SlideShare a Scribd company logo
1 of 15
Facilities Engineering
    Presentation

  M3 Engineering &
Technology Corporation
Overall Site Plan
Facilities Engineering Scope of Work

 §  Process Facilities
 §  Ancillary Facilities
 §  Civil Infrastructure
 §  Power Supply
 §  Fresh Water Supply & Distribution
Facilities Plan
Process Facilities
§  Sulfide Processing Plant
     §  75,000 DSTPD of Sulfide Ore
     §  1,350 DSTPD of Copper Concentrate
     §      15 DSTPD of Molybdenite Concentrate

§  Sulfide Circuit
     §  Primary Gyratory Crusher, Overland Conveyor, Stockpile
     §  SAG Mill & 2 Parallel Ball Mill Circuits
     §  Copper Flotation with Molybdenum Separation Circuit
     §  Concentrate Dewatering / Filtration
     §  Flotation Tailing dewatering, filtration, convey.
     §  Dry Stack Tailing Area
     §  Reagent Area
Process Facilities
§  Oxide Facility
     §  17,000 DSTPD of Oxide Ore by Leach
     §  Approx. 76,800 Pounds Per Day High Purity Cathode Copper

§  Oxide Circuit
     §  Leach Pad for Run of Mine Ore
     §  Raffinate and PLS Ponds
     §  Storm Water Pond
     §  Two Extraction and One Stripper Solvent Extraction Circuit
     §  Electro-winning Facility
     §  Reagent Area
Ancillary Facilities
            (Support Process & Mine)
§    Warehouse Facilities
§    Administration Building
§    Change Room
§    Analytical Laboratory
§    Mine Truck Shop with Tire Shop
§    Mine Truck Wash and Lubrication Facility
§    Gasoline & Diesel Fuel Storage & Dispensing Facilities
§    Ammonium Nitrate Silos and Explosives Magazines
§    Guard Facility with Truck Scale
Civil Infrastructure
§  Modifications to State Route 83 at Intersection with Mine East
       Access Road
§    East Access Road
§    Upgrades to USFS roads and private roads
§    New USFS connecting roads around Plant
§    Perimeter Road around Waste Rock & Dry Stack Tailing
       Facility
§  Overall Site Grading and Drainage
§  In-plant Roads
§  Initial Mine Haul Roads
Civil Infrastructure
§  North Storm Water Diversion Structure
§  Storm Water Diversion to Process Water Temporary Storage
   (PWTS)
§  Storm Water Diversions around Open Pit
§  Dry Stack Tailing Facility water management
§  Compliance – Point Water Management Structure
Power Supply and Distribution
§  Coordination with Tucson Electric Power (TEP)
§  Substation at TEP connection to step down voltage for Fresh
    Water System
§  Rosemont Substation (138 KV to 34.5 KV)
§  Distribution to Process Motor Control Rooms and other
    Facilities
Fresh Water Supply and Distribution
§    Well field
§    20 inch Water Delivery Line with Booster Stations
§    Fresh Water and Fire Water Tank at Process Facilities
§    Potable Water System with Water Treatment Package
§    Fresh Water System
§    Process Water System
§    Fire Water System
§    Pit Dewatering System
M3 EPCM Scope of Work
§  Project Management
§  Basic Engineering
§  Detail Engineering
§  Procurement
§  Construction Management
§  Commissioning
§  Start-Up Assistance
EPCM Status
§  Currently in Basic Engineering Phase
§  Started in May 2008, finish in April 2009
§  Basic Engineering Effort
    §  Update Deliverables with Better Scope Delineation
    §  Improve Quality of Information for update of Capital
        Estimate and Operating Estimate
    §  Finalize Criteria for Detailed Design Effort
§  Effort Currently Supported by Other Consultants:
    §    Geotechnical Services                 Tetra Tech
    §    Geotechnical Drilling Contract        Tetra Tech
    §    Dry Stack Tailings Facility           AMEC
    §    Heap Leach Facility                   Tetra Tech
Basic Engineering Deliverables
§    Project Procedures
§    Drawing, Specification, and Equipment Lists
§    Discipline Design Criteria
§    Major Equipment and Material Specifications
§    Flowsheets
§    General Arrangement Drawings
§    P&IDs
§    Electrical One-Lines
§    Civil Site Plan and Rough Grading Drawings
§    Architectural Drawings
§    Major Concrete Foundation Drawings (Mills)
§    Updated Capital Estimate and Operating Estimate
§    EPCM Schedule
Detail Engineering Phase
§  Planned start in February 2009
§  Engineering effort linked to forecasted availability of vendor
   information
§  Substantial Complete in July 2010
§  Engineering support will continue through construction

More Related Content

What's hot

Aircraft wing design and strength, stiffness and stability analysis by using...
Aircraft  wing design and strength, stiffness and stability analysis by using...Aircraft  wing design and strength, stiffness and stability analysis by using...
Aircraft wing design and strength, stiffness and stability analysis by using...Mani5436
 
Chapter 5 -momentum_equation_and_its_applications
Chapter 5 -momentum_equation_and_its_applicationsChapter 5 -momentum_equation_and_its_applications
Chapter 5 -momentum_equation_and_its_applicationsZackRule
 
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...kl kl
 
Introduction to finite element method
Introduction to finite element methodIntroduction to finite element method
Introduction to finite element methodshahzaib601980
 
Chapter 6 Failure.pptx
Chapter 6 Failure.pptxChapter 6 Failure.pptx
Chapter 6 Failure.pptxDagmawiGenanaw
 
Chimney present
Chimney presentChimney present
Chimney presentmathusaran
 
Presentation-Prdection of Composite Materials
Presentation-Prdection of Composite MaterialsPresentation-Prdection of Composite Materials
Presentation-Prdection of Composite MaterialsHao-Chiang Cheng
 
Equations of motion normal & tangential
Equations of motion  normal & tangentialEquations of motion  normal & tangential
Equations of motion normal & tangentialGrace Palermo
 
Bending and Torsion A.Vinoth Jebaraj
Bending and Torsion A.Vinoth JebarajBending and Torsion A.Vinoth Jebaraj
Bending and Torsion A.Vinoth JebarajVinoth Jebaraj A
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power housearullawrance90
 
Tensile testing ppt
Tensile testing pptTensile testing ppt
Tensile testing pptRahul Yadav
 
02 conservation equations
02 conservation equations02 conservation equations
02 conservation equationsanees solangi
 
Indian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsIndian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsJisha John
 

What's hot (20)

Aircraft wing design and strength, stiffness and stability analysis by using...
Aircraft  wing design and strength, stiffness and stability analysis by using...Aircraft  wing design and strength, stiffness and stability analysis by using...
Aircraft wing design and strength, stiffness and stability analysis by using...
 
Chapter 5 -momentum_equation_and_its_applications
Chapter 5 -momentum_equation_and_its_applicationsChapter 5 -momentum_equation_and_its_applications
Chapter 5 -momentum_equation_and_its_applications
 
Equilibrium
EquilibriumEquilibrium
Equilibrium
 
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...
Solution Manual – Heat and Mass Transfer: Fundamentals and Application, 5th e...
 
Introduction to finite element method
Introduction to finite element methodIntroduction to finite element method
Introduction to finite element method
 
Spur gear
Spur gearSpur gear
Spur gear
 
Chapter 6 Failure.pptx
Chapter 6 Failure.pptxChapter 6 Failure.pptx
Chapter 6 Failure.pptx
 
Chimney present
Chimney presentChimney present
Chimney present
 
Presentation-Prdection of Composite Materials
Presentation-Prdection of Composite MaterialsPresentation-Prdection of Composite Materials
Presentation-Prdection of Composite Materials
 
Equations of motion normal & tangential
Equations of motion  normal & tangentialEquations of motion  normal & tangential
Equations of motion normal & tangential
 
Introduction to fem
Introduction to femIntroduction to fem
Introduction to fem
 
Bending and Torsion A.Vinoth Jebaraj
Bending and Torsion A.Vinoth JebarajBending and Torsion A.Vinoth Jebaraj
Bending and Torsion A.Vinoth Jebaraj
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power house
 
Finite Element Methods
Finite Element  MethodsFinite Element  Methods
Finite Element Methods
 
Design of arch bridges
Design of arch bridgesDesign of arch bridges
Design of arch bridges
 
Tensile testing ppt
Tensile testing pptTensile testing ppt
Tensile testing ppt
 
02 conservation equations
02 conservation equations02 conservation equations
02 conservation equations
 
Tribology
TribologyTribology
Tribology
 
Indian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsIndian standard specification for high strength structural bolts
Indian standard specification for high strength structural bolts
 
Structures and Materials- Section 7 Stress Concentration
Structures and Materials- Section 7 Stress ConcentrationStructures and Materials- Section 7 Stress Concentration
Structures and Materials- Section 7 Stress Concentration
 

Similar to Facilities Engineering Presentation

4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14Kristipoom R-khubut
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
Capabilities and resources
Capabilities and resourcesCapabilities and resources
Capabilities and resourcesMartin de Beer
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillDeanGarratt
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Association for Project Management
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plantRahul Rathod
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingTim Leung
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling ManagementMojrian Web
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14James M. Bright, P.E.
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Permitting and Hydraulic Fracturing, Leslie Savage
Permitting and Hydraulic Fracturing, Leslie SavagePermitting and Hydraulic Fracturing, Leslie Savage
Permitting and Hydraulic Fracturing, Leslie SavageTXGroundwaterSummit
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description detailsAonghus Murray
 

Similar to Facilities Engineering Presentation (20)

Cv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas TulabotCv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas Tulabot
 
Dariush.resume
Dariush.resumeDariush.resume
Dariush.resume
 
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.144.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
4.BLC IPOP -7th August 2014 - Post Session Update -8.8.14
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
The GBHE Project Experience
The GBHE Project ExperienceThe GBHE Project Experience
The GBHE Project Experience
 
Capabilities and resources
Capabilities and resourcesCapabilities and resources
Capabilities and resources
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Tushar resume
Tushar resumeTushar resume
Tushar resume
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plant
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional Drilling
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling Management
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Permitting and Hydraulic Fracturing, Leslie Savage
Permitting and Hydraulic Fracturing, Leslie SavagePermitting and Hydraulic Fracturing, Leslie Savage
Permitting and Hydraulic Fracturing, Leslie Savage
 
Small Hydro Training Module
Small Hydro Training ModuleSmall Hydro Training Module
Small Hydro Training Module
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
Cv english
Cv englishCv english
Cv english
 
 

More from Hudbay Minerals Inc.

Well Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationWell Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationHudbay Minerals Inc.
 
Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Hudbay Minerals Inc.
 
Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Hudbay Minerals Inc.
 
Rosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockRosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockHudbay Minerals Inc.
 
Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Hudbay Minerals Inc.
 
Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Hudbay Minerals Inc.
 
Reclamation Examples - Before and After
Reclamation Examples - Before and AfterReclamation Examples - Before and After
Reclamation Examples - Before and AfterHudbay Minerals Inc.
 
Mine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelMine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelHudbay Minerals Inc.
 
Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Hudbay Minerals Inc.
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyHudbay Minerals Inc.
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont MineHudbay Minerals Inc.
 

More from Hudbay Minerals Inc. (20)

Well Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationWell Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling Presentation
 
Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009
 
Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872
 
Rosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockRosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine Rock
 
Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009
 
Dry Stack Tailings Overview
Dry Stack Tailings OverviewDry Stack Tailings Overview
Dry Stack Tailings Overview
 
Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007
 
Reclamation Requirements
Reclamation RequirementsReclamation Requirements
Reclamation Requirements
 
Reclamation Examples - Before and After
Reclamation Examples - Before and AfterReclamation Examples - Before and After
Reclamation Examples - Before and After
 
Partial Pit Backfill Alternative
Partial Pit Backfill AlternativePartial Pit Backfill Alternative
Partial Pit Backfill Alternative
 
Regional Groundwater Flow Models
Regional Groundwater Flow ModelsRegional Groundwater Flow Models
Regional Groundwater Flow Models
 
Baseline Traffic Study
Baseline Traffic StudyBaseline Traffic Study
Baseline Traffic Study
 
Baseline Noise Study
Baseline Noise StudyBaseline Noise Study
Baseline Noise Study
 
Heap Leach Facilities
Heap Leach FacilitiesHeap Leach Facilities
Heap Leach Facilities
 
Geotechnical Study
Geotechnical StudyGeotechnical Study
Geotechnical Study
 
Mine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelMine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake Model
 
Rosemont Project Orientation
Rosemont Project OrientationRosemont Project Orientation
Rosemont Project Orientation
 
Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water Supply
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont Mine
 

Recently uploaded

How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxnelietumpap1
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 

Recently uploaded (20)

How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 

Facilities Engineering Presentation

  • 1. Facilities Engineering Presentation M3 Engineering & Technology Corporation
  • 3. Facilities Engineering Scope of Work §  Process Facilities §  Ancillary Facilities §  Civil Infrastructure §  Power Supply §  Fresh Water Supply & Distribution
  • 5. Process Facilities §  Sulfide Processing Plant §  75,000 DSTPD of Sulfide Ore §  1,350 DSTPD of Copper Concentrate §  15 DSTPD of Molybdenite Concentrate §  Sulfide Circuit §  Primary Gyratory Crusher, Overland Conveyor, Stockpile §  SAG Mill & 2 Parallel Ball Mill Circuits §  Copper Flotation with Molybdenum Separation Circuit §  Concentrate Dewatering / Filtration §  Flotation Tailing dewatering, filtration, convey. §  Dry Stack Tailing Area §  Reagent Area
  • 6. Process Facilities §  Oxide Facility §  17,000 DSTPD of Oxide Ore by Leach §  Approx. 76,800 Pounds Per Day High Purity Cathode Copper §  Oxide Circuit §  Leach Pad for Run of Mine Ore §  Raffinate and PLS Ponds §  Storm Water Pond §  Two Extraction and One Stripper Solvent Extraction Circuit §  Electro-winning Facility §  Reagent Area
  • 7. Ancillary Facilities (Support Process & Mine) §  Warehouse Facilities §  Administration Building §  Change Room §  Analytical Laboratory §  Mine Truck Shop with Tire Shop §  Mine Truck Wash and Lubrication Facility §  Gasoline & Diesel Fuel Storage & Dispensing Facilities §  Ammonium Nitrate Silos and Explosives Magazines §  Guard Facility with Truck Scale
  • 8. Civil Infrastructure §  Modifications to State Route 83 at Intersection with Mine East Access Road §  East Access Road §  Upgrades to USFS roads and private roads §  New USFS connecting roads around Plant §  Perimeter Road around Waste Rock & Dry Stack Tailing Facility §  Overall Site Grading and Drainage §  In-plant Roads §  Initial Mine Haul Roads
  • 9. Civil Infrastructure §  North Storm Water Diversion Structure §  Storm Water Diversion to Process Water Temporary Storage (PWTS) §  Storm Water Diversions around Open Pit §  Dry Stack Tailing Facility water management §  Compliance – Point Water Management Structure
  • 10. Power Supply and Distribution §  Coordination with Tucson Electric Power (TEP) §  Substation at TEP connection to step down voltage for Fresh Water System §  Rosemont Substation (138 KV to 34.5 KV) §  Distribution to Process Motor Control Rooms and other Facilities
  • 11. Fresh Water Supply and Distribution §  Well field §  20 inch Water Delivery Line with Booster Stations §  Fresh Water and Fire Water Tank at Process Facilities §  Potable Water System with Water Treatment Package §  Fresh Water System §  Process Water System §  Fire Water System §  Pit Dewatering System
  • 12. M3 EPCM Scope of Work §  Project Management §  Basic Engineering §  Detail Engineering §  Procurement §  Construction Management §  Commissioning §  Start-Up Assistance
  • 13. EPCM Status §  Currently in Basic Engineering Phase §  Started in May 2008, finish in April 2009 §  Basic Engineering Effort §  Update Deliverables with Better Scope Delineation §  Improve Quality of Information for update of Capital Estimate and Operating Estimate §  Finalize Criteria for Detailed Design Effort §  Effort Currently Supported by Other Consultants: §  Geotechnical Services Tetra Tech §  Geotechnical Drilling Contract Tetra Tech §  Dry Stack Tailings Facility AMEC §  Heap Leach Facility Tetra Tech
  • 14. Basic Engineering Deliverables §  Project Procedures §  Drawing, Specification, and Equipment Lists §  Discipline Design Criteria §  Major Equipment and Material Specifications §  Flowsheets §  General Arrangement Drawings §  P&IDs §  Electrical One-Lines §  Civil Site Plan and Rough Grading Drawings §  Architectural Drawings §  Major Concrete Foundation Drawings (Mills) §  Updated Capital Estimate and Operating Estimate §  EPCM Schedule
  • 15. Detail Engineering Phase §  Planned start in February 2009 §  Engineering effort linked to forecasted availability of vendor information §  Substantial Complete in July 2010 §  Engineering support will continue through construction