Consultant Agreements
and the Role of the
Consultant
LORMAN EDUCATION SERVICES
Presented by Samantha Ip
December 12, 2014
Fundamentals of Construction Contracts
in British Columbia
Before entering into a contract for
services with a consultant, you should
understand the role of the consultant...
3
How is the Role of the Consultant Defined?
a)The agreement between consultant and owner
b)The construction contract between owner and contractor
c)Applicable industry standards and professional requirements
d)The common law and statutory requirements
e)Consultant insurance requirements
The Role of the Consultant
4
The Role of the Consultant, cont’d
The Industry Standards
1. Architect
a) Bylaw 30.1 of The Code Of Ethics and Professional Conduct
from the Architectural Institute of B.C. (“AIBC”):
• In practicing architecture, an architect shall act with
reasonable care and competence, and shall apply the
knowledge, skill and judgment which are ordinarily applied
by architects currently practicing in B.C.
5
The Role of the Consultant, cont’d
The Industry Standards
1. Architect, Bylaw 30.1, cont’d
a) An architect shall remain informed with respect to the practice of
architecture in B.C.
• This Bylaw approximates the “reasonable architect” test for
negligence.
• It is an architect’s responsibility to recognize personal
impairment to the ability to function competently and, when
so impaired, to withdraw from practicing architecture until
competence is restored.
6
The Role of the Consultant, cont’d
The Industry Standards
1. Architect
b) Bylaw 30.3 of The Code Of Ethics and Professional Conduct:
• An architect shall undertake to perform professional
services only when qualified, together with those whom the
architect may engage as consultants, by education, training
and experience in the specific areas involved.
7
The Role of the Consultant, cont’d
The Industry Standards
1. Architect - Bylaw 30.3, cont’d
• An architect shall limit professional practice to areas of personal
competence or shall engage others (including staff) who are
competent in supplementary areas.
• Where so governed under Provincial statute, other professionals
must be engaged to practice their professions.
 An architect is authorized to undertake architectural services for any
project, but must recognize personal and professional limitations
and must refrain from rendering service in those areas until such
limitations are overcome.
 An architect must be able to manage and coordinate the provision of
other design professionals’ services competently, whether the other
professionals are engaged by the architect or the client
8
The Role of the Consultant, cont’d
The Industry Standards
1. Architect
c) Bylaw 33.4 of The Code Of Ethics and Professional Conduct:
• In practicing architecture, an architect shall take into
account all applicable federal, provincial and municipal
building laws and regulations.
9
The Role of the Consultant, cont’d
The Industry Standards
1. Architect – Bylaw 33.4, cont’d
• This Bylaw recognizes the increasing complexity of laws and
regulations applicable to the practice of architecture. This Bylaw is
complementary to 33.1 in that compliance is mandatory but it
permits the architect to rely on the advice of others qualified by
education, experience or training to provide interpretation.
• In relying on the advice of others, it is incumbent on the architect
to determine that such persons have the requisite credentials and
responsibilities for providing that advice; to brief such persons
properly relating to issues on which advice is sought; and to
confirm such advice in writing.
10
The Role of the Consultant, cont’d
The Industry Standards
2. Engineer
a) Section 22 of Engineers and Geoscientists Act (“EGA”):
• An engineer is not permitted to engage in the practice of a
professional engineer or professional geoscientist unless
the engineer is a member of APEGBC and is licensed.
11
The Role of the Consultant, cont’d
The Industry Standards
2. Engineer
a) Bylaw 14(a)(2) of the Bylaws of the Association requires that
engineers undertake and accept responsibility for professional
assignments only when qualified by training or experience
b) Bylaw 14(a)(6) requires that engineers keep themselves
informed in order to maintain their competence
12
The Role of the Consultant, cont’d
The Industry Standards
• Requirements in the industry standards are often incorporated into
consultant agreements by way of supplementary conditions.
13
The Role of the Consultant, cont’d
What is the Consultant’s Role?
1.Pre-Design: Project budgeting and management, site selection, space
relationships and environmental studies
a) Budgeting is key
14
The Role of the Consultant, cont’d
What is the Consultant’s Role?
2.Design Stage: Project budgeting and management, site selection, space
relationships and environmental studies
a) Schematic design – design concept/proposal for feasibility of
the project
b) Design development – furthering design with consideration of
building code/obtaining development permit
c) Construction documents – reducing design to specifications,
plans and drawings
15
The Role of the Consultant, cont’d
What is the Consultant’s Role?
3.Bidding & Tendering: The consultant represents the owner and acts as
the owner’s agent in preparing and issuing tendering documents and
supervising the tendering process
a) Beware of the very low bid
b) Use supplementary conditions to reduce risk
16
The Role of the Consultant, cont’d
What is the Consultant’s Role?
4.Construction Contract Administration:
a) Field reviews
– Substantial or general conformance?
a) Change orders
b) Payment Certification
17
The Role of the Consultant – Field Review
APEGBC BYLAWS – SECTION 14(b)
• Under this section entitled “Quality Management”, members are
required to establish and maintain documented quality management
processes for their practices, including:
 documented field reviews; and
 documented independent review of structural designs prior to
construction to evaluate the construction documents in order to
determine if the structural systems appear complete.
• Requirement for retention of complete projection documentation for
minimum of 10 years.
18
The Role of the Consultant
What is the Consultant’s Role?
4.Construction Contract Administration:
c) Impartial adjudicator of disputes under CCDC 2
19
The Role of the Consultant
What is the Consultant’s Role?
5.Post-Completion Inspection: Inspections to ensure the work was
constructed as required by the contract documents.
20
• Defined by consultant agreement
• CCDC GC 2.2.7
The Role of the Consultant
DOCUMENT 6C
Between Client and Consultant
February 2007
General Comments on
Document 6C
23
Document 6C - Three Parts
1. AIBC Standard Form of Contract 6C Between Client and
Consultant
2. Schedule of Consultant’s Services
3. Supplementary Conditions: 6C – H to AIUBC Standard
Form of Contract 6C Between Client and Consultant
24
Document 6C - General
• For engagement of the Consultant to provide professional
services in one of the four stated disciplines:
• Architecture
• Structural Engineering
• Mechanical Engineering
• Electrical Engineering
25
Document 6C - General
• One of the Consultants is indicated as the Managing
Consultant – duties under GC1.5
• This contract is considered “pro architect”
• Owners often require a contract with more protection for
themselves by modifying the contract through supplemental
conditions or having a unique contract drafted that is specific
to the project itself
26
Document 6C - General
• Endorsed by AIBC, Fraser Health Authority, Northern Health
Authority, Vancouver Coastal Health, Vancouver Island Health
Authority, Consulting Engineers of B.C., Interior Health
Authority, Provincial Health Services Authority, Quantify
Surveyors Society of B.C.
• Endorsement  familiarity with terms
27
Document 6C - General
Copyright:
• A notice appears on every page of Document 6C 2007
• The use of a copy of Document 6C 2007, in which there is a
discrepancy between the copy and the master Document 6C
on the AIBC website, is a breach of copyright.
• Use supplemental conditions or a “new” contract
28
Document 6C - Five Sections
1. Contract Form A1-22
2. Definitions
3. General Conditions
4. Schedule of Consultant’s Services
5. Schedule of Client’s Responsibilities
CONTRACT FORM
The Articles
30
Document 6C - Notice Requirements
• In writing
• If hand delivered to individual, firm members or officer by
registered post, then considered received by addressee on
date of delivery
• If regular post, then considered delivered within 5 working days
• Email or FAX – not considered official notice
31
Document 6C - The Articles
• Must know Project and Construction Budget (Articles A5 and
A6)
• Anticipated construction procurement (Article A7)
• Anticipated Project delivery model (Article A8)
• Anticipate method of construction pricing (Article A9)
32
Document 6C - The Articles
A7. The anticipated method of construction
procurement is _________________.
• If the method of hiring a builder is not known at the
time of execution of the Contract, then the architect
should warn the client that certain methods of
procurement will result in increased professional
services and fees.
33
Document 6C - The Articles
• Architect may be required to prepare tender documents
• Must ensure that information in the tender documents is
accurate
• Inaccuracies may led to a claim by a contractor/bidder for
negligent misrepresentation
• Architects may also have a duty to warn if the Architect knows
of inaccuracies
34
Document 6C - The Articles
A.10 Schedule of Architect’s Services:
• Consultants should be aware that they must accept a
minimum level of involvement and cannot contract out of
this level of involvement - set out in GC1
• In addition to industry association requirements
• Must add supplementary conditions here
35
Document 6C - The Articles
A.10 Schedule of Architect’s Services:
•Important to have a thorough and complete list of Consultant’s
Services listed as these services will be included in the architect’s
fees payable as set out in
Article A14
•If service is not listed under A10, then it will be an Additional
Service usually at elevated fee rates
36
Document 6C - The Articles
•Article A11 – Client Responsibilities – Supplementary
conditions here if responsibilities in addition to GC2
•Articles A12 & A13 – specifies consultants which Managing
Consultant must coordinate
37
Document 6C - The Articles
•Article A14 - methodology for computing services
listed in Article A10 – ie. not Additional Services
•Articles A15 to A16 – Reimbursable Expenses – GC 14.9 –
• Administrative charges
• % set out
38
Document 6C - The Articles
Article A17 to A19 – Payment
• Client’s obligation to pay an invoice only if submitted as per
requirements of the Contract
• Ensure interest amount is fair
• Note retainer amount now required
39
Document 6C - The Articles
Article A20 – Supplementary Conditions
• Common law duties should be added
• Standard of care required of an architect / engineer:
Common law: duty to exercise the skill, care and diligence
which may reasonably be expected of a person of ordinary
competence, measured by the professional standard
applicable at the time the work is being carried out.
40
Document 6C - The Articles
Suggested SC:
In carrying out its services under this Contract, the
Consultant shall act with reasonable care and
competence, and shall apply the knowledge, skill and
judgment which is ordinarily applied by architects /
engineers currently practicing in the province of British
Columbia.
41
Document 6C - The Articles
Suggested SC:
In carrying out its services under this agreement, the
Consultant shall undertake to perform professional services
which it is qualified, together with those whom the
Consultant may engage as consultants or agents, by
education, training and experience in the specific areas
applicable to this Project.
42
Document 6C - The Articles
Suggested SC:
In carrying out its services under this agreement, the
Consultant shall take into account all applicable
federal, provincial and municipal building laws and
regulations.
In particular, the Consultant shall ensure that all
services and work products created by the Consultant
under this agreement comply with the requirements of
all applicable federal, provincial and municipal building
laws and regulations.
DEFINITIONS
44
Document 6C - The Definitions
“Construction Cost”
• Important because Consultant’s percentage fee is calculated
based on Construction Cost.
• The contract prices of all Project elements designed or
specified by, or as a result of the coordination of, the
Consultant, including cash allowances, building permit fees,
changes, construction management fees or other fees, and all
value-added taxes, whether recoverable or not.
45
Document 6C - The Definitions
“Construction Cost”
• Where there is no contract price for all or part of the Project, the
Construction Cost will be the statement of the probable cost of
construction as determined by or agreed to by the Consultant.
 This entails some risk to the Client
• For the Consultant’s fee, Construction Cost will be at market
value even if Client furnishes labour and material at below
market cost.
46
Document 6C - The Definitions
“Construction Cost” also provides . . .
“In the event that the Client furnishes labour or material
below market cost, or recycled materials are used, the
Construction Cost for purposes of establishing the
Architect’s fee includes the cost of all materials and labour
necessary to complete the Work as if all materials had
been new and as if all labour had been paid for at market
prices at the time of construction”
47
Document 6C - The Definitions
Bylaw 31.3
Except as permitted under Bylaw 32.7 [disclosure of
interest], an architect shall not solicit or accept
compensation or benefit from material or equipment
suppliers in return for specifying or endorsing their
products.
GENERAL CONDITIONS
49
Document 6C - The General Conditions
GC 1.3.1
•Consultant is not required to make exhaustive or continuous on-
site reviews.
•However, the Architect must:
1. attend the site at all critical junctures of the work;
2. inspect all critical points of the work or when problems
may be anticipated due to specialized design details; and
3. turn their mind to the timing of such reviews and their
overall purpose.
50
Document 6C - The General Conditions
GC 1.3.2 and .3
•Consultant is not responsible for the acts or omissions of the
contractor or subcontractors or is not responsible for their
performance of the Work.
•However, consultants have a duty to act reasonably - if a
Consultant is aware of the acts or omissions of others working on
the Work, then the Architect must act reasonably by:
1. taking reasonable steps to ensure that the error is
corrected; and / or
2. warning the Client.
51
Document 6C - The General Conditions
GC 1.5
•Note that the Managing Consultant has the authority for the
overall general direction and coordination of all Consultants,
including coordination of services listed in A12 and A13.
•All notices, directions, instructions, requests, application claims
or other communications shall be made by or through the MC
• Issue and delay if MC not properly coordinating
• Does not promote direct contact between Client and its
Consultants who are not the MC.
52
Document 6C - The General Conditions
GC 1.5 – Cont’d
•MC given authority to make interpretations and decisions on all
matters and claims under the Contract.
•If Contract in question is not with the MC, then the Contract
purports to impose obligations on a non-contracting party – the
MC.
•Client must therefore ensure MC and all other Consultants use
same form of consultant agreement – Document 6C or compatible
document (GC 2.3.5 compatibility requirement)
53
Document 6C - The General Conditions
GC 2.3.4
•Client is required to immediately notify the Consultant in writing if
the Client observes or otherwise becomes aware of any fault or
defect in the Project or any nonconformity with Contract
requirements.
•Owners should ensure the Project team and, in particular, the
Project manager is aware of this obligation.
54
Document 6C - The General Conditions
GC 2.3.6
•Client is required to ensure all Consultants engaged under A13
and specialist consultants obtain and disclose professional liability
insurance compatible with GC 8.
•GC 8 – limitation of Consultant’s liability for any claim in contract
or tort related to performance of services under the Contract is
limited to $250,000 unless otherwise specified.
•Risk management – ensure the Consultant has E&O insurance
which matches the limits of the Consultant’s liability
55
Document 6C - The General Conditions
GC 2.3.6 – Cont’d
•Owners should consider adding terms to the contract regarding
consultant’s insurance:
• Require the Consultant to obtain and maintain E&O
insurance after completion of the Project
• Require direct written notice from Consultant’s insurer
before cancellation of E&O insurance
• Obtain addition project specific insurance or wrap up
insurance
56
Document 6C - The General Conditions
GC 4.1
•The issuance of a Certificate for Payment constitutes a
representation by the Consultant to the Client that the Work
observed during the course of General Review/Field Review is in
“general” conformity with the Contract Documents.
• Change to “substantial” conformity with the Contract
Documents
57
Document 6C - The General Conditions
GC 4.2
•The issuance of a Certificate for Payment shall be a
representation that the Consultant has made an examination to
ascertain how and for what purpose the Contractor has used the
monies paid on account of the contract price, or that the
Contractor has discharged the obligations imposed on the
Contractor by law, or requirements of Worksafe BC, or applicable
statute, which may render the Client personally liable for the
Contractor’s default.
58
Document 6C - The General Conditions
The Consultant should require from the Contractor with each
application for payment:
1. a statutory declaration that all accounts have been paid;
2. a Worksafe BC certificate; and
3. a waiver and release of all claims to the date of the
application for payment.
59
Document 6C - The General Conditions
GC 8.1
•This clause requires the Client to agree that any and all claims,
whether in contract or in tort, against the Consultant shall be
limited to an agreed upon amount or, if no amount is specified,
then to $250,000.
•For most projects, a limit of liability of $250,000 does not
represent the Consultant’s actual risk. It would be poor risk
management for an owner to agree to this limit.
60
Document 6C - The General Conditions
GC 8.2
•This clause calls for the Client to indemnify the Consultant in the
event of a claim by a third party resulting from a claim by the
Client against that third party who then claims against the
Consultant, up to the limit of liability agreed to in GC 8.1.
•This clause limits the Consultant’s exposure under this Contract
to the limit of liability in GC 8.1.
•Could increase owner’s risk in a multi-party claim situation as the
said third party is prevented from claiming over against the
Consultant even if damages caused by Consultant.
61
Document 6C - The General Conditions
GC 8.3
• This clause entitles the Consultant to rely upon the published
product information from manufacturers to relieve themselves
from liability.
• This clause may fall below either of the required common law
standard of care or the standard of care set out in Bylaw 30.1,
requiring an architect to act with reasonable care and
competence…
62
Document 6C - The General Conditions
GC 8.3 – Cont’d
Accordingly, an owner should:
1. eliminate the clause; or
2. require an additional clause be added that the Consultant
at all times, notwithstanding any provision in the Contract,
must perform its duties and responsibilities to the standard
of a reasonably prudent architect / engineer practicing in
British Columbia during the current time period.
63
Document 6C - The General Conditions
GC 10 – Termination
• Either party can terminate the Contract with 7 days’ written
notice if the other party is failing substantially to perform in
accordance with its terms through no fault of the other party
 Could be difficult to establish
• Client can terminate with 7 days’ written notice if Consultant
abandons
• Otherwise Contract terminates one year after earliest of
substantial completion or abandonment.
64
Document 6C - The General Conditions
GC 10 – Termination – Cont’d
• Termination period of one year could be too soon if:
• Mandatory HPO warranty
• Contract warranty
• Extended warranty
• Owners should therefore consider extending the Contract
period
65
Document 6C - The General Conditions
GC 14.2
• No deductions shall be made by the Client from amounts
payable to the Consultant on account of penalty, liquidated
damages, or other sums withheld from payments to
Contractors, or on account of the cost of changes in the Work
other than those for which the Consultant is proven to be
legally responsible or has agreed to pay.
• But note the Owner’s right of set-off at law…
66
Document 6C - The General Conditions
• Owner’s right of set-off…
• This clause does not permit an owner to set off damage
claims against the fees owed to the Architect.
• Owners have a right of set-off unless excluded by the
contract.
• An owner may want to amend this clause to allow a claim
for set-off.
ACEC DOCUMENT 31 - 2009
Engineering Agreement
Between Client And Engineer
GENERAL COMMENTS ON
ACEC DOCUMENT 31 . . .
• Contract is drafted by and for engineers
• That means the document is “pro engineer”
• Owners may want supplemental conditions or a unique
contract
• Copyrighted
• Somewhat simpler than Document 6C but duties of the Client
and Engineer are more thorough
ACEC 31 - 2009
The Components of
the Agreement…
71
ACEC 31 2009 - Five Sections
1. Agreement – Articles A1 to A8
2. Definitions
3. General Conditions
4. Schedule A – Engineer’s Scope of Services
5. Schedule B – Fees & Reimbursable Expenses
THE ARTICLES…
73
ACEC 31 2009 – The Articles
A1.2
•Services are as set out in Schedule A Engineer’s Scope of
Services
•Any change to scope of Services must be made by written order
signed by both parties and identifying the change plus any
adjustments to the Engineer’s Fees and Reimbursable Expenses
74
ACEC 31 2009 – The Articles
A3
•Engineering Agreement documents – ensure list all schedules and
lists or plans relevant to the agreement
•Here is where you insert any supplementary conditions
• SC – similar recommendations to Document 6C in this
presentation
75
ACEC 31 2009 – The Articles
A4
•Fees for Services are set out in Schedule B Fees and
Reimbursable Expenses
A5
•Payment – contemplates that Engineer will issue monthly invoices
•Invoices are due when presented – interest starts running after 30
days - SC required to ensure proper delivery of invoice to Client
76
ACEC 31 2009 – The Articles
A8 – Notices
• Personal delivery, receipted courier or FAX
• Delivery deemed on first Working Day after actual delivery
• Email is not effective notice.
77
ACEC 31 – 2009
THE DEFINITIONS
78
ACEC 31 2009 – Definitions
• “Consultant” shall mean registered/licensed professional
• Note requirement under s. 22 of EGA requires that the
Engineer be licensed and a member of APEGBC
• Under sections 29 to 32 of the EGA - contravention of the
EGA or the Bylaws or incompetence, negligence or
unprofessional conduct may result in an investigation by the
E & G investigation committee and possible subsequent
disciplinary action.
79
ACEC 31 – 2009
GENERAL CONDITIONS
80
ACEC 31 2009 – General Conditions
• GC 5.1 – Engineer is bound by the legislation governing its
profession and this Engineering Agreement does not
derogate from an engineer’s legal obligations at law
 Cannot contract out of legal obligations
• GC 5.2 – Common law duty for Engineer to provide
Services in accordance with care, skill and diligence
normally provided by engineers in performance of
comparable services in similar projects.
81
ACEC 31 2009 – General Conditions
82
ACEC 31 2009 – General Conditions
Part 10 – Termination
•Engineering Agreement is terminated when all Services are
performed, when Engineer dies or becomes incapacitated to
perform.
•If Engineer is in material default in performance of its obligations
and does not correct default with 30 days after Notice, Client may
terminate.
 Without prejudice to Client’s rights at law but Client must
pay for Services & RE to date – but note owner’s right of
set-off
83
ACEC 31 2009 – General Conditions
Part 10 – Termination
•If Client is in default, Engineer can give notice and Client has 30
days to correct default, failing which Engineer can terminate. Client
then must pay promptly.
•If Client does not want to proceed with Project, it can give 30 days’
Notice and then must pay Engineer for Fees & RE plus Suspension
Expenses or Termination Expenses.
84
ACEC 31 2009 – General Conditions
Part 10 – Termination – Recommendations
•30 days’ notice may be excessive for a Project – it would cause
delay in the schedule.
•A mutual right of termination clause with a shorter notice period is
more practical.
85
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Requires Engineer to carry $250,000 per claim limit and $500,000
aggregate limit per year…
•Maintained from commencement of Services until 2 years after
completion of the Services.
 Limit of liability per claim likely too low for most substantial projects.
 2 years post completion is likely too short a period of time for most
deficiency claims.
86
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Requires Client to obtain wrap up insurance and property broad
form / builders risk policy.
•Engineer is an insured under the wrap up liability policy.
87
ACEC 31 2009 – General Conditions
Article 7.2
•This clause allows the Engineer to get
•paid even if the construction does not proceed
•Both parties may want to negotiate on the mechanics of how the
Engineer is to be paid in such a circumstance and may confine
such payment to work done to date.
88
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Limitation of liability – claims against Engineer limited to:
 Claims brought within limitation period or 2 years of
completion or termination of Services, whichever is
sooner.
 BC limitation period is two years from the date from
which a Client knew it had a cause of action.
89
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Limitation of liability – quantum of claims against Engineer limited
to:
 Re-performance of Services; or
 Amount insurance available to Engineer as per the
Engineering Agreement; or
 $250,000
•Very engineer friendly term which owners should revise by
supplementary conditions.
90
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Limitation of liability – limits liability to corporation or
partnership and removes right of claiming against any
member personally.
•This term presents a risk management issue for the owner if
there is insufficient insurance behind the firm / corporation for
the claim, and unduly limits an owner’s claim particularly in
the context of one man shops and claims for
misrepresentation.
91
ACEC 31 2009 – General Conditions
Part 14 – Insurance & Liability
•Limitation of liability – limits claim to direct damages only, and so a
Client cannot claim for consequential damages or loss of profit.
•Severely limits a Client’s rights at law with respect to delay and
impact claims.
92
Consultant Agreements - Concluding Comments
1. Neither the Document 6C nor the ACEC 31 has all of the
requisite terms for a full and balanced contract.
Supplementary conditions are required.
2. The goal should always be to achieve a balanced contract
which is fair to and protects the rights of both parties.
3. The contract must make sense for the project in question in
terms of any contractual limitation of liability and requisite
insurance.
93
Consultant Agreements - Concluding Comments
4. A contract is only a useful risk management tool if the parties
know the terms and follow them.
5. Disputes under a contract should be dealt with expressly and
openly through effective communication.
6. Risk management must involve not only considering the
project during the performance of Services but also
afterwards, particularly given the claims made nature of
insurance policies.
These materials are necessarily of a general nature and cannot be
regarded as legal advice. Clark Wilson LLP will be pleased to
provide additional details on request. Inquiries or comments
concerning these materials should be directed to Samantha Ip.
Clark Wilson LLP
900 – 885 West Georgia Street
Vancouver, BC V6C 3H1
Fax: 604.687.6314
www.cwilson.com
Samantha Ip
Direct Tel: 604.643.3172
Email: ssi@cwilson.com
(351489.1)
D/NJT/506264.1

Weitere ähnliche Inhalte

Was ist angesagt?

BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
Omer Syed
 
Introduction to Architectural Profession.ppt
Introduction to Architectural Profession.pptIntroduction to Architectural Profession.ppt
Introduction to Architectural Profession.ppt
DrSmritiAshok1
 
BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
Russell and Dawson
 

Was ist angesagt? (20)

Architectural drawings
Architectural drawings Architectural drawings
Architectural drawings
 
Building information modelling
Building information modellingBuilding information modelling
Building information modelling
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
A survey on modeling guidelines for quantity takeoff-oriented BIM-based design
A survey on modeling guidelines for quantity takeoff-oriented BIM-based designA survey on modeling guidelines for quantity takeoff-oriented BIM-based design
A survey on modeling guidelines for quantity takeoff-oriented BIM-based design
 
Building information modeling BIM
Building information modeling BIMBuilding information modeling BIM
Building information modeling BIM
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Synergis University 2014-BIM for Construction
Synergis University 2014-BIM for ConstructionSynergis University 2014-BIM for Construction
Synergis University 2014-BIM for Construction
 
Introduction to Architectural Profession.ppt
Introduction to Architectural Profession.pptIntroduction to Architectural Profession.ppt
Introduction to Architectural Profession.ppt
 
Architectural Design Process for Beginners/Students
Architectural Design Process for Beginners/StudentsArchitectural Design Process for Beginners/Students
Architectural Design Process for Beginners/Students
 
Bim
BimBim
Bim
 
What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?What does BIM mean for Civil Engineers?
What does BIM mean for Civil Engineers?
 
Architectural design-process
Architectural design-processArchitectural design-process
Architectural design-process
 
Construction Safety Management
Construction Safety ManagementConstruction Safety Management
Construction Safety Management
 
Project management for engineers and architects
Project management for engineers and architectsProject management for engineers and architects
Project management for engineers and architects
 
What is BIM?
What is BIM?What is BIM?
What is BIM?
 
BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
 
BIM
BIMBIM
BIM
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 

Ähnlich wie Consultant Agreements and the Role of the Consultant

The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
Zainab Zainordin
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 

Ähnlich wie Consultant Agreements and the Role of the Consultant (20)

Understanding AIA Document A201-2017, General Conditions of Construction Cont...
Understanding AIA Document A201-2017, General Conditions of Construction Cont...Understanding AIA Document A201-2017, General Conditions of Construction Cont...
Understanding AIA Document A201-2017, General Conditions of Construction Cont...
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
Dilip Deshmukh (1)
Dilip Deshmukh (1)Dilip Deshmukh (1)
Dilip Deshmukh (1)
 
Matrix207
Matrix207Matrix207
Matrix207
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Fidic
FidicFidic
Fidic
 
Uap Document
Uap DocumentUap Document
Uap Document
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
1 introduction arch_practice
1 introduction arch_practice1 introduction arch_practice
1 introduction arch_practice
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
PP1 Project 2 Project Report
PP1 Project 2 Project ReportPP1 Project 2 Project Report
PP1 Project 2 Project Report
 
Section 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers ManualSection 2 of Philippine Institute of Civil Engineers Manual
Section 2 of Philippine Institute of Civil Engineers Manual
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Professional Practice 2 - Copy.pptx
Professional Practice 2 - Copy.pptxProfessional Practice 2 - Copy.pptx
Professional Practice 2 - Copy.pptx
 
Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)Professional practice of architects-Role of an architect (COA)
Professional practice of architects-Role of an architect (COA)
 

Mehr von Samantha Ip

Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution Exclusion
Samantha Ip
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Samantha Ip
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
Samantha Ip
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?
Samantha Ip
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal Issues
Samantha Ip
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian Perspective
Samantha Ip
 

Mehr von Samantha Ip (12)

Sports & Events
Sports & EventsSports & Events
Sports & Events
 
Pollution Exclusion
Pollution ExclusionPollution Exclusion
Pollution Exclusion
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O Exposure
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian Perspective
 
When It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The PayerWhen It Comes To Defence Costs, First Layer Is Usually The Payer
When It Comes To Defence Costs, First Layer Is Usually The Payer
 
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?Bad Faith Litigation in Canada: Much Ado About Nothing?
Bad Faith Litigation in Canada: Much Ado About Nothing?
 
E&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal IssuesE&O Insurance - An Update on Legal Issues
E&O Insurance - An Update on Legal Issues
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian Perspective
 

Kürzlich hochgeladen

Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
amilabibi1
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Hung Le
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
Kayode Fayemi
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
David Celestin
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
ZurliaSoop
 

Kürzlich hochgeladen (17)

Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Bailey
 
ICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdfICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdf
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
 
Zone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptxZone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptx
 
Introduction to Artificial intelligence.
Introduction to Artificial intelligence.Introduction to Artificial intelligence.
Introduction to Artificial intelligence.
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio III
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar Training
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of Drupal
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatment
 
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait Cityin kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
 

Consultant Agreements and the Role of the Consultant

  • 1. Consultant Agreements and the Role of the Consultant LORMAN EDUCATION SERVICES Presented by Samantha Ip December 12, 2014 Fundamentals of Construction Contracts in British Columbia
  • 2. Before entering into a contract for services with a consultant, you should understand the role of the consultant...
  • 3. 3 How is the Role of the Consultant Defined? a)The agreement between consultant and owner b)The construction contract between owner and contractor c)Applicable industry standards and professional requirements d)The common law and statutory requirements e)Consultant insurance requirements The Role of the Consultant
  • 4. 4 The Role of the Consultant, cont’d The Industry Standards 1. Architect a) Bylaw 30.1 of The Code Of Ethics and Professional Conduct from the Architectural Institute of B.C. (“AIBC”): • In practicing architecture, an architect shall act with reasonable care and competence, and shall apply the knowledge, skill and judgment which are ordinarily applied by architects currently practicing in B.C.
  • 5. 5 The Role of the Consultant, cont’d The Industry Standards 1. Architect, Bylaw 30.1, cont’d a) An architect shall remain informed with respect to the practice of architecture in B.C. • This Bylaw approximates the “reasonable architect” test for negligence. • It is an architect’s responsibility to recognize personal impairment to the ability to function competently and, when so impaired, to withdraw from practicing architecture until competence is restored.
  • 6. 6 The Role of the Consultant, cont’d The Industry Standards 1. Architect b) Bylaw 30.3 of The Code Of Ethics and Professional Conduct: • An architect shall undertake to perform professional services only when qualified, together with those whom the architect may engage as consultants, by education, training and experience in the specific areas involved.
  • 7. 7 The Role of the Consultant, cont’d The Industry Standards 1. Architect - Bylaw 30.3, cont’d • An architect shall limit professional practice to areas of personal competence or shall engage others (including staff) who are competent in supplementary areas. • Where so governed under Provincial statute, other professionals must be engaged to practice their professions.  An architect is authorized to undertake architectural services for any project, but must recognize personal and professional limitations and must refrain from rendering service in those areas until such limitations are overcome.  An architect must be able to manage and coordinate the provision of other design professionals’ services competently, whether the other professionals are engaged by the architect or the client
  • 8. 8 The Role of the Consultant, cont’d The Industry Standards 1. Architect c) Bylaw 33.4 of The Code Of Ethics and Professional Conduct: • In practicing architecture, an architect shall take into account all applicable federal, provincial and municipal building laws and regulations.
  • 9. 9 The Role of the Consultant, cont’d The Industry Standards 1. Architect – Bylaw 33.4, cont’d • This Bylaw recognizes the increasing complexity of laws and regulations applicable to the practice of architecture. This Bylaw is complementary to 33.1 in that compliance is mandatory but it permits the architect to rely on the advice of others qualified by education, experience or training to provide interpretation. • In relying on the advice of others, it is incumbent on the architect to determine that such persons have the requisite credentials and responsibilities for providing that advice; to brief such persons properly relating to issues on which advice is sought; and to confirm such advice in writing.
  • 10. 10 The Role of the Consultant, cont’d The Industry Standards 2. Engineer a) Section 22 of Engineers and Geoscientists Act (“EGA”): • An engineer is not permitted to engage in the practice of a professional engineer or professional geoscientist unless the engineer is a member of APEGBC and is licensed.
  • 11. 11 The Role of the Consultant, cont’d The Industry Standards 2. Engineer a) Bylaw 14(a)(2) of the Bylaws of the Association requires that engineers undertake and accept responsibility for professional assignments only when qualified by training or experience b) Bylaw 14(a)(6) requires that engineers keep themselves informed in order to maintain their competence
  • 12. 12 The Role of the Consultant, cont’d The Industry Standards • Requirements in the industry standards are often incorporated into consultant agreements by way of supplementary conditions.
  • 13. 13 The Role of the Consultant, cont’d What is the Consultant’s Role? 1.Pre-Design: Project budgeting and management, site selection, space relationships and environmental studies a) Budgeting is key
  • 14. 14 The Role of the Consultant, cont’d What is the Consultant’s Role? 2.Design Stage: Project budgeting and management, site selection, space relationships and environmental studies a) Schematic design – design concept/proposal for feasibility of the project b) Design development – furthering design with consideration of building code/obtaining development permit c) Construction documents – reducing design to specifications, plans and drawings
  • 15. 15 The Role of the Consultant, cont’d What is the Consultant’s Role? 3.Bidding & Tendering: The consultant represents the owner and acts as the owner’s agent in preparing and issuing tendering documents and supervising the tendering process a) Beware of the very low bid b) Use supplementary conditions to reduce risk
  • 16. 16 The Role of the Consultant, cont’d What is the Consultant’s Role? 4.Construction Contract Administration: a) Field reviews – Substantial or general conformance? a) Change orders b) Payment Certification
  • 17. 17 The Role of the Consultant – Field Review APEGBC BYLAWS – SECTION 14(b) • Under this section entitled “Quality Management”, members are required to establish and maintain documented quality management processes for their practices, including:  documented field reviews; and  documented independent review of structural designs prior to construction to evaluate the construction documents in order to determine if the structural systems appear complete. • Requirement for retention of complete projection documentation for minimum of 10 years.
  • 18. 18 The Role of the Consultant What is the Consultant’s Role? 4.Construction Contract Administration: c) Impartial adjudicator of disputes under CCDC 2
  • 19. 19 The Role of the Consultant What is the Consultant’s Role? 5.Post-Completion Inspection: Inspections to ensure the work was constructed as required by the contract documents.
  • 20. 20 • Defined by consultant agreement • CCDC GC 2.2.7 The Role of the Consultant
  • 21. DOCUMENT 6C Between Client and Consultant February 2007
  • 23. 23 Document 6C - Three Parts 1. AIBC Standard Form of Contract 6C Between Client and Consultant 2. Schedule of Consultant’s Services 3. Supplementary Conditions: 6C – H to AIUBC Standard Form of Contract 6C Between Client and Consultant
  • 24. 24 Document 6C - General • For engagement of the Consultant to provide professional services in one of the four stated disciplines: • Architecture • Structural Engineering • Mechanical Engineering • Electrical Engineering
  • 25. 25 Document 6C - General • One of the Consultants is indicated as the Managing Consultant – duties under GC1.5 • This contract is considered “pro architect” • Owners often require a contract with more protection for themselves by modifying the contract through supplemental conditions or having a unique contract drafted that is specific to the project itself
  • 26. 26 Document 6C - General • Endorsed by AIBC, Fraser Health Authority, Northern Health Authority, Vancouver Coastal Health, Vancouver Island Health Authority, Consulting Engineers of B.C., Interior Health Authority, Provincial Health Services Authority, Quantify Surveyors Society of B.C. • Endorsement  familiarity with terms
  • 27. 27 Document 6C - General Copyright: • A notice appears on every page of Document 6C 2007 • The use of a copy of Document 6C 2007, in which there is a discrepancy between the copy and the master Document 6C on the AIBC website, is a breach of copyright. • Use supplemental conditions or a “new” contract
  • 28. 28 Document 6C - Five Sections 1. Contract Form A1-22 2. Definitions 3. General Conditions 4. Schedule of Consultant’s Services 5. Schedule of Client’s Responsibilities
  • 30. 30 Document 6C - Notice Requirements • In writing • If hand delivered to individual, firm members or officer by registered post, then considered received by addressee on date of delivery • If regular post, then considered delivered within 5 working days • Email or FAX – not considered official notice
  • 31. 31 Document 6C - The Articles • Must know Project and Construction Budget (Articles A5 and A6) • Anticipated construction procurement (Article A7) • Anticipated Project delivery model (Article A8) • Anticipate method of construction pricing (Article A9)
  • 32. 32 Document 6C - The Articles A7. The anticipated method of construction procurement is _________________. • If the method of hiring a builder is not known at the time of execution of the Contract, then the architect should warn the client that certain methods of procurement will result in increased professional services and fees.
  • 33. 33 Document 6C - The Articles • Architect may be required to prepare tender documents • Must ensure that information in the tender documents is accurate • Inaccuracies may led to a claim by a contractor/bidder for negligent misrepresentation • Architects may also have a duty to warn if the Architect knows of inaccuracies
  • 34. 34 Document 6C - The Articles A.10 Schedule of Architect’s Services: • Consultants should be aware that they must accept a minimum level of involvement and cannot contract out of this level of involvement - set out in GC1 • In addition to industry association requirements • Must add supplementary conditions here
  • 35. 35 Document 6C - The Articles A.10 Schedule of Architect’s Services: •Important to have a thorough and complete list of Consultant’s Services listed as these services will be included in the architect’s fees payable as set out in Article A14 •If service is not listed under A10, then it will be an Additional Service usually at elevated fee rates
  • 36. 36 Document 6C - The Articles •Article A11 – Client Responsibilities – Supplementary conditions here if responsibilities in addition to GC2 •Articles A12 & A13 – specifies consultants which Managing Consultant must coordinate
  • 37. 37 Document 6C - The Articles •Article A14 - methodology for computing services listed in Article A10 – ie. not Additional Services •Articles A15 to A16 – Reimbursable Expenses – GC 14.9 – • Administrative charges • % set out
  • 38. 38 Document 6C - The Articles Article A17 to A19 – Payment • Client’s obligation to pay an invoice only if submitted as per requirements of the Contract • Ensure interest amount is fair • Note retainer amount now required
  • 39. 39 Document 6C - The Articles Article A20 – Supplementary Conditions • Common law duties should be added • Standard of care required of an architect / engineer: Common law: duty to exercise the skill, care and diligence which may reasonably be expected of a person of ordinary competence, measured by the professional standard applicable at the time the work is being carried out.
  • 40. 40 Document 6C - The Articles Suggested SC: In carrying out its services under this Contract, the Consultant shall act with reasonable care and competence, and shall apply the knowledge, skill and judgment which is ordinarily applied by architects / engineers currently practicing in the province of British Columbia.
  • 41. 41 Document 6C - The Articles Suggested SC: In carrying out its services under this agreement, the Consultant shall undertake to perform professional services which it is qualified, together with those whom the Consultant may engage as consultants or agents, by education, training and experience in the specific areas applicable to this Project.
  • 42. 42 Document 6C - The Articles Suggested SC: In carrying out its services under this agreement, the Consultant shall take into account all applicable federal, provincial and municipal building laws and regulations. In particular, the Consultant shall ensure that all services and work products created by the Consultant under this agreement comply with the requirements of all applicable federal, provincial and municipal building laws and regulations.
  • 44. 44 Document 6C - The Definitions “Construction Cost” • Important because Consultant’s percentage fee is calculated based on Construction Cost. • The contract prices of all Project elements designed or specified by, or as a result of the coordination of, the Consultant, including cash allowances, building permit fees, changes, construction management fees or other fees, and all value-added taxes, whether recoverable or not.
  • 45. 45 Document 6C - The Definitions “Construction Cost” • Where there is no contract price for all or part of the Project, the Construction Cost will be the statement of the probable cost of construction as determined by or agreed to by the Consultant.  This entails some risk to the Client • For the Consultant’s fee, Construction Cost will be at market value even if Client furnishes labour and material at below market cost.
  • 46. 46 Document 6C - The Definitions “Construction Cost” also provides . . . “In the event that the Client furnishes labour or material below market cost, or recycled materials are used, the Construction Cost for purposes of establishing the Architect’s fee includes the cost of all materials and labour necessary to complete the Work as if all materials had been new and as if all labour had been paid for at market prices at the time of construction”
  • 47. 47 Document 6C - The Definitions Bylaw 31.3 Except as permitted under Bylaw 32.7 [disclosure of interest], an architect shall not solicit or accept compensation or benefit from material or equipment suppliers in return for specifying or endorsing their products.
  • 49. 49 Document 6C - The General Conditions GC 1.3.1 •Consultant is not required to make exhaustive or continuous on- site reviews. •However, the Architect must: 1. attend the site at all critical junctures of the work; 2. inspect all critical points of the work or when problems may be anticipated due to specialized design details; and 3. turn their mind to the timing of such reviews and their overall purpose.
  • 50. 50 Document 6C - The General Conditions GC 1.3.2 and .3 •Consultant is not responsible for the acts or omissions of the contractor or subcontractors or is not responsible for their performance of the Work. •However, consultants have a duty to act reasonably - if a Consultant is aware of the acts or omissions of others working on the Work, then the Architect must act reasonably by: 1. taking reasonable steps to ensure that the error is corrected; and / or 2. warning the Client.
  • 51. 51 Document 6C - The General Conditions GC 1.5 •Note that the Managing Consultant has the authority for the overall general direction and coordination of all Consultants, including coordination of services listed in A12 and A13. •All notices, directions, instructions, requests, application claims or other communications shall be made by or through the MC • Issue and delay if MC not properly coordinating • Does not promote direct contact between Client and its Consultants who are not the MC.
  • 52. 52 Document 6C - The General Conditions GC 1.5 – Cont’d •MC given authority to make interpretations and decisions on all matters and claims under the Contract. •If Contract in question is not with the MC, then the Contract purports to impose obligations on a non-contracting party – the MC. •Client must therefore ensure MC and all other Consultants use same form of consultant agreement – Document 6C or compatible document (GC 2.3.5 compatibility requirement)
  • 53. 53 Document 6C - The General Conditions GC 2.3.4 •Client is required to immediately notify the Consultant in writing if the Client observes or otherwise becomes aware of any fault or defect in the Project or any nonconformity with Contract requirements. •Owners should ensure the Project team and, in particular, the Project manager is aware of this obligation.
  • 54. 54 Document 6C - The General Conditions GC 2.3.6 •Client is required to ensure all Consultants engaged under A13 and specialist consultants obtain and disclose professional liability insurance compatible with GC 8. •GC 8 – limitation of Consultant’s liability for any claim in contract or tort related to performance of services under the Contract is limited to $250,000 unless otherwise specified. •Risk management – ensure the Consultant has E&O insurance which matches the limits of the Consultant’s liability
  • 55. 55 Document 6C - The General Conditions GC 2.3.6 – Cont’d •Owners should consider adding terms to the contract regarding consultant’s insurance: • Require the Consultant to obtain and maintain E&O insurance after completion of the Project • Require direct written notice from Consultant’s insurer before cancellation of E&O insurance • Obtain addition project specific insurance or wrap up insurance
  • 56. 56 Document 6C - The General Conditions GC 4.1 •The issuance of a Certificate for Payment constitutes a representation by the Consultant to the Client that the Work observed during the course of General Review/Field Review is in “general” conformity with the Contract Documents. • Change to “substantial” conformity with the Contract Documents
  • 57. 57 Document 6C - The General Conditions GC 4.2 •The issuance of a Certificate for Payment shall be a representation that the Consultant has made an examination to ascertain how and for what purpose the Contractor has used the monies paid on account of the contract price, or that the Contractor has discharged the obligations imposed on the Contractor by law, or requirements of Worksafe BC, or applicable statute, which may render the Client personally liable for the Contractor’s default.
  • 58. 58 Document 6C - The General Conditions The Consultant should require from the Contractor with each application for payment: 1. a statutory declaration that all accounts have been paid; 2. a Worksafe BC certificate; and 3. a waiver and release of all claims to the date of the application for payment.
  • 59. 59 Document 6C - The General Conditions GC 8.1 •This clause requires the Client to agree that any and all claims, whether in contract or in tort, against the Consultant shall be limited to an agreed upon amount or, if no amount is specified, then to $250,000. •For most projects, a limit of liability of $250,000 does not represent the Consultant’s actual risk. It would be poor risk management for an owner to agree to this limit.
  • 60. 60 Document 6C - The General Conditions GC 8.2 •This clause calls for the Client to indemnify the Consultant in the event of a claim by a third party resulting from a claim by the Client against that third party who then claims against the Consultant, up to the limit of liability agreed to in GC 8.1. •This clause limits the Consultant’s exposure under this Contract to the limit of liability in GC 8.1. •Could increase owner’s risk in a multi-party claim situation as the said third party is prevented from claiming over against the Consultant even if damages caused by Consultant.
  • 61. 61 Document 6C - The General Conditions GC 8.3 • This clause entitles the Consultant to rely upon the published product information from manufacturers to relieve themselves from liability. • This clause may fall below either of the required common law standard of care or the standard of care set out in Bylaw 30.1, requiring an architect to act with reasonable care and competence…
  • 62. 62 Document 6C - The General Conditions GC 8.3 – Cont’d Accordingly, an owner should: 1. eliminate the clause; or 2. require an additional clause be added that the Consultant at all times, notwithstanding any provision in the Contract, must perform its duties and responsibilities to the standard of a reasonably prudent architect / engineer practicing in British Columbia during the current time period.
  • 63. 63 Document 6C - The General Conditions GC 10 – Termination • Either party can terminate the Contract with 7 days’ written notice if the other party is failing substantially to perform in accordance with its terms through no fault of the other party  Could be difficult to establish • Client can terminate with 7 days’ written notice if Consultant abandons • Otherwise Contract terminates one year after earliest of substantial completion or abandonment.
  • 64. 64 Document 6C - The General Conditions GC 10 – Termination – Cont’d • Termination period of one year could be too soon if: • Mandatory HPO warranty • Contract warranty • Extended warranty • Owners should therefore consider extending the Contract period
  • 65. 65 Document 6C - The General Conditions GC 14.2 • No deductions shall be made by the Client from amounts payable to the Consultant on account of penalty, liquidated damages, or other sums withheld from payments to Contractors, or on account of the cost of changes in the Work other than those for which the Consultant is proven to be legally responsible or has agreed to pay. • But note the Owner’s right of set-off at law…
  • 66. 66 Document 6C - The General Conditions • Owner’s right of set-off… • This clause does not permit an owner to set off damage claims against the fees owed to the Architect. • Owners have a right of set-off unless excluded by the contract. • An owner may want to amend this clause to allow a claim for set-off.
  • 67. ACEC DOCUMENT 31 - 2009 Engineering Agreement Between Client And Engineer
  • 68. GENERAL COMMENTS ON ACEC DOCUMENT 31 . . .
  • 69. • Contract is drafted by and for engineers • That means the document is “pro engineer” • Owners may want supplemental conditions or a unique contract • Copyrighted • Somewhat simpler than Document 6C but duties of the Client and Engineer are more thorough ACEC 31 - 2009
  • 70. The Components of the Agreement…
  • 71. 71 ACEC 31 2009 - Five Sections 1. Agreement – Articles A1 to A8 2. Definitions 3. General Conditions 4. Schedule A – Engineer’s Scope of Services 5. Schedule B – Fees & Reimbursable Expenses
  • 73. 73 ACEC 31 2009 – The Articles A1.2 •Services are as set out in Schedule A Engineer’s Scope of Services •Any change to scope of Services must be made by written order signed by both parties and identifying the change plus any adjustments to the Engineer’s Fees and Reimbursable Expenses
  • 74. 74 ACEC 31 2009 – The Articles A3 •Engineering Agreement documents – ensure list all schedules and lists or plans relevant to the agreement •Here is where you insert any supplementary conditions • SC – similar recommendations to Document 6C in this presentation
  • 75. 75 ACEC 31 2009 – The Articles A4 •Fees for Services are set out in Schedule B Fees and Reimbursable Expenses A5 •Payment – contemplates that Engineer will issue monthly invoices •Invoices are due when presented – interest starts running after 30 days - SC required to ensure proper delivery of invoice to Client
  • 76. 76 ACEC 31 2009 – The Articles A8 – Notices • Personal delivery, receipted courier or FAX • Delivery deemed on first Working Day after actual delivery • Email is not effective notice.
  • 77. 77 ACEC 31 – 2009 THE DEFINITIONS
  • 78. 78 ACEC 31 2009 – Definitions • “Consultant” shall mean registered/licensed professional • Note requirement under s. 22 of EGA requires that the Engineer be licensed and a member of APEGBC • Under sections 29 to 32 of the EGA - contravention of the EGA or the Bylaws or incompetence, negligence or unprofessional conduct may result in an investigation by the E & G investigation committee and possible subsequent disciplinary action.
  • 79. 79 ACEC 31 – 2009 GENERAL CONDITIONS
  • 80. 80 ACEC 31 2009 – General Conditions • GC 5.1 – Engineer is bound by the legislation governing its profession and this Engineering Agreement does not derogate from an engineer’s legal obligations at law  Cannot contract out of legal obligations • GC 5.2 – Common law duty for Engineer to provide Services in accordance with care, skill and diligence normally provided by engineers in performance of comparable services in similar projects.
  • 81. 81 ACEC 31 2009 – General Conditions
  • 82. 82 ACEC 31 2009 – General Conditions Part 10 – Termination •Engineering Agreement is terminated when all Services are performed, when Engineer dies or becomes incapacitated to perform. •If Engineer is in material default in performance of its obligations and does not correct default with 30 days after Notice, Client may terminate.  Without prejudice to Client’s rights at law but Client must pay for Services & RE to date – but note owner’s right of set-off
  • 83. 83 ACEC 31 2009 – General Conditions Part 10 – Termination •If Client is in default, Engineer can give notice and Client has 30 days to correct default, failing which Engineer can terminate. Client then must pay promptly. •If Client does not want to proceed with Project, it can give 30 days’ Notice and then must pay Engineer for Fees & RE plus Suspension Expenses or Termination Expenses.
  • 84. 84 ACEC 31 2009 – General Conditions Part 10 – Termination – Recommendations •30 days’ notice may be excessive for a Project – it would cause delay in the schedule. •A mutual right of termination clause with a shorter notice period is more practical.
  • 85. 85 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Requires Engineer to carry $250,000 per claim limit and $500,000 aggregate limit per year… •Maintained from commencement of Services until 2 years after completion of the Services.  Limit of liability per claim likely too low for most substantial projects.  2 years post completion is likely too short a period of time for most deficiency claims.
  • 86. 86 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Requires Client to obtain wrap up insurance and property broad form / builders risk policy. •Engineer is an insured under the wrap up liability policy.
  • 87. 87 ACEC 31 2009 – General Conditions Article 7.2 •This clause allows the Engineer to get •paid even if the construction does not proceed •Both parties may want to negotiate on the mechanics of how the Engineer is to be paid in such a circumstance and may confine such payment to work done to date.
  • 88. 88 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Limitation of liability – claims against Engineer limited to:  Claims brought within limitation period or 2 years of completion or termination of Services, whichever is sooner.  BC limitation period is two years from the date from which a Client knew it had a cause of action.
  • 89. 89 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Limitation of liability – quantum of claims against Engineer limited to:  Re-performance of Services; or  Amount insurance available to Engineer as per the Engineering Agreement; or  $250,000 •Very engineer friendly term which owners should revise by supplementary conditions.
  • 90. 90 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Limitation of liability – limits liability to corporation or partnership and removes right of claiming against any member personally. •This term presents a risk management issue for the owner if there is insufficient insurance behind the firm / corporation for the claim, and unduly limits an owner’s claim particularly in the context of one man shops and claims for misrepresentation.
  • 91. 91 ACEC 31 2009 – General Conditions Part 14 – Insurance & Liability •Limitation of liability – limits claim to direct damages only, and so a Client cannot claim for consequential damages or loss of profit. •Severely limits a Client’s rights at law with respect to delay and impact claims.
  • 92. 92 Consultant Agreements - Concluding Comments 1. Neither the Document 6C nor the ACEC 31 has all of the requisite terms for a full and balanced contract. Supplementary conditions are required. 2. The goal should always be to achieve a balanced contract which is fair to and protects the rights of both parties. 3. The contract must make sense for the project in question in terms of any contractual limitation of liability and requisite insurance.
  • 93. 93 Consultant Agreements - Concluding Comments 4. A contract is only a useful risk management tool if the parties know the terms and follow them. 5. Disputes under a contract should be dealt with expressly and openly through effective communication. 6. Risk management must involve not only considering the project during the performance of Services but also afterwards, particularly given the claims made nature of insurance policies.
  • 94. These materials are necessarily of a general nature and cannot be regarded as legal advice. Clark Wilson LLP will be pleased to provide additional details on request. Inquiries or comments concerning these materials should be directed to Samantha Ip. Clark Wilson LLP 900 – 885 West Georgia Street Vancouver, BC V6C 3H1 Fax: 604.687.6314 www.cwilson.com Samantha Ip Direct Tel: 604.643.3172 Email: ssi@cwilson.com (351489.1) D/NJT/506264.1

Hinweis der Redaktion

  1. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  2. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  3. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  4. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  5. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  6. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  7. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  8. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  9. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  10. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  11. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  12. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  13. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  14. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  15. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  16. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  17. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  18. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  19. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  20. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  21. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  22. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  23. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  24. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  25. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  26. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  27. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  28. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  29. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  30. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  31. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  32. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  33. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  34. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  35. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  36. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  37. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  38. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  39. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  40. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  41. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  42. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  43. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  44. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  45. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  46. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  47. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  48. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  49. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  50. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  51. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  52. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  53. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  54. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  55. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  56. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  57. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  58. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  59. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  60. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  61. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  62. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  63. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  64. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  65. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  66. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  67. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  68. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  69. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  70. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  71. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  72. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  73. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  74. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  75. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  76. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  77. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  78. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  79. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  80. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  81. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  82. _______________________________________________________________ ______________________________________________________________________________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________ _______________________________________________________________
  83. Content on this page is flexible, i.e. if a lawyer wants it to read differently, fine … this is a starting point. Some may prefer to have the heading “Questions or Comments” followed simply with their contact info. Our website should always be included on the last slide. TO PRINT THE PRESENTATION: Take the usual steps (i.e. file – print) … select the printer and format you want (i.e. slides, handouts, notes pages, etc.) … make sure the grayscale option is selected. There is no longer any need to change the slide background before printing handouts.