Why Outsourcing Fails
- Postmortem Report
of Failed Outsourcing
Projects




Kamalanaban Ganesan
CMC Limited
Satya Sekhar Akkala
CMC Limited
Akhilesh Bahuguna
CMC Limited
Contents
   1.1      Abstract                                          3 
   1.2      Introduction                                      3 
   1.3      How we categorized that a project failed          3 
   1.4      Reasons for Failure:                              4 
   1.5      Lack of Outsourcing Knowledge                     4 
   1.5.1    Case Study #1:                                    5 
   1.6      Overselling                                       5 
   1.6.1    Case study #2:                                    5 
   1.7      Lack of precision and domain knowledge            6 
   1.7.1    Case study #3:                                    6 
   1.8      Expectation Mismatch                              7 
   1.8.1    Case study #4:                                    7 
   1.8.2    Case study #5:                                    7 
   1.9      Poor commitment                                   8 
   1.9.1    Case study #6:                                    8 
   1.10     Non controllable challenges                       8 
   1.10.1  Case study #7:                                     8 
   1.11     Cultural differences                              9 
   1.11.1  Case study #8:                                     9 
   1.12     Lessons learnt – Best Practices                   9 
   1.13     References                                        10 
   1.14     Conclusion                                        10 
   1.15     About authors                                     10 




2|Page
1.1 Abstract
         Outsourcing projects are cost-driven and involve lot of risks. India has grown in IT for
         the past decade due to the outsourcing trend in developed countries. Since
         US/European countries found India a cost-effective option, they were outsourcing their
         operations, development and maintenance activities as projects to India to save
         dollars. Various companies in India are working on these projects for several years
         and doing it successfully. In recent days the economic growth in India resulted in an
         increase in cost of various raw materials and resources. This resulted in reduction in
         margin and thereby increased risks in executing projects within budgets.

         Obviously failed projects will teach us great lessons. We have consolidated the list of
         lessons learnt from all failed projects in this paper. Also, the secret behind the
         successful projects are listed as key mantras of success. These simple historical data
         will surely help the project managers’ community.


         1.2 Introduction
         The world is trying to be competitive on a global scale by reducing the operational cost
         to bring in competitive products and services in their respective industry. In the
         present scenario, outsourcing has become essential rather than optional to retain the
         market leadership. In our team, we as project managers worked in this outsourcing
         business for a few decades. Having worked with multiple customers across different
         geographies, each project taught us few lessons which are being utilized for the
         subsequent project. However this will be a continuous cycle.

         As our best practice, we are habituated to add the lessons learnt in Projects Asset
         Library in our company database to serve as input for future projects. This has helped
         our new projects considerably. We surveyed and found a great trend during our
         steering committee meetings across all projects. After seeing this trend, we realized
         that our experience should be shared with our project managers’ community. This has
         triggered the purpose of introducing this post-mortem report as a PMI Conference
         paper.

         This report contains our experience with outsourcing projects. We interviewed several
         outsourcing managers and observed that most of them agreed that our observations
         are common across the IT industry.

         The analysis reveals that there are seven major fundamental causes for the failure of
         any outsourcing project. Interestingly they are not directly related to technical
         attributes of the projects, i.e., Requirements, Scope, etc. It is understood that most of
         the factors are related to relationship, communication, processes & practices, culture
         and perceptions. We detailed our findings in this paper.


         1.3 How we categorized that a project failed
         The main objective in the outsourcing business is to deliver values to the client
         besides the project requirements. We observed in few cases that though the project
         requirements are met, still the project / relationship is considered as a failure because
         of not meeting key stake-holders’ expectations/perceptions.



3|Page
1.4 Reasons for Failure:
         We observed that there are seven key reasons which contribute to most of the failed
         outsourcing projects, despite having sufficient processes and technical capabilities.

             Lack of outsourcing knowledge
             Overselling
             Lack of precision & domain knowledge
             Expectation mismatch
             Poor commitment
             Non controllable challenges
             Cultural differences
         Figure 1 illustrates the percentage of project failure observed due to seven listed
         reasons for failure




                           Figure 1: Reasons for outsourcing project failures


         1.5 Lack of Outsourcing Knowledge
         Most of the project failures are due to the lack of outsourcing knowledge or expertise
         with the client/outsourcing companies. Before outsourcing the project the client should
         check whether their organization is ready to outsource the project to partnering
         companies. Also, both organizations should have patience to wait for the results. The
         outsourcing benefit cannot be seen in a few projects. Our experience shows each
         relationship has its own breakeven time to see the intended favorable results. It varies
         based on the project’s complexity and environment. The client organization should be
         committed to make the outsourcing successful, irrespective of few short term failures,
         if any.


4|Page
1.5.1 Case Study #1:
         Company A decided to outsource. The top management team approached major
         companies in India and evaluated them in terms of capabilities, cost, and expertise
         and then decided to outsource a project to Company Y. The T&M contract model was
         chosen. Offsite team went onsite for a requirements study; client provided the
         marketing specification and asked them to design the requirements for one of the
         major systems. The team collected the requirements for that subsystem (line card)
         and started working on it. The project was well planned and executed. Requirement,
         Design, Implementation was done and stand-alone testing was performed as per the
         plan and requirement. The product was delivered. Once the customer’s product
         qualification team started testing in integrated environment, several bugs were logged
         in the bug tracker. As a result of this new requirements and features were added. The
         team fixed the issues in the last stages and this caused dissatisfaction to the client.

         The top management team reviewed this project and found that the offsite team
         struggled to implement the project and this resulted in schedule and costs overrun.
         They decided that outsourcing did not make any sense.

         Later, Company Y analyzed and shared the following findings with Company A to
         make the outsourcing successful:

         1. The client team shall adopt collaborative approach and proactively plan for
            necessary support to the offsite team.
         2. Offsite team shall be treated as client’s extended team rather than adopting the
            vendor approach.
         3. Relationship evaluation model shall not be limited only to short term goals but also
            oriented towards long term benefits.
         4. The process mapping shall be done at organization level to ensure synergy.


         1.6 Overselling
         Client’s top management wanted to outsource everything to save cost to stay in the
         competition. Sometimes the outsourcing companies need to take the project in order
         not to allow another vendor to work for the client. Once the project is kicked off and
         starts moving, client expectation mismatch is observed. This creates turbulence in the
         relationship. The client organization should be mature enough to judge capabilities of
         the partnering company and also account for the risk mitigation before outsourcing. It
         is always safe and worthy to take calculated risks in execution.

         1.6.1 Case study #2:
         Company “A” started outsourcing few projects to company Y. Around six projects were
         running well without any issue. This triggered the other division in Company A to
         outsource a large program almost equivalent to that of the present total team strength
         of six projects. Company Y found this as a great opportunity. Though there was no
         team available offsite, it decided to take the project and ramp up fast. Due to market
         conditions the team could not ramp up and show the resources to the client team.
         Onsite team developed the perception and decided that this program cannot be
         started.




5|Page
Then Company A’s other division awarded that project to another outsourcing
         company in Australia. The sales guy’s overselling caused the larger program to be lost.
         If the sales/offsite team had openly explained the problem to the client and requested
         for time to ramp up the team in a phased manner, this project might have been
         awarded to Company Y. The overselling and expectation mismatch killed this
         opportunity.


         1.7 Lack of precision and domain knowledge
         Generally, client always assumes that everyone in the offsite team has domain
         experts and tries to measure them with the same yard stick they use for their
         engineers, who are working in that specific domain for several decades. Also, if the
         ramp-up is fast the domain knowledge cannot be developed in weeks/months. It takes
         at-least one or two projects for acquiring product specific knowledge.

         In India, the number of companies engaged in end-to-end product development are
         very few. The international standards and compliances for technologies are the main
         body of knowledge. So we have usually very few engineers specialized in various
         domains required for different product segments. However, if managed properly, we
         have people with the aptitude and attitude to learn and develop those skills quickly. If
         the team is provided with infrastructure and time,it is observed that within few months
         the offsite team acquired competency to handle the domain level requirements and
         problems.

         1.7.1 Case study #3:
         Company Y approached Company A for a new outsourcing opportunity. At that time,
         Company A had an immediate problem and was looking for a solution for one of its
         upcoming projects in a three months deadline with sizeable portion of activity left. The
         project had immense revenue potential whereas company A had already spent more
         than six months to complete just requirement and architecture design activity. As
         usual, the sales team promised the solution before three months. Since it was the
         breeder project, company Y picked up its best resources and formed the team in a
         week’s time. The team planned aggressively and proactively to complete the project in
         all areas like design, implementation, procurement, manufacturing, shipping, etc.

         With the team’s dedication and hard work the project got completed just around the
         deadline. Obviously the client was amazed, however during the product qualification
         testing the product exhibited lots of manufacturing and reliability issues, and soon the
         client was unhappy about extremely poor yield and a few missing requirements. The
         client with their vast domain knowledge felt that the unstated requirements were
         obvious for the product to qualify in that market segment whereas the outsourcing
         companies were taking them for the first time. The manufacturing was subcontracted
         to an Indian vendor whose manufacturing capabilities were way behind its US
         counterpart.

         Though the project was a failure from the scope, time and cost definition, and there
         were quite a few night-mares in the relationship immediately after the project
         completion phase, yet there was a silver lining. The client got convinced about
         company Y’s design skills and decided to continue with design outsourcing but
         retaining the manufacturing work with them. Eventually the design outsourcing
         business with the client grew to over a million dollars per month.




6|Page
1.8 Expectation Mismatch
         Most of the project manager’s time was spent in communication management to
         correct the expectation between client and team. But sometimes the relationship is
         getting gets affected due to wrong expectations. The observed reasons are mainly
         due no proper understanding with the client execution team, unclear communication,
         implicit requirements, and unrealistic yard stick for performance measurement.
         Also, while starting the project with offsite team, both parties should create an
         environment to openly discuss and understand the expectations and have mutual
         concurrence in their expectations.
         The expectation mismatch is highly dynamic, and has significant impact even in some
         matured relationships because of inability to show long term continuous and
         consistent value additions.
         1.8.1 Case study #4:
         Company A wanted to do outsourcing due to business requirement and approached
         Company X. The project was awarded to company X with a budget of $1million. The
         requirements were provided and the client expected that the project will be completed
         as per schedule. T&M model was chosen. There was no review planned by the top
         management team. Company X ramped up the team and started billing. Since, more
         resources were available company X decided to put more people in the team initially.
         Everyone started understanding the project and the study phase, design phase was in
         progress. One fine day, before the scheduled time, the accounts department of Client
         Company refused the invoice because of budget overrun. The client’s top
         management team asked for the status, it was 30% as per the planned schedule but
         the budget was overrun. Client showed dissatisfaction and the relationship ended.
         Since the bills are paid as per the T&M and the progress is as per the schedule,
         company X expected that company A was happy. But Company A expected that the
         schedule was fine and the project will run as per the expected plan. Unfortunately here
         the project failed because of expectation mismatch due to communication gap.
         1.8.2 Case study #5:
         Company B outsourced a project to company Y as a pilot project. Company Y started
         the project and design was in progress. The client team asked for status, offsite team
         sent the intermediate design where the designer was trying to experiment the best
         possible design. Since it was an intermediate status, offsite team named the design
         file as initial draft and sent it to client to show the status.

         Offsite team expected that since the design file is named as initial draft client will not
         check the correctness. But client team reviewed it and found the design was totally
         wrong. This issue was escalated to client's top management team and commented
         that the offsite team is technically incapable. Next day the design team got a shock.
         Finally the design team traveled onsite and explained the issue and illustrated their
         capabilities to the customer.

         The expectation mismatch could happen due to communication issues like wrong
         wording during communication, one way communication where client confirmation was
         not immediately taken, and poor communication planning.




7|Page
1.9 Poor commitment
         No support and non collaborative approach from client team will always result in
         outsourcing failure. In most of the cases where we see poor commitment from client
         team, was due to the fact that the outsourcing was seen valuable at corporate
         management level but it was not valued by the execution teams. For successful
         outsourcing, the corporate management should get the buy-in from the execution
         team with organizational motivating factors.

         Also, the offsite team project manager should facilitate the team to have self
         commitment on its part of work and relationships to make it successful.

         1.9.1 Case study #6:
         Company A has good outsourcing relationship with Company B and has executed a
         few projects successfully. Director of Engineering recommended one for his project
         team to use outsourcing and get benefited by it. Since the Director asked, the PM
         gave a chunk of activities to the offsite team for execution. The offsite team came up
         with requirement clarifications and asked for more documentation. The PM clarified
         the point at a very high level saying details should be developed by vendor. Project
         team completed the work as per their understanding and shared the deliverable for
         client review. Client pointed out several reworks and tried to fail the offsite team. In
         this environment the team failed after several attempts in multiple fragment of work
         and clearly the culprit was “no support from client team”.


         1.10 Non controllable challenges
         It was seen that the outsourcing failed with few customers due to non controllable
         project factors like inflation, market boom and unjustifiable salary hike demands /
         attrition, new emerging competitors and pressure          to reduce margins, mass
         resignations, political instabilities, government policies, new taxes, and natural
         calamities. This could be overcome by risk management best practices and produce
         less impact.

         1.10.1 Case study #7:
         Company A decided to outsource product development and supply to the existing
         outsourcing partner Company X. The company X was asked to provide their
         capabilities on that domain. Since Company X doesn't have the capability to develop,
         it recommended the partnering company Y to deliver this project. The company Y
         provided an estimate and the client asked for fixed price contract to mitigate the risks.

         Since this was a first project to Company Y from Company A, it decided to take up this
         contract and started development. During execution, external factors changed. The
         dollar got depreciated, market was booming, attrition was high, expenses increased,
         increased tax hit the raw material costs. This hit the project badly and resulted in loss.
         Because of the team change the project schedule got delayed.

         This delay has impacted the product delivery of end client and client (Company A)
         ended up in paying a huge penalty. The relationship was hit miserably and ended
         prematurely.




8|Page
1.11 Cultural differences
         In outsourcing, multi cultural team is unavoidable. Even though it appears to be trivial,
         considerable amount of client dissatisfaction has been observed due to cultural
         differences.
         The cultural training should be provided to both teams involved in execution. The
         outsourcing organization should educate the client and offsite team with well known
         cultural issues and best practices.
         Periodical onsite visits to client team and inviting client team offsite has shown
         considerable improvement in the relationship. Team outings, commonly interested
         activities (like games, celebrations, cooking, etc) apart from work will always bring
         down the cultural differences.
         1.11.1 Case study #8:
         The Company A from Japan decided to outsource some of its projects to Company X
         in India after several stages of evaluation. Japanese manager was appointed as the
         outsourcing manager to handle the offsite team. He had never stayed outside Japan,
         and hence didn’t prove to be efficient in handling a multi cultural team.

         Though the team was formed with proven team members at offsite, the project
         schedule slipped due to repeated rework on the modules with lot of cosmetic changes.
         The cultural barrier with executing team and client led this project to failure because of
         schedule slippage.

         In general, the outsourcing aware organizations would always provide sufficient
         training to the teams involved from different geographies and culture to cross the
         cultural barrier.


         1.12 Lessons learnt – Best Practices
         1. For new relationships, always educate the client about outsourcing processes,
            lessons learnt, and best practices.
         2. Proactive gap analysis (process, organization structure, reporting, etc.,) and
            expected impact/suggestions to be provided to avoid repeating the lessons.
         3. Top management of both the companies should follow-up closely and review the
            project at least once every month until the relationship is stabilized. This creates
            commitment among execution team for success.
         4. The PgM/PM processes and best practices should be used as required for the
            project.
         5. Exhaustive risk analysis and mitigation mechanisms should be in place during
            overselling. Educate the client as much as possible during sudden ramp up and
            have daily updates to keep him updated.
         6. Conduct exhaustive trainings and workshops to train the team on customer
            specific domain/skill, including client actively for knowledge transfers on key
            domains Get buy-in from client by explaining the usefulness of developing
            expertise at offshore.
         7. Check for all possible gaps in communication plan to avoid expectation mismatch.




9|Page
8. The client organization should be educated to understand the importance of
                  openness and facilitate the offsite team to come forward and explain issues.
               9. The client organization should plan outsourcing at organization level and educate
                  the importance/outcome of outsourcing to execution teams and ensure the buy-in
                  from execution team before starting the outsourcing.
               10. The client organization should be mature enough to have realistic expectation on
                   any value additions and commitments, irrespective of offsite team promises.
               11. Exhaustive risk analysis and mitigation mechanisms should be in place for the
                   uncontrollable factors. Some of the factors could be easily overcome by client
                   awareness, right contracting model and best practices.
               12. Cultural awareness and training should be provided to both the organizations do
                   deal with multi cultural teams.


               1.13 References
               Previously executed projects of all three authors for the past 15 years.


               1.14 Conclusion
               To conclude, any outsourcing organization could use this paper to understand the
               commonly observed causes for failure and the best practices to overcome them.


               1.15 About authors




               Akhilesh Bahuguna works for CMC Limited as Deputy General Manager and
               heads the Telecom vertical. He has vast experience in the development of
               technologies for communication networks and infrastructure in India, both from
               indigenous development and technology absorption & deployment from
               telecom majors like Alcatel, Ericsson, Lucent, Tellabs and others. Out of his
               18+ years of experience, more than 10 years were spent in managing large
               and complex programs with a multisite workforce spread. He holds his
               Masters in Optoelectronics and Optical communications from Indian Institute
               of Technology, Delhi.




10 | P a g e
Satya Sekhar Akkala works for CMC Limited as Senior Manager and heads
               the Railroad vertical. He has over 20 years of experience with 15+ years in
               Project / Program Management. He holds his Bachelors in Electronics and
               Communication Engineering from Nagarjuna University, Andra Pradesh.




               Kamalanaban Ganesan works for CMC Limited as Manager and leads a
               Telecom offshore development centre. He has over 12 years of experience
               with 6+ years in project / engineering Management. Prior to CMC, He worked
               with BEL, Shuttle Technology, SCM Microsystems, Sirius Semiconductors,
               and Force Computers. He holds his Bachelors in Electronics and
               Communication Engineering from University of Madras, Chennai. He is PMP
               certified since February 2007.




11 | P a g e

Weitere ähnliche Inhalte

Was ist angesagt?

Managing Technical Debt
Managing Technical DebtManaging Technical Debt
Managing Technical DebtKaizenko
 
Daryl Elfield - Power to the People - EuroSTAR 2011
Daryl Elfield - Power to the People - EuroSTAR 2011Daryl Elfield - Power to the People - EuroSTAR 2011
Daryl Elfield - Power to the People - EuroSTAR 2011TEST Huddle
 
19 project management trends for 2019 By Experts
 19 project management trends for 2019 By Experts 19 project management trends for 2019 By Experts
19 project management trends for 2019 By ExpertsInvensis Learning
 
PMI-ACP Lesson 04 Nugget 1 Agile Estimation
PMI-ACP Lesson 04 Nugget 1 Agile EstimationPMI-ACP Lesson 04 Nugget 1 Agile Estimation
PMI-ACP Lesson 04 Nugget 1 Agile EstimationThanh Nguyen
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2Thanh Nguyen
 
Comparing PMP and PRINCE2 Certifications | Invensis Learning
Comparing PMP and PRINCE2 Certifications | Invensis LearningComparing PMP and PRINCE2 Certifications | Invensis Learning
Comparing PMP and PRINCE2 Certifications | Invensis LearningInvensis Learning
 
Speak Like a Test Manager
Speak Like a Test ManagerSpeak Like a Test Manager
Speak Like a Test ManagerTechWell
 
Technical Debt 101
Technical Debt 101Technical Debt 101
Technical Debt 101Intechnica
 
Technical Debt: Sources and Impacts
Technical Debt: Sources and ImpactsTechnical Debt: Sources and Impacts
Technical Debt: Sources and ImpactsAgile Velocity
 
Technical Debt - PHPBenelux
Technical Debt - PHPBeneluxTechnical Debt - PHPBenelux
Technical Debt - PHPBeneluxenaramore
 
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014Mary Poppendieck: The Aware Organization - Lean IT Summit 2014
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014Institut Lean France
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsMichael Krigsman
 
Ba tips: the complexity of workshops
Ba tips:  the complexity of workshopsBa tips:  the complexity of workshops
Ba tips: the complexity of workshopsCraig Brown
 
Inhouse vs-off-the-shelf-may
Inhouse vs-off-the-shelf-mayInhouse vs-off-the-shelf-may
Inhouse vs-off-the-shelf-mayAyodeji Adesina
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility examJamil Faraj , PMP
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3Thanh Nguyen
 
Tackling Software Development Nightmares
Tackling Software Development NightmaresTackling Software Development Nightmares
Tackling Software Development NightmaresJames Douglas
 
7 Steps to Pay Down the Interest on Your IT Technical Debt
7 Steps to Pay Down the Interest on Your IT Technical Debt7 Steps to Pay Down the Interest on Your IT Technical Debt
7 Steps to Pay Down the Interest on Your IT Technical DebtCAST
 

Was ist angesagt? (20)

Managing Technical Debt
Managing Technical DebtManaging Technical Debt
Managing Technical Debt
 
Daryl Elfield - Power to the People - EuroSTAR 2011
Daryl Elfield - Power to the People - EuroSTAR 2011Daryl Elfield - Power to the People - EuroSTAR 2011
Daryl Elfield - Power to the People - EuroSTAR 2011
 
19 project management trends for 2019 By Experts
 19 project management trends for 2019 By Experts 19 project management trends for 2019 By Experts
19 project management trends for 2019 By Experts
 
PMI-ACP Lesson 04 Nugget 1 Agile Estimation
PMI-ACP Lesson 04 Nugget 1 Agile EstimationPMI-ACP Lesson 04 Nugget 1 Agile Estimation
PMI-ACP Lesson 04 Nugget 1 Agile Estimation
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
 
Comparing PMP and PRINCE2 Certifications | Invensis Learning
Comparing PMP and PRINCE2 Certifications | Invensis LearningComparing PMP and PRINCE2 Certifications | Invensis Learning
Comparing PMP and PRINCE2 Certifications | Invensis Learning
 
Speak Like a Test Manager
Speak Like a Test ManagerSpeak Like a Test Manager
Speak Like a Test Manager
 
Technical Debt 101
Technical Debt 101Technical Debt 101
Technical Debt 101
 
Technical debt
Technical debtTechnical debt
Technical debt
 
Technical Debt: Sources and Impacts
Technical Debt: Sources and ImpactsTechnical Debt: Sources and Impacts
Technical Debt: Sources and Impacts
 
Technical Debt - PHPBenelux
Technical Debt - PHPBeneluxTechnical Debt - PHPBenelux
Technical Debt - PHPBenelux
 
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014Mary Poppendieck: The Aware Organization - Lean IT Summit 2014
Mary Poppendieck: The Aware Organization - Lean IT Summit 2014
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and Solutions
 
Ba tips: the complexity of workshops
Ba tips:  the complexity of workshopsBa tips:  the complexity of workshops
Ba tips: the complexity of workshops
 
Inhouse vs-off-the-shelf-may
Inhouse vs-off-the-shelf-mayInhouse vs-off-the-shelf-may
Inhouse vs-off-the-shelf-may
 
Technical Debt
Technical DebtTechnical Debt
Technical Debt
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
 
Tackling Software Development Nightmares
Tackling Software Development NightmaresTackling Software Development Nightmares
Tackling Software Development Nightmares
 
7 Steps to Pay Down the Interest on Your IT Technical Debt
7 Steps to Pay Down the Interest on Your IT Technical Debt7 Steps to Pay Down the Interest on Your IT Technical Debt
7 Steps to Pay Down the Interest on Your IT Technical Debt
 

Andere mochten auch (7)

Rsc 04
Rsc 04Rsc 04
Rsc 04
 
Gvt 01
Gvt 01Gvt 01
Gvt 01
 
Rsc 03
Rsc 03Rsc 03
Rsc 03
 
Trn 12
Trn 12Trn 12
Trn 12
 
Rsc 02
Rsc 02Rsc 02
Rsc 02
 
Sft 02
Sft 02Sft 02
Sft 02
 
Sft 01
Sft 01Sft 01
Sft 01
 

Ähnlich wie Rsc 07

Business Case Template
Business Case TemplateBusiness Case Template
Business Case TemplateDemand Metric
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development ProcessSattrix Software Solutions
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projectsWalter Akers
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guideeuwebsc01
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guideeuweben01
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guideeuwebtc01
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Phil Comelio
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closureVelita Furtado
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problemsMaksudul Munna
 
Agile adoption julen c. mohanty
Agile adoption   julen c. mohantyAgile adoption   julen c. mohanty
Agile adoption julen c. mohantyJulen Mohanty
 
Social Media Business Case
Social Media Business Case Social Media Business Case
Social Media Business Case Demand Metric
 
190228 service design in japan en
190228 service design in japan en190228 service design in japan en
190228 service design in japan enKenji Hiramoto
 
Top 10 Project Manager Interview Questions You Need.pdf
Top 10 Project Manager Interview Questions You Need.pdfTop 10 Project Manager Interview Questions You Need.pdf
Top 10 Project Manager Interview Questions You Need.pdfDivya Malik
 
PMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsPMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsDaniel_Mccrea
 
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docx
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docxSheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docx
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docxlesleyryder69361
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
Webinar program business case template
Webinar program business case templateWebinar program business case template
Webinar program business case templateDemand Metric
 

Ähnlich wie Rsc 07 (20)

Business Case Template
Business Case TemplateBusiness Case Template
Business Case Template
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projects
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guide
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guide
 
Business Case Guide
Business Case GuideBusiness Case Guide
Business Case Guide
 
Services for business_2014
Services for business_2014Services for business_2014
Services for business_2014
 
PMCourse businesscase
PMCourse businesscasePMCourse businesscase
PMCourse businesscase
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Top 10 project mgt. problems
Top 10 project mgt. problemsTop 10 project mgt. problems
Top 10 project mgt. problems
 
Agile adoption julen c. mohanty
Agile adoption   julen c. mohantyAgile adoption   julen c. mohanty
Agile adoption julen c. mohanty
 
Social Media Business Case
Social Media Business Case Social Media Business Case
Social Media Business Case
 
190228 service design in japan en
190228 service design in japan en190228 service design in japan en
190228 service design in japan en
 
Top 10 Project Manager Interview Questions You Need.pdf
Top 10 Project Manager Interview Questions You Need.pdfTop 10 Project Manager Interview Questions You Need.pdf
Top 10 Project Manager Interview Questions You Need.pdf
 
PMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for ProfessionalsPMP - Project Initiation Template for Professionals
PMP - Project Initiation Template for Professionals
 
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docx
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docxSheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docx
Sheet1Lectocomp Electronics Manufacturing CompanyProject RisksAsse.docx
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
Webinar program business case template
Webinar program business case templateWebinar program business case template
Webinar program business case template
 
PM_lecture.pdf
PM_lecture.pdfPM_lecture.pdf
PM_lecture.pdf
 

Mehr von PMInstituteIndia (20)

Piyush govil archana_sharma
Piyush govil  archana_sharmaPiyush govil  archana_sharma
Piyush govil archana_sharma
 
D john peter
D john peterD john peter
D john peter
 
Trn 10
Trn 10Trn 10
Trn 10
 
Trn 11
Trn 11Trn 11
Trn 11
 
Trn 09
Trn 09Trn 09
Trn 09
 
Trn 08
Trn 08Trn 08
Trn 08
 
Trn 07
Trn 07Trn 07
Trn 07
 
Trn 06
Trn 06Trn 06
Trn 06
 
Trn 05
Trn 05Trn 05
Trn 05
 
Trn 04
Trn 04Trn 04
Trn 04
 
Trn 03
Trn 03Trn 03
Trn 03
 
Trn 02
Trn 02Trn 02
Trn 02
 
Trn 01
Trn 01Trn 01
Trn 01
 
Sps 01
Sps 01Sps 01
Sps 01
 
Sft 03
Sft 03Sft 03
Sft 03
 
Sft 04
Sft 04Sft 04
Sft 04
 
Rsc 06
Rsc 06Rsc 06
Rsc 06
 
Rsc 05
Rsc 05Rsc 05
Rsc 05
 
Rsc 01
Rsc 01Rsc 01
Rsc 01
 
Pmt 05
Pmt 05Pmt 05
Pmt 05
 

Kürzlich hochgeladen

Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 

Kürzlich hochgeladen (20)

Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 

Rsc 07

  • 1. Aum gam ganapataye namya. Why Outsourcing Fails - Postmortem Report of Failed Outsourcing Projects Kamalanaban Ganesan CMC Limited Satya Sekhar Akkala CMC Limited Akhilesh Bahuguna CMC Limited
  • 2. Contents 1.1  Abstract 3  1.2  Introduction 3  1.3  How we categorized that a project failed 3  1.4  Reasons for Failure: 4  1.5  Lack of Outsourcing Knowledge 4  1.5.1  Case Study #1: 5  1.6  Overselling 5  1.6.1  Case study #2: 5  1.7  Lack of precision and domain knowledge 6  1.7.1  Case study #3: 6  1.8  Expectation Mismatch 7  1.8.1  Case study #4: 7  1.8.2  Case study #5: 7  1.9  Poor commitment 8  1.9.1  Case study #6: 8  1.10  Non controllable challenges 8  1.10.1  Case study #7: 8  1.11  Cultural differences 9  1.11.1  Case study #8: 9  1.12  Lessons learnt – Best Practices 9  1.13  References 10  1.14  Conclusion 10  1.15  About authors 10  2|Page
  • 3. 1.1 Abstract Outsourcing projects are cost-driven and involve lot of risks. India has grown in IT for the past decade due to the outsourcing trend in developed countries. Since US/European countries found India a cost-effective option, they were outsourcing their operations, development and maintenance activities as projects to India to save dollars. Various companies in India are working on these projects for several years and doing it successfully. In recent days the economic growth in India resulted in an increase in cost of various raw materials and resources. This resulted in reduction in margin and thereby increased risks in executing projects within budgets. Obviously failed projects will teach us great lessons. We have consolidated the list of lessons learnt from all failed projects in this paper. Also, the secret behind the successful projects are listed as key mantras of success. These simple historical data will surely help the project managers’ community. 1.2 Introduction The world is trying to be competitive on a global scale by reducing the operational cost to bring in competitive products and services in their respective industry. In the present scenario, outsourcing has become essential rather than optional to retain the market leadership. In our team, we as project managers worked in this outsourcing business for a few decades. Having worked with multiple customers across different geographies, each project taught us few lessons which are being utilized for the subsequent project. However this will be a continuous cycle. As our best practice, we are habituated to add the lessons learnt in Projects Asset Library in our company database to serve as input for future projects. This has helped our new projects considerably. We surveyed and found a great trend during our steering committee meetings across all projects. After seeing this trend, we realized that our experience should be shared with our project managers’ community. This has triggered the purpose of introducing this post-mortem report as a PMI Conference paper. This report contains our experience with outsourcing projects. We interviewed several outsourcing managers and observed that most of them agreed that our observations are common across the IT industry. The analysis reveals that there are seven major fundamental causes for the failure of any outsourcing project. Interestingly they are not directly related to technical attributes of the projects, i.e., Requirements, Scope, etc. It is understood that most of the factors are related to relationship, communication, processes & practices, culture and perceptions. We detailed our findings in this paper. 1.3 How we categorized that a project failed The main objective in the outsourcing business is to deliver values to the client besides the project requirements. We observed in few cases that though the project requirements are met, still the project / relationship is considered as a failure because of not meeting key stake-holders’ expectations/perceptions. 3|Page
  • 4. 1.4 Reasons for Failure: We observed that there are seven key reasons which contribute to most of the failed outsourcing projects, despite having sufficient processes and technical capabilities. Lack of outsourcing knowledge Overselling Lack of precision & domain knowledge Expectation mismatch Poor commitment Non controllable challenges Cultural differences Figure 1 illustrates the percentage of project failure observed due to seven listed reasons for failure Figure 1: Reasons for outsourcing project failures 1.5 Lack of Outsourcing Knowledge Most of the project failures are due to the lack of outsourcing knowledge or expertise with the client/outsourcing companies. Before outsourcing the project the client should check whether their organization is ready to outsource the project to partnering companies. Also, both organizations should have patience to wait for the results. The outsourcing benefit cannot be seen in a few projects. Our experience shows each relationship has its own breakeven time to see the intended favorable results. It varies based on the project’s complexity and environment. The client organization should be committed to make the outsourcing successful, irrespective of few short term failures, if any. 4|Page
  • 5. 1.5.1 Case Study #1: Company A decided to outsource. The top management team approached major companies in India and evaluated them in terms of capabilities, cost, and expertise and then decided to outsource a project to Company Y. The T&M contract model was chosen. Offsite team went onsite for a requirements study; client provided the marketing specification and asked them to design the requirements for one of the major systems. The team collected the requirements for that subsystem (line card) and started working on it. The project was well planned and executed. Requirement, Design, Implementation was done and stand-alone testing was performed as per the plan and requirement. The product was delivered. Once the customer’s product qualification team started testing in integrated environment, several bugs were logged in the bug tracker. As a result of this new requirements and features were added. The team fixed the issues in the last stages and this caused dissatisfaction to the client. The top management team reviewed this project and found that the offsite team struggled to implement the project and this resulted in schedule and costs overrun. They decided that outsourcing did not make any sense. Later, Company Y analyzed and shared the following findings with Company A to make the outsourcing successful: 1. The client team shall adopt collaborative approach and proactively plan for necessary support to the offsite team. 2. Offsite team shall be treated as client’s extended team rather than adopting the vendor approach. 3. Relationship evaluation model shall not be limited only to short term goals but also oriented towards long term benefits. 4. The process mapping shall be done at organization level to ensure synergy. 1.6 Overselling Client’s top management wanted to outsource everything to save cost to stay in the competition. Sometimes the outsourcing companies need to take the project in order not to allow another vendor to work for the client. Once the project is kicked off and starts moving, client expectation mismatch is observed. This creates turbulence in the relationship. The client organization should be mature enough to judge capabilities of the partnering company and also account for the risk mitigation before outsourcing. It is always safe and worthy to take calculated risks in execution. 1.6.1 Case study #2: Company “A” started outsourcing few projects to company Y. Around six projects were running well without any issue. This triggered the other division in Company A to outsource a large program almost equivalent to that of the present total team strength of six projects. Company Y found this as a great opportunity. Though there was no team available offsite, it decided to take the project and ramp up fast. Due to market conditions the team could not ramp up and show the resources to the client team. Onsite team developed the perception and decided that this program cannot be started. 5|Page
  • 6. Then Company A’s other division awarded that project to another outsourcing company in Australia. The sales guy’s overselling caused the larger program to be lost. If the sales/offsite team had openly explained the problem to the client and requested for time to ramp up the team in a phased manner, this project might have been awarded to Company Y. The overselling and expectation mismatch killed this opportunity. 1.7 Lack of precision and domain knowledge Generally, client always assumes that everyone in the offsite team has domain experts and tries to measure them with the same yard stick they use for their engineers, who are working in that specific domain for several decades. Also, if the ramp-up is fast the domain knowledge cannot be developed in weeks/months. It takes at-least one or two projects for acquiring product specific knowledge. In India, the number of companies engaged in end-to-end product development are very few. The international standards and compliances for technologies are the main body of knowledge. So we have usually very few engineers specialized in various domains required for different product segments. However, if managed properly, we have people with the aptitude and attitude to learn and develop those skills quickly. If the team is provided with infrastructure and time,it is observed that within few months the offsite team acquired competency to handle the domain level requirements and problems. 1.7.1 Case study #3: Company Y approached Company A for a new outsourcing opportunity. At that time, Company A had an immediate problem and was looking for a solution for one of its upcoming projects in a three months deadline with sizeable portion of activity left. The project had immense revenue potential whereas company A had already spent more than six months to complete just requirement and architecture design activity. As usual, the sales team promised the solution before three months. Since it was the breeder project, company Y picked up its best resources and formed the team in a week’s time. The team planned aggressively and proactively to complete the project in all areas like design, implementation, procurement, manufacturing, shipping, etc. With the team’s dedication and hard work the project got completed just around the deadline. Obviously the client was amazed, however during the product qualification testing the product exhibited lots of manufacturing and reliability issues, and soon the client was unhappy about extremely poor yield and a few missing requirements. The client with their vast domain knowledge felt that the unstated requirements were obvious for the product to qualify in that market segment whereas the outsourcing companies were taking them for the first time. The manufacturing was subcontracted to an Indian vendor whose manufacturing capabilities were way behind its US counterpart. Though the project was a failure from the scope, time and cost definition, and there were quite a few night-mares in the relationship immediately after the project completion phase, yet there was a silver lining. The client got convinced about company Y’s design skills and decided to continue with design outsourcing but retaining the manufacturing work with them. Eventually the design outsourcing business with the client grew to over a million dollars per month. 6|Page
  • 7. 1.8 Expectation Mismatch Most of the project manager’s time was spent in communication management to correct the expectation between client and team. But sometimes the relationship is getting gets affected due to wrong expectations. The observed reasons are mainly due no proper understanding with the client execution team, unclear communication, implicit requirements, and unrealistic yard stick for performance measurement. Also, while starting the project with offsite team, both parties should create an environment to openly discuss and understand the expectations and have mutual concurrence in their expectations. The expectation mismatch is highly dynamic, and has significant impact even in some matured relationships because of inability to show long term continuous and consistent value additions. 1.8.1 Case study #4: Company A wanted to do outsourcing due to business requirement and approached Company X. The project was awarded to company X with a budget of $1million. The requirements were provided and the client expected that the project will be completed as per schedule. T&M model was chosen. There was no review planned by the top management team. Company X ramped up the team and started billing. Since, more resources were available company X decided to put more people in the team initially. Everyone started understanding the project and the study phase, design phase was in progress. One fine day, before the scheduled time, the accounts department of Client Company refused the invoice because of budget overrun. The client’s top management team asked for the status, it was 30% as per the planned schedule but the budget was overrun. Client showed dissatisfaction and the relationship ended. Since the bills are paid as per the T&M and the progress is as per the schedule, company X expected that company A was happy. But Company A expected that the schedule was fine and the project will run as per the expected plan. Unfortunately here the project failed because of expectation mismatch due to communication gap. 1.8.2 Case study #5: Company B outsourced a project to company Y as a pilot project. Company Y started the project and design was in progress. The client team asked for status, offsite team sent the intermediate design where the designer was trying to experiment the best possible design. Since it was an intermediate status, offsite team named the design file as initial draft and sent it to client to show the status. Offsite team expected that since the design file is named as initial draft client will not check the correctness. But client team reviewed it and found the design was totally wrong. This issue was escalated to client's top management team and commented that the offsite team is technically incapable. Next day the design team got a shock. Finally the design team traveled onsite and explained the issue and illustrated their capabilities to the customer. The expectation mismatch could happen due to communication issues like wrong wording during communication, one way communication where client confirmation was not immediately taken, and poor communication planning. 7|Page
  • 8. 1.9 Poor commitment No support and non collaborative approach from client team will always result in outsourcing failure. In most of the cases where we see poor commitment from client team, was due to the fact that the outsourcing was seen valuable at corporate management level but it was not valued by the execution teams. For successful outsourcing, the corporate management should get the buy-in from the execution team with organizational motivating factors. Also, the offsite team project manager should facilitate the team to have self commitment on its part of work and relationships to make it successful. 1.9.1 Case study #6: Company A has good outsourcing relationship with Company B and has executed a few projects successfully. Director of Engineering recommended one for his project team to use outsourcing and get benefited by it. Since the Director asked, the PM gave a chunk of activities to the offsite team for execution. The offsite team came up with requirement clarifications and asked for more documentation. The PM clarified the point at a very high level saying details should be developed by vendor. Project team completed the work as per their understanding and shared the deliverable for client review. Client pointed out several reworks and tried to fail the offsite team. In this environment the team failed after several attempts in multiple fragment of work and clearly the culprit was “no support from client team”. 1.10 Non controllable challenges It was seen that the outsourcing failed with few customers due to non controllable project factors like inflation, market boom and unjustifiable salary hike demands / attrition, new emerging competitors and pressure to reduce margins, mass resignations, political instabilities, government policies, new taxes, and natural calamities. This could be overcome by risk management best practices and produce less impact. 1.10.1 Case study #7: Company A decided to outsource product development and supply to the existing outsourcing partner Company X. The company X was asked to provide their capabilities on that domain. Since Company X doesn't have the capability to develop, it recommended the partnering company Y to deliver this project. The company Y provided an estimate and the client asked for fixed price contract to mitigate the risks. Since this was a first project to Company Y from Company A, it decided to take up this contract and started development. During execution, external factors changed. The dollar got depreciated, market was booming, attrition was high, expenses increased, increased tax hit the raw material costs. This hit the project badly and resulted in loss. Because of the team change the project schedule got delayed. This delay has impacted the product delivery of end client and client (Company A) ended up in paying a huge penalty. The relationship was hit miserably and ended prematurely. 8|Page
  • 9. 1.11 Cultural differences In outsourcing, multi cultural team is unavoidable. Even though it appears to be trivial, considerable amount of client dissatisfaction has been observed due to cultural differences. The cultural training should be provided to both teams involved in execution. The outsourcing organization should educate the client and offsite team with well known cultural issues and best practices. Periodical onsite visits to client team and inviting client team offsite has shown considerable improvement in the relationship. Team outings, commonly interested activities (like games, celebrations, cooking, etc) apart from work will always bring down the cultural differences. 1.11.1 Case study #8: The Company A from Japan decided to outsource some of its projects to Company X in India after several stages of evaluation. Japanese manager was appointed as the outsourcing manager to handle the offsite team. He had never stayed outside Japan, and hence didn’t prove to be efficient in handling a multi cultural team. Though the team was formed with proven team members at offsite, the project schedule slipped due to repeated rework on the modules with lot of cosmetic changes. The cultural barrier with executing team and client led this project to failure because of schedule slippage. In general, the outsourcing aware organizations would always provide sufficient training to the teams involved from different geographies and culture to cross the cultural barrier. 1.12 Lessons learnt – Best Practices 1. For new relationships, always educate the client about outsourcing processes, lessons learnt, and best practices. 2. Proactive gap analysis (process, organization structure, reporting, etc.,) and expected impact/suggestions to be provided to avoid repeating the lessons. 3. Top management of both the companies should follow-up closely and review the project at least once every month until the relationship is stabilized. This creates commitment among execution team for success. 4. The PgM/PM processes and best practices should be used as required for the project. 5. Exhaustive risk analysis and mitigation mechanisms should be in place during overselling. Educate the client as much as possible during sudden ramp up and have daily updates to keep him updated. 6. Conduct exhaustive trainings and workshops to train the team on customer specific domain/skill, including client actively for knowledge transfers on key domains Get buy-in from client by explaining the usefulness of developing expertise at offshore. 7. Check for all possible gaps in communication plan to avoid expectation mismatch. 9|Page
  • 10. 8. The client organization should be educated to understand the importance of openness and facilitate the offsite team to come forward and explain issues. 9. The client organization should plan outsourcing at organization level and educate the importance/outcome of outsourcing to execution teams and ensure the buy-in from execution team before starting the outsourcing. 10. The client organization should be mature enough to have realistic expectation on any value additions and commitments, irrespective of offsite team promises. 11. Exhaustive risk analysis and mitigation mechanisms should be in place for the uncontrollable factors. Some of the factors could be easily overcome by client awareness, right contracting model and best practices. 12. Cultural awareness and training should be provided to both the organizations do deal with multi cultural teams. 1.13 References Previously executed projects of all three authors for the past 15 years. 1.14 Conclusion To conclude, any outsourcing organization could use this paper to understand the commonly observed causes for failure and the best practices to overcome them. 1.15 About authors Akhilesh Bahuguna works for CMC Limited as Deputy General Manager and heads the Telecom vertical. He has vast experience in the development of technologies for communication networks and infrastructure in India, both from indigenous development and technology absorption & deployment from telecom majors like Alcatel, Ericsson, Lucent, Tellabs and others. Out of his 18+ years of experience, more than 10 years were spent in managing large and complex programs with a multisite workforce spread. He holds his Masters in Optoelectronics and Optical communications from Indian Institute of Technology, Delhi. 10 | P a g e
  • 11. Satya Sekhar Akkala works for CMC Limited as Senior Manager and heads the Railroad vertical. He has over 20 years of experience with 15+ years in Project / Program Management. He holds his Bachelors in Electronics and Communication Engineering from Nagarjuna University, Andra Pradesh. Kamalanaban Ganesan works for CMC Limited as Manager and leads a Telecom offshore development centre. He has over 12 years of experience with 6+ years in project / engineering Management. Prior to CMC, He worked with BEL, Shuttle Technology, SCM Microsystems, Sirius Semiconductors, and Force Computers. He holds his Bachelors in Electronics and Communication Engineering from University of Madras, Chennai. He is PMP certified since February 2007. 11 | P a g e