BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
Bim based process mining master thesis presentation
1. BIM based process mining
Enabling knowledge reassurance and fact-based problem
discovery within the AECFM industry
Graduation thesis for Construction Management and Engineering Msc by :
Stijn van Schaijk
4. Complexity in the construction
sector?
• Winch (1987): construction projects are amongst
the most complex of all activities.
• Gidado (1996): rapid increase in the complexity of
construction processes.
• Lots of specialists/experts/companies
14. How?
• Knowledge reassurance with Building Information
Modelling and Process Mining.
• Learn from previous projects.
• Finding bottlenecks and planning deviation.
• Develop a method with tools to reuse data from
previous projects.
21. Case study: Construction design
process mining
• Analysis of the design process of a road project
22. Case study: Construction design
process mining
• Event log export from Relatics
• ± 140.000 events
23. Planned process of verification a specification
1. Create/Import Specification
2. Connect Specification to Upper/Lower Specification
3. Assign Specification description
4. Assign control responsibility
5. Assign Specification to Project phase
6. Assign Specification to Person
7. Connect Specification to Work package activity 1
8. Connect Specification to Work package activity 2
9. Connect Specification to Work package activity 3
10. Create work package (WPA) verification
11. Assign work package (WPA) verification to Person
12. Add document of prove
13. Add note to WPA verification
29. Conclusion case study
“Process mining analytics did us realize that we use our
IT systems to store information, but those systems don’t
automatically facilitate an efficient process.”
-Process engineer, contractor
More info? Read
http://www.slideshare.net/StijnvanSchaijk/case-study-
construction-design-process-mining
31. Continuous improvement cycle
during construction projects
• How: Plan, (Autonomous-) Capture, Analyse and
Reuse process data from construction sites
• Finding and storing bottlenecks and planning deviation
35. Capture
1. Scan construction site with drone
2. Create As-built point cloud model (Structure from
motion)
3. Compare As-built with As-planned
4. Merge results with event log
36. 1. Scan construction site with drones
(Dreamfocus Droned
https://www.youtube.com/watch?v=QbBf31bY0xw )
37. 2. Create As-built point cloud
model
• Structure from motion techniques, how does it
work?
38. Take a lot of images of an object
• Around 300 pictures generated from drone movie
39. Identify points in the images that can
possibly be detected in other images
44. Elements missing according to
dronescan
• Week 26 : 9 missing elements - windows and
insulation parts.
• Week 27 : 50 missing elements - windows
• Week 28 : 89 missing elements - windows,
insulation, brick facades, and prefab elements.
• Week 29 : 18 missing elements - windows,
insulation and brick facades.
• Week 30 : 4 missing elements - windows.
62. Results & discussion
• Discovered potentials process mining in
construction industry.
• Read case study design process mining
• http://www.slideshare.net/StijnvanSchaijk/case-study-construction-design-process-
mining
• Read case study facility management process
mining:
• http://www.slideshare.net/StijnvanSchaijk/case-study-process-mining-with-facility-
management-data