing to approved section design NO 48 150,000= 7,200,000=
Total Internal Finishes Carried To Summary 44,840,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings
Bill No. 2
Element No.7
17. Lightning Protection
Supply, install, connect and set to
work the following, all as described in the
Specifications and Drawings.
7 .01 Copper tape of Hard Drawn High
Conductivity copper plate 3mm x 25mm cross
section for Down Conductors, bonded to
the iron sheet roof complete with fixing
clips and all accessories as by FURSE or equal.
LM 28 @ 40,000 =
1,120,000=
7 .02 Air terminals complete with Tape
Adapter and all accessories as by FURSE or
equal. NO 2 @150,000= 300,000=
7 .03 Test Blocks complete as by FURSE or equal. NO 2 @100,000= 200,000=
7 .04 Earth electrodes made from Hard drawn
copper or copper weld 20mm diameter by
1200mm in two length screwed together
complete
with cap, earth clamp, manhole
and all accessories.
NO 2 120,000= 240,000=
7 .05 50mm diameter heavy duty P.V.C pipe LM 4 10,000= 40,000=
TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY. 1,900,000=
18. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings
Bill No. 2
Element No.8
Rain Water harvest
8 .01 P.V.C downpipes 110mm diameter
complete with all fittings
nessecary for erection
(refer to drawing) LM 96 @6,000= 576,000=
8 .02 P.V.C gutters complete with gutter
brackets at 1000mm c/c including all fittings
nessecary for erection LM 176 @20,000= 3,520,000=
8 .03 5,000 litre pvc tank placed on ground
concrete base (measured separetely),
complete with all accessories. NO 1 @300,000= 300,000=
8 .04 25mm gate valves as Peglar heavy duty
or equal approved. NO 1 @40,000= 40,000=
8 .05 12mm Stand by pipe, complete with
12mm bib tap and all accessories Item 1 @ 37,000= 37,000=
Concrete Tank Base
9 .14 1.5m high Ground concrete water
tank base, made in masonry brickwork, well
compacted hardcore, with 150mm thick
slab on top as shown in drawing, for the
19. above water tank, complete.
NO 2 @ 1.000,000= 2,000,000=
TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000=
SUMMARY FOR PROPOSED CONSTRUCTION OF A PRIMARY SCHOOL AT IGEL
1 SUB-STRUCTURE 260,452,000=
2 SUPERSTRUCTURE 93,724,800=
3 ROOFING 103,696,000=
4 DOORS AND WINDOWS 50,416,000=
5 EXTERNAL FINISHES 28,992,000=
6 INTERNAL FINISHES 44,840,000=
7 LIGHTNING PROTECTION 1,900,000=
8 RAIN WATER HARVEST 6,473,000=
GRAND TOTAL 590,493,800=
20. BUDGET FOR PUTTING UP A SECONDARY SCHOOL 16 BLOCK OF CLASSROOMS
Item Description Unit Quantity Rate(Ushs) Amount(Ushs) Ugandan shillings
Element NO 1
Substructure: (All Provisional)
Site Preparation
1.01 Excavate oversite to remove
top soil average 150mm thick and
remove from site. SM 1504 @ 1000= 1;504,000=
1.02 Treat surface of subsoil or fillings and
surroundings with approved
chemical antitermite
solution: provide ten year guarantee. SM 1504 @ 1000= 1,504,000=
Excavation and Earthworks.
Note: Rates for excavation to
include for keeping excavations
free from water
and planking and strutting
to sides of excavations
1.03 Excavate to reduce levels and
remove from site. CM 216 @ 2000= 432,000=
21. 1.04 Excavate trenches for wall
foundations: commencing from
reduced levels : not
exceeding 1.5m deep . CM 248 @4000= 992,000=
1.05 Extra over excavation for excavating
in rock CM 48 30,000= 1,440,000=
Disposal of excavated material
1.06 Selected excavated material in filling
to foundation trenches : around walling :
placed in 200mm layers : watered and
compacted to 95% MDD CM 176 2000= 352,000=
1.07 Remove surplus excavated
material from site CM 128 4,000= 512,000=
Hardcore
1.08 150mm Filling : deposit, spread, level
and compact : 50mm selected quarry dust
blinding. CM 752 10,000= 7,520,000=
Vibrated Insitu concrete grade 15 mix
(1:3:6 / 20mmaggregate) as described:-
1.09 Foundations in trenches CM 512 10,000= 5,120,000=
Vibrated reinforced concrete grade 20
mix (1:2:4 / 20mm Aggregate) as
described in :-
1.11 Ramp for the Disabled CM 128 150,000= 19,200,000=
1.10 100mm thick ground floor slab SM 9600 10,000= 96,000,000=
22. 1.12 Horizontal Ground beam CM 192 250,000= 48,000,000=
High yield tensile steel bar reinforcement
to BS 4449 as described including
cutting to lengths, bending, hoisting and
fixing including all necessary tying
wire and spacing blocks.
1.12 R8 bars for links KG 944 3,000= 2,832,000=
1.13 Y12 bars. KG 2280 4,000= 9,120,000=
Total Carried to Collection 194,528,000=
Item / Description Unit Quantity Rate(Ushs) Amount (Ushs) Ugandan shillings
Reinforcement
1.12 Mesh reinforcement Ref No.
A98 size 200 x 200 mm weighing 1.54
kg per square metre: in floor slab:
including all necessary supports SM 840 @ 10,000= 8,400,000=
Sawn formwork as described to:
1.13 Vertical edges of surface bed :
over 75mm but not exceeding 150 mm high. LM 368 @ 7,500= 2,760,000=
23. Brickwork in burnt clay bricks in cement and
sand mortar (1:4) mix; with and
including 25 x 3mm hoop iron strips
laid horizontally every alternate course.
1.14 230 mm thick plinth walling. SM 488 @ 40,000= 19,520,000=
Sundries
1.15 One layer 1000 gauge polythene sheet
damp proof membrane Under bed :
300mm laps. SM 840 @9,500= 7,980,000=
1.16
Allow for " Dieldrex " or other approved
anti-termite treatment in sides and bottom
of foundation trenches and ground surface
below hard-core filling( SEE ITEM
No.1.02) SM 1744 @ 8,000= 13,952,000=
Splash apron
1.17
75mm thick concrete (grade 20) splash apron on
75mm hardcore base well rammed and apron
finished with 25mm thick cement and
sand (1:3) screed trowelled smooth to gentle falls
with division strips every 2.00 metre length and
including 150mm thick clay bricks edge wall
average 500mm deep rendered on
and including 450mm x 150mm thick concrete
24. grade 15 foundation and all necessary excavations
and disposal of spoil and formwork to edge of apron
Cement and Sand ( 1: 4 ) as described:- SM 288 @36,000= 10
,368,000=
1.18 20mm thick rendering to plinth walls
Prepare and apply two coats of bituminous paint on:- SM 184 @ 8,000=
1,472,000=
1.19 Rendered plinth walls SM 184 @ 8,000=
1,472,000=
Total Carried to Collection
Page E1- 1/ 194,528,000=
Page E1- 2/ 65,924,000=
Total Substructure To Summary 260,452,000=
25. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings
Bill No. 2
Element No. 2
Super structure:
Vibrated Insitu reinforced concrete grade
20 mix (1:2:4 / 20mm Aggregate) as
described:-
2.01 Ring beams CM 24 @400,000= 9,600,000=
Mild steel reinforcement as described including
cutting to lengths, bending, hoisting and fixing
including all necessary tying wire and
spacing blocks. hoisting and fixing including
all necessary tying wire and spacing blocks. .
2.02 8 mm diameter bar KG 944 @4,000 = 3,776,000=
High yield tensile steel bar reinforcement to
BS 4449 as described including cutting to
lengths, bending, hoisting and fixing including
all necessary tying wire and spacing blocks.
2.03 12 mm diameter bar KG 2,280 @4,000 = 9,120,000=
Sawn formwork as described to:
2.04 Sides and soffites of beams SM 192 @18,000 = 3,456,000=
Damp proof courses : hessian based bituminous
felt: bedded in cement and
sand (1:3) mortar : 300mm laps.
26. 2.05 Horizontal : 230mm ditto LM 416 @2,500 = 1,040,000=
Brickwork in burnt clay bricks in cement and
sand mortar (1:4) mix;with and
including 25 x 3mm hoop iron strips laid
horizontally every alternate course.
2.06 230 mm thick below ring beam walling. SM 776 46,800= 36,316,800=
2.07 230mm Thick above ring beam and gable walling SM 272 46,800= 12,729,600=
2.08 Labour and materials in eaves filling on
230mm wall for average height of 300mm LM 368 46,800= 17,222,400=
Permanent Vents
2.09 Permanent Vent filled in with Kajjansi
ventilation bricks or other equal and
approved; bat proof gauze and coffee tray
wire backing complete with necessary
timber framing and beading.
SM 8 58,000= 464,000=
Total Super Structure To Summary 93,724,800=
27. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings
Bill No. 2
Elemnt No.3
Roof:
Roof Construction
The followings 10nos. Timber trusses each
spanning 6.46M x 1.58M rise,
comprising of well treated members bolted
together to approval as described
and hoisted and fixed in position at about 3.30M
above floor level.
Sawn cypress pressure impregnated with
Preservative:-
3.01 50 x 100mm Purlins LM 1400 @10,000 = 14,000,000=
3.02 50 x 100mm Strut /tie LM 432 @10,000 = 4,320,000=
3.03 50 x 150mm Ridge LM 144 @12,000 = 1,728,000=
3.04 50 x 150mm Tie beam LM 520 @ 12,000 = 6240,000=
3.05 50 x 100mm Rafters LM 752 @10,000 = 7,520,000=
3.06 75 x 100mm Wall Plate LM 264 @12,000 = 3,168,000=
3.07 75 x 100mm overhangs LM 240 @12,000 = 2,880,000=
Roof Covering
3.08 28 Gauge pre-painted iron roofing sheets
fixed with 1.5 side corrugation laps and
150mm end laps with and including approved
roofing nails or galvanized steel
drive screws with plastic washers and fller biocks to
manufacturer's instructions. SM 1248 @38,000= 47,424,000=
28. 3.09 28 Gauge plain (pre-coated) roll top ridge capping. LM 1368 @ 12,000= 16,416,000=
Eaves
3.10 25 x 225mm Wrot Cypress fascia board
and badge boards LM 416 @ 10,000= 4,160,000
Painting Knot prime stop and apply three coats
of gloss oil paint to timber surfaces.
.
3.11 Knot, prime, stop and apply three coats of gloss
oil paint to wood fascia 200-
300mm girth. SM 144 @ 10,000= 1,440,000=
Total Roof Carried To Summary 103,696,000=
29. Item Description Unit Quantity Rate (Ushs) Amount (Ushs) Ugandan shillings
Bill No.1
Element No.4
Doors and Windows:
Windows
Vibrated Precast concrete grade 20
mix (1:2:4 / 20mm aggregate) : units
reinforced as necessary and finished fair
face on all exposed sides as
described:-
4.01 75 x 285 mm sunk weathered and
throated window cill Purpose made steel
casement windows manufactured from
standard W20
sections: manufacture, assemble and deliver
to site : Supply and fix
ironmongery comprising approved hinges
, pivoting mechanisms, stays,
fasteners to opening lights: plugged and screwed
or built into walling : one
coat red oxide primer before delivery. all to LM 160 @3000 = 3,480,000=
Architects details Purpose made steel
casement windows manufactured
from standard W20
sections: manufacture, assemble and
deliver to site : Supply and fix
4.02 Window type W1 : Size 1200 x 1200mm
30. overall height: NO 112 @250,000 = 28,000,000=
Glass and Glazing
4.03 4mm thick clear sheet glass to metal
window with putty SM 160 70,000= 11,200,000=
Prepare touch up primer and apply one
undercoat and two finishing coats of
gloss oil paint : on glazed metal surfaces
4.04 General Surfaces : windows SM 320 3000= 960,000=
Total Carried to Collection 43,640,000=
31. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Doors
Purpose made steel casement doors
manufactured from Standard W20
Sections complete as described to
Architects details
4 .05 Door size 900 x 2400mm with
permanent louvered vents 300mm
included : D1 NO 16 @300,000 = 4,800,000=
Prepare, knot prime, stop and apply
three coats of gloss oil paint: on
woodwork.
4.06 General surface of metal doors SM 72 @ 3,000 =
216,000=
Supply and fix the following approved
ironmongeries complete with
marching screws, handles and keys
to hard wood.
4.07 Tower bolt complete with Padlocks NO 16 @ 100,000 =
1,600,000=
4.08 25mm diameter rubber door stopper. NO 16 @10,000=
160,000 =
Total Carried to Collection 0
COLLECTION
Page E4- 4/ 43,640,000=
32. Page E4- 5/ 6,776,000=
Total Doors and Windows Carried To Summary 50,416,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2
Element No. 5
External Finishes:
Floor Finishes
Cement and sand (1:3) screeds and
pavings : one coat: steel trowell finish :
laid on concrete
5.01 30mm thick screed in the verandah SM 160 @ 10,000 = 1,600,000=
5.02 25 x 200mm skirting with square top
edge and coved junction at bottom of paving. LM 352 @10,000 = 3,520,000=
Cement and sand ( 1:4) render trowelled
smooth on concrete or masonry
5.03 15mm to walls. SM 976 @ 10,000 = 9,760,000=
Two coats tyrolene rendering on masonry
5.04 Walls and concrete surfaces SM 544 @ 8.000 = 4,352,000=
33. Painting : 'Sadolin Paints' or equal and approved.
5.05 Prepare and apply one undercoat
and two finishing coats weaher guard on
plastered surfaces. SM 432 @ 10,000 = 4,320,000=
5.06 Ditto to tyrolean surfaces. SM 544 @ 10,000 = 5,440,000=
Total External Walls Finishes Carried To Summary 28,992,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2
Element No.6
Internal Finishes
Floor Finishes
Cement and sand (1:3) screeds and
pavings :
one coat: steel trowell finish :
laid on concrete
6.01 30mm thick screed SM 752 @10,000 = 7,520,000
6.02 25 x 100mm skirting with square top
edge and coved junction at bottom of paving. LM 424 @5000 = 2,120,000
Wall Finishes
Cement and sand ( 1:2:9) lime plaster
trowelled smooth on brick wall or
masonry
34. 6.03 15mm thick cement and sand plaster :
steel trowell finish to walls. SM 1280 @ 10,000 = 12,800,000
Painting
6.04 Prepare and apply one undercoat
and three finishings coats of matt
vinyl paint to
plastered surfaces. SM 1280 @10,000 = 12,800,000=
Black Board as described:-
6.05 Provide Black board, size:
4200mm long x 1200mm highx 20mm
thick complete
with chalk rails and painted in approved b/b paint NO 16 @ 150,000 = 2,400,000=
6.06 Provide3No pin boardsin each classroom,size:
1200mm x1200mm with hard wood
timber framing to approved section design NO 48 150,000= 7,200,000=
Total Internal Finishes Carried To Summary 44,840,000=
Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
35. Bill No. 2
Element No.7
Lightning Protection
Supply, install, connect and set to
work the following, all as described in the
Specifications and Drawings.
7 .01 Copper tape of Hard Drawn High
conductivity copper plate 3mm x 25mm cross
section for Down Conductors,bonded to
the iron sheet roof complete with fixing
clips and all accessories as by FURSE or equal.
LM 28 40,000= 1,120,000=
7 .02 Air terminals complete with Tape
Adapter and all accessories as by FURSE or
equal. NO 2 150,000= 300,000=
7 .03 Test Blocks complete as by FURSE or equal. NO 2 100,000= 200,000=
7 .04 Earth electrodes made from Hard drawn
copper or copper weld 20mm diameter by
1200mm in two length screwed together
complete
with cap, earth clamp, manhole
and all accessories.
NO 2 120,000= 240,000=
7 .05 50mm diameter heavy duty P.V.C pipe LM 4 10,000= 40,000=
TOTAL LIGHTNING PROTECTION CARRIED TO SUMMARY. 1,900,000=
36. Item Description Unit Quantity Rate (Ushs) Amount (Ugandan shillings)
Bill No. 2
Element No.8
Rain Water harvest
8 .01 P.V.C downpipes 110mm diameter
complete with all fittings
nessecary for erection
(refer to drawing) LM 96 @ 6,000 = 576,000=
8 .02 P.V.C gutters complete with gutter
brackets at 1000mm c/c including all fittings
nessecary for erection LM 176 @20,000 = 3,520,000=
8 .03 5,000 litre pvc tank placed on ground
concrete base (measured separetely),
complete with all accessories. NO 1 @300,000= 300,000=
8 .04 25mm gate valves as Peglar heavy duty
or equal approved. NO 1 @ 40,000= 40,000=
37. 8 .05 12mm Stand by pipe, complete with
12mm bib tap and all accessories Item 1 @ 37,000= 37,000=
Concrete Tank Base
9 .14 1.5m high Ground concrete water
tank base, made in masonry brickwork, well
compacted hardcore, with 150mm thick
slab on top as shown in drawing, for the
above water tank, complete.
NO 2 @ 1000,000=
2,000,000=
TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000=
SUMMARY FOR PROPOSED CONSTRUCTION OF A SECONDARY SCHOOL AT IGEL
1 SUBSTRUCTURE 260,452,000=
2 SUPERSTRUCTURE 93,724,800=
3 ROOFING 103,696,000=
4 DOORS AND WINDOWS 50,416,000=
5 EXTERNAL FINISHES 28,992,000=
6 INTERNAL FINISHES 44,840,000=
7 LIGHTNING PROTECTION 1,900,000=
38. 8 RAIN WATER HARVEST 6,473,000=
GRAND TOTAL 590,493,800=
BUDGET FOR THE PROPOSED CONSTRUCTION OF 5 STANCE DRAINABLE PIT LATRINE
FOR BOTH THE PRIMARY ,HEALTH CENTRE AND SECONDARY SCHOOL AT IGEL KOLE
DISTRICT.
Item Description Unit Quantity Rate [Ushs) Amount [ Ugandan shillings)
BILL No 5
ELEMENT NO 1
SUBSTRUCTURE
(All Provisional)
Site Preparation
1.01 Excavate oversite
to remove top
soil average 150mm thick and
remove from site. SM 51 @ 1000 = 51,000=
39. 1.02 Treat surface of subsoil or
fillings and surroundings with
approved chemical
anti-termite solution:
provide ten year guarantee. SM 51 @300= 15,300=
Excavation and Earthworks.
Note: Rates for excavation to include
for keeping excavations free
from water and planking
and strutting to sides of excavations
1.03 Excavate to reduce levels
and remove from site. CM 15 @ 10,000= 150,000=
1.04 Excavate pit including all
earth work support and keeping
excavations free from water
and mud up to 1.5m CM N/A
1.05 Ditto but up to 3m CM 22 @ 30,000= 660,000=
1.06 Ditto but up to 4m CM N/A
1.07 Extra over excavation
for excavating in rock CM 5 @30,000= 150,000=
Disposal of excavated material
1.08 Selected excavated material
in filling to foundation trenches :
around walling : placed in 200mm layers
: watered and compacted to 95% MDD CM 3 @30,000= 90,000=
40. 1.09 Remove surplus excavated
material from site CM 43 @ 20,000= 860,000=
1.10 150mm Filling : deposit, spread,
level and compact : 50mm selected
quarry dust blinding. SM 22 @5,000= 110,000=
Insitu concrete grade 20
mix (1:2:4 / 20mm aggregate) as described:-
1.11 150mm thick pit floor bed using
mix 1:2:4 mass concrete CM 2 @200,000= 400,000=
1.12 230x 230mm columns and
beams mix 1:2:4/19mm CM 3 @400,000= 1,200,000=
1.13 100mm thick reinforced suspended floor
slab using mix 1:2:4 concrete. SM 13 @30,000= 390,000=
Total Carried to Collection 4,476,300=
Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
41. Vibrated Insitu reinforced
concrete grade 20
mix (1:2:4 / 20mm aggregate)
as described:-
1.14 100mm thick slab in verandah SM 12 @30,000= 360,000=
1.15 Ramp for the Disabled CM 1 @200,000= 200,000=
Reinforcement
1.16 Mesh reinforcement
Ref No. A98 size 200 x 200 mm
weighing 1.54 kg per square metre:
in floor slab:
including all necessary supports SM 21 @20,000= 440,000=
Mild steel rod reinforcement
as described.
1.17 8 mm diameter bar KG 52 @3000= 156,000=
High yield tensile steel bar
reinforcement to
BS 4449 as described.
1.18 12 mm diameter bar KG 121 @ 4000= 484,000=
Sawn formwork as described to:
1.19 230x230mm columns: over
75mm but not exceeding 150
mm high. LM 50 @10,000= 500,000=
1.20 Sides of the pit ringbeam
300mm wide: over 75mm but
42. not exceeding 150 mm high. LM 8 @10,000= 80,000=
1.21 Soffit of 100mm thick slab:
over 75mm but not exceeding
150 mm high. SM 25 @ 20,000= 500,000=
1.22 Edge of slab 100mm high:
over 75mm but not
exceeding 150 mm high. LM 25 @10,000= 250,000=
Brickwork in burnt clay bricks
in cement and sand mortar (1:3) mix;
with and including 25 x
3mm hoop iron strips laid
horizontally every alternate course.
1.23 230 mm thick plinth walling. SM 45 @46,800= 2,106,000=
1000 gauge vertical DPM SM 50 0
Finishes to the pit
1.24 15mm cement and sand
(1:4 mix) trawelled smooth and
hard using water resistant
cement additive. SM 53 10,000= 530,000=
1.25 25mm cement,sand screed finished
smooth to a gentle slope SM 23 10,000= 230,000=
Vent pipe
1.26 Supply and fix 3No 100mm diameter
uPVC vent pipes 3.5m long with
fly screen at the top complete
with mosquito wire netting. LM 11 10,000= 110,000=
43. Total Carried to Collection
Splash apron
1.27
75mm thick concrete (grade 20)
splash apron on 75mm hardcore
base well rammed and apron
finished with 25mm thick cement
and sand (1:3) screed trowelled
smooth to gentle falls with division
strips every 2.00 metre length and
including 150mm thick clay bricks edge
wall average 500mm deep
rendered on and including
450mm x 150mm thick concrete grade 15
foundation and all necessary
excavations and disposal of spoil and
formwork to edge of apron SM 11 @ 30,000= 330,000=
Total Carried to Collection 6,276,000=
44. Item Description Unit Quantity Rate
(Ushs)
Amount
(Ushs)
COLLECTION
Page E1- 1/ 4,476,300=
Page E1- 2/ 6,276,000=
TOTAL SUBSTRUCTURE CARRIED TO SUMMARY 10,752,300=
Item Description Unit Quantity Rate Ushs) Amount Ugandan
shillings)
ELEMENT NO. 2
SUPER STRUCTURE
Vibrated Insitu reinforced
concrete grade 20 mix
(1:2:4 / 20mm Aggregate)
as described:-
2.01 Ring beams CM 1 @400,000= 400,000=
Mild steel reinforcement as
described including cutting to
lengths, bending, hoisting and
45. fixing including all necessary
tying wire and spacing blocks.
2.02 8 mm diameter bar KG 30 @ 3,000= 90,000=
High yield tensile steel bar
reinforcement to BS 4449 as
described including cutting to
lengths, bending, hoisting and
fixing including all necessary
tying wire and spacing blocks.
2.03 12 mm diameter bar KG 88 @4,000= 352,000=
Sawn formwork as described to:
2.04 Sides and soffites of beams SM 14 @10,000= 140,000=
Damp proof courses : hessian based
bituminous felt: bedded in cement
and sand (1:3) mortar : 300mm laps.
2.05 Horizontal : 200mm ditto LM 28 @ 2500= 70,000=
Brickwork in burnt clay bricks
in cement and sand mortar
(1:3) mix;with and including 25 x
3mm hoop iron strips laid horizontally
every alternate course.
2.06 230mm thick below
ring beam walling. SM 49 @46,800= 2,293,200=
2.07
Labour and materials in eaves
46. filling on 230mm wall for average
height of 300mm LM 32 @10,000= 320,000=
Permanent Vents
2.08 Permanent Vent filled in with
Kajjansi ventilation bricks or other
equal and approved; bat proof gauze
and coffee tray wire backing complete
with necessary timber
framing and beading. SM 1 @60,000= 60,000=
Disability Handrail
2.08 Provide handrials for the disabled
comprised of 35mm diameter
MS grip bars for the diasbled
complete installed to architects details Item 1 150,000= 150,000=
TOTAL SUPER STRUCTURE CARRIED TO SUMMARY 3,875,200=
…………………………………………………………………………………………………………………
…………………………….
47. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 3
ROOF
Roof Construction
The following in roof
construction including all
bolting, gusset plates, fixing
trusses to ring
beams with holding down bolts
and hoisting and fixing
approximately 3.0mm above ground
level.
Sawn cypress pressure impregnated
with preservative:-
3.01 50 x 100mm Purlins LM 20 @10,000= 200,000=
3.02 50 x 150mm Rafters LM 11 @12,000= 132,000=
3.03 75 x 100mm Wall Plate LM 13 @ 12,000= 144,000=
Roof Covering
3.04 28 Gauge pre-painted iron
roofing sheets fixed with 1.5 side
corrugation laps and 150mm end laps
with and including approved
roofing nails or galvanized
steel drive screws with
plastic washers to
manufacturer's instructions. SM 18 @ 38,000= 684,000=
48. Eaves
3.05 25 x 225mm Wrot
Cypress fascia board Painting LM 18 @15,000= 270,000=
Painting
Knot prime stop and apply three
coats of gloss oil paint to timber surfaces.
3.06 Knot, prime, stop and apply
three coats of gloss oil paint to
wood fascia 200-300mm girth. SM 9 @10,000= 90,000=
TOTAL ROOF CARRIED TO SUMMARY 1,520,000=
49. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 4
DOORS
Doors
Purpose made steel casement
doors manufactured from
Standard W20
Sections complete as
described to Architects details
4.01 Door size 900 x 2400mm
with permanent louvered vents
300mm included. NO 6 200,000= 1,200,000=
Prepare, knot prime, stop
and apply three coats of
gloss oil paint: on metal
4.02 General Surfaces : doors SM 23 3,000= 69,000=
Supply and fix the following
approved ironmongeries complete
with marching screws,
handles and keys to hard wood.
4.03 Tower bolt complete
with Pudlocks NO 6 30,000= 180,000=
TOTAL DOORS AND WINDOWS CARRIED TO SUMMARY 1,449,000=
50. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 5
EXTERNAL FINISHES
Floor Finishes
Cement and sand (1:3) screeds
and pavings : one coat:
steel trowell finish :
laid on concrete
5.01 30mm thick screed in
the verandah aand ramps SM 15 @10,000= 150,000=
5.02 25 x 200mm skirting with
square top edge and coved
junction at bottom of paving. LM 6 @ 5000= 30,000=
Cement and sand ( 1:4) render
trowelled smooth on
concrete or masonry
5.03 15mm to walls. SM 56 @10,000= 560,000=
Two coats tyrolene rendering
on masonry
5.04 Walls and concrete surfaces SM 56 @5000= 280,000=
Painting : 'Sadolin Paints' or
51. equal and approved.
5.05 Prepare and apply one
undercoat and two finishing coats
weather guard paint
on plastered surfaces. SM 15 @10,000= 150,000=
5.06 Ditto to tyrolean surfaces Item 56 10,000= 560,000=
5.07 Supply and fix to position
standard engraved foundation
stones from approved product
from either
slates or marbles or terrazzo
to engineer's details. Item 1 150,000= 150,000=
TOTAL EXTERNAL WALLS FINISHES CARRIED TO SUMMARY 1,880,000=
Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 6
INTERNAL FINISHES
Floor Finishes
Cement and sand (1:3) screeds
and pavings : one coat:
52. steel trowell finish :
aid on concrete
6.01 30mm thick screed SM 11 @10,000= 110,000=
6.02 25 x 200mm skirting with
square top edge and coved junction
at bottom of paving. LM 27 @ 5,000= 135,000=
Wall Finishes
6.03 15mm thick cement and
sand plaster : steel trowell finish
to walls. SM 55 @ 10,000= 550,000=
Painting
6.04 Prepare and apply one
undercoat and three finishings
coats matt vinyl paint to
plastered surfaces. SM 55 @10,000= 550,000=
TOTAL INTERNAL FINISHES CARRIED TO SUMMARY 1,345,000= Ugandan shillings
…………………………………………………………………………………………………………………
……………………….
53. ELEMENT NO. 7
WATER SUPPLY
Supply, install, connect and
set to work the following,
all as described in the Specifications
and Drawings.
Water Supply
7.01 250 litre uPVC tank placed on
ground concrete base
(measured separately ) ,complete
with lockable
tap and washout approved NO 1 @500,000= 500,000=
7.03 Install 4"PVC pipe with approved
floor trap to urinal, including splash
apron for hand washing tanks NO 3 @50,000= 150,000=
7.04
1m high ground concrete water
tank base made in masonry brickwork,
well compacted with 150mm
thick slab on top as directed on site
for the tanks as above complete
with 1x1m spash apron,
concealed drain pipe and soakaway
complete
.(inc. metallic lockable burgler proffing metallic grills
engraved in concrete for protecting the tank) NO 1 @500,000= 500,000=
54. 7.05 Provive sock away pit size 1.5m
diameter and 1.2m depth complete
with drain pipe/floor trap from
urinal or wash room. Item 1 100,000=
TOTAL WATER SUPPLY CARRIED TO SUMMARY. 1,250,000=
55. BILL No 5
SUMMARY FOR PROPOSED CONSTRUCTION OF1 BLOCK OF 5 STANCE VIP LATRINE IN
SCHOOL IN IGEL KOLE DISTRICT
1 SUBSTRUCTURE 10,752,300=
2 SUPERSTRUCTURE 3,875,200=
3 ROOFING 1,520,000=
4 DOORS 1,449,000=
5 EXTERNAL FINISHES 1,880,000=
6 INTERNAL FINISHES 1,345,000=
7 WATER SUPPLY 1,250,000=
FIVE STANCE VIP LATINE TOTAL TO SUMMARY FOR
PRIMARY HEALTH CENTRE AND SECONDARY WE MULTIPLY FUGURE X3
22,071,500= x 3
56. BUDGET FOR THE PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE
DISTRICT.
Item Description Unit Quantity Rate [Ushs) Amount [Ugandan shillings)
ELEMENT NO 1
SUBSTRUCTURE (All Provisional)
Site Preparation
1.01 Excavate over site to remove
Top soil average 150mm thick and
Remove from site. SM 324 @1,000= 324,000=
1.03 Treat surface of subsoil or
1.04 fillings and surroundings
1.05 with approved
1.06 chemical anti-termite
Solution: provide
Ten year guarantee. SM 324 @ 1,000= 324,000=
Excavation and Earthworks.
Note: Rates for excavation to
57. Include for keeping excavations
Free from water
And planking and strutting to
Sides of excavations
1.03 Excavate to reduce levels
And remove from site. CM 54 @5,000= 270,000=
1.04 Excavate trenches for wall
Foundations: commencing
From reduced levels: not
Exceeding 1.5m deep. CM 81 @ 5,000= 405,000=
1.05 Extra over excavation
For excavating in rock CM 5 @30,000= 150,000=
Disposal of excavated material
1.07 Selected excavated material
1.08 in filling to foundation trenches :
1.09 around walling :
Placed in 200mm layers: watered and
Compacted to 95% MDD CM 60 @ 5,000= 300,000=
1.07 Remove surplus excavated
material from site CM 11 @20,000= 220,000=
Hardcore
1.08 150mm Filling: deposit, spread,
Level and compact: 50mm selected
Quarry dust
Blinding. SM 324 @ 5,000= 1,620,000=
Vibrated Insitu concrete grade 15
58. Mix (1:3:6 / 20mm aggregate) as described:-
1.09 Foundations in trenches CM 14 @200,000= 2,800,000=
Vibrated reinforced concrete grade 20
Mix (1:2:4) as described in :-
1.10 100mm thick ground floor slab SM 105 @ 30,000= 3,150,000=
1.11 Ramp for the Disabled SM 9 @30,000= 270,000=
Total Carried to Collection 9,833,000=
Item Description Unit Quantity Rate Ushs) Amount Ushs)
Reinforcement
1.12 Mesh reinforcement
Ref No. A98 size 200 x 200 mm
weighing 1.54 kg per square
metre: in floor slab: including
all necessary supports SM 95 @11,500= 1,092,500=
Sawn formwork as described to:
59. 1.13 Vertical edges of surface bed:
over 75mm but not exceeding
150 mm high. LM 44 @ 7,500= 330,000=
Brickwork in burnt clay bricks in
Cement and sand mortar (1:4) mix;
With and
Including 25 x 3mm hoop iron
strips laid horizontally
every alternate course.
1.14 230 mm thick plinth walling. SM 88 @46,800= 4,118,400=
Sundries
1.15 One layer 1000 gauge
polythene sheet damp proof
membrane Under bed : 300mm
laps. SM 95 @5,000= 475,000=
1.16
Allow for " Dieldrex " or other
approved anti-termite treatment
in sides and bottom
of foundation trenches and
ground surface below
hard-core filling(SEE ITEM
No.1.02) SM 335 @300= 100,500=
Splash apron
1.17
75mm thick concrete (grade 20)
60. splash apron on 75mm
hardcore base well
rammed and apron finished
with 25mm thick cement
and sand (1:3) screed
trowelled smooth to gentle
falls with division strips every 2.00
metre length and
Including 150mm thick concrete
Block edge wall average 500mm
Deep rendered on
And including 450mm x 150mm thick
Concrete grade 15 foundation and all
necessary excavations and disposal
of spoil and formwork to edge of apron SM 27 30,000= 810,000=
Cement and Sand ( 1: 4 ) as described:-
1.18 Plinth Rendering SM 19 10,000= 190,000=
Prepare and apply two coats of
bituminous paint on:-
1.19 Rendered plinth walls SM 19 10,000= 190,000=
Total Carried to Collection 7,306,400=
COLLECTION
Page E1- 1/ 9,833,000=
Page E1- 2/ 7,306,400=
61. TOTAL SUBSTRUCTURE TO SUMMARY 17,139,400=
ELEMENT NO. 2
SUPER STRUCTURE
Insitu concrete grade 20 / 20mm:
Vibrated, reinforced as described
2.01 Ring beams CM 6 @400,000= 2,400,000=
Mild steel reinforcement as described
including cutting to lengths, bending,
hoisting and fixing including all
necessary tying wire and spacing blocks.
2.02 8 mm diameter bar KG 107 @ 3,000= 321,000=
High yield tensile steel bar reinforcement
to BS 4449 as described including
cutting to lengths, bending, hoisting and
fixing including all necessary tying
wire and spacing blocks.
2.03 12 mm diameter bar KG 263 @4,000= 1,052,000=
Sawn formwork as described to:
2.04 Sides and soffites of beams SM 42 @ 10,000= 420,000=
Damp proof courses : hessian based
bituminous felt: bedded in cement and
sand (1:3) mortar : 300mm laps.
2.05 Horizontal : 200mm ditto LM 99 @ 2,500= 247,500=
Brickwork in burnt clay bricks in cement
62. and sand mortar (1:4) mix;with and
including 25 x 3mm hoop iron strips laid
horizontally every alternate course.
2.06 230 mm thick below ring beam walling. SM 233 @46,800= 10,904,400=
2.07 230mm Thick above ring
beam and gable walling SM 73 @46,800= 3,416,400=
2.08 Labour and materials in eaves filling
on 230mm wall for average height of 300mm LM 77 @5,000= 385,000=
Permanent Vents
2.09
Permanent Vent filled in with Kajjansi ventilation
bricks or other equal and
approved; bat proof gauze and coffee tray
wire backing complete with necessary
timber framing and beading.
SM 1 @ 60,000= 60,000=
TOTAL SUPER STRUCTURE TO SUMMARY 19,206,300=
Ugandan shillings
63. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 3
ROOF
Roof Construction
The followings 06nos. Timber
trusses each spanning
8.12M x 1.98M rise,
comprising of well treated
members bolted together to
approval as described
and hoisted and fixed in position
at about 3.30M above floor level.
Sawn cypress/ pine pressure
impregnated with preservative:-
3.01 50 x 100mm Purlins LM 145 @ 10,000= 1,450,000=
3.02 50 x 100mm Strut /tie LM 130 @10,000= 1,300,000=
3.04 50 x 150mm Tie beam LM 155 @ 12,000= 1,860,000=
3.05 50 x 100mm Rafters LM 120 @10,000= 1,200,000=
3.06 75 x 100mm Wall Plate LM 55 @12,000= 144,000=
Roof Covering
3.07
28 Gauge pre-painted iron roofing
sheets fixed with 1 ½ side
corrugation laps and
150mm end laps with and including
64. filler blocks at the ridges, approved roofing
nails or galvanized steel drive screws
with plastic washers to manufacturer's
instructions.
SM 166 @38,000= 6,308,000=
3.08 28 Gauge plain (pre-coated)
roll top ridge capping. LM 22 @12,000= 264,000=
Eaves
3.09 25 x 225mm Wrot Cypress/ pine fascia
board LM 61 @15,000= 915,000=
3.10 100 x 50 mm wrot cypress or pine
in fascia and badge board carriers LM 61 @15,000= 915,000=
Painting
Knot prime stop and apply three coats
of gloss oil paint to timber surfaces.
3.11 Knot, prime, stop and apply three coats
of gloss oil paint to wood fascia 200-
300mm girth. SM 26 @7500= 195,000=
TOTAL ROOF CARRIED TO SUMMARY 14,551,000=
Ugandan shillings
65. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 4
DOORS AND WINDOWS
Windows
Precast concrete grade 25 / 20mm
]aggregate : units reinforced
as necessary
and finished fair face on
all exposed sides.
4.01 75 x 285 mm sunk weathered
and throated window cill LM 11 @55,000= 605,000=
Purpose made steel casement
windows manufactured from
standard W20
sections: manufacture, assemble
and deliver to site : Supply and fix
ironmongery comprising
approved hinges, pivoting
mechanisms, stays,
fasteners to opening lights:
plugged and screwed or
built into walling : one
4.02 Window type W1 :
Size 1500 x 1500mm overall height: NO 6 @300,000= 1,800,000=
66. 4.04 Window type W3 :
Size 900 x 900mm overall height: NO 2 200,000= 400,000=
Burglar proofing grille comprising
12mm square bars 150mm centres both
ways in cobweb pattern as described.
4.06 Window type W1 :
Size 1500 x 1500mm overall height: NO 6 150,000= 900,000=
4.08 Window type W3 :
Size 900 x 900mm overall height: NO 2 100,000= 200,000=
Glass and Glazing
4.10 4mm thick clear sheet glass to metal
window with putty SM 9 78,000 702,000=
4.11 Ditto but obscure glass SM 2 78,000 156,000=
Prepare touch up primer and apply one
undercoat and two finishing coats of
gloss oil paint : on glazed metal surfaces
4.12 General Surfaces : windows SM 24 3000= 72,000=
Total Carried to Collection 4,835,000= Ugandan
shillings
67. Item Description Unit Quantity Rate Ushs) ( Amount Ugandan shillings)
Doors
Wrot Mahogany : selected and
kept clean.
4.13
Supply and fix 1.5mm thick
metallic door frame (Jamb profile)
size:900 x2400mm
comprising 300mm high lourved
vent for full width.door
shutter size 800 x2100mm NO 6 @ 200,000= 1,200,000=
all to Architects details
Purpose made steel casement
doors (including frames)
manufactured from
Standard W20 Sections
complete as described to
Architects details
4.15 Door size 1200 x 2400mm with
permanent louvered vents 300mm
included.(D1) NO 2 @500,000= 1,000,000=
4.16 Door size 900 x 2400mm with
permanent louvered vents
68. 300mm included.(D2) NO 2 @400,000= 800,000=
Prepare, knot prime, stop and
apply three coats of gloss oil paint: on
woodwork.
4.17 General Surfaces : doors SM 23 @ 3000= 69,000=
4.18 Ditto but general surface
of metal doors SM 9 @ 3000= 27,000=
Supply and fix the following approved
Ironmongeries complete with marching
screws, handles and keys to hard wood.
4.19 4 - Lever mortice lock as for Union
England ( or Italy ) specially
made for external Casement door. NO 2 @200,000= 400,000=
4.20 3-lever mortise lock Code No. 2277 NO 8 @ 100,000= 800,000=
4.21 25mm diameter rubber door stopper. NO 8 @10,000= 80,000=
4.22 Supply and fix purpose made steel
door frames in jamb
profile 1.5mm thick all to
Architects detail NO 6 @ 200,000= 1,200,000=
Total Carried to Collection
COLLECTION
Page E4- 4/ 4,835,000=
Page E4- 5/ 5,576,000=
TOTAL DOORS AND WINDOWS TO SUMMARY 10,411,000=
Ugandan shillings
69. Item Description Unit Quantity Rate Ushs) Amount Ugandan shillings)
ELEMENT NO. 5
EXTERNAL FINISHES
Floor Finishes
Cement and sand (1:3) screeds
and pavings : one coat:
steel trowell finish :
laid on concrete
5.01 30mm thick screed in
the verandah SM 6 @ 10,000= 60,000=
5.02 25 x 200mm skirting with square
top edge and coved junction at
bottom of paving. LM 10 @5000= 50,000=
Cement and sand ( 1:4) render
trowelled smooth on
concrete or masonry
5.03 15mm to walls. SM 129 @10,000= 1,290,000=
Two coats tyrolene
rendering on masonry
5.04 Walls and concrete surfaces SM 128 @10,000= 1,280,000=
70. Painting : 'Sadolin Paints' or
equal and approved.
5.05 Prepare and apply one undercoat
and two finishing coats
of weather guard on
plastered surfaces. SM 129 @ 10,000= 1,290,000=
5.06 Ditto to tyrolean surfaces SM 128 @10,000= 1,280,000=
TOTAL EXTERNAL FINISHESTO SUMMARY 5,250,000=
Ugandan shillings
Item Description Unit Quantity Rate Ushs) (Amount Ugandan shillings)
ELEMENT NO. 6
INTERNAL FINISHES
Floor Finishes
Cement and sand (1:3) screeds
and pavings : one coat: steel
trowell finish :
laid on concrete
6.01 30mm thick screed SM 78 @ 10,000= 780,000
71. 6.02 25 x 200mm skirting with
square top edge and coved junction
at bottom of paving. LM 97 @ 5000= 485,000=
Wall Finishes
6.03 15mm thick cement and sand
plaster : steel trowell finish to walls. SM 270 @ 10,000= 2,700,000=
Painting
6.04 Prepare and apply one
undercoat and three finishings coats
of matt vinyl paint to
plastered surfaces. SM 270 @10,000= 2,700,000=
Ceiling Finishes
6.05 9 x 24 SWG galvanized expanded
metal lathing U-nailed to timber
branderings SM 78 @5000= 780,000=
6.06 Cement and sand (1:4)
pricking course to metal lathing SM 78 @10,000= 780,000=
6.07 12mm cement and sand plaster
to ceiling SM 78 @ 10,000= 780,000=
6.08 Extra for 150 x 15mm thick
cement and sand cornice LM 120 @5,000= 600,000=
Pressure impregnated sawn Cypress
6.09 50 x 100mm branderings LM 140 @2000= 280,000=
6.10 50 x 100mm joists LM 153 @ 2000= 306,000=
72. Prepare and apply three coats of first
grade emulsion paint on:.
6.11 Plastered ceiling SM 78 @ 10,000= 780,000=
6.12 Cornice : Over 100 but
not exceeding 200mm girth. LM 120 @ 2000= 240,000=
TOTAL INTERNAL FINISHES TO SUMMARY. 10,431,000=
Ugandan Shilling
Item Description Unit Quantity Rate Ushs) { Amount in Ugandan shillings)
ELEMENT NO. 7
LIGHTNING PROTECTION
Supply, install, connect and set to
work the following, all as
described in the
Specifications and Drawings.
Lightning Protection.
7.01
Copper tape of Hard Drawn High
conductivity copper plate
73. 3mm x 25mm cross
section for Down Conductors,
bonded to the iron sheet roof
complete with fixing
clips and all accessories as by
FURSE or equal. LM 21 @ 40,000= 840,000=
7 .02 Air terminals complete with
Tape Adapter and all
accessories as by FURSE or
equal. NO 2 @150,000= 300,000=
7 .03 Test Blocks complete
as by FURSE or equal. NO 2 @100,000= 200,000=
7 .04
Earth electrodes made from Hard
drawn copper or copper weld 20mm
diameter by
1200mm in two length screwed
together complete with cap,
earth clamp, manhole
and all accessories.
NO 2 @ 120,000= 240,000=
7.05 50 mmm diameter heavy
duty P.V.C pipe LM 4 @ 10,000= 40,000=
74. TOTAL ELECTRICAL INSTALLATION SUMMARY. 1,620,000= Ugandan Shilling
Item Description Unit Quantity Rate (Ushs) Amount(Ushs)
Bill No. 2
Element No.8
Rain Water harvest
8 .01 P.V.C downpipes 110mm diameter
complete with all fittings
nessecary for erection
(refer to drawing) LM 96 @6,000= 576,000=
8 .02 P.V.C gutters complete with gutter
brackets at 1000mm c/c including all fittings
nessecary for erection LM 176 @20,000= 3,520,000=
8 .03 5,000 litre pvc tank placed on ground
concrete base (measured separetely),
75. complete with all accessories. NO 1 @ 300,000= 300,000=
8 .04 25mm gate valves as Peglar heavy duty
or equal approved. NO 1 @40,000= 40,000=
8 .05 12mm Stand by pipe, complete with
12mm bib tap and all accessories Item 1 @ 37,000= 37,000=
Concrete Tank Base
8 .06 1.5m high Ground concrete water
tank base, made in masonry brickwork, well
compacted hardcore, with 150mm thick
slab on top as shown in drawing, for the
above water tank, complete.
NO 2 @ 1000,000= 2,000,000=
TOTAL RAIN WATER HARVEST CARRIED TO SUMMARY 6,473,000=
Ugandan Shilling
76. Bill No.6
SUMMARY OF PROPOSED CONSTRUCTION OF HEALTH CENTRE AT IGEL KOLE
DISTRICT
1 - SUB-STRUCTURE 17,139,400=
2 -SUPERSTRUCTURE 19,206,300=
3 -ROOFING 14,551,000=
4 -DOORS AND WINDOWS 10,411,000=
5 -EXTERNAL FINISHES 5,250,000=
6 - INTERNAL FINISHES 10,431,000=
7 - LIGHTNING PROTECTION 1,620,000=
8 - RAIN WATER HARVEST 6,473,000=
GRAND TOTAL 85,081,700 Ugandan Shilling