SlideShare ist ein Scribd-Unternehmen logo
1 von 26
Downloaden Sie, um offline zu lesen
John Tumazos
Very Independent Research
Metals and Natural Resources Conference
Presenter: Navin Dyal, CFO
Monday, March 30, 2015
This presentation contains certain statements that constitute forward-looking information within the meaning of applicable securities laws (“forward-looking
statements”), which reflects management’s expectations regarding Teranga Gold Corporation’s (“Teranga” or the “Company”) future growth, results of operations
(including, without limitation, future production and capital expenditures), performance (both operational and financial) and business prospects (including the timing
and development of new deposits and the success of exploration activities) and opportunities. Wherever possible, words such as “plans”, “expects”, “does not
expect”, “budget”, “scheduled”, “estimates”, “forecasts”, “anticipate” or “does not anticipate”, “believe”, “intend”, “ability to” and similar expressions or statements that
certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, have been used to identify such forward looking
information. Although the forward-looking information contained in this presentation reflect management’s current beliefs based upon information currently available
to management and based upon what management believes to be reasonable assumptions, Teranga cannot be certain that actual results will be consistent with
such forward looking information. Such forward-looking statements are based upon assumptions, opinions and analysis made by management in light of its
experience, current conditions and its expectations of future developments that management believe to be reasonable and relevant. These assumptions include,
among other things, the ability to obtain any requisite Senegalese governmental approvals, the accuracy of mineral reserve and mineral resource estimates, gold
price, exchange rates, fuel and energy costs, future economic conditions and courses of action. Teranga cautions you not to place undue reliance upon any such
forward-looking statements, which speak only as of the date they are made.
The risks and uncertainties that may affect forward-looking statements include, among others: the inherent risks involved in exploration and development of mineral
properties, including government approvals and permitting, changes in economic conditions, changes in the worldwide price of gold and other key inputs, changes
in mine plans and other factors, such as project execution delays, many of which are beyond the control of Teranga, as well as other risks and uncertainties which
are more fully described in the Company’s Revised Annual Information Form dated April 24, 2014, and in other company filings with securities and regulatory
authorities which are available at www.sedar.com. Teranga does not undertake any obligation to update forward-looking statements should assumptions related to
these plans, estimates, projections, beliefs and opinions change. Nothing in this report should be construed as either an offer to sell or a solicitation to buy or sell
Teranga securities.
This presentation is dated as of the date on the front cover. All references to the Company include its subsidiaries unless the context requires otherwise.
This presentation contains references to Teranga using the words “we”, “us”, “our” and similar words and the reader is referred to using the words “you”, “your” and
similar words.
All dollar amounts stated are denominated in U.S. dollars unless specified otherwise.
FORWARD-LOOKING STATEMENTS
2
Canadian-based gold mining company with large mine license
and regional land package in Senegal
EMERGING MID-TIER GOLD PRODUCER
WITH ATTRACTIVE LONG-TERM GROWTH PROFILE
Refer to endnote (5) on slide 21
Capital Structure
(as of March 26, 2015)
Basic common shares outstanding 352,801,091
Stock options outstanding 13,616,111
Average daily trading volume 1,774,430
Number of shares owned by insiders 3,043,030
Enterprise value C$182M / US$146M
Market capitalization C$222M / US$178M
Operates only gold mine and mill in Senegal located
90 kilometres from major gold mines in Mali
Large resource base of 6.1Moz in Measured and Indicated
(inclusive of reserves) and 2.4Moz in Inferred with ability to
convert resources into reserves and make new discoveries(5)
Debt-free and generating positive free cash flow
Publicly listed on Toronto (TSX: TGZ)
and Australian (ASX: TGZ) stock exchanges
3
INVESTMENT HIGHLIGHTS
4Refer to endnotes (1), (2), (5) on slide 21
Large long-life reserve & resource base in stable region(5)
Low all-in sustaining costs(1)
Positive free cash flow & earnings(2)
Debt-free balance sheet
Significant organic growth profile





FRANCO-NEVADA INVESTMENT VALIDATES TERANGA’S
LONG-TERM CASH FLOW AND GROWTH POTENTIAL
In connection with Teranga’s acquisition of OJVG in 2014,
Franco-Nevada invested $135 million in exchange
for a fixed and floating stream on Teranga’s
future production
Highlights of Teranga Stream Transaction
for Franco-Nevada
 High quality, high margin  Favourable cost structure
 Exploration and expansion
potential
 Long-term optionality Security of tenure
 Well-run operation with an
established track record
Fixed gold deliveries of 22,500 ounces per year from
2014 to 2019 with trailing 6% gold stream once fixed
deliveries completed in 2019
Franco-Nevada to pay 20% of spot gold price per ounce
delivered (6% stream is equivalent to a 4.8% NSR royalty)
Streaming agreement covers Teranga’s
current mine license and land package
5
SENEGAL: A LAND OF OPPORTUNITY
Senegalese government views mining as pillar for economic
growth and supports mining companies by offering attractive
royalty and ownership structures Africa
Senegal
Teranga Gold’s
Sabodala Mine
A stable democracy and member of West African Economic & Monetary Union
Potential for world-class discoveries similar to the
deposits (+5 million ounces) that have been found
on the same geographical gold belt in Mali
Long-term asset consolidation potential
6
Breakdown of 2014 Administrative & CSR Expenses
$15.6 million
 Following 18-month collaborative planning process
with local, regional and national stakeholders,
created Teranga Development Strategy which
focuses on:
o economic sustainability
o agriculture and food security
o youth education and training
 Nationalizing our workforce with 90% of 1,050
employees from Senegal, with more than half from
the local region
 Health and safety is a key priority – currently at
~550 days without a lost time injury
COMMITTED TO MINING RESPONSIBLY
Comprehensive CSR program is imperative to long-term success in Senegal
Corporate Office CSR and Government Relations Legal and Other Depreciation Audit Fees
53%23%
16%
5% 3%
7
MANAGEMENT’S STRONG OPERATIONAL TRACK RECORD
Commenced mill
expansion to double
throughput
Discovered
high-grade Gora
satellite deposit
Began systematic
regional exploration
program
2010
Acquired Sabodala
gold mine and
regional land
package that
together total
1,488 km2
Completed initial
public offering
Completed mill
expansion
Completed
development plan
for high-grade Gora
satellite deposit
Expanded M&I by
800,000 ounces
Doubled 2P reserves
and mine life through
acquisition of OJVG
Established long-
term fiscal and
investment
agreement with
government of
Senegal
Eliminated inherited
“out-of-money”
hedge book
Successfully
integrated OJVG
Commenced
production at Masato
Reduced AISC per
ounce by 28%
since 2012
Paid off remaining
bank debt
2011 2012 2013 2014
M&I
2.3Moz
M&I
6.1Moz
M&I
6.2Moz
M&I
2.1Moz
M&I
2.9Moz
8
DRIVERS OF VALUATION
9
Attractive free
cash flow and
profitability
Strong
balance sheet
High return
organic
growth
initiatives
Refer to endnote (1) on slide 21
$556 $641 $710
$650
to
$700
$1,200
$1,033
$865
$900 to $975
2012 2013 2014 2015F
Cash Cost/oz All-In Sustaining Cost/oz
(1) (1)
Cash Costs and All-in Sustaining CostsQ4 2014 production of 71,278 ounces represents the
second highest quarterly production in Teranga’s history -
- mill costs were below $14 per tonne
INCREASING PROFITABILITY BY
LOWERING COSTS AND ONGOING OPTIMIZATION
* All-in sustaining
costs exclude
Franco-Nevada
stream impact of
approximately
$100/oz as stream
is treated as
deferred revenue
Mine production costs projected to be between
$147M and $155M in 2015 versus $156M in 2014
Fuel sensitivity: $0.10/litre change in fuel = $20/oz
Consume ~50M litres of fuel per annum
(20M litres of LFO/30M litres of HFO)
Currency: 40% - 50% of expenses are Euro denominated
10% change in Euro = $40/oz
10
GROWING FREE CASH FLOW
($50)
$78
Annual Free Cash Flow
per Ounce of Gold Sold
Free Cash Flow/oz 2014 Free Cash Flow/oz (excl. Franco-Nevada)
Significantly increasing free cash flow since 2012 despite declining gold prices
(2) (2)
Refer to endnote (2) on slide 21
20132012 2014
$189
$291
($11M)
$16M
$1,669
$1,411
$1,266
2012 2013 2014
Annual Free Cash Flow
vs. Average Gold Price per Ounce
Free Cash Flow Gold Price Average/oz (London PM Fix)
$39M
(2)
11
($75M)
($32M)
$32M
$1,669
$1,411
$1,266
2012 2013 2014
Improving Net Cash (Debt)
vs. Declining Average Gold Price
Net Cash (Debt) Gold Price Average/oz (London PM Fix)
Generating free cash flow from operations and
building higher cash balances
STRONG DEBT-FREE BALANCE SHEET
12Refer to endnote (7) on slide 21
(7)
Stockpile Cost Analysis @ $1,200 Gold Price
Tonnes 11.1 million tonnes
Grade 0.8 g/t
Recovery 89%
Recovered Ounces 255,000
Processing $15.00 - $16.00 per tonne
G&A and Sustaining CAPEX $2.00 per tonne
Royalty 5%
Future Costs ~ $800 - $850 per ounce
Debt-free as of mid-February 2015
Inventory of nearly 300,000 ounces in low-grade ore
stockpile represents a valuable asset providing
operating flexibility - can be processed at future costs of
$800 to $850 per ounce
THREE PHASE GROWTH STRATEGY
13Refer to endnote (6) on slide 21
Increase production to
250,000 – 350,000 oz
per year(6)
Phase I
Mine License
Phase II
Exploration
Production
Increase production to
400,000 – 500,000 oz
per year(6)
Near-term Medium-term
Capital intensive
Enhance throughput
Increase reserves by
converting resources and
through exploration
Opportunities
Capital Required
Timing
New discoveries on
mine license (246km2)
and regional land package
(1,055km2)
Phase III
Asset Consolidation
Increase production to
500,000+ oz
per year(6)
Long-term
Capital intensive
Regional processing facility
New joint ventures in
Senegal
Asset consolidation
Incremental capital
PHASE I: LOW COST NEAR-TERM ORGANIC GROWTH
Phase I
Mine License
Near-term opportunity
Enhance throughput
Increase reserves by
converting resources and
through exploration
Incremental capital required
Increase production to
250,000 – 350,000 oz
per year(6)
14Refer to endnote (6) on slide 21
PHASE II: MEDIUM-TERM ORGANIC GROWTH
Refer to endnote (6) on slide 21
Phase II
Exploration
Medium-term opportunity
New discoveries on mine
license (246km2)
New discoveries on regional
land package (1,055km2)
Capital intensive
Increase production to
400,000 – 500,000 oz
per year(6)
SENEGAL MALI
+12M oz Au
discovered
+40M oz Au
discovered
15
PHASE III: LONG-TERM ASSET CONSOLIDATION IN SENEGAL
212 koz
250 – 350 koz(6)
400 – 500 koz(6)
500+ koz(6)
2014 Phase I Phase II Phase III
Production Range
16
Phase III
Asset Consolidation
Long-term opportunity
Regional processing facility
New joint ventures in Senegal
Asset consolidation
Capital intensive
Increase production beyond
500,000 oz per year(6)
Refer to endnote (6) on slide 21
Assumptions
 $1,200 per ounce gold price assumption
 High-grade Gora deposit comes into production
by beginning of Q4 2015
 Gora and mill optimization development cost of
approximately $125 per ounce included in all-in
sustaining costs
Levers / Sensitivities
 2015 cash costs expected to be in range of $650-
$700 with the following sensitivities:
– 10% change in currency $40/oz
– $0.10/litre change in fuel $20/oz
 Between $5.0 and $6.0 million of the total capex
relating to the mill optimization may be deferred
pending upcoming exploration and heap leach
results to ensure the best allocation of capital
2015 OUTLOOK
Units 2014 Actual 2015 Guidance(4)
Total material mined (‘000t) 29,321 28,500 - 30,500
Ore mined (‘000t) 6,174 6,500 - 7,500
Grade mined (g/t) 1.54 1.40 - 1.60
Ore milled (‘000t) 3,622 3,600 - 3,800
Head grade (g/t) 2.03 2.00 - 2.20
Gold produced(3)(6) (‘000 oz) 212 200 - 230
Total cash costs(1)
(including royalties)
$/oz sold 710 650 - 700
All-in sustaining costs(1) $/oz sold 865 900 - 975*
Mine production costs
(net of capitalized deferred stripping)
$ millions 156.4 147 - 155
Capital expenditures $ millions 18.9 49.0 - 58.0
17Refer to endnotes (1),(3), (4) and (6) on slide 21
*All-in sustaining costs exclude Franco-Nevada stream impact of approximately $100/oz as stream is
treated as deferred revenue
CATALYSTS FOR FUTURE GROWTH
Internal rate of return hurdle is 20%+
18
Catalyst Timing Impact
Gora H2 2015 30K - 45K oz
Mill Optimization 2015 - 2016 5% - 10% increase in throughput
2015 - 2017 10% - 20% increase in gold production
Mine License Exploration 2015 - 2019
Extend mine life / add to reserves /
increase production
Regional Land Package Exploration Ongoing
Extend mine life / add to reserves /
increase production
Heap Leach
INVESTMENT HIGHLIGHTS
Refer to endnotes (1), (2), (5) on slide 21
Large long-life
reserve &
resource base in
stable region
Low all-in
sustaining costs(1)
Positive
free cash flow &
earnings(2)
Debt-free
balance sheet
Significant organic
growth profile
• 6.1 million ounces of gold in measured and indicated resources(5)
• 2P reserve life of 11 years (based on 2015 production)(5)
• Only mill in Senegal (French West Africa), a safe stable democracy with a progressive mining code
• 28% improvement in all-in sustaining costs since 2012 -- 2015 guidance is for trend to continue
• Our production flexibility allows us to minimize both material movement and capital spending
• Stable G&A with ~25% committed to CSR initiatives, which are imperative to our success in Senegal
• Attractive sustainable free cash flow generation
• Free cash flow per ounce of gold in line with senior gold companies
• Three consecutive years of positive earnings and $100M+ in retained earnings in 5 years of production
• Strong debt-free balance sheet
• Improving financial flexibility with standby facility
• Ability to fund near-term growth through cash flow from operations
• Heap leaching and mill optimization provide catalysts for future organic growth
• Opportunity for conversion of resources to reserves and new discoveries on large mine license (246km2)
• Potential for world-class discoveries on regional land package (1,055km2)
• )
19
DRIVERS OF VALUATION
Attractive free
cash flow and
profitability
Strong
balance sheet
High return
organic
growth
initiatives
20
1. Total cash costs per ounce and all-in sustaining costs per ounce are non-IFRS financial measures and do not have a standard meaning under IFRS. Please refer to the Non-
IFRS Financial Measures section in the Company’s 2014 fourth quarter results available on the Company’s website at www.terangagold.com. All-in sustaining costs include:
total cash costs, administrative expenses (including share based compensation, and excluding corporate depreciation expense and social community costs not related to
current operations), capitalized deferred stripping, capitalized reserve development, and mine site sustaining & development capital expenditures as defined by the World
Gold Council. Total cash costs per ounce and all-in sustaining costs per ounce are prior to a non-cash inventory write-down (or reversals thereof) to net realizable value.
2. Free cash flow (“FCF”) is defined as operating cash flow less capital expenditures and includes the impact of the Franco-Nevada stream. FCF per ounce and FCF per ounce
(excluding Franco-Nevada) are non-IFRS financial measures. For 2013 and 2014, FCF is before the OJVG transaction costs.
3. 24,375 gold ounces of production are to be sold to Franco Nevada at 20% of the spot gold price.
4. Key assumptions: Gold spot price/ounce - US$1,200, Light fuel oil - US$0.95/litre, Heavy fuel oil - US$0.76/litre, US/Euro exchange rate - $1.20, USD/CAD exchange rate -
$0.85.Other important assumptions include: any political events are not expected to impact operations, including movement of people, supplies and gold shipments; grades
and recoveries will remain consistent with the life-of-mine plan to achieve the forecast gold production; and no unplanned delays in or interruption of scheduled production.
5. Mineral Reserves and Mineral Resources estimates as at December 31, 2013 as per technical reports and Company disclosure. For more information regarding Teranga
Gold’s Mineral Reserves and Resources, please refer to the full National Instrument 43-101 Technical Report released on March 13, 2014 available on the Company’s
website at www.terangagold.com.
6. Over the past several years more than twelve million ounces of measured and indicated resources have been identified within the south eastern Senegal region, including the
Massawa, Golouma, Makabingui and Mako projects, along with the Company’s own Sabodala gold mine. With exploration work completed to date and the prior exploration
success seen in the area Management believes there is a reasonable basis for an exploration target that would substantiate the annual production targets set by the second
and third phases of our vision. However, the potential quantity and grade of an exploration target is conceptual in nature. There has been insufficient exploration to determine
a mineral resource of the size required to achieve the production target we have established and there is no certainty that further exploration work will result in the
determination of mineral resources or that the production target itself will be realized.
7. Net cash (debt) is defined as total borrowings and financial derivative liabilities less cash and cash equivalents, bullion receivable and restricted cash.
8. Source: BMO Capital Markets, Gold Mining Research’s Gold Pages (February 2, 2015)
In U.S. dollar amounts unless stated otherwise
ENDNOTES
21
MINERAL RESOURCES SUMMARY
As at December 31, 2014
Measured Indicated Measured and Indicated
Tonnes Grade Au Tonnes Grade Au Tonnes Grade Au
Area (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
Sabodala 23.73 1.21 0.92 19.55 1.23 0.77 43.28 1.22 1.70
Gora 0.49 5.27 0.08 1.84 4.93 0.29 2.32 5.00 0.37
Niakafiri 0.30 1.74 0.02 10.50 1.10 0.37 10.70 1.12 0.39
ML Other
Subtotal Sabodala 24.52 1.30 1.02 31.89 1.40 1.43 56.41 1.36 2.46
Masato 1.55 0.96 0.05 50.26 1.04 1.67 51.81 1.03 1.72
Golouma 12.04 2.69 1.04 12.04 2.69 1.04
Kerekounda 2.20 3.77 0.27 2.20 3.77 0.27
Somigol Other 18.72 0.93 0.56 18.72 0.93 0.56
Subtotal Somigol 1.55 0.96 0.05 83.22 1.33 3.54 84.77 1.32 3.59
Total 26.07 1.28 1.07 115.11 1.35 4.97 141.18 1.33 6.05
Inferred Resources
Tonnes Au Au
Area (Mt) (g/t) (Moz)
Sabodala 18.42 0.93 0.55
Gora 0.21 3.38 0.02
Niakafiri 7.20 0.88 0.21
ML Other 10.60 0.97 0.33
Subtotal Sabodala 36.43 0.94 1.11
Masato 19.18 1.15 0.71
Golouma 2.46 2.01 0.16
Kerekounda 0.34 4.21 0.05
Somigol Other 12.87 0.84 0.35
Subtotal Somigol 34.86 1.13 1.26
Total 71.29 1.03 2.37
Notes for Mineral Resources Summary:
1. CIM definitions were followed for Mineral Resources.
2. Mineral Resource cut-off grades for Sabodala, Masato, Golouma, Kerekounda and Somigol Other are 0.2 g/t Au for oxide and 0.35 g/t Au for fresh.
3. Mineral Resource cut-off grades for Niakafiri are 0.3 g/t Au for oxide and 0.5 g/t Au for fresh.
4. Mineral Resource cut-off grade for Gora is 0.5 g/t Au for oxide and fresh.
5. Mineral Resource cut-off grade for Niakafiri West and Soukhoto is 0.3 g/t Au for oxide and fresh.
6. Mineral Resource cut-off grade for Diadiako is 0.2 g/t Au for oxide and fresh.
7. Measured Resources include stockpiles which total 11.30 Mt at 0.82 g/t Au for 0.30 Mozs.
8. High grade assays were capped at grades ranging from 10 g/t to 30 g/t Au at Sabodala, 20 g/t to 70 g/t Au at Gora, from 4 g/t to 25 g/t Au at Masato, from 5 g/t to 70 g/t for Golouma, from 11 g/t to 50 g/t at Kerekounda, and from 0.8 g/t to 110 g/t at Somigol Other.
9. The figures above are “Total” Mineral Resources and include Mineral Reserves.
10. Neither underground Mineral Resources nor Mineral Reserves have been generated by the Company, therefore global Mineral Resources have been reported at the determined cut-off grades. A detailed underground analysis will be undertaken to follow-up on the underground resource potential; however, this is not a
priority in the near term.
11. Sum of individual amounts may not equal due to rounding.
For clarity, the mineral Resource estimates disclosed above with respect to Niakafiri, Gora and ML Other (which includes Niakafiri, Niakafiri West, Soukhoto and Diadiako) were prepared and first disclosed under the JORC Code 2004. It has not been updated
since to comply with JORC Code 2012 on the basis that the information has not materially changed since it was last reported. Refer to Teranga Gold Corporation’s ASX Quarterly December 31, 2013 report filed on January 30, 2014 for further details. All material
assumptions and technical parameters previously disclosed continue to be applicable and have not materially changed. See Competent Person Statements on pages 33 and 34 for further details.
22
MINERAL RESERVES SUMMARY
As at December 31, 2014
Proven Probable Proven and Probable
Tonnes Grade Au Tonnes Grade Au Tonnes Grade Au
Area (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
Sabodala 1.98 1.52 0.10 2.48 1.48 0.12 4.45 1.50 0.21
Gora 0.48 4.66 0.07 1.35 4.79 0.21 1.83 4.76 0.28
Niakafiri 0.23 1.69 0.01 7.58 1.12 0.27 7.81 1.14 0.29
Stockpiles 11.30 0.82 0.30 11.30 0.82 0.30
Subtotal Sabodala 13.99 1.07 0.48 11.41 1.63 0.60 25.40 1.32 1.09
Masato 26.93 1.13 0.98 26.93 1.13 0.98
Golouma 6.47 2.24 0.46 6.47 2.24 0.46
Kerekounda 0.88 3.26 0.09 0.88 3.26 0.09
Subtotal Somigol 34.28 1.39 1.53 34.28 1.39 1.53
Total 13.99 1.07 0.48 45.69 1.45 2.12 59.68 1.36 2.62
Notes for Reserves Summary:
1. CIM definitions were followed for Mineral Reserves.
2. Mineral Reserve cut off grades for Sabodala are 0.40 g/t Au for oxide and 0.5 g/t Au for fresh based on a $1,250/oz gold price and metallurgical recoveries between 90 percent and 93 percent.
3. Mineral Reserve cut off grades for Niakafiri are 0.35 g/t Au for oxide and 0.5 g/t Au for fresh based on a $1,350/oz gold price and metallurgical recoveries between 90 percent and 92 percent.
4. Mineral Reserve cut off grade for Gora is 0.76 g/t Au for oxide and fresh based on $1,200/oz gold price and metallurgical recovery of 95 percent.
5. Mineral Reserve cut off grades for Masato are 0.4 g/t Au for oxide and 0.5 g/t for fresh based on $1,200/oz gold price and metallurgical between 90 percent and 93 percent.
6. Mineral reserve cut off grades for Golouma and Kerekounda are 0.4 g/t Au for oxide and 0.5 g/t for fresh based on $1,250/oz gold price and metallurgical between 90 percent and 93 percent.
7. Sum of individual amounts may not equal due to rounding.
8. The Niakafiri deposit is adjacent to the Sabodala village and relocation of at least some portion of the village will be required which will necessitate a negotiated resettlement program with the affected community members.
9. The Gora deposit is intended to be merged into the Sabodala mining license which the State of Senegal has agreed to in principal subject to completion and receipt of an approved environmental and social impact assessment which is
ongoing.
10. There are no other known political, legal or environmental risks that could materially affect the potential development of the identified mineral resources or mineral reserves other than as already set out in the Company’s Annual Information
Form dated March 31, 2014 (revised April 24, 2014). Refer to RISK FACTORS beginning on page 60.
For clarity, the mineral Reserve estimates disclosed above with respect to Niakafiri and Gora was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with JORC Code
2012 on the basis that the information has not materially changed since it was last reported. Refer to Teranga Gold Corporation’s ASX Quarterly December 31, 2013 report filed on January 30, 2014 for further
details. All material assumptions and technical parameters previously disclosed continue to be applicable and have not materially changed. See Competent Person Statements on pages 33 and 34 for further details.
23
The technical information contained in this presentation relating to the mineral reserve estimates for Sabodala, the stockpiles, Masato, Golouma and Kerekounda is based on, and fairly represents,
information compiled by Mr. William Paul Chawrun, P. Eng who is a member of the Professional Engineers of Ontario, which is currently included as a "Recognized Overseas Professional Organization" in
a list promulgated by the ASX from time to time. Mr. Chawrun is a full-time employee of Teranga and is a "qualified person" as defined in NI 43-101 and a "competent person" as defined in the 2012
Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr. Chawrun has sufficient experience relevant to the style of mineralization and type of
deposit under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves". Mr. Chawrun has consented to the inclusion in this document of the matters based on his compiled information in the form and context in which it appears in this
presentation.
The technical information contained in this presentation relating to the mineral reserve estimates for Gora and Niakafiri is based on, and fairly represents, information and supporting documentation
prepared by Julia Martin, P.Eng. who is a member of the Professional Engineers of Ontario and a Member of AusIMM (CP). Ms. Martin is a full time employee with AMC Mining Consultants (Canada)
Ltd., is independent of Teranga, is a “qualified person” as defined in NI 43-101 and a “competent person” as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves”. Ms. Martin has sufficient experience relevant to the style of mineralization and type of deposit under consideration and to the activity she is undertaking to qualify as
a Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Ms. Martin is a “Qualified Person” under
National Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Martin has reviewed and accepts responsibility for the Mineral Reserve estimates for Gora and Niakafiri disclosed in this
document and has consented to the inclusion of the matters based on her information in the form and context in which it appears in this presentation.
The technical information contained in this presentation relating to mineral resource estimates for Niakafiri, Gora, Niakafiri West, Soukhoto, and Diadiako is based on, and fairly represents, information
compiled by Ms. Patti Nakai-Lajoie. Ms. Patti Nakai-Lajoie, P. Geo., is a Member of the Association of Professional Geoscientists of Ontario, which is currently included as a "Recognized Overseas
Professional Organization" in a list promulgated by the ASX from time to time. Ms. Nakai-Lajoie is a full time employee of Teranga and is not "independent" within the meaning of National Instrument 43-
101. Ms. Nakai-Lajoie has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which she is undertaking to qualify as a Competent
Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Ms. Nakai-Lajoie is a "Qualified Person" under National
Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Nakai-Lajoie has consented to the inclusion in this document of the matters based on her compiled information in the form and context
in which it appears in this presentation.
24
COMPETENT AND QUALIFIED PERSONS STATEMENT
The technical information contained in this presentation relating to mineral resource estimates for Sabodala, Masato, Golouma, Kerekounda, and Somigol Other are based on, and fairly represents,
information compiled by Ms. Patti Nakai-Lajoie. Ms. Patti Nakai-Lajoie, P. Geo., is a Member of the Association of Professional Geoscientists of Ontario, which is currently included as a "Recognized
Overseas Professional Organization" in a list promulgated by the ASX from time to time. Ms. Nakai-Lajoie is a full time employee of Teranga and is not "independent" within the meaning of National
Instrument 43-101. Ms. Nakai-Lajoie has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which she is undertaking to
qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Ms. Nakai-Lajoie is a "Qualified
Person" under National Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Nakai-Lajoie has consented to the inclusion in this presentation of the matters based on her compiled
information in the form and context in which it appears in this document.
Teranga’s exploration programs are being managed by Mr. Peter Mann, FAusIMM. Mr. Mann is a full time employee of Teranga and is not "independent" within the meaning of National Instrument
43-101. Mr. Mann has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr. Mann is a "Qualified Person" under
National Instrument 43-101 Standards of Disclosure for Mineral Projects. The technical information contained in this presentation relating exploration results are based on, and fairly represents,
information compiled by Mr. Mann. Mr. Mann has verified and approved the data disclosed in this presentation, including any sampling, analytical and test data underlying the information. The
reverse circulation samples are prepared at site and assayed in the SGS laboratory located at the site. Analysis for diamond drilling is sent for fire assay analysis at ALS Johannesburg, South
Africa. Mr. Mann has consented to the inclusion in this presentation of the matters based on his compiled information in the form and context in which it appears herein.
Teranga's disclosure of mineral reserve and mineral resource information is governed by NI 43-101 under the guidelines set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the
"CIM") Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as may be amended from time to time by the CIM ("CIM Standards"). CIM definitions of the terms
"mineral reserve", "proven mineral reserve", "probable mineral reserve", "mineral resource", "measured mineral resource", "indicated mineral resource" and "inferred mineral resource", are
substantially similar to the JORC Code corresponding definitions of the terms "ore reserve", "proved ore reserve", "probable ore reserve", "mineral resource", "measured mineral resource", "indicated
mineral resource" and "inferred mineral resource", respectively. Estimates of mineral resources and mineral reserves prepared in accordance with the JORC Code would not be materially different if
prepared in accordance with the CIM definitions applicable under NI 43-101. There can be no assurance that those portions of mineral resources that are not mineral reserves will ultimately be
converted into mineral reserves.
COMPETENT AND QUALIFIED PERSONS STATEMENT
25
121 KING STREET WEST
SUITE 2600
TORONTO, ON M5H 3T9
TELEPHONE: +1.416.594.000
EMAIL: INVESTOR@TERANGAGOLD.COM
WWW.TERANGAGOLD.COM
TSX:TGZ / ASX:TGZ

Weitere ähnliche Inhalte

Was ist angesagt?

05 12-15 agm slides final
05 12-15 agm slides final05 12-15 agm slides final
05 12-15 agm slides finalTeranga Gold
 
05 27-15 may investor presentation
05 27-15 may investor presentation05 27-15 may investor presentation
05 27-15 may investor presentationTeranga Gold
 
12 02-15-scotia-conference-december-presentation-handout-final
12 02-15-scotia-conference-december-presentation-handout-final12 02-15-scotia-conference-december-presentation-handout-final
12 02-15-scotia-conference-december-presentation-handout-finalTeranga Gold
 
November Investor Presentation
November Investor Presentation November Investor Presentation
November Investor Presentation Teranga Gold
 
Rbc conference may 2013
Rbc conference may 2013Rbc conference may 2013
Rbc conference may 2013Teranga Gold
 
PDAC Investor Presentation - March 3, 2015
PDAC Investor Presentation - March 3, 2015PDAC Investor Presentation - March 3, 2015
PDAC Investor Presentation - March 3, 2015Crocodile Gold Corp
 
Newmarket Gold Inc - Corporate Presentation
Newmarket Gold Inc - Corporate PresentationNewmarket Gold Inc - Corporate Presentation
Newmarket Gold Inc - Corporate PresentationAdnet Communications
 
TerangaGold - May Investor Presentation
TerangaGold - May Investor PresentationTerangaGold - May Investor Presentation
TerangaGold - May Investor PresentationTeranga Gold
 
08 12-16 teranga gold august marketing presentation final
08 12-16 teranga gold august marketing presentation final08 12-16 teranga gold august marketing presentation final
08 12-16 teranga gold august marketing presentation finalTeranga Gold
 
07 30-15 q2 results presentation final3
07 30-15 q2 results presentation final307 30-15 q2 results presentation final3
07 30-15 q2 results presentation final3Teranga Gold
 
07 30-15-q2-results-presentation-final3
07 30-15-q2-results-presentation-final307 30-15-q2-results-presentation-final3
07 30-15-q2-results-presentation-final3Teranga Gold
 
Teranga Gold Q1 2015 Financial and Operating Results
Teranga Gold Q1 2015 Financial and Operating Results Teranga Gold Q1 2015 Financial and Operating Results
Teranga Gold Q1 2015 Financial and Operating Results Teranga Gold
 
Teranga Gold Q2 2014 Results
Teranga Gold Q2 2014 ResultsTeranga Gold Q2 2014 Results
Teranga Gold Q2 2014 ResultsTeranga Gold
 
Newmarket gold corporate presentation january 5 2016
Newmarket gold corporate presentation january 5 2016Newmarket gold corporate presentation january 5 2016
Newmarket gold corporate presentation january 5 2016Adnet Communications
 
Corporate Presentation - September 2015
Corporate Presentation - September 2015Corporate Presentation - September 2015
Corporate Presentation - September 2015Adnet Communications
 
Newmarket Gold Corporate Presentation
Newmarket Gold Corporate PresentationNewmarket Gold Corporate Presentation
Newmarket Gold Corporate PresentationAdnet Communications
 
Newmarket gold corporate presentation oct v9
Newmarket gold corporate presentation oct v9Newmarket gold corporate presentation oct v9
Newmarket gold corporate presentation oct v9Adnet Communications
 
Teranga Gold First Quarter Financial & Operating Results
Teranga Gold First Quarter Financial & Operating ResultsTeranga Gold First Quarter Financial & Operating Results
Teranga Gold First Quarter Financial & Operating ResultsTeranga Gold
 
Td securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalTd securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalSemafoCorporate
 

Was ist angesagt? (20)

05 12-15 agm slides final
05 12-15 agm slides final05 12-15 agm slides final
05 12-15 agm slides final
 
05 27-15 may investor presentation
05 27-15 may investor presentation05 27-15 may investor presentation
05 27-15 may investor presentation
 
12 02-15-scotia-conference-december-presentation-handout-final
12 02-15-scotia-conference-december-presentation-handout-final12 02-15-scotia-conference-december-presentation-handout-final
12 02-15-scotia-conference-december-presentation-handout-final
 
November Investor Presentation
November Investor Presentation November Investor Presentation
November Investor Presentation
 
Rbc conference may 2013
Rbc conference may 2013Rbc conference may 2013
Rbc conference may 2013
 
PDAC Investor Presentation - March 3, 2015
PDAC Investor Presentation - March 3, 2015PDAC Investor Presentation - March 3, 2015
PDAC Investor Presentation - March 3, 2015
 
Newmarket Gold Inc - Corporate Presentation
Newmarket Gold Inc - Corporate PresentationNewmarket Gold Inc - Corporate Presentation
Newmarket Gold Inc - Corporate Presentation
 
TerangaGold - May Investor Presentation
TerangaGold - May Investor PresentationTerangaGold - May Investor Presentation
TerangaGold - May Investor Presentation
 
08 12-16 teranga gold august marketing presentation final
08 12-16 teranga gold august marketing presentation final08 12-16 teranga gold august marketing presentation final
08 12-16 teranga gold august marketing presentation final
 
07 30-15 q2 results presentation final3
07 30-15 q2 results presentation final307 30-15 q2 results presentation final3
07 30-15 q2 results presentation final3
 
07 30-15-q2-results-presentation-final3
07 30-15-q2-results-presentation-final307 30-15-q2-results-presentation-final3
07 30-15-q2-results-presentation-final3
 
Teranga Gold Q1 2015 Financial and Operating Results
Teranga Gold Q1 2015 Financial and Operating Results Teranga Gold Q1 2015 Financial and Operating Results
Teranga Gold Q1 2015 Financial and Operating Results
 
Teranga Gold Q2 2014 Results
Teranga Gold Q2 2014 ResultsTeranga Gold Q2 2014 Results
Teranga Gold Q2 2014 Results
 
Investor presentation dec 2016
Investor presentation dec 2016Investor presentation dec 2016
Investor presentation dec 2016
 
Newmarket gold corporate presentation january 5 2016
Newmarket gold corporate presentation january 5 2016Newmarket gold corporate presentation january 5 2016
Newmarket gold corporate presentation january 5 2016
 
Corporate Presentation - September 2015
Corporate Presentation - September 2015Corporate Presentation - September 2015
Corporate Presentation - September 2015
 
Newmarket Gold Corporate Presentation
Newmarket Gold Corporate PresentationNewmarket Gold Corporate Presentation
Newmarket Gold Corporate Presentation
 
Newmarket gold corporate presentation oct v9
Newmarket gold corporate presentation oct v9Newmarket gold corporate presentation oct v9
Newmarket gold corporate presentation oct v9
 
Teranga Gold First Quarter Financial & Operating Results
Teranga Gold First Quarter Financial & Operating ResultsTeranga Gold First Quarter Financial & Operating Results
Teranga Gold First Quarter Financial & Operating Results
 
Td securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-finalTd securities-mining-conference-january-2016-final
Td securities-mining-conference-january-2016-final
 

Andere mochten auch

Producing and Exploring: June 2012
Producing and Exploring: June 2012Producing and Exploring: June 2012
Producing and Exploring: June 2012Teranga Gold
 
Teranga Gold Investor Presentation August 2014
Teranga Gold Investor Presentation August 2014Teranga Gold Investor Presentation August 2014
Teranga Gold Investor Presentation August 2014Teranga Gold
 
Producing & Exploring: Third Quarter Results Conference Call/Webcast
Producing & Exploring: Third Quarter Results Conference Call/WebcastProducing & Exploring: Third Quarter Results Conference Call/Webcast
Producing & Exploring: Third Quarter Results Conference Call/WebcastTeranga Gold
 
Agm july 2013 final
Agm july 2013 finalAgm july 2013 final
Agm july 2013 finalTeranga Gold
 
European Gold Forum 2014
European Gold Forum 2014European Gold Forum 2014
European Gold Forum 2014Teranga Gold
 
11 21-2016-teranga-gold-swiss-mining-final
11 21-2016-teranga-gold-swiss-mining-final11 21-2016-teranga-gold-swiss-mining-final
11 21-2016-teranga-gold-swiss-mining-finalTeranga Gold
 

Andere mochten auch (7)

Producing and Exploring: June 2012
Producing and Exploring: June 2012Producing and Exploring: June 2012
Producing and Exploring: June 2012
 
Teranga Gold Investor Presentation August 2014
Teranga Gold Investor Presentation August 2014Teranga Gold Investor Presentation August 2014
Teranga Gold Investor Presentation August 2014
 
Producing & Exploring: Third Quarter Results Conference Call/Webcast
Producing & Exploring: Third Quarter Results Conference Call/WebcastProducing & Exploring: Third Quarter Results Conference Call/Webcast
Producing & Exploring: Third Quarter Results Conference Call/Webcast
 
Agm july 2013 final
Agm july 2013 finalAgm july 2013 final
Agm july 2013 final
 
European Gold Forum 2014
European Gold Forum 2014European Gold Forum 2014
European Gold Forum 2014
 
July 2012
July 2012July 2012
July 2012
 
11 21-2016-teranga-gold-swiss-mining-final
11 21-2016-teranga-gold-swiss-mining-final11 21-2016-teranga-gold-swiss-mining-final
11 21-2016-teranga-gold-swiss-mining-final
 

Ähnlich wie Teranga Gold John Tumazos Very Independent Conference

Swiss Mining Institute Conference
Swiss Mining Institute ConferenceSwiss Mining Institute Conference
Swiss Mining Institute ConferenceTeranga Gold
 
John Tumazos Very Independent Research Conference
John Tumazos Very Independent Research ConferenceJohn Tumazos Very Independent Research Conference
John Tumazos Very Independent Research ConferenceTeranga Gold
 
07 30-15 q2 results presentation final
07 30-15 q2 results presentation final07 30-15 q2 results presentation final
07 30-15 q2 results presentation finalTeranga Gold
 
Annual General & Special Meeting of Shareholders
Annual General  & Special Meeting of Shareholders Annual General  & Special Meeting of Shareholders
Annual General & Special Meeting of Shareholders Teranga Gold
 
June 2013 teranga gold presentation
June 2013 teranga gold presentationJune 2013 teranga gold presentation
June 2013 teranga gold presentationTeranga Gold
 
18 06 05 06 121 ny presentation 1x1
18 06 05 06 121 ny presentation 1x118 06 05 06 121 ny presentation 1x1
18 06 05 06 121 ny presentation 1x1Teranga Gold
 
Teranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold
 
Asx report slides final
Asx report slides final Asx report slides final
Asx report slides final Teranga Gold
 
2018 march swiss mining lunch presentation-final
2018 march swiss mining lunch presentation-final2018 march swiss mining lunch presentation-final
2018 march swiss mining lunch presentation-finalTeranga Gold
 
Tgz q1 2018 results webcast
Tgz q1 2018 results webcastTgz q1 2018 results webcast
Tgz q1 2018 results webcastTeranga Gold
 
Teranga gold 1x1 presentation bmo 2018
Teranga gold 1x1 presentation   bmo 2018Teranga gold 1x1 presentation   bmo 2018
Teranga gold 1x1 presentation bmo 2018Teranga Gold
 
2018 pdac presentation
2018 pdac presentation2018 pdac presentation
2018 pdac presentationTeranga Gold
 
2018 aug-7-8 - teranga presentation - vancouver marketing
2018 aug-7-8 - teranga presentation - vancouver marketing2018 aug-7-8 - teranga presentation - vancouver marketing
2018 aug-7-8 - teranga presentation - vancouver marketingTeranga Gold
 
Producing & Exploring: Denver Gold Forum 2013
Producing & Exploring: Denver Gold Forum 2013Producing & Exploring: Denver Gold Forum 2013
Producing & Exploring: Denver Gold Forum 2013Teranga Gold
 
BMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceBMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceTeranga Gold
 
121 london teranga presentation - 1x1
121 london   teranga presentation - 1x1121 london   teranga presentation - 1x1
121 london teranga presentation - 1x1Teranga Gold
 
07 28-16-teranga-gold-q2-2016-slides-final2
07 28-16-teranga-gold-q2-2016-slides-final207 28-16-teranga-gold-q2-2016-slides-final2
07 28-16-teranga-gold-q2-2016-slides-final2Teranga Gold
 

Ähnlich wie Teranga Gold John Tumazos Very Independent Conference (17)

Swiss Mining Institute Conference
Swiss Mining Institute ConferenceSwiss Mining Institute Conference
Swiss Mining Institute Conference
 
John Tumazos Very Independent Research Conference
John Tumazos Very Independent Research ConferenceJohn Tumazos Very Independent Research Conference
John Tumazos Very Independent Research Conference
 
07 30-15 q2 results presentation final
07 30-15 q2 results presentation final07 30-15 q2 results presentation final
07 30-15 q2 results presentation final
 
Annual General & Special Meeting of Shareholders
Annual General  & Special Meeting of Shareholders Annual General  & Special Meeting of Shareholders
Annual General & Special Meeting of Shareholders
 
June 2013 teranga gold presentation
June 2013 teranga gold presentationJune 2013 teranga gold presentation
June 2013 teranga gold presentation
 
18 06 05 06 121 ny presentation 1x1
18 06 05 06 121 ny presentation 1x118 06 05 06 121 ny presentation 1x1
18 06 05 06 121 ny presentation 1x1
 
Teranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 Presentation
 
Asx report slides final
Asx report slides final Asx report slides final
Asx report slides final
 
2018 march swiss mining lunch presentation-final
2018 march swiss mining lunch presentation-final2018 march swiss mining lunch presentation-final
2018 march swiss mining lunch presentation-final
 
Tgz q1 2018 results webcast
Tgz q1 2018 results webcastTgz q1 2018 results webcast
Tgz q1 2018 results webcast
 
Teranga gold 1x1 presentation bmo 2018
Teranga gold 1x1 presentation   bmo 2018Teranga gold 1x1 presentation   bmo 2018
Teranga gold 1x1 presentation bmo 2018
 
2018 pdac presentation
2018 pdac presentation2018 pdac presentation
2018 pdac presentation
 
2018 aug-7-8 - teranga presentation - vancouver marketing
2018 aug-7-8 - teranga presentation - vancouver marketing2018 aug-7-8 - teranga presentation - vancouver marketing
2018 aug-7-8 - teranga presentation - vancouver marketing
 
Producing & Exploring: Denver Gold Forum 2013
Producing & Exploring: Denver Gold Forum 2013Producing & Exploring: Denver Gold Forum 2013
Producing & Exploring: Denver Gold Forum 2013
 
BMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceBMO Global Metals & Mining Conference
BMO Global Metals & Mining Conference
 
121 london teranga presentation - 1x1
121 london   teranga presentation - 1x1121 london   teranga presentation - 1x1
121 london teranga presentation - 1x1
 
07 28-16-teranga-gold-q2-2016-slides-final2
07 28-16-teranga-gold-q2-2016-slides-final207 28-16-teranga-gold-q2-2016-slides-final2
07 28-16-teranga-gold-q2-2016-slides-final2
 

Mehr von Teranga Gold

Tgz q2 2018 results webcast
Tgz q2 2018 results webcastTgz q2 2018 results webcast
Tgz q2 2018 results webcastTeranga Gold
 
121 singapore teranga presentation - 1x1
121 singapore   teranga presentation - 1x1121 singapore   teranga presentation - 1x1
121 singapore teranga presentation - 1x1Teranga Gold
 
Teranga gold agm 2018
Teranga gold   agm 2018Teranga gold   agm 2018
Teranga gold agm 2018Teranga Gold
 
2018 february slides 1x1-final
2018 february slides 1x1-final2018 february slides 1x1-final
2018 february slides 1x1-finalTeranga Gold
 
2018 january 1x1 investor presentation vancouver-final
2018 january 1x1 investor presentation vancouver-final2018 january 1x1 investor presentation vancouver-final
2018 january 1x1 investor presentation vancouver-finalTeranga Gold
 
Website slides november 26, 2017 - final
Website slides   november 26, 2017 - finalWebsite slides   november 26, 2017 - final
Website slides november 26, 2017 - finalTeranga Gold
 
Tgz q3 2017 results webcast final
Tgz q3 2017 results webcast   finalTgz q3 2017 results webcast   final
Tgz q3 2017 results webcast finalTeranga Gold
 
2017 beaver creek final
2017 beaver creek final2017 beaver creek final
2017 beaver creek finalTeranga Gold
 
Sprott Natural Resource Symposium
Sprott Natural Resource SymposiumSprott Natural Resource Symposium
Sprott Natural Resource SymposiumTeranga Gold
 
Sprott Natural Resource Symposium
Sprott Natural Resource Symposium Sprott Natural Resource Symposium
Sprott Natural Resource Symposium Teranga Gold
 
European Gold Forum
European Gold Forum European Gold Forum
European Gold Forum Teranga Gold
 
04 27-2017-q1-slides-final3
04 27-2017-q1-slides-final304 27-2017-q1-slides-final3
04 27-2017-q1-slides-final3Teranga Gold
 
European Gold Forum Investor Presentation
European Gold Forum Investor PresentationEuropean Gold Forum Investor Presentation
European Gold Forum Investor PresentationTeranga Gold
 
teranga gold swiss mining presentation
teranga gold swiss mining presentationteranga gold swiss mining presentation
teranga gold swiss mining presentationTeranga Gold
 
Third Quarter Financial and Operating Results
Third Quarter Financial and Operating ResultsThird Quarter Financial and Operating Results
Third Quarter Financial and Operating ResultsTeranga Gold
 
09 14-16 teranga gold pgm summit investor presentation final
09 14-16 teranga gold pgm summit investor presentation final09 14-16 teranga gold pgm summit investor presentation final
09 14-16 teranga gold pgm summit investor presentation finalTeranga Gold
 
Teranga Gold August Investor Presentation
Teranga Gold August Investor Presentation Teranga Gold August Investor Presentation
Teranga Gold August Investor Presentation Teranga Gold
 
August Investor Presentation
August Investor Presentation August Investor Presentation
August Investor Presentation Teranga Gold
 

Mehr von Teranga Gold (20)

Tgz q2 2018 results webcast
Tgz q2 2018 results webcastTgz q2 2018 results webcast
Tgz q2 2018 results webcast
 
121 singapore teranga presentation - 1x1
121 singapore   teranga presentation - 1x1121 singapore   teranga presentation - 1x1
121 singapore teranga presentation - 1x1
 
Teranga gold agm 2018
Teranga gold   agm 2018Teranga gold   agm 2018
Teranga gold agm 2018
 
2018 february slides 1x1-final
2018 february slides 1x1-final2018 february slides 1x1-final
2018 february slides 1x1-final
 
2018 january 1x1 investor presentation vancouver-final
2018 january 1x1 investor presentation vancouver-final2018 january 1x1 investor presentation vancouver-final
2018 january 1x1 investor presentation vancouver-final
 
Website slides november 26, 2017 - final
Website slides   november 26, 2017 - finalWebsite slides   november 26, 2017 - final
Website slides november 26, 2017 - final
 
Tgz q3 2017 results webcast final
Tgz q3 2017 results webcast   finalTgz q3 2017 results webcast   final
Tgz q3 2017 results webcast final
 
2017 dgf final2
2017 dgf final22017 dgf final2
2017 dgf final2
 
2017 beaver creek final
2017 beaver creek final2017 beaver creek final
2017 beaver creek final
 
2017 Q2 Results
2017 Q2 Results2017 Q2 Results
2017 Q2 Results
 
Sprott Natural Resource Symposium
Sprott Natural Resource SymposiumSprott Natural Resource Symposium
Sprott Natural Resource Symposium
 
Sprott Natural Resource Symposium
Sprott Natural Resource Symposium Sprott Natural Resource Symposium
Sprott Natural Resource Symposium
 
European Gold Forum
European Gold Forum European Gold Forum
European Gold Forum
 
04 27-2017-q1-slides-final3
04 27-2017-q1-slides-final304 27-2017-q1-slides-final3
04 27-2017-q1-slides-final3
 
European Gold Forum Investor Presentation
European Gold Forum Investor PresentationEuropean Gold Forum Investor Presentation
European Gold Forum Investor Presentation
 
teranga gold swiss mining presentation
teranga gold swiss mining presentationteranga gold swiss mining presentation
teranga gold swiss mining presentation
 
Third Quarter Financial and Operating Results
Third Quarter Financial and Operating ResultsThird Quarter Financial and Operating Results
Third Quarter Financial and Operating Results
 
09 14-16 teranga gold pgm summit investor presentation final
09 14-16 teranga gold pgm summit investor presentation final09 14-16 teranga gold pgm summit investor presentation final
09 14-16 teranga gold pgm summit investor presentation final
 
Teranga Gold August Investor Presentation
Teranga Gold August Investor Presentation Teranga Gold August Investor Presentation
Teranga Gold August Investor Presentation
 
August Investor Presentation
August Investor Presentation August Investor Presentation
August Investor Presentation
 

Kürzlich hochgeladen

Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Probe Gold
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024CollectiveMining1
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalayResources
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 

Kürzlich hochgeladen (12)

Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024
 
Korea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment ReportKorea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment Report
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR Presentation
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 

Teranga Gold John Tumazos Very Independent Conference

  • 1. John Tumazos Very Independent Research Metals and Natural Resources Conference Presenter: Navin Dyal, CFO Monday, March 30, 2015
  • 2. This presentation contains certain statements that constitute forward-looking information within the meaning of applicable securities laws (“forward-looking statements”), which reflects management’s expectations regarding Teranga Gold Corporation’s (“Teranga” or the “Company”) future growth, results of operations (including, without limitation, future production and capital expenditures), performance (both operational and financial) and business prospects (including the timing and development of new deposits and the success of exploration activities) and opportunities. Wherever possible, words such as “plans”, “expects”, “does not expect”, “budget”, “scheduled”, “estimates”, “forecasts”, “anticipate” or “does not anticipate”, “believe”, “intend”, “ability to” and similar expressions or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, have been used to identify such forward looking information. Although the forward-looking information contained in this presentation reflect management’s current beliefs based upon information currently available to management and based upon what management believes to be reasonable assumptions, Teranga cannot be certain that actual results will be consistent with such forward looking information. Such forward-looking statements are based upon assumptions, opinions and analysis made by management in light of its experience, current conditions and its expectations of future developments that management believe to be reasonable and relevant. These assumptions include, among other things, the ability to obtain any requisite Senegalese governmental approvals, the accuracy of mineral reserve and mineral resource estimates, gold price, exchange rates, fuel and energy costs, future economic conditions and courses of action. Teranga cautions you not to place undue reliance upon any such forward-looking statements, which speak only as of the date they are made. The risks and uncertainties that may affect forward-looking statements include, among others: the inherent risks involved in exploration and development of mineral properties, including government approvals and permitting, changes in economic conditions, changes in the worldwide price of gold and other key inputs, changes in mine plans and other factors, such as project execution delays, many of which are beyond the control of Teranga, as well as other risks and uncertainties which are more fully described in the Company’s Revised Annual Information Form dated April 24, 2014, and in other company filings with securities and regulatory authorities which are available at www.sedar.com. Teranga does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Nothing in this report should be construed as either an offer to sell or a solicitation to buy or sell Teranga securities. This presentation is dated as of the date on the front cover. All references to the Company include its subsidiaries unless the context requires otherwise. This presentation contains references to Teranga using the words “we”, “us”, “our” and similar words and the reader is referred to using the words “you”, “your” and similar words. All dollar amounts stated are denominated in U.S. dollars unless specified otherwise. FORWARD-LOOKING STATEMENTS 2
  • 3. Canadian-based gold mining company with large mine license and regional land package in Senegal EMERGING MID-TIER GOLD PRODUCER WITH ATTRACTIVE LONG-TERM GROWTH PROFILE Refer to endnote (5) on slide 21 Capital Structure (as of March 26, 2015) Basic common shares outstanding 352,801,091 Stock options outstanding 13,616,111 Average daily trading volume 1,774,430 Number of shares owned by insiders 3,043,030 Enterprise value C$182M / US$146M Market capitalization C$222M / US$178M Operates only gold mine and mill in Senegal located 90 kilometres from major gold mines in Mali Large resource base of 6.1Moz in Measured and Indicated (inclusive of reserves) and 2.4Moz in Inferred with ability to convert resources into reserves and make new discoveries(5) Debt-free and generating positive free cash flow Publicly listed on Toronto (TSX: TGZ) and Australian (ASX: TGZ) stock exchanges 3
  • 4. INVESTMENT HIGHLIGHTS 4Refer to endnotes (1), (2), (5) on slide 21 Large long-life reserve & resource base in stable region(5) Low all-in sustaining costs(1) Positive free cash flow & earnings(2) Debt-free balance sheet Significant organic growth profile     
  • 5. FRANCO-NEVADA INVESTMENT VALIDATES TERANGA’S LONG-TERM CASH FLOW AND GROWTH POTENTIAL In connection with Teranga’s acquisition of OJVG in 2014, Franco-Nevada invested $135 million in exchange for a fixed and floating stream on Teranga’s future production Highlights of Teranga Stream Transaction for Franco-Nevada  High quality, high margin  Favourable cost structure  Exploration and expansion potential  Long-term optionality Security of tenure  Well-run operation with an established track record Fixed gold deliveries of 22,500 ounces per year from 2014 to 2019 with trailing 6% gold stream once fixed deliveries completed in 2019 Franco-Nevada to pay 20% of spot gold price per ounce delivered (6% stream is equivalent to a 4.8% NSR royalty) Streaming agreement covers Teranga’s current mine license and land package 5
  • 6. SENEGAL: A LAND OF OPPORTUNITY Senegalese government views mining as pillar for economic growth and supports mining companies by offering attractive royalty and ownership structures Africa Senegal Teranga Gold’s Sabodala Mine A stable democracy and member of West African Economic & Monetary Union Potential for world-class discoveries similar to the deposits (+5 million ounces) that have been found on the same geographical gold belt in Mali Long-term asset consolidation potential 6
  • 7. Breakdown of 2014 Administrative & CSR Expenses $15.6 million  Following 18-month collaborative planning process with local, regional and national stakeholders, created Teranga Development Strategy which focuses on: o economic sustainability o agriculture and food security o youth education and training  Nationalizing our workforce with 90% of 1,050 employees from Senegal, with more than half from the local region  Health and safety is a key priority – currently at ~550 days without a lost time injury COMMITTED TO MINING RESPONSIBLY Comprehensive CSR program is imperative to long-term success in Senegal Corporate Office CSR and Government Relations Legal and Other Depreciation Audit Fees 53%23% 16% 5% 3% 7
  • 8. MANAGEMENT’S STRONG OPERATIONAL TRACK RECORD Commenced mill expansion to double throughput Discovered high-grade Gora satellite deposit Began systematic regional exploration program 2010 Acquired Sabodala gold mine and regional land package that together total 1,488 km2 Completed initial public offering Completed mill expansion Completed development plan for high-grade Gora satellite deposit Expanded M&I by 800,000 ounces Doubled 2P reserves and mine life through acquisition of OJVG Established long- term fiscal and investment agreement with government of Senegal Eliminated inherited “out-of-money” hedge book Successfully integrated OJVG Commenced production at Masato Reduced AISC per ounce by 28% since 2012 Paid off remaining bank debt 2011 2012 2013 2014 M&I 2.3Moz M&I 6.1Moz M&I 6.2Moz M&I 2.1Moz M&I 2.9Moz 8
  • 9. DRIVERS OF VALUATION 9 Attractive free cash flow and profitability Strong balance sheet High return organic growth initiatives
  • 10. Refer to endnote (1) on slide 21 $556 $641 $710 $650 to $700 $1,200 $1,033 $865 $900 to $975 2012 2013 2014 2015F Cash Cost/oz All-In Sustaining Cost/oz (1) (1) Cash Costs and All-in Sustaining CostsQ4 2014 production of 71,278 ounces represents the second highest quarterly production in Teranga’s history - - mill costs were below $14 per tonne INCREASING PROFITABILITY BY LOWERING COSTS AND ONGOING OPTIMIZATION * All-in sustaining costs exclude Franco-Nevada stream impact of approximately $100/oz as stream is treated as deferred revenue Mine production costs projected to be between $147M and $155M in 2015 versus $156M in 2014 Fuel sensitivity: $0.10/litre change in fuel = $20/oz Consume ~50M litres of fuel per annum (20M litres of LFO/30M litres of HFO) Currency: 40% - 50% of expenses are Euro denominated 10% change in Euro = $40/oz 10
  • 11. GROWING FREE CASH FLOW ($50) $78 Annual Free Cash Flow per Ounce of Gold Sold Free Cash Flow/oz 2014 Free Cash Flow/oz (excl. Franco-Nevada) Significantly increasing free cash flow since 2012 despite declining gold prices (2) (2) Refer to endnote (2) on slide 21 20132012 2014 $189 $291 ($11M) $16M $1,669 $1,411 $1,266 2012 2013 2014 Annual Free Cash Flow vs. Average Gold Price per Ounce Free Cash Flow Gold Price Average/oz (London PM Fix) $39M (2) 11
  • 12. ($75M) ($32M) $32M $1,669 $1,411 $1,266 2012 2013 2014 Improving Net Cash (Debt) vs. Declining Average Gold Price Net Cash (Debt) Gold Price Average/oz (London PM Fix) Generating free cash flow from operations and building higher cash balances STRONG DEBT-FREE BALANCE SHEET 12Refer to endnote (7) on slide 21 (7) Stockpile Cost Analysis @ $1,200 Gold Price Tonnes 11.1 million tonnes Grade 0.8 g/t Recovery 89% Recovered Ounces 255,000 Processing $15.00 - $16.00 per tonne G&A and Sustaining CAPEX $2.00 per tonne Royalty 5% Future Costs ~ $800 - $850 per ounce Debt-free as of mid-February 2015 Inventory of nearly 300,000 ounces in low-grade ore stockpile represents a valuable asset providing operating flexibility - can be processed at future costs of $800 to $850 per ounce
  • 13. THREE PHASE GROWTH STRATEGY 13Refer to endnote (6) on slide 21 Increase production to 250,000 – 350,000 oz per year(6) Phase I Mine License Phase II Exploration Production Increase production to 400,000 – 500,000 oz per year(6) Near-term Medium-term Capital intensive Enhance throughput Increase reserves by converting resources and through exploration Opportunities Capital Required Timing New discoveries on mine license (246km2) and regional land package (1,055km2) Phase III Asset Consolidation Increase production to 500,000+ oz per year(6) Long-term Capital intensive Regional processing facility New joint ventures in Senegal Asset consolidation Incremental capital
  • 14. PHASE I: LOW COST NEAR-TERM ORGANIC GROWTH Phase I Mine License Near-term opportunity Enhance throughput Increase reserves by converting resources and through exploration Incremental capital required Increase production to 250,000 – 350,000 oz per year(6) 14Refer to endnote (6) on slide 21
  • 15. PHASE II: MEDIUM-TERM ORGANIC GROWTH Refer to endnote (6) on slide 21 Phase II Exploration Medium-term opportunity New discoveries on mine license (246km2) New discoveries on regional land package (1,055km2) Capital intensive Increase production to 400,000 – 500,000 oz per year(6) SENEGAL MALI +12M oz Au discovered +40M oz Au discovered 15
  • 16. PHASE III: LONG-TERM ASSET CONSOLIDATION IN SENEGAL 212 koz 250 – 350 koz(6) 400 – 500 koz(6) 500+ koz(6) 2014 Phase I Phase II Phase III Production Range 16 Phase III Asset Consolidation Long-term opportunity Regional processing facility New joint ventures in Senegal Asset consolidation Capital intensive Increase production beyond 500,000 oz per year(6) Refer to endnote (6) on slide 21
  • 17. Assumptions  $1,200 per ounce gold price assumption  High-grade Gora deposit comes into production by beginning of Q4 2015  Gora and mill optimization development cost of approximately $125 per ounce included in all-in sustaining costs Levers / Sensitivities  2015 cash costs expected to be in range of $650- $700 with the following sensitivities: – 10% change in currency $40/oz – $0.10/litre change in fuel $20/oz  Between $5.0 and $6.0 million of the total capex relating to the mill optimization may be deferred pending upcoming exploration and heap leach results to ensure the best allocation of capital 2015 OUTLOOK Units 2014 Actual 2015 Guidance(4) Total material mined (‘000t) 29,321 28,500 - 30,500 Ore mined (‘000t) 6,174 6,500 - 7,500 Grade mined (g/t) 1.54 1.40 - 1.60 Ore milled (‘000t) 3,622 3,600 - 3,800 Head grade (g/t) 2.03 2.00 - 2.20 Gold produced(3)(6) (‘000 oz) 212 200 - 230 Total cash costs(1) (including royalties) $/oz sold 710 650 - 700 All-in sustaining costs(1) $/oz sold 865 900 - 975* Mine production costs (net of capitalized deferred stripping) $ millions 156.4 147 - 155 Capital expenditures $ millions 18.9 49.0 - 58.0 17Refer to endnotes (1),(3), (4) and (6) on slide 21 *All-in sustaining costs exclude Franco-Nevada stream impact of approximately $100/oz as stream is treated as deferred revenue
  • 18. CATALYSTS FOR FUTURE GROWTH Internal rate of return hurdle is 20%+ 18 Catalyst Timing Impact Gora H2 2015 30K - 45K oz Mill Optimization 2015 - 2016 5% - 10% increase in throughput 2015 - 2017 10% - 20% increase in gold production Mine License Exploration 2015 - 2019 Extend mine life / add to reserves / increase production Regional Land Package Exploration Ongoing Extend mine life / add to reserves / increase production Heap Leach
  • 19. INVESTMENT HIGHLIGHTS Refer to endnotes (1), (2), (5) on slide 21 Large long-life reserve & resource base in stable region Low all-in sustaining costs(1) Positive free cash flow & earnings(2) Debt-free balance sheet Significant organic growth profile • 6.1 million ounces of gold in measured and indicated resources(5) • 2P reserve life of 11 years (based on 2015 production)(5) • Only mill in Senegal (French West Africa), a safe stable democracy with a progressive mining code • 28% improvement in all-in sustaining costs since 2012 -- 2015 guidance is for trend to continue • Our production flexibility allows us to minimize both material movement and capital spending • Stable G&A with ~25% committed to CSR initiatives, which are imperative to our success in Senegal • Attractive sustainable free cash flow generation • Free cash flow per ounce of gold in line with senior gold companies • Three consecutive years of positive earnings and $100M+ in retained earnings in 5 years of production • Strong debt-free balance sheet • Improving financial flexibility with standby facility • Ability to fund near-term growth through cash flow from operations • Heap leaching and mill optimization provide catalysts for future organic growth • Opportunity for conversion of resources to reserves and new discoveries on large mine license (246km2) • Potential for world-class discoveries on regional land package (1,055km2) • ) 19
  • 20. DRIVERS OF VALUATION Attractive free cash flow and profitability Strong balance sheet High return organic growth initiatives 20
  • 21. 1. Total cash costs per ounce and all-in sustaining costs per ounce are non-IFRS financial measures and do not have a standard meaning under IFRS. Please refer to the Non- IFRS Financial Measures section in the Company’s 2014 fourth quarter results available on the Company’s website at www.terangagold.com. All-in sustaining costs include: total cash costs, administrative expenses (including share based compensation, and excluding corporate depreciation expense and social community costs not related to current operations), capitalized deferred stripping, capitalized reserve development, and mine site sustaining & development capital expenditures as defined by the World Gold Council. Total cash costs per ounce and all-in sustaining costs per ounce are prior to a non-cash inventory write-down (or reversals thereof) to net realizable value. 2. Free cash flow (“FCF”) is defined as operating cash flow less capital expenditures and includes the impact of the Franco-Nevada stream. FCF per ounce and FCF per ounce (excluding Franco-Nevada) are non-IFRS financial measures. For 2013 and 2014, FCF is before the OJVG transaction costs. 3. 24,375 gold ounces of production are to be sold to Franco Nevada at 20% of the spot gold price. 4. Key assumptions: Gold spot price/ounce - US$1,200, Light fuel oil - US$0.95/litre, Heavy fuel oil - US$0.76/litre, US/Euro exchange rate - $1.20, USD/CAD exchange rate - $0.85.Other important assumptions include: any political events are not expected to impact operations, including movement of people, supplies and gold shipments; grades and recoveries will remain consistent with the life-of-mine plan to achieve the forecast gold production; and no unplanned delays in or interruption of scheduled production. 5. Mineral Reserves and Mineral Resources estimates as at December 31, 2013 as per technical reports and Company disclosure. For more information regarding Teranga Gold’s Mineral Reserves and Resources, please refer to the full National Instrument 43-101 Technical Report released on March 13, 2014 available on the Company’s website at www.terangagold.com. 6. Over the past several years more than twelve million ounces of measured and indicated resources have been identified within the south eastern Senegal region, including the Massawa, Golouma, Makabingui and Mako projects, along with the Company’s own Sabodala gold mine. With exploration work completed to date and the prior exploration success seen in the area Management believes there is a reasonable basis for an exploration target that would substantiate the annual production targets set by the second and third phases of our vision. However, the potential quantity and grade of an exploration target is conceptual in nature. There has been insufficient exploration to determine a mineral resource of the size required to achieve the production target we have established and there is no certainty that further exploration work will result in the determination of mineral resources or that the production target itself will be realized. 7. Net cash (debt) is defined as total borrowings and financial derivative liabilities less cash and cash equivalents, bullion receivable and restricted cash. 8. Source: BMO Capital Markets, Gold Mining Research’s Gold Pages (February 2, 2015) In U.S. dollar amounts unless stated otherwise ENDNOTES 21
  • 22. MINERAL RESOURCES SUMMARY As at December 31, 2014 Measured Indicated Measured and Indicated Tonnes Grade Au Tonnes Grade Au Tonnes Grade Au Area (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) Sabodala 23.73 1.21 0.92 19.55 1.23 0.77 43.28 1.22 1.70 Gora 0.49 5.27 0.08 1.84 4.93 0.29 2.32 5.00 0.37 Niakafiri 0.30 1.74 0.02 10.50 1.10 0.37 10.70 1.12 0.39 ML Other Subtotal Sabodala 24.52 1.30 1.02 31.89 1.40 1.43 56.41 1.36 2.46 Masato 1.55 0.96 0.05 50.26 1.04 1.67 51.81 1.03 1.72 Golouma 12.04 2.69 1.04 12.04 2.69 1.04 Kerekounda 2.20 3.77 0.27 2.20 3.77 0.27 Somigol Other 18.72 0.93 0.56 18.72 0.93 0.56 Subtotal Somigol 1.55 0.96 0.05 83.22 1.33 3.54 84.77 1.32 3.59 Total 26.07 1.28 1.07 115.11 1.35 4.97 141.18 1.33 6.05 Inferred Resources Tonnes Au Au Area (Mt) (g/t) (Moz) Sabodala 18.42 0.93 0.55 Gora 0.21 3.38 0.02 Niakafiri 7.20 0.88 0.21 ML Other 10.60 0.97 0.33 Subtotal Sabodala 36.43 0.94 1.11 Masato 19.18 1.15 0.71 Golouma 2.46 2.01 0.16 Kerekounda 0.34 4.21 0.05 Somigol Other 12.87 0.84 0.35 Subtotal Somigol 34.86 1.13 1.26 Total 71.29 1.03 2.37 Notes for Mineral Resources Summary: 1. CIM definitions were followed for Mineral Resources. 2. Mineral Resource cut-off grades for Sabodala, Masato, Golouma, Kerekounda and Somigol Other are 0.2 g/t Au for oxide and 0.35 g/t Au for fresh. 3. Mineral Resource cut-off grades for Niakafiri are 0.3 g/t Au for oxide and 0.5 g/t Au for fresh. 4. Mineral Resource cut-off grade for Gora is 0.5 g/t Au for oxide and fresh. 5. Mineral Resource cut-off grade for Niakafiri West and Soukhoto is 0.3 g/t Au for oxide and fresh. 6. Mineral Resource cut-off grade for Diadiako is 0.2 g/t Au for oxide and fresh. 7. Measured Resources include stockpiles which total 11.30 Mt at 0.82 g/t Au for 0.30 Mozs. 8. High grade assays were capped at grades ranging from 10 g/t to 30 g/t Au at Sabodala, 20 g/t to 70 g/t Au at Gora, from 4 g/t to 25 g/t Au at Masato, from 5 g/t to 70 g/t for Golouma, from 11 g/t to 50 g/t at Kerekounda, and from 0.8 g/t to 110 g/t at Somigol Other. 9. The figures above are “Total” Mineral Resources and include Mineral Reserves. 10. Neither underground Mineral Resources nor Mineral Reserves have been generated by the Company, therefore global Mineral Resources have been reported at the determined cut-off grades. A detailed underground analysis will be undertaken to follow-up on the underground resource potential; however, this is not a priority in the near term. 11. Sum of individual amounts may not equal due to rounding. For clarity, the mineral Resource estimates disclosed above with respect to Niakafiri, Gora and ML Other (which includes Niakafiri, Niakafiri West, Soukhoto and Diadiako) were prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with JORC Code 2012 on the basis that the information has not materially changed since it was last reported. Refer to Teranga Gold Corporation’s ASX Quarterly December 31, 2013 report filed on January 30, 2014 for further details. All material assumptions and technical parameters previously disclosed continue to be applicable and have not materially changed. See Competent Person Statements on pages 33 and 34 for further details. 22
  • 23. MINERAL RESERVES SUMMARY As at December 31, 2014 Proven Probable Proven and Probable Tonnes Grade Au Tonnes Grade Au Tonnes Grade Au Area (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) Sabodala 1.98 1.52 0.10 2.48 1.48 0.12 4.45 1.50 0.21 Gora 0.48 4.66 0.07 1.35 4.79 0.21 1.83 4.76 0.28 Niakafiri 0.23 1.69 0.01 7.58 1.12 0.27 7.81 1.14 0.29 Stockpiles 11.30 0.82 0.30 11.30 0.82 0.30 Subtotal Sabodala 13.99 1.07 0.48 11.41 1.63 0.60 25.40 1.32 1.09 Masato 26.93 1.13 0.98 26.93 1.13 0.98 Golouma 6.47 2.24 0.46 6.47 2.24 0.46 Kerekounda 0.88 3.26 0.09 0.88 3.26 0.09 Subtotal Somigol 34.28 1.39 1.53 34.28 1.39 1.53 Total 13.99 1.07 0.48 45.69 1.45 2.12 59.68 1.36 2.62 Notes for Reserves Summary: 1. CIM definitions were followed for Mineral Reserves. 2. Mineral Reserve cut off grades for Sabodala are 0.40 g/t Au for oxide and 0.5 g/t Au for fresh based on a $1,250/oz gold price and metallurgical recoveries between 90 percent and 93 percent. 3. Mineral Reserve cut off grades for Niakafiri are 0.35 g/t Au for oxide and 0.5 g/t Au for fresh based on a $1,350/oz gold price and metallurgical recoveries between 90 percent and 92 percent. 4. Mineral Reserve cut off grade for Gora is 0.76 g/t Au for oxide and fresh based on $1,200/oz gold price and metallurgical recovery of 95 percent. 5. Mineral Reserve cut off grades for Masato are 0.4 g/t Au for oxide and 0.5 g/t for fresh based on $1,200/oz gold price and metallurgical between 90 percent and 93 percent. 6. Mineral reserve cut off grades for Golouma and Kerekounda are 0.4 g/t Au for oxide and 0.5 g/t for fresh based on $1,250/oz gold price and metallurgical between 90 percent and 93 percent. 7. Sum of individual amounts may not equal due to rounding. 8. The Niakafiri deposit is adjacent to the Sabodala village and relocation of at least some portion of the village will be required which will necessitate a negotiated resettlement program with the affected community members. 9. The Gora deposit is intended to be merged into the Sabodala mining license which the State of Senegal has agreed to in principal subject to completion and receipt of an approved environmental and social impact assessment which is ongoing. 10. There are no other known political, legal or environmental risks that could materially affect the potential development of the identified mineral resources or mineral reserves other than as already set out in the Company’s Annual Information Form dated March 31, 2014 (revised April 24, 2014). Refer to RISK FACTORS beginning on page 60. For clarity, the mineral Reserve estimates disclosed above with respect to Niakafiri and Gora was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with JORC Code 2012 on the basis that the information has not materially changed since it was last reported. Refer to Teranga Gold Corporation’s ASX Quarterly December 31, 2013 report filed on January 30, 2014 for further details. All material assumptions and technical parameters previously disclosed continue to be applicable and have not materially changed. See Competent Person Statements on pages 33 and 34 for further details. 23
  • 24. The technical information contained in this presentation relating to the mineral reserve estimates for Sabodala, the stockpiles, Masato, Golouma and Kerekounda is based on, and fairly represents, information compiled by Mr. William Paul Chawrun, P. Eng who is a member of the Professional Engineers of Ontario, which is currently included as a "Recognized Overseas Professional Organization" in a list promulgated by the ASX from time to time. Mr. Chawrun is a full-time employee of Teranga and is a "qualified person" as defined in NI 43-101 and a "competent person" as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr. Chawrun has sufficient experience relevant to the style of mineralization and type of deposit under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr. Chawrun has consented to the inclusion in this document of the matters based on his compiled information in the form and context in which it appears in this presentation. The technical information contained in this presentation relating to the mineral reserve estimates for Gora and Niakafiri is based on, and fairly represents, information and supporting documentation prepared by Julia Martin, P.Eng. who is a member of the Professional Engineers of Ontario and a Member of AusIMM (CP). Ms. Martin is a full time employee with AMC Mining Consultants (Canada) Ltd., is independent of Teranga, is a “qualified person” as defined in NI 43-101 and a “competent person” as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Ms. Martin has sufficient experience relevant to the style of mineralization and type of deposit under consideration and to the activity she is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Ms. Martin is a “Qualified Person” under National Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Martin has reviewed and accepts responsibility for the Mineral Reserve estimates for Gora and Niakafiri disclosed in this document and has consented to the inclusion of the matters based on her information in the form and context in which it appears in this presentation. The technical information contained in this presentation relating to mineral resource estimates for Niakafiri, Gora, Niakafiri West, Soukhoto, and Diadiako is based on, and fairly represents, information compiled by Ms. Patti Nakai-Lajoie. Ms. Patti Nakai-Lajoie, P. Geo., is a Member of the Association of Professional Geoscientists of Ontario, which is currently included as a "Recognized Overseas Professional Organization" in a list promulgated by the ASX from time to time. Ms. Nakai-Lajoie is a full time employee of Teranga and is not "independent" within the meaning of National Instrument 43- 101. Ms. Nakai-Lajoie has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which she is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Ms. Nakai-Lajoie is a "Qualified Person" under National Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Nakai-Lajoie has consented to the inclusion in this document of the matters based on her compiled information in the form and context in which it appears in this presentation. 24 COMPETENT AND QUALIFIED PERSONS STATEMENT
  • 25. The technical information contained in this presentation relating to mineral resource estimates for Sabodala, Masato, Golouma, Kerekounda, and Somigol Other are based on, and fairly represents, information compiled by Ms. Patti Nakai-Lajoie. Ms. Patti Nakai-Lajoie, P. Geo., is a Member of the Association of Professional Geoscientists of Ontario, which is currently included as a "Recognized Overseas Professional Organization" in a list promulgated by the ASX from time to time. Ms. Nakai-Lajoie is a full time employee of Teranga and is not "independent" within the meaning of National Instrument 43-101. Ms. Nakai-Lajoie has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which she is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Ms. Nakai-Lajoie is a "Qualified Person" under National Instrument 43-101 Standards of Disclosure for Mineral Projects. Ms. Nakai-Lajoie has consented to the inclusion in this presentation of the matters based on her compiled information in the form and context in which it appears in this document. Teranga’s exploration programs are being managed by Mr. Peter Mann, FAusIMM. Mr. Mann is a full time employee of Teranga and is not "independent" within the meaning of National Instrument 43-101. Mr. Mann has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr. Mann is a "Qualified Person" under National Instrument 43-101 Standards of Disclosure for Mineral Projects. The technical information contained in this presentation relating exploration results are based on, and fairly represents, information compiled by Mr. Mann. Mr. Mann has verified and approved the data disclosed in this presentation, including any sampling, analytical and test data underlying the information. The reverse circulation samples are prepared at site and assayed in the SGS laboratory located at the site. Analysis for diamond drilling is sent for fire assay analysis at ALS Johannesburg, South Africa. Mr. Mann has consented to the inclusion in this presentation of the matters based on his compiled information in the form and context in which it appears herein. Teranga's disclosure of mineral reserve and mineral resource information is governed by NI 43-101 under the guidelines set out in the Canadian Institute of Mining, Metallurgy and Petroleum (the "CIM") Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as may be amended from time to time by the CIM ("CIM Standards"). CIM definitions of the terms "mineral reserve", "proven mineral reserve", "probable mineral reserve", "mineral resource", "measured mineral resource", "indicated mineral resource" and "inferred mineral resource", are substantially similar to the JORC Code corresponding definitions of the terms "ore reserve", "proved ore reserve", "probable ore reserve", "mineral resource", "measured mineral resource", "indicated mineral resource" and "inferred mineral resource", respectively. Estimates of mineral resources and mineral reserves prepared in accordance with the JORC Code would not be materially different if prepared in accordance with the CIM definitions applicable under NI 43-101. There can be no assurance that those portions of mineral resources that are not mineral reserves will ultimately be converted into mineral reserves. COMPETENT AND QUALIFIED PERSONS STATEMENT 25
  • 26. 121 KING STREET WEST SUITE 2600 TORONTO, ON M5H 3T9 TELEPHONE: +1.416.594.000 EMAIL: INVESTOR@TERANGAGOLD.COM WWW.TERANGAGOLD.COM TSX:TGZ / ASX:TGZ