B. M. Shahrier Majumder, PMP
PMP® Exam Preparation
Project Quality Management
www.wizardea.com | contact@wizardea.com
Learning Objectives
Upon completion of this topic you will learn about
– The processes, activities and documentation items for Project
Quality Management
– Elements (and deliverables) for Project Quality Management
– Tools and techniques of the key activities of the Project Quality
Management
3
www.wizardea.com | contact@wizardea.com
Quality Management
Project Quality Management includes the processes and activities of the
performing organization that determine quality policies, objectives and
responsibilities so that the project will satisfy the needs for which it was
undertaken. procedures and processes of quality planning, quality
assurance and quality control, with continuous process improvement
activities conducted throughout, as appropriate.
4
www.wizardea.com | contact@wizardea.com
Key Activities of Quality Management
• Plan Quality: The process of identifying quality requirements and/or
quality standards for the project and product, and documenting how
the project will demonstrate compliance.
• Perform Quality Assurance: The process of auditing the quality
requirements and results from quality control measurements to
ensure appropriate quality standards and operational definition are
used.
• Perform Quality Control: The process of monitoring and recording
results of executing the quality activities to asses performance and
recommend necessary changes.
5
www.wizardea.com | contact@wizardea.com
Plan Quality | Data Flow Diagram
6
www.wizardea.com | contact@wizardea.com
Plan Quality
Inputs Tools & Techniques Outputs
Scope baseline
Stakeholder register
Cost performance baseline
Schedule baseline
Risk register
Enterprise environmental
factors
Organizational process
assets
Cost-benefit analysis
Cost of Quality
Control charts
Benchmarking
Design of experiments
Statistical sampling
Flowcharting
Proprietary quality
management methodologies
Additional quality planning
tools
Quality management plan
Quality metrics
Quality checklists
Process improvement plan
Project document updates
7
www.wizardea.com | contact@wizardea.com
Plan Quality > Inputs
• Enterprise Environmental Factors
•Governmental agencies rules, standards and guidelines
specific to the application area, may affect the project
• Organizational Process Assets
•Organizational quality policies, regulations and guidelines
•Historical databases
•Lessons learned from previous project specific to the
application area, may affect the project
8
www.wizardea.com | contact@wizardea.com
Plan Quality > Tools and Techniques
• Cost-benefit Analysis
– Consider the trade-offs of the cost of quality
• Constant focus on stakeholder satisfaction
• Constant focus on the bottom line (benefits must outweigh the costs)
• Cheaper and more efficient to prevent defects than have to spend time
and money fixing them later
– Benefits of meeting quality requirements are
• Stakeholder satisfaction is increased
• Costs are lower
• Productivity is higher
• There is less rework
9
www.wizardea.com | contact@wizardea.com
Plan Quality > Tools and Techniques
• Cost of Quality
– Total cost of all efforts to achieve product/service quality
– Measures all work to ensure conformance to requirements and all
work resulting from nonconformance to requirements
– 3 types of costs
• Prevention costs
• Appraisal cost
• Failure cost
– Internal
– External
10
www.wizardea.com | contact@wizardea.com
Plan Quality > Tools and Techniques
• Benchmarking
• Comparing similar activities to the current activities
• Current activities become a standard to measure performance
against (benchmark)
• Design of Experiments
• An analytical technique that identifies the elements or variables
that will have the greatest or optimal effect on overall project
outcomes
• A statistical method
11
www.wizardea.com | contact@wizardea.com
Plan Quality > Outputs
• Quality Management Plan
• Quality management plan is a component or subsidiary plan of the
project management plan
• Describes how the project management team will enforce the Quality
Policy
• Documents the resources required to carry out the plan, the
responsibilities of the project team in quality implementation and all
processes and procedures that are used to satisfy quality
requirements
• Must address quality control, quality assurance and continuous
process improvement for the project
• Quality actions will be assigned to activities in the WBS
12
www.wizardea.com | contact@wizardea.com
Quality Planning >> Outputs
 Quality Metrics
 Specifically describes what is measured and how it will be measured
according to the Quality Control Plan and process
 Quality Checklists
 A tool and technique of the Risk Identification process
 An input to the Quality Control Process
 Process Improvement Plan
 Process boundaries
 Process configuration
 Process metrics
 Target for improved performance
13
www.wizardea.com | contact@wizardea.com
Perform Quality Assurance | Data Flow Diagram
14
14
www.wizardea.com | contact@wizardea.com
Perform Quality Assurance
Inputs Tools & Techniques Outputs
Quality management plan
Quality metrics
Work performance
information
Quality control measurements
Plan Quality and Perform
Quality Control tools and
techniques
Quality audits
Process analysis
Organization process assets
updates
Change request
Project management plan
updates
Project document updates
15
15
www.wizardea.com | contact@wizardea.com
Perform Quality Assurance > Inputs
• Work Performance Information
• Technical performance measures
• Project deliverables status
• Schedule progress
• Cost incurred
16
www.wizardea.com | contact@wizardea.com
Perform Quality Assurance > Tools and
Techniques
• Quality Audit
• Structured review of quality management activities
• May be in-house or independent
• Identify all the good /bad practices being implemented
• Identify all gaps/shortcomings
• Share the good practices introduced or implemented in similar projects
in the organization and industry
• Proactively offer assistance in a positive manner to improve
implementation of processes to help the team raise productivity
• Highlight contributions of each audit in the lesson learned repository of
the organization
17
www.wizardea.com | contact@wizardea.com
Perform Quality Assurance > Tools and
Techniques
• Process Analysis
• Follows the steps as specified in the process improvement plan
to identify the improvements from an organizational and
technical standpoint
• Looks at the problems encountered, constraints experienced
and other non-value added activities identified
• Root Cause Analysis
18
www.wizardea.com | contact@wizardea.com
Perform Quality Control
19
19
www.wizardea.com | contact@wizardea.com
Perform Quality Control
Inputs Tools & Techniques Outputs
Quality management plan
Quality metrics
Quality checklists
Work performance
measurements
Approved change requests
Deliverables
Organization process assets
Cause and effect diagram
Control charts
Flowcharting
Histogram
Pareto chart
Run chart
Scatter diagram
Statistical sampling
Inspection
Approved change request
review
Quality control measurements
Validated changes
Validate deliverables
Organizational process assets
updates
Change requests
Project management plan
updates
20
20
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Cause Effect Diagram
21
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Control Chart
– Stable Process
– Unstable Process
22
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Flow charting
23
www.wizardea.com | contact@wizardea.com
Perform Quality Control >> Tools and
Techniques
• Histogram
A histogram (or frequency
distribution chart) is a bar graph
that groups data by
predetermined intervals to show
the frequency of the data set. It
provides a way to measure and
analyze data collected about a
process or problem, and may
provide a basis for what to work
on first.
24
24
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Pareto Chart
The Pareto chart is a special type of histogram, used to view causes
of a problem in order of severity from largest to smallest. It is a simple
statistical tool that graphically shows the 20-80 rule where 20% of the
sources cause 80% of the problems.
25
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Run Chart
Chronological order that displays changes and trends in the central
tendency (average)
26
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Scatter Diagram
A scatter plot is used for problem solving and understanding cause-
and-effect relationships. It shows whether a relationship exists
between two variables, by testing how one variable influences the
response (other variable).
27
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
 Statistical Sampling
Selecting a portion of the population (0% - 100%)
Statistical terms
Mean – sum of measurements divided by number of measurements
under consideration
Median – value having as many observations above it as below it when
the observations are arranged in increasing or decreasing sequence of
value
Mode – most frequently occurring observation
 If two modes, considered bimodal
 If three or more modes, not a viable measure of central tendency
28
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
 Statistical Sampling (Continue)
Range – difference between the largest measurement and
the smallest measurement
Variance:
 Population or process variance – sum of the squared
deviations from the mean divided by the number of
measurements
 Sample variance – sum of the squared deviations from the
mean divided by number of measurements minus 1 (n-1)
Standard deviation – positive square root of the variance
29
www.wizardea.com | contact@wizardea.com
Perform Quality Control > Tools and Techniques
• Inspection
– Inspections are formal manual techniques that are a natural
evolution of desk checking. This procedure requires a team,
usually directed by a moderator.
– Measuring, examining, and testing
– Determine whether results conform to requirements
– Conducted at any level
30
www.wizardea.com | contact@wizardea.com
Quality Management > Some Important Concept
• Gold Plating:
– Giving the customer extras
– Adds no value to the project
• Just in Time (JIT):
– Decreasing inventory close to zero
– Forces attention to quality
• Total Quality Management (TQM):
– Company and employees focus on finding the ways to
continuously improve the quality of their business practices and
products
31
www.wizardea.com | contact@wizardea.com
Questions
32
• [mail.shahrier@gmail.com]
• http://bd.linkedin.com/in/shahrier

Weitere ähnliche Inhalte

Was ist angesagt?

2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Project integration management
Project integration managementProject integration management
Project integration managementEhsan Ullah
 
Project Management Course slide 1
Project Management Course slide 1Project Management Course slide 1
Project Management Course slide 1Ahmed Alageed
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesAndrew Mikityuk
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration ManagementMartin Sillaots
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
Project integration management
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
 
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK GuideNetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK GuideSwati Chhabra
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
Project integration management
Project integration managementProject integration management
Project integration managementSaad Al Jabri
 
Top 20 Best Project Management Software
Top 20 Best Project Management SoftwareTop 20 Best Project Management Software
Top 20 Best Project Management SoftwareMopinion
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkAndrew Mikityuk
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Fida Karim 🇵🇰
 

Was ist angesagt? (20)

2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Project Management Course slide 1
Project Management Course slide 1Project Management Course slide 1
Project Management Course slide 1
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
1. introduction
1. introduction1. introduction
1. introduction
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Project integration management
Project integration managementProject integration management
Project integration management
 
4. PMP Training - Scope management
4. PMP Training - Scope management4. PMP Training - Scope management
4. PMP Training - Scope management
 
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK GuideNetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
NetCom Learning :The Ultimate Key to Project Managers Success - PMBOK Guide
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Top 20 Best Project Management Software
Top 20 Best Project Management SoftwareTop 20 Best Project Management Software
Top 20 Best Project Management Software
 
PMP Preparation 1 - Framework
PMP Preparation 1 - FrameworkPMP Preparation 1 - Framework
PMP Preparation 1 - Framework
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 

Ähnlich wie PMP Exam Preparation Course: 07 Project Quality Management

10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management BhuWan Khadka
 
Product quality management
Product quality managementProduct quality management
Product quality managementSunil Meena
 
Quality Management Presentation
Quality Management PresentationQuality Management Presentation
Quality Management Presentationbrianbish10795
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Quality management
Quality managementQuality management
Quality managementAPOORVNIGAM2
 
Project quality management
Project quality managementProject quality management
Project quality managementsyeda zoya mehdi
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementmzedan
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagementDhamo daran
 
Quality management slides
Quality management slidesQuality management slides
Quality management slidesSaba Afaq
 
PROJECT QUALITY MANAGEMENT-1.pptx
PROJECT QUALITY MANAGEMENT-1.pptxPROJECT QUALITY MANAGEMENT-1.pptx
PROJECT QUALITY MANAGEMENT-1.pptxOmkarSutar57
 
Quality assurance
Quality assuranceQuality assurance
Quality assuranceSahil Shah
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptAhtashamArshad4
 
Lect.02.09.13
Lect.02.09.13Lect.02.09.13
Lect.02.09.13h_tixid
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 

Ähnlich wie PMP Exam Preparation Course: 07 Project Quality Management (20)

10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management
 
Product quality management
Product quality managementProduct quality management
Product quality management
 
Quality Management Presentation
Quality Management PresentationQuality Management Presentation
Quality Management Presentation
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
Quality management mod
Quality management modQuality management mod
Quality management mod
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Quality management
Quality managementQuality management
Quality management
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagement
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
7- PMP Training - Quality Management
7- PMP Training - Quality Management7- PMP Training - Quality Management
7- PMP Training - Quality Management
 
PROJECT QUALITY MANAGEMENT-1.pptx
PROJECT QUALITY MANAGEMENT-1.pptxPROJECT QUALITY MANAGEMENT-1.pptx
PROJECT QUALITY MANAGEMENT-1.pptx
 
Quality assurance
Quality assuranceQuality assurance
Quality assurance
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.ppt
 
Lect.02.09.13
Lect.02.09.13Lect.02.09.13
Lect.02.09.13
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 

Mehr von B M Shahrier Majumder, PMP, CSM (6)

PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
CMMI Appraisal Summary
CMMI Appraisal SummaryCMMI Appraisal Summary
CMMI Appraisal Summary
 
Southtech continues ISO 9001
Southtech continues ISO 9001Southtech continues ISO 9001
Southtech continues ISO 9001
 
Southtech Achieved CMMI L3
Southtech Achieved CMMI L3Southtech Achieved CMMI L3
Southtech Achieved CMMI L3
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Information System Dashboard
Information System DashboardInformation System Dashboard
Information System Dashboard
 

Kürzlich hochgeladen

GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxnelietumpap1
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 

Kürzlich hochgeladen (20)

GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 

PMP Exam Preparation Course: 07 Project Quality Management

  • 1. www.wizardea.com | contact@wizardea.com B. M. Shahrier Majumder, PMP PMP® Exam Preparation
  • 3. www.wizardea.com | contact@wizardea.com Learning Objectives Upon completion of this topic you will learn about – The processes, activities and documentation items for Project Quality Management – Elements (and deliverables) for Project Quality Management – Tools and techniques of the key activities of the Project Quality Management 3
  • 4. www.wizardea.com | contact@wizardea.com Quality Management Project Quality Management includes the processes and activities of the performing organization that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken. procedures and processes of quality planning, quality assurance and quality control, with continuous process improvement activities conducted throughout, as appropriate. 4
  • 5. www.wizardea.com | contact@wizardea.com Key Activities of Quality Management • Plan Quality: The process of identifying quality requirements and/or quality standards for the project and product, and documenting how the project will demonstrate compliance. • Perform Quality Assurance: The process of auditing the quality requirements and results from quality control measurements to ensure appropriate quality standards and operational definition are used. • Perform Quality Control: The process of monitoring and recording results of executing the quality activities to asses performance and recommend necessary changes. 5
  • 6. www.wizardea.com | contact@wizardea.com Plan Quality | Data Flow Diagram 6
  • 7. www.wizardea.com | contact@wizardea.com Plan Quality Inputs Tools & Techniques Outputs Scope baseline Stakeholder register Cost performance baseline Schedule baseline Risk register Enterprise environmental factors Organizational process assets Cost-benefit analysis Cost of Quality Control charts Benchmarking Design of experiments Statistical sampling Flowcharting Proprietary quality management methodologies Additional quality planning tools Quality management plan Quality metrics Quality checklists Process improvement plan Project document updates 7
  • 8. www.wizardea.com | contact@wizardea.com Plan Quality > Inputs • Enterprise Environmental Factors •Governmental agencies rules, standards and guidelines specific to the application area, may affect the project • Organizational Process Assets •Organizational quality policies, regulations and guidelines •Historical databases •Lessons learned from previous project specific to the application area, may affect the project 8
  • 9. www.wizardea.com | contact@wizardea.com Plan Quality > Tools and Techniques • Cost-benefit Analysis – Consider the trade-offs of the cost of quality • Constant focus on stakeholder satisfaction • Constant focus on the bottom line (benefits must outweigh the costs) • Cheaper and more efficient to prevent defects than have to spend time and money fixing them later – Benefits of meeting quality requirements are • Stakeholder satisfaction is increased • Costs are lower • Productivity is higher • There is less rework 9
  • 10. www.wizardea.com | contact@wizardea.com Plan Quality > Tools and Techniques • Cost of Quality – Total cost of all efforts to achieve product/service quality – Measures all work to ensure conformance to requirements and all work resulting from nonconformance to requirements – 3 types of costs • Prevention costs • Appraisal cost • Failure cost – Internal – External 10
  • 11. www.wizardea.com | contact@wizardea.com Plan Quality > Tools and Techniques • Benchmarking • Comparing similar activities to the current activities • Current activities become a standard to measure performance against (benchmark) • Design of Experiments • An analytical technique that identifies the elements or variables that will have the greatest or optimal effect on overall project outcomes • A statistical method 11
  • 12. www.wizardea.com | contact@wizardea.com Plan Quality > Outputs • Quality Management Plan • Quality management plan is a component or subsidiary plan of the project management plan • Describes how the project management team will enforce the Quality Policy • Documents the resources required to carry out the plan, the responsibilities of the project team in quality implementation and all processes and procedures that are used to satisfy quality requirements • Must address quality control, quality assurance and continuous process improvement for the project • Quality actions will be assigned to activities in the WBS 12
  • 13. www.wizardea.com | contact@wizardea.com Quality Planning >> Outputs  Quality Metrics  Specifically describes what is measured and how it will be measured according to the Quality Control Plan and process  Quality Checklists  A tool and technique of the Risk Identification process  An input to the Quality Control Process  Process Improvement Plan  Process boundaries  Process configuration  Process metrics  Target for improved performance 13
  • 14. www.wizardea.com | contact@wizardea.com Perform Quality Assurance | Data Flow Diagram 14 14
  • 15. www.wizardea.com | contact@wizardea.com Perform Quality Assurance Inputs Tools & Techniques Outputs Quality management plan Quality metrics Work performance information Quality control measurements Plan Quality and Perform Quality Control tools and techniques Quality audits Process analysis Organization process assets updates Change request Project management plan updates Project document updates 15 15
  • 16. www.wizardea.com | contact@wizardea.com Perform Quality Assurance > Inputs • Work Performance Information • Technical performance measures • Project deliverables status • Schedule progress • Cost incurred 16
  • 17. www.wizardea.com | contact@wizardea.com Perform Quality Assurance > Tools and Techniques • Quality Audit • Structured review of quality management activities • May be in-house or independent • Identify all the good /bad practices being implemented • Identify all gaps/shortcomings • Share the good practices introduced or implemented in similar projects in the organization and industry • Proactively offer assistance in a positive manner to improve implementation of processes to help the team raise productivity • Highlight contributions of each audit in the lesson learned repository of the organization 17
  • 18. www.wizardea.com | contact@wizardea.com Perform Quality Assurance > Tools and Techniques • Process Analysis • Follows the steps as specified in the process improvement plan to identify the improvements from an organizational and technical standpoint • Looks at the problems encountered, constraints experienced and other non-value added activities identified • Root Cause Analysis 18
  • 20. www.wizardea.com | contact@wizardea.com Perform Quality Control Inputs Tools & Techniques Outputs Quality management plan Quality metrics Quality checklists Work performance measurements Approved change requests Deliverables Organization process assets Cause and effect diagram Control charts Flowcharting Histogram Pareto chart Run chart Scatter diagram Statistical sampling Inspection Approved change request review Quality control measurements Validated changes Validate deliverables Organizational process assets updates Change requests Project management plan updates 20 20
  • 21. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Cause Effect Diagram 21
  • 22. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Control Chart – Stable Process – Unstable Process 22
  • 23. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Flow charting 23
  • 24. www.wizardea.com | contact@wizardea.com Perform Quality Control >> Tools and Techniques • Histogram A histogram (or frequency distribution chart) is a bar graph that groups data by predetermined intervals to show the frequency of the data set. It provides a way to measure and analyze data collected about a process or problem, and may provide a basis for what to work on first. 24 24
  • 25. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Pareto Chart The Pareto chart is a special type of histogram, used to view causes of a problem in order of severity from largest to smallest. It is a simple statistical tool that graphically shows the 20-80 rule where 20% of the sources cause 80% of the problems. 25
  • 26. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Run Chart Chronological order that displays changes and trends in the central tendency (average) 26
  • 27. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Scatter Diagram A scatter plot is used for problem solving and understanding cause- and-effect relationships. It shows whether a relationship exists between two variables, by testing how one variable influences the response (other variable). 27
  • 28. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques  Statistical Sampling Selecting a portion of the population (0% - 100%) Statistical terms Mean – sum of measurements divided by number of measurements under consideration Median – value having as many observations above it as below it when the observations are arranged in increasing or decreasing sequence of value Mode – most frequently occurring observation  If two modes, considered bimodal  If three or more modes, not a viable measure of central tendency 28
  • 29. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques  Statistical Sampling (Continue) Range – difference between the largest measurement and the smallest measurement Variance:  Population or process variance – sum of the squared deviations from the mean divided by the number of measurements  Sample variance – sum of the squared deviations from the mean divided by number of measurements minus 1 (n-1) Standard deviation – positive square root of the variance 29
  • 30. www.wizardea.com | contact@wizardea.com Perform Quality Control > Tools and Techniques • Inspection – Inspections are formal manual techniques that are a natural evolution of desk checking. This procedure requires a team, usually directed by a moderator. – Measuring, examining, and testing – Determine whether results conform to requirements – Conducted at any level 30
  • 31. www.wizardea.com | contact@wizardea.com Quality Management > Some Important Concept • Gold Plating: – Giving the customer extras – Adds no value to the project • Just in Time (JIT): – Decreasing inventory close to zero – Forces attention to quality • Total Quality Management (TQM): – Company and employees focus on finding the ways to continuously improve the quality of their business practices and products 31