Introduction to the construction industry
FNBE
Final project
2
Table of Contents
Introduction ........................................................................................................................................................3
Goals ............................................................................................................................................................3
Objectives ....................................................................................................................................................3
Benefits of rooftop garden ..........................................................................................................................3
Project definition ................................................................................................................................................4
Deliverables .................................................................................................................................................4
Budget .........................................................................................................................................................4
Schedule ......................................................................................................................................................4
Project constraints .......................................................................................................................................5
Basic site analysis .........................................................................................................................................5
Land and its attributes .................................................................................................................................6
Authorization ......................................................................................................................................................8
Essentials ...........................................................................................................................................................14
Risk ....................................................................................................................................................................14
Minutes of meeting ..........................................................................................................................................15
3
Introduction
This document proposes to construct a rooftop garden with a small café at Taylor’s University. The
sole purpose to this building is to provide students an opportunity to relax and feel one with nature. There
will also be a small café where a few light snacks and basic beverages would be served.
Unfortunately there is not much greenery on the Taylor’s campus. There is a need to greenery. Not
only does it provide a tranquil serene environment, it also has environmental benefits. In addition it is
visually appealing.
Due to the scarcity of land in Taylor’s by putting a rooftop garden, there is no problem in finding
adequate space to grow the garden.
Goals
- To create a structure that will be environmentally friendly.
- It will give people an opportunity to relax and feel nature
- To make use of space that is not being utilized to its full potential
Objectives
- To create a rooftop garden
- To create a café and seating area in rooftop garden
-
Rooftop gardens have several benefits
Primarily it improves the quality of air. The plants will absorb the Carbon Dioxide in the atmosphere and
release Oxygen thereby improving the air quality.
Secondly it increases energy conservation. Rooftop gardens reflect light and heat. Therefore the building will
remain cool and energy that would usually be used to cool a building may no longer be necessary.
Rooftop gardens may be beneficial in areas which accumulate a great deal of rain. Storm runoff water can
especially overflow sewer systems. The plants can absorb some of the rainwater and limit the runoff from
excess water. Rooftop gardening, in turn, has the potential to reduce the occurrences of flooding.
Rooftop gardening can potentially protect rooftops from damage and deterioration. The lifetime of a rooftop
can be shortened due to ultraviolet radiations, severe temperatures or excess winds.
In addition, rooftop gardens are visually appealing.
4
Project definition
Deliverable
After this project has been implemented, the deliverables include
A rooftop garden, in which several different types of plants are grown to give a visually appealing view
Areas in which seating is provided. This will give students and opportunity to sit and use the space as they so
desire. These include gazebos.
A café that will provide additional seating as well as some common beverages and snacks.
Budget
Schedule
Breakdown
Cost
MRM
Legal fees 5699
breach of contract 500
cost of rooftop garden ($20 per foot) 611506.6
cost of benches (115) 345
café 315650
Total 933700.6
5
Project constraints
Although there is a set amount of days for which the authorities and permits will be issued, in many
cases there are complications and amendments have to be made. This can delay the project
One of the primary project constraints that will be faced in this project is the weather. If there is
rainy weather, there will be no work done for that day and the rooftop will have to be dry one the work can
commence again.
There are cases where the client changes their mind about the details of the project and this can
cause the architect to revise their original drawings.
Basic site analysis
6
Land and its attributes
As expected the plot of land is flat terrain and is primarily made of concrete. There are some
machinery that is kept on the roof top which will most likely need to be moved or an extra floor will have to
be built above the level where these machinery items are kept.
There is some wiring at the rooftop. Large open, unused space
The entrance to the rooftop The view from the rooftop
The other side of the view from the rooftop
7
There is a pillar the segregates two parts of the rooftop.
8
Authorization
No Procedure Time to
complete
Cost
associated
MRM
1 Submission to Local Authority through OSC
Builders can apply for all the pre-building approvals at the One Stop
Center of the Municipality of Kuala Lumpur. However, the builder still
needs to visit each of the agencies that provide the pre-approvals in order
to obtain confirmation. The One Stop Center charges a processing fee of
MYR 480. This process is partly regulated by Federal Territory (Planning)
Act, 1982.
Agency: Majlis Bandaraya Petaling Jaya MBPJ
1 480
2 Obtain Development Order (DO) from Planning Dept
Planning permission, which is issued as a Development Order by the
Planning Department of the local authority, authorizes development of
the land. The permit is valid for 12 months, within which time
construction must begin.
The processing time for the applications is usually as follows:
• 120 days for large-scale projects (consisting of complicated
development plans, buildings of more than five levels, construction
involving layout plans for a development area of more than 2 acres, or
projects affecting the population density and change of zone area)
• 60 days for mid-scale projects (requiring construction plans of buildings
of fewer than five levels, a temporary change in land/building usage
involving a land area of fewer than 5,000 square feet or involving
changes/additions/alterations made to the available shops/housing units)
• 45 days for small-scale projects (involving suggested
additions/changes/alterations to existing bungalow units, two-story units
and terrace units, and new bungalow units built in accordance with
approved layout plans only)
Agency: Majlis Bandaraya Petaling Jaya MBPJ
28 0
4 Obtain Sewerage Approval
Agency: Indah Water
14 0
5 Obtain Fire Safety (Arch) Comment 14 0
9
Fire safety procedures are regulated by Fire Services Act 1988 and
Uniform Building Bylaws 1984 (Chapter 8)
Agency: Bomba
6 Obtain Hoarding & Signboard Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 1,514
7 Obtain RORO Bin Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
8 Obtain Earthwork Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 100
9 Obtain Road and Drainage Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
10 Obtain Landscape Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
11 Obtain Street Lighting Approval
Street lightning regulations are governed by Street, Drainage and Building
Act, 1974
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
12 Obtain Car Park Approval
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
13 Obtain MSMA and SPAH Approvals
Agency: Majlis Bandaraya Petaling Jaya MBPJ
7 0
14 Obtain Building Plan Approval
The approval of the building plans authorizes construction of the building
17 1301
10
within 12 months from the date of approval. Approval is granted by the
Building Department of the local authority.
The filing fees for the application for building plan approval are MYR
10.00 per 10 sq. m. or any part thereof (a minimum of MYR 100.00) under
the First Schedule of the Federal Territory of Kuala Lumpur Building By-
Laws of 1985. In the case here, involving a 1,300.6 sq. m. built-up area,
the application fee would be MYR 1,300.60.
Agency: Majlis Bandaraya Petaling Jaya MBPJ
15 Obtain Fire Safety (M&E) Approval
Agency: Bomba
14 0
16 Obtain Permission to start work from Building Department (KMB)
Agency: Majlis Bandaraya Petaling Jaya MBPJ
1 0
17 Notification to start Earthwork from Engineering Department (B FORM)
Agency: Majlis Bandaraya Petaling Jaya MBPJ
1 0
18 Notification to Start Sewerage Work (PDC 6)
Agency: Majlis Bandaraya Petaling Jaya MBPJ
1 0
19 Request sewerage inspection
Agency: Indah Water
1 0
20 Sewerage inspection
Agency: Indah Water
1 0
21 Sewerage report
Agency: Indah Water
1 0
22 Request Road & Drainage Clearance 1 0
11
After construction has been completed, a final inspection is conducted by
the Building Department to issue its approval. Approval is granted only
after all approvals are obtained from the various departments listed in
the development order, and is meant to ensure that the construction has
been completed in compliance with the approved building plan and the
requirements listed in it. The period of 3 to 4 months is just an estimate
and might vary with the time it takes the various other departments or
agencies to issue their approvals.
The Building Department supervises the construction work stage-by-stage
by conducting on-site inspections and reviewing the progress report
usually submitted by the architect after each stage.
Agency: Indah Water
23 Road and Drainage Inspection
Agency: Municipality of Kuala Lumpur DBKL
1 0
24 Road and Drainage Report
Agency: Municipality of Kuala Lumpur DBKL
12 0
25 Request Sewerage Clearance
Agency: Indah Water
1 0
26 Sewerage Inspection
Agency: Indah Water
1 0
27 Sewerage Report
Agency:Indah Water
12 0
28 Request Fire Safety Clearance
Agency:Bomba
1 111
29 Fire Safety Inspection 1 0
12
Agency: Bomba
30 Fire Safety Report
Agency: Bomba
12 0
31 Request Water Clearance
Agency: Water Authority SYABAS
1 1000
32 Water Inspection
Agency: Water Authority SYABAS
1 0
33 Water Report
Agency: Water Authority SYABAS
11 3
34 Deposit G1 - G21 Forms and F Form to OSC
The Certificate of Completion has been introduced substituting the
Certificate of Fitness for Occupation in 2007. Upon the coming into force
(in force from November 27, 2007) of By-Law 23 of the Building (Federal
Territory of Kuala Lumpur)(Amendment) By-Laws 1985, the Certificate of
Completion is issued when forms G1 to G21 in respect of stage
certifications as set out in the Second Schedule of the By-Laws 1985 have
been duly certified and received by the principal submitting person. This
person must also certify in Form F that the construction and completion
of building was under his supervision and that to the best of his
knowledge and belief the building has been constructed and completed in
accordance with the Act, the By-Laws and the approved plans.
Agency: Majlis Bandaraya Petaling Jaya MBPJ
1 495
35 Deposit G1 - G21 Forms and F Form to Board of Arch / Eng Malaysia
A copy of forms G1 G2 should also be submitted to the Order of
Architects and Engineers of Malaysia
Agency: Board of Architecs and Engineers of Malaysia
1 0
36 Obtain Water Connection 1 30
13
Agency: Water Authority SYABAS
37 Obtain Telco Connection
Agency: Telekom Malaysa (Telco)
15 495
Electricity Connection
38
Agency: Tenaga National Berhad TNB
1 100
14
Essentials
Risk
The roof must be strong enough to carry the weight of soil.
Unless someone can water and maintain the plants everyday, an irrigation system is required
The plants will need extra care from the scorching heat of the sun
If the drainage system gets clogged and there is a lot of water, the membrane can break and cause leaks into
the building.
15
16
17

More Related Content

Similar to The Project Brief

Document 1
Document 1Document 1
Document 1Erik Ong
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
 
SHP development in India - A roadmap
SHP development in India - A roadmapSHP development in India - A roadmap
SHP development in India - A roadmapNikhil Jaipurkar
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
Ici magazine (
Ici magazine (Ici magazine (
Ici magazine (kiraly93
 
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks Ajjay Kumar Gupta
 
Mascot Manorath - Landlinker.in
Mascot Manorath - Landlinker.inMascot Manorath - Landlinker.in
Mascot Manorath - Landlinker.inLand Linker
 
Eia project (solar power plant)
Eia project (solar power plant)Eia project (solar power plant)
Eia project (solar power plant)AmiraAbdulWanis
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh PrasadRajesh Prasad
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Quang Nguyễn
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CVTawfig Adham
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plantRusiru Sanjaya
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Kiran Singh
 

Similar to The Project Brief (20)

Document 1
Document 1Document 1
Document 1
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
SHP development in India - A roadmap
SHP development in India - A roadmapSHP development in India - A roadmap
SHP development in India - A roadmap
 
Solar Power
Solar PowerSolar Power
Solar Power
 
Arrow Consulting PMP
Arrow Consulting PMPArrow Consulting PMP
Arrow Consulting PMP
 
영문=10mw. fiji
영문=10mw. fiji영문=10mw. fiji
영문=10mw. fiji
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Ici magazine (
Ici magazine (Ici magazine (
Ici magazine (
 
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks
How to Start CLC Blocks Making Business. Cellular Lightweight Concrete Blocks
 
Mascot Manorath - Landlinker.in
Mascot Manorath - Landlinker.inMascot Manorath - Landlinker.in
Mascot Manorath - Landlinker.in
 
Eia project (solar power plant)
Eia project (solar power plant)Eia project (solar power plant)
Eia project (solar power plant)
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
Bala Resume
Bala ResumeBala Resume
Bala Resume
 
Tawfig Khidir - CV
Tawfig Khidir - CVTawfig Khidir - CV
Tawfig Khidir - CV
 
10 mw solar power plant
10 mw solar power plant10 mw solar power plant
10 mw solar power plant
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01
 

More from Anshika Hari Dass (9)

The rooftop garden brief
The rooftop garden briefThe rooftop garden brief
The rooftop garden brief
 
Letterhead
LetterheadLetterhead
Letterhead
 
Envelop
EnvelopEnvelop
Envelop
 
Name Card
Name CardName Card
Name Card
 
LandsTect
LandsTectLandsTect
LandsTect
 
Bubble city
Bubble cityBubble city
Bubble city
 
Magazine
MagazineMagazine
Magazine
 
Group documentation
Group documentationGroup documentation
Group documentation
 
Individual documentation
Individual documentationIndividual documentation
Individual documentation
 

Recently uploaded

(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)oannq
 
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...JeylaisaManabat1
 
Inspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxInspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxShubham Rawat
 
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxJackieSparrow3
 
南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证kbdhl05e
 

Recently uploaded (6)

(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)
 
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
 
Inspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxInspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptx
 
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptx
 
南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证
 

The Project Brief

  • 1. Introduction to the construction industry FNBE Final project
  • 2. 2 Table of Contents Introduction ........................................................................................................................................................3 Goals ............................................................................................................................................................3 Objectives ....................................................................................................................................................3 Benefits of rooftop garden ..........................................................................................................................3 Project definition ................................................................................................................................................4 Deliverables .................................................................................................................................................4 Budget .........................................................................................................................................................4 Schedule ......................................................................................................................................................4 Project constraints .......................................................................................................................................5 Basic site analysis .........................................................................................................................................5 Land and its attributes .................................................................................................................................6 Authorization ......................................................................................................................................................8 Essentials ...........................................................................................................................................................14 Risk ....................................................................................................................................................................14 Minutes of meeting ..........................................................................................................................................15
  • 3. 3 Introduction This document proposes to construct a rooftop garden with a small café at Taylor’s University. The sole purpose to this building is to provide students an opportunity to relax and feel one with nature. There will also be a small café where a few light snacks and basic beverages would be served. Unfortunately there is not much greenery on the Taylor’s campus. There is a need to greenery. Not only does it provide a tranquil serene environment, it also has environmental benefits. In addition it is visually appealing. Due to the scarcity of land in Taylor’s by putting a rooftop garden, there is no problem in finding adequate space to grow the garden. Goals - To create a structure that will be environmentally friendly. - It will give people an opportunity to relax and feel nature - To make use of space that is not being utilized to its full potential Objectives - To create a rooftop garden - To create a café and seating area in rooftop garden - Rooftop gardens have several benefits Primarily it improves the quality of air. The plants will absorb the Carbon Dioxide in the atmosphere and release Oxygen thereby improving the air quality. Secondly it increases energy conservation. Rooftop gardens reflect light and heat. Therefore the building will remain cool and energy that would usually be used to cool a building may no longer be necessary. Rooftop gardens may be beneficial in areas which accumulate a great deal of rain. Storm runoff water can especially overflow sewer systems. The plants can absorb some of the rainwater and limit the runoff from excess water. Rooftop gardening, in turn, has the potential to reduce the occurrences of flooding. Rooftop gardening can potentially protect rooftops from damage and deterioration. The lifetime of a rooftop can be shortened due to ultraviolet radiations, severe temperatures or excess winds. In addition, rooftop gardens are visually appealing.
  • 4. 4 Project definition Deliverable After this project has been implemented, the deliverables include A rooftop garden, in which several different types of plants are grown to give a visually appealing view Areas in which seating is provided. This will give students and opportunity to sit and use the space as they so desire. These include gazebos. A café that will provide additional seating as well as some common beverages and snacks. Budget Schedule Breakdown Cost MRM Legal fees 5699 breach of contract 500 cost of rooftop garden ($20 per foot) 611506.6 cost of benches (115) 345 café 315650 Total 933700.6
  • 5. 5 Project constraints Although there is a set amount of days for which the authorities and permits will be issued, in many cases there are complications and amendments have to be made. This can delay the project One of the primary project constraints that will be faced in this project is the weather. If there is rainy weather, there will be no work done for that day and the rooftop will have to be dry one the work can commence again. There are cases where the client changes their mind about the details of the project and this can cause the architect to revise their original drawings. Basic site analysis
  • 6. 6 Land and its attributes As expected the plot of land is flat terrain and is primarily made of concrete. There are some machinery that is kept on the roof top which will most likely need to be moved or an extra floor will have to be built above the level where these machinery items are kept. There is some wiring at the rooftop. Large open, unused space The entrance to the rooftop The view from the rooftop The other side of the view from the rooftop
  • 7. 7 There is a pillar the segregates two parts of the rooftop.
  • 8. 8 Authorization No Procedure Time to complete Cost associated MRM 1 Submission to Local Authority through OSC Builders can apply for all the pre-building approvals at the One Stop Center of the Municipality of Kuala Lumpur. However, the builder still needs to visit each of the agencies that provide the pre-approvals in order to obtain confirmation. The One Stop Center charges a processing fee of MYR 480. This process is partly regulated by Federal Territory (Planning) Act, 1982. Agency: Majlis Bandaraya Petaling Jaya MBPJ 1 480 2 Obtain Development Order (DO) from Planning Dept Planning permission, which is issued as a Development Order by the Planning Department of the local authority, authorizes development of the land. The permit is valid for 12 months, within which time construction must begin. The processing time for the applications is usually as follows: • 120 days for large-scale projects (consisting of complicated development plans, buildings of more than five levels, construction involving layout plans for a development area of more than 2 acres, or projects affecting the population density and change of zone area) • 60 days for mid-scale projects (requiring construction plans of buildings of fewer than five levels, a temporary change in land/building usage involving a land area of fewer than 5,000 square feet or involving changes/additions/alterations made to the available shops/housing units) • 45 days for small-scale projects (involving suggested additions/changes/alterations to existing bungalow units, two-story units and terrace units, and new bungalow units built in accordance with approved layout plans only) Agency: Majlis Bandaraya Petaling Jaya MBPJ 28 0 4 Obtain Sewerage Approval Agency: Indah Water 14 0 5 Obtain Fire Safety (Arch) Comment 14 0
  • 9. 9 Fire safety procedures are regulated by Fire Services Act 1988 and Uniform Building Bylaws 1984 (Chapter 8) Agency: Bomba 6 Obtain Hoarding & Signboard Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 1,514 7 Obtain RORO Bin Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 8 Obtain Earthwork Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 100 9 Obtain Road and Drainage Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 10 Obtain Landscape Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 11 Obtain Street Lighting Approval Street lightning regulations are governed by Street, Drainage and Building Act, 1974 Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 12 Obtain Car Park Approval Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 13 Obtain MSMA and SPAH Approvals Agency: Majlis Bandaraya Petaling Jaya MBPJ 7 0 14 Obtain Building Plan Approval The approval of the building plans authorizes construction of the building 17 1301
  • 10. 10 within 12 months from the date of approval. Approval is granted by the Building Department of the local authority. The filing fees for the application for building plan approval are MYR 10.00 per 10 sq. m. or any part thereof (a minimum of MYR 100.00) under the First Schedule of the Federal Territory of Kuala Lumpur Building By- Laws of 1985. In the case here, involving a 1,300.6 sq. m. built-up area, the application fee would be MYR 1,300.60. Agency: Majlis Bandaraya Petaling Jaya MBPJ 15 Obtain Fire Safety (M&E) Approval Agency: Bomba 14 0 16 Obtain Permission to start work from Building Department (KMB) Agency: Majlis Bandaraya Petaling Jaya MBPJ 1 0 17 Notification to start Earthwork from Engineering Department (B FORM) Agency: Majlis Bandaraya Petaling Jaya MBPJ 1 0 18 Notification to Start Sewerage Work (PDC 6) Agency: Majlis Bandaraya Petaling Jaya MBPJ 1 0 19 Request sewerage inspection Agency: Indah Water 1 0 20 Sewerage inspection Agency: Indah Water 1 0 21 Sewerage report Agency: Indah Water 1 0 22 Request Road & Drainage Clearance 1 0
  • 11. 11 After construction has been completed, a final inspection is conducted by the Building Department to issue its approval. Approval is granted only after all approvals are obtained from the various departments listed in the development order, and is meant to ensure that the construction has been completed in compliance with the approved building plan and the requirements listed in it. The period of 3 to 4 months is just an estimate and might vary with the time it takes the various other departments or agencies to issue their approvals. The Building Department supervises the construction work stage-by-stage by conducting on-site inspections and reviewing the progress report usually submitted by the architect after each stage. Agency: Indah Water 23 Road and Drainage Inspection Agency: Municipality of Kuala Lumpur DBKL 1 0 24 Road and Drainage Report Agency: Municipality of Kuala Lumpur DBKL 12 0 25 Request Sewerage Clearance Agency: Indah Water 1 0 26 Sewerage Inspection Agency: Indah Water 1 0 27 Sewerage Report Agency:Indah Water 12 0 28 Request Fire Safety Clearance Agency:Bomba 1 111 29 Fire Safety Inspection 1 0
  • 12. 12 Agency: Bomba 30 Fire Safety Report Agency: Bomba 12 0 31 Request Water Clearance Agency: Water Authority SYABAS 1 1000 32 Water Inspection Agency: Water Authority SYABAS 1 0 33 Water Report Agency: Water Authority SYABAS 11 3 34 Deposit G1 - G21 Forms and F Form to OSC The Certificate of Completion has been introduced substituting the Certificate of Fitness for Occupation in 2007. Upon the coming into force (in force from November 27, 2007) of By-Law 23 of the Building (Federal Territory of Kuala Lumpur)(Amendment) By-Laws 1985, the Certificate of Completion is issued when forms G1 to G21 in respect of stage certifications as set out in the Second Schedule of the By-Laws 1985 have been duly certified and received by the principal submitting person. This person must also certify in Form F that the construction and completion of building was under his supervision and that to the best of his knowledge and belief the building has been constructed and completed in accordance with the Act, the By-Laws and the approved plans. Agency: Majlis Bandaraya Petaling Jaya MBPJ 1 495 35 Deposit G1 - G21 Forms and F Form to Board of Arch / Eng Malaysia A copy of forms G1 G2 should also be submitted to the Order of Architects and Engineers of Malaysia Agency: Board of Architecs and Engineers of Malaysia 1 0 36 Obtain Water Connection 1 30
  • 13. 13 Agency: Water Authority SYABAS 37 Obtain Telco Connection Agency: Telekom Malaysa (Telco) 15 495 Electricity Connection 38 Agency: Tenaga National Berhad TNB 1 100
  • 14. 14 Essentials Risk The roof must be strong enough to carry the weight of soil. Unless someone can water and maintain the plants everyday, an irrigation system is required The plants will need extra care from the scorching heat of the sun If the drainage system gets clogged and there is a lot of water, the membrane can break and cause leaks into the building.
  • 15. 15
  • 16. 16