8. Why move to cloud hosting?
● Current hardware reaching end of life
1. Carry on as we were
2. Invest in new hardware
3. Outsource hosting completely
4. Host in the cloud
9. Three Phase Plan
● Phase 1
○ Move existing architecture to AWS
● Phase 2
○ Make most of AWS technologies, elastic beanstalk
● Phase 3
○ Extend product
10. First Steps
● Start by configuring a VPC
● Separating concerns via security groups
Web Layer
App Support Layer
Application Layer
Database Layer
11.
12. it didn't work...
● No Multicast
● NAT Instance
● SMTP Throttled
● Documents in Database
● DR position no better
● Couldn't Pen Test
● Couldn't use RDS
13. Client Objections
"I like to know that my data is in that box
over there with the flashing lights on."
Information Security Officer at a client insurer