2. Nunce
Deck operating manual
Deck operating manual
1. Principal particulars
1. Barge characteristics
2. General arrangement
2. Ballast system
1. Capacity plan
2. Ballast valve remote control system
3. Ballast level remote gauge system
4. Ballast arrangement and equipment
5. Ballast operations
3. Helicopter operations
1. Helideck
2. Helideck routine operations
3. Helicopter refueling
4. Bunkering management
1. Bunkering stations
2. Bunkering hoses and connections
3. Oil pollution prevention and SOPEP plan
4. Bunkering operations
5. Anchoring systems
1. Anchoring arrangement
2. Anchoring equipment description
3. Anchoring winches
4. Anchoring winch operating procedures
6. Lifting equipment
1. Deck cargo crane
2. Palfinger crane
3. Cargo lift
4. Medic crane
2
3. Nunce
Deck operating manual
Principal particulars
3
3
4. Nunce
Deck operating manual
Barge characteristics
PRINCIPAL PARTICULARS
Length Overall 122,00 m
Breadth 42,00 m
Depth Moulded 8.40 m
Draft 5.00 m
Built 2008
GRT/NRT 21.160 / 6349 T
Class/Notation ABS/ABS + A1 Accom. / Work Barge E, M,
AMCCU, CRC, UWILD
Flag LIBERIA
Port of registry Monrovia
CARGO CAPACITIES
Deadweight 5000 t
Deck Strength 10 t/m2
Clear Deck Area 900 m² (hard wood cladding)
Fuel Oil 2 x 1360 m3
Fresh Water 2 x 1500 m3
Ballast Water 6300 m3
Industrial Water equal to FW quantity minus 1000 m³
PROVISION STORES
Cold rooms 1 x 50 m³ + 1 x 25 m³ Each @ -20°c
Vegetable Room 1 x 50 m³ + 1 x 25 m³ Each @ + 5°c
Dry Store 60 m2
Bottle store 30 m³
Dropping zone on deck Yes 2x 20 feet container dedicated area on
deck (beside frigo rooms)
PUMPS
SURF refueling 6 m³/h
Catamaran/Seacor Cheetah 15 m³/h
Fuel Oil 2 x 50m³/hr. @ 35 m head
Fresh Water 2 x Press set 40m³/hr. @ 40m head
Ballast Water 2 x 200 m³/hr. @ 30m head
Industrial Water 50 m³/h @ 40 m head
Separators Yes (L.O & MGO)
4
5. Nunce
Deck operating manual
Barge characteristics
MACHINERY
Main Generator 3 x 1260 kw @ 450V / 3 Phase / 60 Hz
MAN 6 x 28 / 32 H
Emergency Gen Set 1 x 592 kW @ 450V / 3 Phase / 60 Hz
Air Compressors 3 x electric 10 bar
HVAC Yes in Accomodations / Engines areas /
Workshops
Water Maker 2 x 140 ton/day
Sewage Treatment 2 x 450 men minimum IMO/USCG Standard
Oil Water Separator 15 PPm Yes
PROTECTION / TREATMENT
Hull ICCP (impressed current cathodic protection)
Seawater seachests, filters & lines Anti-fouling system
WORKSHOPS (on deck)
Barge 85 m² 1 c/w lathe, pneumatic and mechanical tools,
grinding machines, 1 x radial drill, hacksaw
machine,
1 x Arc welding & 1 Portable Arc welding sets
Electric workshop 45 m² Yes equipped for control and repairs
Client workshop 80 m² 1 lathe machine (4 mt between center)
mechanical tools,
hacksaw machine, 1 x Arc welding & 1
Portable Arc welding sets
Safety workshop 45 m²
Elect & instrum 20 m² In engine room
5
6. Nunce
Deck operating manual
Barge characteristics
DECK EQUIPMENTS
8 Point Mooring 8 x single drum Electro hydraulic c/w tension
sensor & length paid out
indicators / 16 Fairleads x 360° - dubble
sheaves
Winches control Local or remote control from barge control
room with CCTV
Rated Pull 85t x 10m / min. @ 1st Layer (1st speed)
45t x 30m / min. @ 1st Layer (2nd speed)
Brake Capacity 200 ton (Static) @ 1st Layer
Anchor Wire 8 x 2000 m (L) x 76mm Diameter
Anchors 8 x 12 ton
Capstan (bridle winch) Yes
Provision crane None
Main crane Electric / Hydraulic
Main Crane Hook 25 t x 32m Radius
Whip Hoist 8 t x 32m Radius
STORES
Barge store 75 m³ & 75 m³ Forward & Aft
Spare store 25 m³ & 30 m³ Forward & Aft
Rope store 10 m³ & 10 m³ Forward & Aft
General store 50 m³ Aft
Engine spare parts lift (2 levels) Yes
HELIDECK
Suitable for S- 61
Refueling station Yes w/ 2 x 4000 lt
6
7. Nunce
Deck operating manual
Barge characteristics
ACCOMMODATION
Cabin min. 11,8 m² floor area (incl. bathroom)
Double Berth 178 x 2 berth
TOTAL 356 Berth (expandable to 450)
Facilities All rooms equipped with Radio, TV & internet
connections
Automatic telephone Every accommodation room, office, public
space, engine area
RADIO & NAVIGATION EQUIPMENT
Radio control room Yes 20 m² H24 manned x 2men
GMDSS Yes
SSB Yes
INMARSAT C + Telex / SSAS Yes
INMARSAT F Yes
Faxsimile receiver Yes
VHF/DSC Radio Tel Yes
Navtec Receiver Yes
SART Yes
EPIRB Yes
Portable VHF Marine Radio (with Yes
DSC)
VHF Air Band Receiver Yes
Beacon Yes
Radar ARPA Yes
AIS Yes
Gyro compass Yes
Echo Sounder No
Meteo display station Yes
GPS Yes
Fog horn Yes Audio beam system (2 miles)
Sound Powered Tel. Yes
PA System Yes
International call Yes 4 cabins
7
8. Nunce
Deck operating manual
Barge characteristics
FIRE FIGHTING & SURVIVAL EQUIPMENT
Fire Pump 2 x 180 m³/ 120m head
Fire Monitors 2 x Foam monitors (helideck)
2 x water monitors
Emergency Fire Pump 1 x 75 m³/hr. @ 80 m head
Life Raft 42 x 25 p
Fast Rescue Boat 1 x 35 Kts - 3 men elect / hydraulic
launching davit
Fire Detection System in all enclosed Yes
spaces.
Gas Detection System in all enclosed Yes
spaces
Hi-Fog system Machinery store Rooms, generators rooms,
utility rooms, winches room & Paint locker
Hi- Fog system Yes in whole accommodation spaces
GALLEY
GALLEY 270 m² Services 450 people over 2 hours max
Bakery 35 m² 2 x man @ 24h
Mess room 500 m² 240 Services 450 people over 2 hours max
seats
MEDICAL
MEDICAL total 108 m² Hospital 1 x 4 berth + examination room +
transit (beside Helideck)
OFFICES
OFFICES 20 m² 2 desks 26 x Client & 8 x Barge
Client Archives 40 m³ 2 Rooms
Telecom eqpt room 10 m² Yes
Conference Room 110 / 70 / 65 Client Meeting room / Barge meeting room
m² / Training room
Administration office 20 m² Yes w/ 2 desk
8
9. Nunce
Deck operating manual
Barge characteristics
ENTERTAINMENT
TV Room 180 / 95 / All equipped w/ 110 cm Plasma screen & 20
60 m³ satellite channels + inner.
Recreation Room 45 m² 1 x room
Library Yes
Internet room Yes Equipped w/ 12 PC
Fitness room 60 m² Full equipped & Air cond.
OTHER FACILITIES
2 x 140m2 Luggage Rooms + 2 x 140m2 Muster
Rooms (convertible)
1 x 70 m² deck changing / toilet room
1 x 30 m² deck transit lounge
1 x 10 m² deck dirty coffee room
9
10. Nunce
Deck operating manual
General arrangement plan
10
12. Nunce
Deck operating manual
Ballast Tanks
Inside a ballast tank (4ps)
Suction and filling
at the bottom of the
12 tank
13. Nunce
Deck operating manual
Ballast valve remote control system
13
14. Nunce
Deck operating manual
Ballast level remote gauge system
Confer to “associated plans and drawings to Nunce deck
operating manual folio”
Ballast level remote gauge system
Air pipe for remote gauging system
inside ballast tanks
14
15. Nunce
Deck operating manual
Ballast arrangement and equipment
• Two main longitudinal symmetrical ballast lines of 7 side
ballasts
• There is no double bottom tank
• Two ballast centrifugal pumps (300m3/h) taken suction from
main sea water chest
• Crossover line allows cross feeding from suctions valves
• Crossover line allows cross feeding from a ballast line to the
other
• Pumps are used either for ballasting and deballasting
• Emergency suctions from bilge system and flooding
15
16. Nunce
Deck operating manual
Ballast system plan
16
17. Nunce
Deck operating manual
Ballast operations
General guidance
A responsible officer must be always on duty and in charge of the
follow up of the ballast condition at all time and report to the
barge master when ballast operations are completed.
For accurate measure of quantity of water in ballast, refer to the
sounding table.
Precautions to take prior filling or emptying of a ballast
tank
Ballast operations will not jeopardize the stability and sea
behavior of the barge.
There is no works in progress in relation with ballast
system (inspection, maintenance…).
HPU for remote control valve is available and ready
(working pressure at 150bar).
Ballast pumps (1 and/or 2) are available and ready and
that starting will not overload the busbar.
Level gauges are readable (not inhibited or shut off).
17
18. Nunce
Deck operating manual
Ballast filling procedure
1. Select the ballast to fill by operating the corresponding
remote valves on the ballast synoptic.
2. Set the ballast pump remote control valves for ballasting.
3. Open manual suction valve corresponding to the ballast
pump.
4. Close the manual overboard valve.
5. Start the ballast pump
6. Check for pressure gauge
7. Check for level gauge
General guidance
a. Operate the valves one by one on the synoptic to avoid big
drop of pressure of the HPU
b. Operate only the necessary hydraulic valves to reach the
ballast tank
c. Do not fill two or more tank at the same time on the same line
d. When ballasting, make sure to avoid to overflow the tank,
high level alarm are set to 90% of full capacity.
18
19. Nunce
Deck operating manual
Ballast emptying procedure
1. Select the ballast to empty by operating the corresponding
remote valves on the ballast synoptic.
2. Set the ballast pump remote control valves for emptying.
3. Open manual suction valve corresponding to the ballast
pump.
4. Close the manual overboard valve.
5. Start the ballast pump
6. Check for pressure gauge
7. Check for level gauge
General guidance
a. Operate the valves one by one on the synoptic to avoid big
drop of pressure of the HPU
b. Operate only the necessary hydraulic valves to reach the
ballast tank
c. Do not empty two or more tank at the same time on the same
line
d. During ballast emptying, be careful to not loose suction from
the pump while capacity get at very low level: check pressure
gauge on pump.
19
20. Nunce
Deck operating manual
Helicopter operations
Aerospatiale Dolphin approaching NUNCE
20 NUNCE Helideck at night
21. Nunce
Deck operating manual
Helideck
The accommodation barge Nunce is fitted with an helideck on the
upper end of D deck at the aft of the barge:
The helideck structures were designed according to landing areas
– Guidance on standards, CAP 437, Rev 5 Offshore Helicopter and
reviewed for helicopter type Sikorsky S61N (MTOW of 9300 Kg)
NUNCE Helideck
21
23. Nunce
Deck operating manual
Helicopter routine operations
SCOPE:
This procedure applies to all employees engaged in helideck
operations on board Accommodation Barge NUNCE.
PURPOSE:
This procedure describes the roles and responsibilities of
personnel involved, to ensure the safety and security of persons
transferred by helicopter and the efficiency of the operations.
FORMS:
HLO helideck daily inspection
REFERENCE:
CAP 437 – Offshore Helicopter Landing Areas – Guidance on
Standards
23 Dolphin landing on NUNCE
24. Nunce
Deck operating manual
Responsibilities
Barge Master:
Check that HLO team carry out their job according to prevailing
standards and site procedures.
Have authority over the HLO team.
Ensure that the validity of the certificates of the helideck personnel
concerned.
Ensure that the standards of certification, inspection, equipment,
maintenance and any corrective action on the helideck and the
refueling station.
Ensure of the presence and correct operation of the means of
telecommunication, weather stations and the movement
measuring instruments of the floating support.
Hold the site’s “helicopter” emergency procedures and coordinates
any implementation.
Safety officer:
Ensure that all safety equipment related to the helideck are fully
operational and correctly maintained.
Ensure that HLO teams are fully aware and informed about their
duties in an emergency situations such as crash on deck, ditching
or medical evacuation.
Is the intervention leader concerning all emergency situations may
arise on board
HLO:
Ensure at all times the safe sequence of helicopter operations,
while landing, taking off nor refueling.
To ensure the safe embarkation and disembarkation of passengers
The HLO has perfect knowledge of the standard CAP 437 ("Offshore
Helicopter Landing Areas – Guidance on Standards") and shall have
a current copy on site.
Responsible for the safety aspect of the refueling operations
HDA:
Assisting HLO during helicopter operations
One HAD must always act as fireman, fireman outfit worn, and be
24 at the foam monitor during all movement of helicopters.
25. Nunce
Deck operating manual
Responsibilities
Radio Operator:
They monitor flight safety between the various land and offshore
sites, in coordination with the operators of Echo Charlie and the
Head of Helicopter Operations in Luanda and on the sites.
They record the radio messages transmitted by the pilot on the
helicopter operations log.
They give the pilot any useful information concerning flight safety.
Administrator:
Summoning the passengers to the departure lounge, weighs them
and records the weights on the manifest.
searching baggage in the presence of the passengers to make sure
that they do not transport any prohibited or dangerous objects.
He weighs baggage and records on the passenger manifest.
He shows the passengers the video of the safety instructions
Site Coordinating Logistic Officer:
He works in permanent liaison with the radio operator and the
HLO teams of the installation and, as required, the radio operators
of the other offshore sites at which the helicopter needs to reach.
He prints the final manifest and gives it with 3 copies to the
landing officer (HLO)
He makes sure that the total weight of baggage and freight in the
compartment remains within the limit allowed by the air operator
and pilot.
25
26. Nunce
Deck operating manual
Safety highlights
The Client Logistic coordinator, via the helicopter Company will
inform Nunce personnel of the helicopter arrival with sufficient
notice to allow mobilization of the stand-by/work boat and
helideck crew.
During helicopter operations crane boom will be positioned so
that there is no possibility of interference with the helicopter and
the crane operator will not be in the crane cab.
During landing or takeoff, the HLO remains visible at all times to
the pilot by being necessary at the top of the access stairs. His
presence shall only be allowed outside the helideck during
landing & take-off, maintaining the greatest possible distance
from the limits of the helicopter's landing gear contact surface.
The HLO and the HDA must be equipped with lightweight fire-
resistant suits and safety goggles.
The HLO will also be equipped with hands-free VHF earphones
enabling him to communicate with the pilot.
NOTA 1 : the international (in English language) radio phraseology
must be followed at all times to avoid any confusion or
misunderstanding
NOTA 2: the words “clear” or “clearance” must be avoided as only
air traffic controllers (ATC licensee) are allowed to use these
words.
26
27. Nunce
Deck operating manual
Helicopter routine works sequence
30 min before landing
Radio Operator
Informs the landing officer (HLO) so that he may ensure safety on
the helideck, and awaits confirmation.
Telling HLO the ETA and the number of passengers and parcels to
unload/load, and notifies any fuel requirements.
Inform the ships operating in the transfer zone alongside barge.
Administrator:
He summons the passengers to the departure lounge by PA for a
reminder of the safety instructions, weighs them and their
baggage and records the weights on the passenger manifest
He prints the final manifest and gives it with 3 copies to the
landing officer (HLO)
HLO
Verify the Helideck is available and ready:
• No obstruction, in 210 Obstacle Free Sector (OFS) up to a
distance of 1000metres from the helideck.
• Helideck area clear of any loose material.
• Safety net tightness , hammock effect.
• The net is stretched and the hooking points in place..
• No explosive atmosphere, no flammable liquids or gas
• No hot air or hot gas above the helideck
• No strong wind (> 45 knots) and no gust or eddy, such to
enable free movements of crew, in safe conditions.
• Availability of the safety equipments for firefighting and crash
• The foam monitors are directed laterally and not facing the
helicopter (in the event of unexpected release) and a portable
CO2 extinguisher is available if a fire starts in the engine
casing.
• Good overall condition of the wind sock
• Good lighting within the helideck zone, good lighting of masts,
obstruction, and wind sock
• Inform the radio operator of the helideck readiness
27
28. Nunce
Deck operating manual
Helicopter routine works sequence
15 minutes before Landing
Radio Operator
Summons the technical team (HLO, HDA, firemen) onto the
helideck.
Summons the passengers onto the helideck or in front of the
departure lounge depending on the site, and makes a roll call
according to the manifest.
Passengers visiting for the day, are generally exempted from the
safety briefing, must join the group at this moment after returning
their t-card. Any passenger not answering the call will be refused
embarkation.
HLO
Inform to stop all cranes operations and set the jibs of cranes at
the normal not working positions
Verify firefighting equipment and the PPE worn by the helideck
crew.
Places HDA in position: one HDA at the foam monitor upwind. The
second one will act as the first attack firefighter.
Cancel the access to the helideck to people not being member of
the HLO team.
In case of refueling, verify the equipment are in good operational
conditions and that documents are available.
Confirm the stop of cranes operations and that the jibs of cranes
are down.
Verify the good working and functioning of the portable vhf by
testing the transmission.
Collect manifest from radio room.
28
29. Nunce
Deck operating manual
Helicopter routine works sequence
5 minutes before Landing
HLO
Ensure that all passengers, baggage and freight is ready for
departure and awaiting on the special dedicated area.
Check that luggage and freight comply with the manifest.
All luggage not declared or considered not complying with the
manifest or for safety nor security reason will be refused.
Just before Landing
HLO
Inform the helicopter that the helideck is available for landing and
that fire fighting equipment is ready.
Message is “NUNCE helideck available for landing”. Or “NUNCE
green deck”.
29
30. Nunce
Deck operating manual
Helicopter routine works sequence
Disembarking and embarking passengers
• Disembarking and embarking passengers may be carried out
with the rotor turning or motor and blades stopped
• In the case of a complete stop, it is important not to approach
the helicopter before the rotor completely stops because the
blades of some helicopters (especially with the S76), at low
speed, may "drop" and pass at a height lower than the head of
a man.
• Under no circumstances may passengers go round the
helicopter, whether by the front or the back. Only the HLO and
the HDA are allowed to do it, by the front only, to collect or
bring back baggage, and only when access to the
compartment, stairs side, is impossible (see Annex 2:
Circulation around Helicopter).
• After landing, the pilot gives the HLO permission to approach
with a thumb-up and by switching off his rotating navigation
lights.
30
31. Nunce
Deck operating manual
Helicopter routine works sequence
The HLO then has to carry out the following actions
• Advance to the helicopter by its side safety area according
type of helicopter, see drawing in Annex 1
• Take receipt of the manifest of disembarking passengers from
the pilot.
• Check on the action of the HDA, who collects the baggage of
the disembarking passengers and brings it close to the stairs.
• During this time, the passengers wait in the helicopter.
• Long items will be carried horizontally to prevent
contact with rotor blades.
• Open the doors descent stairs side, and this side only, for
disembarking passengers, and leads them out of the helideck
by the side of the helicopter facing these stairs.
• Passengers descend with their life jackets on.
• Check on the collecting of life jackets from disembarking
passengers by the HDA outside the helideck and distribution
of them to embarking passengers
• If embarkation is done with the rotor turning, all
passengers must put on their life jackets before going
up on the helideck.
• Check on loading of embarking passengers' baggage in the
helicopter's baggage compartment by the HDA.
• Guide embarking passengers to the doors of the helicopter,
stairs side, (and this side only), and checks on the correct
buckling of safety belts.
• Close all helicopter doors.
• Deliver to the pilot, four copies of the manifest of embarking
passengers, freight and retains receipt of a signed
• Ask the pilot for confirmation of the door closing lights, and
returns to the station at the access to the helideck.
• If the helicopter motor and blades are stopped, the HLO and
HDAs have to lash the helicopter to the pilot’s
recommendations
31
32. Nunce
Deck operating manual
Helicopter routine works sequence
Before helicopter take off
HLO
Verify with the pilot the locking of doors
Push aside in safe area all people remaining on the helideck zone
Verify no leak of jet fuel or oil, no obstruction in the take-off area
Verify helideck is ready, and the wheels or skid is clear from the
safety net
Give to the helicopter pilot the manual signal “All is clear””, with
pus turned up, and confirm by radio he may take-off.
Once helicopter has departed
HLO
Inform the crane operator and the supply boat the end of
helicopter operations
The HLO team remains in place for 5 minutes after takeoff.
Radio Operator
Record all times
Perform the radio watch
32
33. Nunce
Deck operating manual
Helicopter routine works sequence
Periodical Checks and Tests
Each day and before any landing or take-off, the HLO shall perform
a thorough examination of the helideck area and the safety
equipment.
He has to follow a check list to do this and will recordt any
observations or remarks in the HLO workbook.
Findings, if any, will have to be dealt with immediately.
Filled checklist will be kept in dedicated file.
33
34. Nunce
Deck operating manual
HLO daily checklist of helideck
Items M Tu W Th F Sa Su
Helideck Surface
Colour condition - NonSlip characteristic – Drainage
Helideck Marking
Perimeter line – Aiming circle – Chevron
Surface Net
Condition – Tension – Tie down points
Perimeter Safety Net
Condition…
Perimeter Lighting
All working – Brightness – Condition of lens
Flood Lighting
All working – Effective Dazzle protection
Fire Protection
Foam Monitors: condition - Foam tank Full
Dry Powder extinguishers: Condition – (2*50kg)
CO2 extinguishers: Condition – (2*5kg)
CO2 extinguihsers: Condition- (2*9kg)
Hose reels
Water Hydrants – Hoses - Nozzles
Rescue Equipment
Crash rescue box – Inventory (as per box checklist)
SCABA: Condition – Nominal Pressure
Protective Clothing
Quantity - General Condition
Additional Equipment
Helicopter “do not land” flag available
Alarm push buttons
Sandbags – Tiedown ropes
Radio Equipment
Portable VHF w/Headset
Weather Equipment
Anemometer – AirTemp – Barometer – Windsock…
Access Points
34 Hand rails – Safety Notices
35. Nunce
Deck operating manual
Safe areas around helicopters
Annex 1
35
36. Nunce
Deck operating manual
Safe areas around helicopters
Annex 1
36
37. Nunce
Deck operating manual
Safe areas around helicopters
Annex 1
37
38. Nunce
Deck operating manual
Safe areas around helicopters
Annex 1
38
39. Nunce
Deck operating manual
Helicopter refueling
Refueling station
SCOPE:
This procedure applies to Helideck affected on board the
Accommodation Barge NUNCE.
PURPOSE:
This procedure provides guidelines to refuel the helicopters,
describing checks and duties of the personnel involved for a safe
operation.
REFERENCES:
CAP437
Manufacturer’s manual “WILMAX engineering
39
40. Nunce
Deck operating manual
Responsibilities
RESPONSIBILITY
The HLO is in overall charge of all helideck refueling operations.
PROCEDURE
General
Jet A1 is classified as IMDG class 3 (flammable liquids).
Before arrival, the Pilot must inform the Radio of any need in
refueling, stating the requested volume.
The HLO positions himself so that he can see and be seen by the
Pilot and the HDAs involved in this operation.
Helicopter must shutdown for refueling and have passengers
disembarked.
Should occur any strong rain, thunderstorm in the vicinity, turning
machine or source of sparks, refueling can’t be continued.
Equipment and specific items
Helicopter refueling station is on the D-deck Portside Aft
Jet A1 fuel tanks and pumps are on Main deck Starboard side
Forward.
40
41. Nunce
Deck operating manual
Refueling operation sequence
Initial State
The initial state considered in this procedure start when helicopter
is landed, rotor stopped.
INITIAL STATE
HELICOPTER LANDED – ROTOR STOPPED
PASSENGERS DISEMBARKED – HELICOPTER CREW ON STATION
Before refueling
Connect the line between tank and pump HDA
Check that there is no leak HDA
Check the filter (air jet fuel) HLO
Check the counter HLO
Check the grounding cable HLO
Check the Emergency stop HLO
Perform a general check of the system by flushing HLO
Check that the inlet of the pump corresponds to the selected HLO
tank
Drain tank, the filter of the pump and take a sample in a sampling HDA
bottle
Perform the water detection test HLO
Drain the tank and the filter of the pump until there is no more HDA
water
Make labelling of sample with sampling date HDA
41
42. Nunce
Deck operating manual
Refueling operation sequence
Refueling
Inform the Radio Room for hot works suspension HLO
Check that all passengers have left the helicopter and stand in HLO
safe area
Reset the counter HLO
Exhibit the fuel quantity control records to the Pilot HLO
Take a sample from the refuelling nozzle. HLO
Show the sample to the Pilot and perform the water detection HLO
test in front of him.
Make labelling of sample with sampling date and keep it until the HLO
next day
Ground the helicopter HLO
Unwind the refuelling hose HLO
Open the plug of the helicopter tank and insert the nozzle HDA
Check that the firemen and HDA are ready to their station HLO
Check the counter figure HLO
Start the pump on Pilot request only and after both Pilot and HDA
HLO
agreed on the volume to be delivered
Check the working order of the flicker light HDA
Record the differential pressure during the transfer HDA
Stop transferring on Pilot request, or when reaching the HDA
agreed volume to deliver, or in case of nay trouble
42
43. Nunce
Deck operating manual
Refueling operation sequence
After refueling
Remove the nozzle and its grounding cable. HDA
Check that the plug of the tank is locked HLO
Disconnect the grounding cable and show the free end to the HDA
Pilot
Carefully stow the equipment. HDA
Record the delivered quantity as stated by the counter. HLO
Take a sample from the refuelling nozzle and show it to the HLO
Pilot.
Make labelling of sample with sampling date and keep it. HLO
Fill the Jet A1 Delivery Coupon and makes it signed by the Pilot. HLO
Check that the helideck is free, stuff stowed and helideck team HLO
away
Inform the Pilot, inform the CCR for resuming hot works HLO
43
44. Nunce
Deck operating manual
Refueling operation sequence
Final Status
•Helicopter on helideck, rotor stopped
•Passenger disembarked, crew on board
•Helicopter tanks refueled
•Helideck available
FINAL STATE
HELICOPTER REFUELED
44
45. Nunce
Deck operating manual
Bunkering management
SCOPE:
This procedure applies to Accommodation Barge NUNCE.
PURPOSE:
To ensure a safe and very low environmental impact transfer of
hydrocarbons (mainly constituted by light MDO) between the
barge and other vessels either receiving nor supplying.
RESPONSIBILITIES:
The chief engineer is responsible for all transfer of hydrocarbons
on board the barge.
The safety officer is in charge of the deck operations and the
implementation of the safety measures during bunkering
operations.
The 2nd engineer is in charge of the availability and the
preparation of the engine room for bunkering operations. He is in
charge of the follow up of bunkering operations
REFERENCES
MARPOL 73/78 convention
ISGOTT manual
Environmental company policy
45
47. Nunce
Deck operating manual
Bunkering hoses and connections
Starboardside bunkering station
Hose Type Coupling Number Max rate Use for
Black/ brown 15m/3” TODO 2 50m3/h Supply’s DO
marked type bunkering
Black/brown 25m/2” Manual 1 6m3/h Surfers DO
marked handle bunkering
ZVA 25
Portside bunkering stations (mid and fwd)
Hose Type Coupling Quantity Max rate Use for
HD 25m/2” cam lock 1 15m3/h Cheetah DO
50L/brown bunkering
marked
Black/brown 25m/2” Manual 1 6m3/h Surfers DO
marked handle bunkering
ZVA 25
ToDo connection ToDo principle
47
48. Nunce
Deck operating manual
Oil pollution prevention and
SOPEP plan
SCOPE:
This procedure applies to all personnel on board the
Accommodation Barge NUNCE and covers oil pollution prevention
on board the Accommodation Barge.
AIM:
To give guidance in implementing Company guidelines on the
subject of preventing contamination of the environment.
Emergency Plan:
Accommodation Barge NUNCE is in possession of a SOPEP (Ship Oil
Pollution Emergency Plan) (MARPOL 73/78).
This plan defines and describes actions required to address spills
due to breach or loss of containment.
This plan provides the following but non limitative actions:
1. Response designed to ensure that any on board spill is
contained onboard and not discharged into the sea.
2. Control the spill and minimize hazard to human life
and the environment by means of cleaning up,
temporary containment and/or isolation.
3. Reporting procedures.
48
49. Nunce
Deck operating manual
Bunkering operations
Surfers (fast crew boats transferring personnel between the barge
and the platforms within the field) are regularly refueling by the
barge crew.
Refueling surfer general and safety guidance
1. No smoking/no naked flames policy in force
2. Refueling is performed one vessel at a time
3. Check of equipment condition (fuel hose, pistol, coupling)
have to be done each time before refueling.
4. Surfer pilot is in charge of follow up quantity delivered and
must inform on time the pumpman for stopping the pump.
Refueling sequence
1. Surfer pilot request for refueling
2. Surfer proceed to the boat landing
3. The deck hand in charge (pumpman) bring the fuel hose fitted
with a gasoil pistol to the surfer crew
4. When the surfer is ready to receive fuel, the pumpman will
start the pump and be on stand by until the completion of the
refueling
5. When the surfer received the requested quantity, surfer pilot
inform the pumpman to stop the pump
6. The pumpman pick up back the hose and confirm by reading
the counter the quantity given to the surfer.
GO pistol ZVA25
49
50. Nunce
Deck operating manual
Bunkering operations
Supply vessels bunkering general and safety guidance
• Bunker management application plan in force including
safety measures prior bunkering (see following check-list)
• No smoking/no naked flames policy in force
• Bunkering is performed one vessel at a time
• Check of equipment condition (fuel hose, couplings, piping)
and correct settings of valves have to be done each time
before refueling.
50
51. Nunce
Deck operating manual
Supply vessels bunkering
Bunker requisition must be done at least 8h before
.
1. Supply vessel request for approaching bunkering station.
2. Bunkering safety measures have to be implemented before
the connection.
3. When connection is completed, exchange of safety check-lists
is done to ensure each other is ready for the bunkering
operation: barge safety officer and supply vessel captain have
to fill and sign.
4. Bunker ticket has to be checked and signed by both chief
engineers.
5. When confirmation is done on each side, pump is started at a
slow rate to check tightness of connections and leaking if any:
this is the integrity check.
6. Then a pump emergency stop is performed to ensure that it is
working normally.
7. If all safety checks are performed without any fault, pump rate
is increased until the maximum admissible rate by the
installation.
8. One engineer is on stand-by at the manifold during the whole
bunkering operation.
9. Soundings have to be regularly checked to avoid any overflow.
10. Safety officer will remain fully available and maintain radio
watch.
11. If topping of tanks is necessary, pump rate will be decreased
accordingly until the completion of tanks.
12. When transfer is completed, pump is stopped and bunker
confirm receipt will send to the receiving installation.
13. In normal conditions there is no need to flush the line as the
connection are ToDo type coupling and will remain fully tight
when they are disconnected.
14. The hose is picked up back and secured to the barge.
51
57. Nunce
Deck operating manual
Anchor winches
REFERENCE:
•Manufacturer’s manual NORCRANE
Description
The Nor Crane & Winch‘s Hydraulic Mooring Winch model type
NCW MW-85-200-H is designed for safe and reliable personnel
handling operation.
This hydraulic mooring winch consists of a single hauling drum
mounted on a high tensile steel main shaft, supported on the
fabricated winch base-plate by heavy duty roller type bearings.
The bearings are mounted in steel housings, fitted with external
grease lubrication points, bolted to the winch base-plate.
The drum is fitted with a spring loaded, hydraulic released band
brake, giving a fail-safe to “ON” mode during operation. This brake
is a wrap-up design consisting of two halves warp around the race
of the drum flange. The brake would operate through a hydraulic
cylinder and spring loaded system, through mechanical linkages
to provide the required holding load. All brake straps are lined
with a high grade non-asbestos marine lining that is bolted to
position. A spanner is provided to manually override onto the
cylinder in a case of emergency. Also a hydraulically operated
ratchet assembly is provided for stopping the
drum at full braking load in as standby of drum brake.
The drum can engaged or disengaged by means of a hydraulically
57 operated dog clutch, which is installed at the intermediate shaft
to allow the engagement of drum to drive unit.
58. Nunce
Deck operating manual
Anchor winches
A mechanical fresh water cooled disc tension drag brake is installed
on another pinion shaft to ensure the drum is under controlled
payout dynamically for operation of anchor deployment.
Transmission would be from two low speed high torque medium
pressure hydraulic motors.
The motors would be positioned at one side of the winch, driving
through a guarded doubled stage spur reduction gearing.
An automatic spooling device is provided for the wire spool
smoothly on drum. This device comprises a lead-screw and drive
tongue, guide bar, side support frames, fabricated bushed carriage
completed with vertical rollers, manually operated clutch and
chain drive mechanism driver and driven sprockets, chain and
fabricated steel guard.
58
59. Nunce
Deck operating manual
Machinery data
Subject Specifications
Working Drum:
Drum Capacity 2000m x Ø76mm S.W.R (11 Layers)
85Tonne x 0~10m/min (1st Speed)
Duty Pull (1st layer) 42.5Tonne x 0~20m/min (2nd Speed)
56Tonne x 0~15m/min (1st Speed)
Duty Pull (5th Layer) 28Tonne x 0~30m/min (2nd Speed)
38Tonne x 0~22.5m/min (1st Speed)
Duty Pull (Top Layer) 19Tonne x 0~45m/min (2nd Speed)
Brake Holding 200Tonne (Static @ 1st layer)
Spring Loaded, Hydraulic Released
Brake Assembly Fail-Safe Band Break
Ratchet Holding 200Tonne (Static @ 1st layer)
Ratchet Assembly Hydraulic Operated
0~16Tonne x 100m/min (1st Layer)
Drag Brake Tension 0~10.5Tonne x 150m/min (5th Layer)
Air Loaded, Spring Released, Fresh-
Water Cooled Disc Tension Brake for
Drag Brake Assembly Anchor Deployment
Hydraulic Motor #1:
Brand / Model SAI S7-4300-9-H-D250
Component bulletin, Chapter 3, Section
3,6,1 see manufacturer’s manual
Hydraulic Motor #2:
Brand / Model SAI S7-4300-9-H-D250-L
Component bulletin, Chapter 3, Section
3,6,1 see manufacturer’s manual
Control:
• Local control box near the winch.
• Remote control panel at barge control room.
59
60. Nunce
Deck operating manual
Winch general overview
Drum Capacity 2000m x Ø76mm S.W.R (11 Layers)
85Tonne x 0~10m/min (1st Speed)
Duty Pull (1st layer) 42.5Tonne x 0~20m/min (2nd Speed)
56Tonne x 0~15m/min (1st Speed)
Duty Pull (5th Layer) 28Tonne x 0~30m/min (2nd Speed)
38Tonne x 0~22.5m/min (1st Speed)
Duty Pull (Top Layer) 19Tonne x 0~45m/min (2nd Speed)
60
61. Nunce
Deck operating manual
Band brake
Brake holding
•200t (Static on 1st layer)
Brake Assembly
•Spring loaded, hydraulic
released
•Fail-Safe band break
Band brake
Fail-safe system
61
65. Nunce
Deck operating manual
Drag brake
A mechanical fresh water cooled disc tension drag brake is
installed on another pinion shaft to ensure the drum is
under controlled payout dynamically for operation of
anchor deployment.
Drag Brake Tension
0~16Tonne x 100m/min (1st Layer)
0~10.5Tonne x 150m/min (5th Layer)
Drag Brake Assembly
Air Loaded, Spring Released, Fresh-
Water Cooled Disc Tension Brake for
Anchor Deployment
65
66. Nunce
Deck operating manual
Spooling device
An automatic spooling device is provided for the wire
spool smoothly on drum. This device
comprises a lead-screw and drive tongue, guide bar, side
support frames, fabricated
bushed carriage completed with vertical rollers, manually
operated clutch and chain drive
mechanism driver and driven sprockets, chain and
fabricated steel guard.
66
67. Nunce
Deck operating manual
Hydraulic power pack
Description
The Electro-Hydraulic Power Pack would comprise of 2 x 110kW + 1
x 7.5kW electric motor, 440V / 3pH / 60Hz supply, Class ‘F’
insulation, IP55, TEFC.
The motor are flexibly coupled to the hydraulic pressure
compensated pump and are mounted on a fabricated skid base
plate all suitable for below deck mounting.
All components are mounted on the power pack and internally
piped to a bulkhead tray.
3 x 110kW softstarter & 1 x 7.5kW Direct-On-Line are supplied
along with the power pack.
67
74. Nunce
Deck operating manual
Remote control panel features description
Item Features Functions
In the “PAY OUT” mode it controls the drum and allows the rope to
Directional Control Winch
01. release, while in the “HEAVE” mode it controls the drum to coil the
“PAY OUT” / “HEAVE”
rope.
It opens the drum brake and disengages the clutch from the drum so
“EMERGENCY RELEASE”
04. that the drum is free to rotate. After the emergency release button is
push button
re-set, the brake remains closed.
To engage the clutch to the drum, turn the selector to “IN” position.
Clutch selector “IN” /
09. To disengage the clutch from the drum, turn the selector to “OUT”
“OUT”
position.
“CLUTCH IN” indicating
10. It indicates the clutch is engaged to the upper or lower drum.
light.
“CLUTCH OUT” indicating
11. It indicates the clutch is disengaged to the drum.
light
Station selector “LC” / To allow control from either the remote control in the wheel house
12.
“WH” or local control near the
To set the drum to High speed, turn the selector to “HI”. To set the
14. Speed selector “HI / LO” drum to low speed, turn the selector to “LO”. Turning of the selector
must be done only when the winch is not rotating /moving.
A three positions brake control. When turn to “ON” mode, the brake
is always closed. Turn to “AUTO” mode, and the brake band shall
Brake selector “ON” /
15. open once the winch rotates, and it automatically closes when the
“AUTO” / “OFF”
winch stops. It works together with the main valve. When turn to
“OFF” the brake band is open.
This indicates the brake band is closed. The brake is holding the
16. Brake “ON” indicating light
drum.
Brake “OFF” indicating This indicates the brake band is open. The brake is not holding the
17.
Light drum
To engage the ratchet to hold the drum, turn the selector to “IN”
position. The ratchet will hold the drum in conjunction with the
Ratchet selector “IN / brake or when the brake slip. To disengage the ratchet from the
OUT” drum, turn the selector to “OUT” position. < Warning: The ratchet to
be used only when the brake slips. It must not be used
20.
independently.
Ratchet “OUT” indicating
It indicates the ratchet is not fully engaged to the drum.
light
Ratchet “IN” indicating
It indicates the ratchet is fully engaged to the drum.
light
An audio alarm that activates once the system has a fault. Check the
21. “BUZZER”
actual fault with the indicating light.
To check the bulb is working. Push the button and all the bulbs shall
22. “LAMP TEST” push button.
be lighted, otherwise, bulb is faulty.
“POWER FAILURE”
23. It indicates that the AC system power is not available.
indication light
“POWER ON” indication It indicates the system power is switched on, and ready for
24.
light operation.
74
75. Nunce
Deck operating manual
Winch local control console
75
76. Nunce
Deck operating manual
Winch local control features
Item Features Functions
In the “PAY OUT” mode it controls the drum and allows the rope to
Directional Control Winch
01. release, while in the “HEAVE” mode it controls the drum to coil the
“PAY OUT” / “HEAVE”
rope.
02. “MAIN PRESSURE” Display It indicates the main hydraulic system pressure in bar.
03. “PILOT PRESSURE” display It indicates the control hydraulic system pressure in bar.
It opens the drum brake and disengages the clutch from the drum so
“EMERGENCY RELEASE”
04. that the drum is free to rotate. After the emergency release button is
push button
re-set, the brake remains closed.
“EMERGENCY STOP” push Push the button to stop the hydraulic pump station in the HPU. The
05. button for Hydraulic Power button must be reset once it is activated, otherwise, the pump
Unit (HPU) station would not start.
To set the drum to High speed, turn the selector to “HI”. To set the
06. Speed selector “HI / LO” drum to low speed, turn the selector to “LO”. Turning of the selector
must be done only when the winch is not rotating /moving.
To engage the clutch to the drum, turn the selector to “IN” position.
Clutch selector “IN” /
07. To disengage the clutch from the drum, turn the selector to “OUT”
“OUT”
position.
A three positions brake control. When turn to “ON” mode, the brake
is always closed. Turn to “AUTO” mode, and the brake band shall
Brake selector “ON” /
08. open once the winch rotates, and it automatically closes when the
“AUTO” / “OFF”
winch stops. It works together with the main valve. When turn to
“OFF” the brake band is open.
“STATION ON” Indicator It indicates the system power is switched on and ready for
09.
Light operation.
To engage the ratchet to hold the drum, turn the selector to “IN”
position. The ratchet will hold the drum in conjunction with the
Ratchet selector “IN / brake or when the brake slip. To disengage the ratchet from the
10.
OUT” drum, turn the selector to “OUT” position. < Warning: The ratchet to
be used only when the brake slips. It must not be used
independently.
Lock selector “WO” / For maintenance purpose. Switch to “MA” when doing maintenance
11.
“MA” on the equipment & select to “WO” for normal operation.
76
77. Nunce
Deck operating manual
Local control for main and pilot pumps
See Procedure 04.19
77
78. Nunce
Deck operating manual
Winches operating instructions
Operation instructions
1. Start-up of power pack
Prior to every start up of power pack, ensure the following checks:
• Suction valves to the hydraulic pump are opened.
• Check oil level in reservoir to be at least 3/4 full at level gauge.
• There is incoming electrical supply to starter.
• Cooling circuit is lined up and valves are open.
• Press motor “START” button on the control to start the pump
station
2. Heave / Payout of Wire Rope
i) Clutch Engagement
• Switch brake control to “ON”
• Switch speed control to “ LOW”
• Turn clutch control to “IN” and check whether the clutch “IN”
indicating light is on.
• When the clutch control light indicates out, then slowly turn the
directional control in
the “PAYOUT” position until the clutch control “IN” indicating light
is on. Stop the
control once the clutch is engaged.
ii) Heave / Payout
• Ensure brake selector is switched to “ AUTO”.
• Turn to the required speed mode.
• Turn the directional control to “HEAVE” or “PAYOUT” position.
• Varies the speed by turning the direction control to the required
direction.
• Apply the band brake and disengage the clutch after every
operation.
78
79. Nunce
Deck operating manual
Dragging system for wire release
Note concerning the dragging system for release wire for
deployment of anchors
3 Drag Brake Application
• This brake is used in the wire pull out during deployment of
anchors.
• Switch brake control to “ON”.
• Switch speed control to “LOW”.
• Turn clutch control to “OUT” and check whether the clutch
“OUT” indicating light is lightened.
• Whenever the clutch is lightened at “IN”, turn the control lever
slightly in both directions to loosen the clutch.
• Turn the drag brake to “ON” position for a constant brake
application.
4. Shut-Down Operation
• Band brake is applied.
• Jaw clutch is disengaged from the drive mechanism.
• Switch-off electrical starter at the power pack.
• Do a visual inspection of the components associated with the
equipment and check for any components that may be loose.
Ensure cable/rope is properly secured. Any leaks within the
hydraulic system must be rectified.
• Complete the shut down operation then lubricate the exposed
areas and greasing points where necessary.
79
81. Nunce
Deck operating manual
Deck cargo crane
REFERENCE:
Manufacturer’s manual (PELLEGRINI)
GENERAL INFORMATION
SCOPE OF WORK
This Specification covers the minimum technical requirements for
the design,
materials, manufacture, inspection, testing and assembly of ONE
pedestal crane Type A suitable to be installed the accommodation
barge Nunce.
81
82. Nunce
Deck operating manual
Deck cargo crane
Third Party and Certifying Authority is ABS.
In the event of conflict between the above standards and the
regulations of the Certifying Authority, the latter shall prevail.
Marine Equipment Pellegrini certifies that the design and
construction of the furnished crane are authenticated in
accordance with API 2C Spec (without monogram).
82
83. Nunce
Deck operating manual
Deck cargo crane
CODES AND STANDARDS
REFERENCES CODES
The crane is designed and constructed tested and certified
according to the latest edition of following:
ORDER OF PREFERENCE
Any Government Regulations or Construction Code, listed in the
Project
Specifications, in the Requisition or in the Purchase Order, have
precedence except where this Specification is more stringent.
specification for offshore cranes 6th edition,
API Spec. 2C September 2004
API Spec. 9A specification for wire ropes
recommended practice for planning, designing,
fabrication and erection of structural steel for
API RP 2A building
lifting gear - instruction for calculation,
CRN UNI 7670 manufacture and maintenance
steel structure for calculation, manufacture and
CRN B.U. N. 73 maintenance
AWS D 1.1 structural welding code
specification for welding earthmoving and
AWS D 14.3 construction equipment
ASTM or
Equivalent materials
IEC STANDARD
ISO mechanical equipment standards
83
84. Nunce
Deck operating manual
Deck cargo crane
REQUIREMENTS
GENERAL
The design philosophy for the offshore pedestal crane is of stand-
alone/independent operation.
The crane is designed for the life, duty and service conditions as stated in the
technical data and in the Shipyard’s Technical Specification.
The electro-hydraulic pedestal crane is Type A as shown in figure 1 crane
assembly of API Spec. 2C 6th Edition, September 2004.
The crane is capable of lifting, swinging, luffing and lowering loads at
capacities, radii and speeds in conditions as specified in the technical data,
specifications and drawings.
Safe Working Load (SWL) is the actual loads that can be lifted and are not
include the hook, block and hoist rope weights.
The crane is self-contained, electro-hydraulic driven, hydraulically operated,
ram luffing, stiff boom box type, pedestal mounted and fully revolving;
furnished with a pedestal adaptor, an enclosed cabin and all auxiliary
equipment suitable for duties associated with an offshore vessel.
The function of the crane includes but not necessarily be limited to the
following:
A) Offloading item such as wire line equipment and coil tubing package, the
heaviest maintenance item materials (drilling tubular goods) from supply boat.
B) Transportation of personnel to/ from a supply boat.
C) Handling materials on platform deck.
D) Removing heavy components with various characteristics for their
installation on the deck at permanent locations (lay down areas).
The crane is provided with lifting lugs on all major assemblies to facilitate
erection or disassembly of the complete crane package.
The crane is equipped with a main hoist and auxiliary hoist.
The main hoist is capable of reeving various multi-falls of rope to achieve a
range of lifts for heavy loads.
The auxiliary hoist is of single fall, used for lifting light loads.
The crane’s flood-lights and electric equipment installed on the boom are
certified for safe area (unless otherwise specified).
The crane is continuous rotary type, rotating in both direction through 400°
limited.
The crane's power is sufficient to ensure that the one movement under full
load, full speed and under worst conditions.
Simultaneous operation is possible at reduced speed.
All areas of the crane are accessible for inspection, maintenance and repairs.
No feature on the crane presents or creates a safety hazard to personnel.
84
85. Nunce
Deck operating manual
Deck cargo crane
DESIGN
The crane is designed and constructed in accordance with API SPEC
2C,
Specification for Offshore Cranes, 6th edition, September 2004.
The crane is designed to provide the SWL capacities at the required
load, radii and speeds.
These SWL capacities are used to determine the Category 1 (static)
and Category 2 (dynamic) design loads as defined in API SPEC 2C.
For the purpose of evaluating the dynamic ratings for lifts from
boats, off-lead and side-lead angles are used as stated in the
technical data for the sea states indicated.
Also the maximum operating wind speed is included in the
evaluation of side forces.
The out-of-service wind speed is considered with the boom in the
horizontal position restrained in a rest.
Detailed calculations are prepared for all primary loaded members
of the crane, such as:
• Pedestal adaptor.
• Swing Circle bearing.
• Revolving Base structure.
• Frame.
• Boom.
• Running ropes.
• Boom foot pins and sheave pins, etc.
• Hoist winches drums and shafts.
85
86. Nunce
Deck operating manual
Deck cargo crane
MEP's standard specifications and procedures are reviewed by the
Shipyard.
Bearings supporting rotation are sleeve or antifriction types.
All antifriction bearings are selected in accordance with AFBMA or
equivalent and have an L-10 life exceeding the equivalent of 5,000
hours and are of suitable size for the loads and speeds specified.
Slew bearing is selected in order to stand about 25.000 hours prior
to any replacement.
Gears are designed for sufficient strength and surface durability
using service factors in accordance with AGMA or equivalent.
All hoist gearing is enclosed and provided with positive means of
lubrication.
Adequate lubrication is provided for all moving contact points of
the hoist and drives.
Where lifetime lubricated bearings are used, means of external
lubrication are not required.
Stainless steel grease fittings are provided for all sheave pins and
hinge pins.
The selection of materials is suitable for the crane application,
offering adequate corrosion protection for the proper function of
the crane and its component parts.
Crane is provided with self-maintenance devices for
removing/installing sheaves, winches, drums and hydraulic motors.
86
87. Nunce
Deck operating manual
Deck cargo crane
GENERAL DATA
PROJECT ACCOMMODATION BARGE
CLIENT COSCO SHIPYARD
MACHINERY ONE PEDESTAL OFFSHORE CRANE
MANUFACTURER MARINE EQUIPMENTS PELLEGRINI
MANUFACTURER'S TYPE CHCD 25/32 EH
ABS Certified and in COMPLIANCE
DESIGN AND PROJECT WITH A.P.I. 2C (6th EDITION)
ENVIRONMENTAL CONDITIONS
The pedestal offshore crane is suitable to withstand and correctly
operate at following conditions:
WIND DATA
Wind speed m/sec. 30 (steady state conditions) 40 (gust)
The above reported values are defined
at 45 m above Chart Datum
AIR TEMPERATURE
Minimum 0 °C
Maximum +35 °C
AIR RELATIVE HUMIDITY
Minimum 64%
Maximum 99%
87
88. Nunce
Deck operating manual
Deck cargo crane
AREA CLASSIFICATION
As per the available specifications it does not appear any
mentioning to hazardous areas. For this reason the supplied crane
is suitable to be installed in safe area.
LOAD
The supplied crane is designed to hoist the nominal SWL up to sea
condition with SWH=2,5m.
For higher SWH, the crane capacity is reduced in full accordance
with API 2C.
Maximum mounting misalignment of the crane pedestal from the
vertical is 0,5°.
TRANSPORTATION OF PERSONNEL
The transportation of personnel crane rated load in according with
Standard API-2C as per par 4.1.2. is the least of the following:
• Max 33% of the calculated SWL for non-personnel load ratting of
the whip hoist.
• Maximum load based on load line reeving and wire rope design
factor per Section 7.2.4.3.
• Maximum load based on load hoist line pull available,
considering line reeving losses with MEP’s design reeving for a load
at the boom head, calculated in accordance with paragraph 8.1.7
of API 2C.
MEP fulfil load tables, listing the net loads to be hoisted, hence,
according to API standard, the weights of the crane components
(such as tackle, weights, hooks, slings) are added thereto.
88
89. Nunce
Deck operating manual
Deck cargo crane
PERFORMANCES
Full load Main Hoist 25 ton at 0 - 20 m/min
Empty hook 0 - 40 m/min
Full load Whip Hoist 8 ton at 60 m/min
Empty hook Whip Hoist 0 - 60 m/min
Min. Boom Angle operating 15°
Stowage/inspection 0°
Slewing Range 400° limited
Slewing Speed 0 – 0,8 rpm
Max. Hook Travel Main Hoist 60m (4 rope falls)
Max. Hook Travel Whip Hoist 65m (single rope fall)
160kW based on one operation at full
Main Driver Capacity load and speed (as per data table)
Diameter of Pedestal Adaptor 2830 mm
Height of Pedestal Adaptor 1600 mm
Electrical feeding from plant 440V-60Hz AC 3Ph
Electrical feeding for aerial signalling 220V-60Hz- AC 1Ph
DESIGN
Life 20 Years
Duty 8 Hours/Day continuous
89
90. Nunce
Deck operating manual
Deck cargo crane
TECHNICAL DATA CHCD 25/32 EH NOTE
Please refer to annexed sketch n°
Crane type Offshore Stiff Boom Crane HD1520CA
Quantity 1
Total lift weight main 25 ton at all radius up to Up to SWH=2,5m de-rating in
winch (Maximum) 32m accordance with API 2C for higher SWH
8 ton at all radius up to
35,5m. Rated for man
Total lifting weight for riding (4 persons + basket =
auxiliary winch 700kg)
Installation area Crane in safe area
Main Hook speed (full
load) 0-20 m/min
Main Hook speed (no load) 0-40 m/min
Aux Hook speed 0-60 m/min
Slewing speed 0-0,8 rpm
Slewing angle 400° limited
Minimum working radius please check
Max. working radius 32m/35,5m the annexed sketch
About 60m for main hook
Hook stroke and 65m for aux hook TBC
Nominal SWL up to
Operative sea condition SWH=2,5m Cb in accordance with API 2C
Design temperature
(min/Max) 0°C/+35°C
Number of falls (main/aux) 4/1
Design Certification/third
party ABS Without Class Notation
Integrated on the auxiliary Performances and characteristics in
Man riding winch winch. accordance with ABS Rules
Working hydraulic
pressure 160 -250 bar
Available feeding from
board 440V 3Ph 60Hz TBC
Suitable for one manoeuvre at full load
Electric motors total and speed. Simultaneous manoeuvres
output power S2-30min 160kW are possible at reduced speed
In accordance with API 2C for the
List/trim Up to 5°/2° operative sea conditions
90
107. Nunce
Deck operating manual
Crane control system operator’s manual
3) Crane control system
Chcd 25-32
107
108. Nunce
Deck operating manual
Crane control system operator’s manual
3) Crane control system
Chcd 25-32
Feature overview
1.1 - Real-time display
All the monitored data are displayed on the instrument's screen,
as well as the following:
Actual load expressed graphically as a percentage of the maximum
acceptable load
Actual Boom Inclination and working radius
Several possible alarm conditions (see “Alarming” below)
108
109. Nunce
Deck operating manual
Crane control system operator’s manual
1.2 - Alarming
Possible alarm conditions which may be displayed by means of a
flashing red text (alarm) or blue text (warning) in the middle of the
screen include:
!!!EMERGENCY !!!
This indicates that the emergency button has been pushed
By pass Overload
This one appears while the alarm by-pass switch is activated, to
remind the operator that the instrument cannot signal some
potentially harming conditions.
By-pass Collision
This one appears (where present) while the anti-collision by-pass
switch is activated, to remind the operator that the instrument
cannot signal some potentially harming conditions.
GOPS
This one appears when crane is in GOPS Working condition
(current load > 120% than SWL).
!!! GOPS: Turn the lever to ACTIVATE it!!! These BLUE words
means that GOPS can be activated by turning the lever
!!! GOPS ACTIVATED !!! These RED words means that GOPS has
been activated
109
110. Nunce
Deck operating manual
Crane control system operator’s manual
Alarms signaled by the instrument are:
Overload pre-alarm
This means that the current load, expressed as a percentage of the
load limit, is greater than a configured threshold value (see the
“Setup” section for details). This condition is signaled visually by a
yellow area in the current load bar graph.
Overload
This means that the current load, expressed as a percentage of the
load limit, is greater than a configured threshold value (see the
“Setup” section for details). This condition is signaled visually by a
red area in the current load bar graph.
Communications fault
A red, blinking circle indicates a wrong communication between
screen and the CPU. This should never happen, as long as the
instrument has not been damaged; if the indication appears during
operation, please contact the manufacturer for assistance.
NOTE: A green blinking circle appears in normal communication.
Service messages
Appears when machine needs service maintenance.
Collision Information
Screen displays possible actions for crane operator, in collision
conditions (see the “Anticollision” section for details.)
110
111. Nunce
Deck operating manual
Crane control system operator’s manual
1.3 - Data logging
A list of the recorded data and their format, in the order in which
they appear on each record, follows:
•Current date and time, in the form yyyy-mm-dd hh.mm.ss
•Actual load, expressed in kilograms
•Load limit, expressed in kilograms
•Actual load, expressed as a percentage of the load limit
•Actual boom inclination expressed in degrees minutes
•(degrees *10)
•Actual jib aperture expressed in degrees minutes
•Actual unthread length expressed in millimeters
•Actual crane rotation expressed in degrees minutes
•Work radius, expressed in millimeters for MAIN winch
•Work radius, expressed in millimeters for AUX winch
•Boom height expressed in millimeters
•Sea state, as selected by the operator
111
112. Nunce
Deck operating manual
Crane control system operator’s manual
•A boolean value (1 or 0) indicating whether Aux or Main winch is
selected
•A boolean value (1 or 0) indicating whether the crane is
considered to be in boom rest position;
•A boolean value (1 or 0) indicating whether personnel mode
selection is active
•A boolean value (1 or 0) indicating whether wave mode selection
is active
•A boolean value (1 or 0) indicating whether a gross overload
condition exists
•A boolean value (1 or 0) indicating whether a gross overload
button was pushed but there is not a GOPS condition (load in not
bigger than 150% than SWL)
•A boolean value (1 or 0) indicating whether a By pass OVERLOAD
button is active
•A boolean value (1 or 0) indicating whether a By pass COLLISION
button is active
•A boolean value (1 or 0) indicating whether the EMERGENCY
button is active 5
•A boolean value (1 or 0) indicating whether a collision condition
is active.
•A boolean value (1 or 0) indicating whether maintenance is
needed.
•Raw boom inclinometer input value (for assistance and
troubleshooting purposes)
•Raw unthread sensor input value (for assistance and
troubleshooting purposes)
•Raw load cell input value (for assistance and troubleshooting
purposes)
•Raw jib inclinometer input value (for assistance and
troubleshooting purposes)
112
113. Nunce
Deck operating manual
Main screen: During normal operation, the
instrument screen appears as follows:
2.1 - Load bar graph
The colored bar shows the current load applied to the hoist, in terms of
percentage of the acceptable load. The instruments computes the
acceptable load in real time, based on the sea state and current luffing value.
A yellow area in the bar indicates that the current load is greater than the
pre-alarm threshold.
A red area in the bar indicates that the current load is greater than the alarm
threshold.
2.2 - Current load
To the right of the bar graph, the load currently applied to the hoist is shown,
expressed in ton.
2.3 - Load limit (SWL)
The load limit (Safe Working Load), depending upon the sea state, selected
hoist (when available) and working radius, is displayed immediately below
the current load value.
2.4 - Radius
Working radius is expressed in meters.
2.5 - Luffing
The luffing value is expressed in degrees.
2.6 - Communication icon
113 A green circle indicates a right communication. A red circle indicates a wrong
communication
114. Nunce
Deck operating manual
Palfinger crane
REFERENCE:
Manufacturer’s manual (PALFINGER)
GENERAL INFORMATION
SCOPE OF WORK
This Specification covers the minimum technical requirements for
the design, materials, manufacture, inspection, testing and
assembly of ONE pedestal crane Type A suitable to be installed
the accommodation barge Nunce.
114