DEMOLITION WORKS

General Objective

C3001 / UNIT 4 / 1

: To understand demolition works in a safe and
economical manner

Specific Objectives :
At the end of this unit you should be able to:
•

understand demolition processes.

•

explain demolition methods.

•

describe safety precautions taken in demolition of building.

•

recognize machineries used in demolition.
DEMOLITION WORKS

4.0

C3001 / UNIT 4 / 2

INTRODUCTION

DO YOU KNOW?
With the increased number of fatal accidents caused by demolition of high rise
buildings, safety in demolition works becomes a great concern to both the Government
and the public. The reasons leading to such horrible accidents are many, of which the lack
of planning and supervision are the major ones.

Following the issuance of various practice notes to Authorized Persons,
Registered Structural Engineers and Contractors, regarding the safety measures for
demolition works for the protection of the Public, the Building Department has recently
prepared a draft of the Code of Practice for Demolition of Building.
DEMOLITION WORKS

C3001 / UNIT 4 / 3

It is intended to be followed by specialist demolition contractors for the
demolition of various building works in Malaysia, aiming at minimizing the risks of
injury to persons and damage to properties, the risks of endangering the health and safety
of site personnel and damage to the environment in the vicinity.

The Code sets out the guidelines for demolition of the buildings from roof level to
ground level and the demolition of basement, underground tanks, as well ascertain
common civil engineering structures, but not major civil engineering works such as
underpinning, excavation, highway bridges, dams and nuclear reactors.

General guidelines are also given for the design of temporary works and checking of
temporary structures. The code covers common methods typically used in the demolition
of buildings in Malaysia, but exhaustive guidelines for all methods are not given. The
code does not intend to discourage any other demolition methods, which may be used
subject to approval. The content of the unit includes the following topics:

•

Demolition Processes

•

Demolition Methods

•

Machinery used in demolition
Based on the Oxford Fajar dictionary demolition
means to “ pull to or knock down a building ”,
and another meaning for demolition is a “ highly
skilled and dangerous activity in terms of
damage to life and property”.

4.1

Rina , what is the meaning
of “Demolition” ?

Demolition Tariffs And Reasons For Demolition
C3001 / UNIT 4 / 4

DEMOLITION WORKS
DEMOLITION WORKS

C3001 / UNIT 4 / 5

Does anybody know the causes of
demolition?

??????
No…sir

4.2

Causes Of Demolition

It’s ok, let me tell you about the causes
of demolition, the example are:
Commercials
Aesthetic
Human health
Human safety
Building new buildings
Renovation
Structure problems
Environment ( near slopes )
Population density
Adjacent buildings
Traffic
DEMOLITION WORKS

C3001 / UNIT 4 / 6

Let us list together the
demolition processes

Demolition Processes
1. Before demolition
a. identify site locations, special site restrictions and impact of special
buildings
b. identify buildings/structures to be demolished
c. verify dimensions of site and building
d. identify hoardings requirements
e. verify building construction, types of materials
f. verify existing fixtures
g. verify the building use
h. verify utilities location
i. prepare demolition schedule
j. test and remove hazardous materials
DEMOLITION WORKS

C3001 / UNIT 4 / 7

k. identify the safety measures for protection of the public

l. arrange for debris handling
m. prepare demolition plan
n. prepare stability report with calculations
o. apply consent (also submit supervision plan, names and details of
Technically Competent Persons.

2. During demolition
a. install site precautionary measures
b. remove hazardous materials
c. inform site personnel the specifics and precautionary measures
d. establish emergency access
e. establish line of communication to supervisor
f. progress work in accordance with method statements approved.
g. remove debris to avoid accumulation
h. control dust emission
i. adequate supervision
j. protect party walls
k. ensure workers follow safety procedures
l. ensure machines and equipment are well maintained.
m. provide security
n. schedule regular inspection and maintenance of scaffolding.
DEMOLITION WORKS

C3001 / UNIT 4 / 8

3. After demolition
a. clear debris and level site
b. secure boundaries
c. protect all excavations
d. for sloping site and/or site with retaining wall
i. seal ground surface
ii. provide surface drainage
iii. provide demolition plan to the foundation contractor for
maintaining the supports.

Let’s answer the questions
in the next activity to test
our knowledge.
DEMOLITION WORKS

C3001 / UNIT 4 / 9

State whether the following questions are True
or False.
1.

Commercials, aesthetic, human
health, human safety, build new
building are the example of the causes
of demolition.

2.

Demolition processes have 3
situations; it is before, during and
after.

3.

Demolition means to “ pull to or
knock down a building ”, and another
meaning for demolition is a “ highly
skilled and dangerous activity in terms
of damage to life and property”.
DEMOLITION WORKS

C3001 / UNIT 4 / 10
DEMOLITION WORKS

C3001 / UNIT 4 / 11

1.
2.

True

3.

4.2

True

True

Types And Ways Of Demolition
In many circumstances, buildings and structures should be demolished in the

reverse order to their erection; although where partial demolition is involved a more
careful evaluation of the nature of the effects of the demolition is necessary.
Normally, the demolition contractor is able to adopt a method of work which:-
DEMOLITION WORKS



C3001 / UNIT 4 / 12

gradually reduces the height of the building; or arranges the deliberate controlled
collapse of the building or structure so that work can be completed at ground
level.

The choice of demolition technique will depend on the nature of the building or
structure and its environment. Risks to the public, operatives involved in the demolition
process and adjacent structures and buildings should be considered.
Demolition techniques may be categorized as:•

Piecemeal demolition, using hand-held tools or machines, to reduce the height of
the building or structure gradually;

•

Deliberate controlled collapse, demolition to be completed at ground level.

4.2.1 Manual
Demolition of buildings or structure by hand-held tools such as electric or
pneumatic breakers, sometimes as a preliminary to using other methods, should be
carried out, where practicable, in the reverse order to the original construction sequence.
Lifting appliances may be necessary to hold larger structural members during cutting and
for lowering severed structural members and other debris. Chutes may be used to
DEMOLITION WORKS

C3001 / UNIT 4 / 13

discharge debris into a vehicle or hopper. Foundations would normally be grubbed up by
excavation machines.

Figure 4.1 demolition by hand

4.2.2 Machinery’s Components
Simple roof structures supported on wall plates should normally be demolished to
the level of wall plates by hand, but if this may involve unsafe working, then demolition
totally by machine may be appropriate.
DEMOLITION WORKS

C3001 / UNIT 4 / 14

Where a building that is to be demolished by machine is attached to another
structure, the two properties should be separated by the use of hand methods before the
main demolition process begins.
When any part of a building is being demolished by a balling machine, pusher
arm or similar equipment, only the machine operator and banks man should be allowed
close to the working area. The cabs of all machines should be strong enough to protect
the operator against the fall of debris. In particular, the windscreen and roof light should
be of shatterproof material and guarded by a grille of steel bars or a substantial mesh.

Figure 4.2

4.3.2.1

Demolition by machinery’s components

Balling machine
Balling machines generally comprise a drag-line type crawler chassis fitted with a

lattice crane jib. The demolition ball, with a steel anti-spin device, is suspended from the
lifting rope and swung by the drag rope.
DEMOLITION WORKS

C3001 / UNIT 4 / 15

Balling should only be carried out by skilled operatives under the control of
experienced supervisors using well maintained machines adequate for the proposed duty
and standing on a firm, level base.
The manufacturer should be consulted before a machine is used for balling to
establish any restrictions on the type or length of jib or the weight of the ball.
Balling operations subject cranes to dynamic stresses and wear, and the ball
chosen should have the minimum weight necessary for effective use. In many cases,
demolition balls of quite light weight will be adequate.
Floors should be demolished by dropping the ball on the highest remaining floor
and allowing the debris to fall inside the building. The debris should be removed
regularly to prevent excessive weight accumulating on the lower floors.
Walls or columns can be demolished either by swinging the ball in line with the
stationary jib, using the drag rope, or by slewing the jib. The ball should not swing by
derricking the jib.
DEMOLITION WORKS

C3001 / UNIT 4 / 16

Figure 4.3

Demolition ball

Figure 4.4

Demolition ball
DEMOLITION WORKS

C3001 / UNIT 4 / 17

Figure 4.5

Ball crane

Figure 4.6

Ball crane

Figure 4.7

Ball crane
DEMOLITION WORKS

4.3.2.2

C3001 / UNIT 4 / 18

Hydraulic pusher arm
Articulated, hydraulically-powered pusher-arm machines are normally mounted

on a tracked or wheeled chassis, and have a toothed plate or hook for applying for
applying a horizontal force to a wall. The machine should stand on a firm level base and
apply force by a controlled movement of the pusher arm.

Figure 4.8

Figure 4.9

Mini Hydraulic Breaker

Hydraulic Breaker

Figure 4.10

Hydraulic Mobile crane
( 20 T - 200 T )
DEMOLITION WORKS

4.3.2.3

C3001 / UNIT 4 / 19

Long arm excavator

Figure 4.11

Long Arm Excavator

Figure 4.12

Long Arm Excavator
DEMOLITION WORKS

4.3.2.4

C3001 / UNIT 4 / 20

Dynamite
If explosives are to be used for demolition, the planning and execution, include

pre-weakening, should be under the control of a person competent in these techniques.
For large demolition, the competent person is likely to be an experienced explosive
engineer; for smaller work, a shot-firer may be sufficient.
When the use of explosives is contemplated, it is usual to employ a technique that
will ensure the total demolition of the whole building by staging a controlled collapse.
The explosive charges are set and fired in a sequence that will weaken the structure in
such a way that the building collapses in upon itself.
Although we tend to think of explosives as devices producing spectacular bomblike explosions, the use of non-explosive "explosives" is now at an advanced stage. These
non-explosive techniques are essentially expanding charges that achieve the same results
as explosives but without the noise and initial devastating blast.

“Did you understand all the information in this

unit? If you have difficulties go through the notes
again. Now let us answer the question in the next
activity”.
DEMOLITION WORKS

C3001 / UNIT 4 / 21

Complete the sentences below by providing the
correct answers.
1.

Demolition means…………………..

2.

Demolition techniques may be categorized
as ………………

3.

Manual and Machinery components are
………………………

4.

List the machinery’s components. Write
your answers in the space below.
a) ………………………….
b) ………………………….
c) …………………………..
d) …………………………..

5.

Who should be allowed close to the
working area?
DEMOLITION WORKS

C3001 / UNIT 4 / 22

1.

Based on the Oxford Fajar dictionary Demolition means
to “pull or knock down a building”, and another meaning
for demolition is a “highly skilled and dangerous activity
in terms of damage to life and property”.

2.

Demolition techniques may be categorized as:Piecemeal demolition, using hand-held tools or machines,
to reduce the height of the building or structure gradually;

•

•

Deliberate controlled collapse,
completed at ground level.

demolition

to

be
DEMOLITION WORKS

3. Manual and machinery components are ways of
demolition
4. a) balling machine

b) hydraulic pusher arm
long arm excavator
dynamite
5.

The machine operator and banks man should be
allowed closed to the working area

C3001 / UNIT 4 / 23
DEMOLITION WORKS

C3001 / UNIT 4 / 24

Answer the following questions:
1.

Give FIVE of the most important safety precautions which must be
taken into account before starting a demolition project to prevent your
actions from undermining the structural integrity of the building?

2.

Give THREE proper attire and tools needed to ensure a safe
environment in a demolition project?

3.

Give FIVE steps that need to be taken to ensure the homeowner’s
safety.

4.

Explain how to schedule the best time to start a demolition project.

5.

List three examples of Machinery’s Components.
DEMOLITION WORKS

C3001 / UNIT 4 / 25

ANSWER NO. 1
•

Always know exactly what it is you're about to remove. Before you move or
remove anything, always check to see what's behind it, below it and what it might
support.

•

Never assume that a structural member you're about to remove doesn't support
anything

•

When removing framing that is near electrical wiring, shut off the electricity, even
if you're not removing the wiring. Do the same for any plumbing or gas lines. A
single nick with a saw blade or a drill can cause disastrous results.

•

When removing electrical wiring, turn off the circuit breaker or remove the fuse
controlling the circuit you're working on, and then post a note on the electrical
panel warning others not to turn it back on.

•

Never attempt to work on a gas or water line without first making certain it has
been shut off. Also, do not assume that a shutoff valve works - after closing the
valve, test the line to be absolutely sure it's off.
DEMOLITION WORKS

C3001 / UNIT 4 / 26

ANSWER NO. 2
•

Use only the proper tool that is designed for a particular task - don't improvise. If
you are prying up a board, use a heavy pry, not a big screwdriver. On the other
hand, use a screwdriver to remove a screw; don't yank it out with a pry bar.

•

If you don't have the proper tool for the job, don't proceed until you are able to
buy or rent one. If you need a jack to lift a heavy beam, get one - don't try to rig
up a couple of 2 X 4 as a lever. If scaffolding is required to work safely at a given
height, get some and take the time to set it up correctly - balancing a 2 X 12 on a
couple of ladders is an invitation for disaster.

•

Wear the appropriate clothings. Demolition work requires long pants, a heavy
shirt, and solid shoes - allowing your crew to work in shorts and tennis hoes can
net you a serious fine. Wear gloves, and always wear eye protection. If anyone is
working above you, or if there is any potential for falling objects, make hard hats
mandatory.
DEMOLITION WORKS

C3001 / UNIT 4 / 27

ANSWER NO. 3
•

Secure all tools at lunchtime, at the end of the day, and during absence from the
job site, cords need to be unplugged and sharp tools placed in a safe and secure
enclosure. Remember that children are fascinated with construction sites, and this
curiosity can lead to serious injuries.

•

Motorized equipment needs to be securely locked and the keys placed in a safe
locked area.

•

Take down ladders at the end of the day. This includes covering holes in the floor
and placing temporary barricades over window and door openings.

•

If you cannot cover or otherwise close off an area - such as an open trench that is
still in use - ring the area with caution tape and place lighted barricades at regular
intervals as a warning.

•

Cover holes and other danger spots.
DEMOLITION WORKS

C3001 / UNIT 4 / 28

ANSWER NO. 4
•

In most cases, demolition work is best left until the last possible moment in order
to help avoid weather and security problems. The addition should be completely
framed, roofed, and enclosed with siding, and exterior windows and doors should
be installed, before the walls connecting the addition with the existing house
should be removed.

•

Try to work in stages as much as possible, again doing only as much

demolition work as necessary for a particular phase of the construction. You may,
for example, need to remove a small section of siding at the base of the wall in
order to align the new foundation with the old one, or perhaps take down some
drywall to line up the new ceiling joints.

•

Even if it's all coming down eventually, it's best to remove only what you

need to accomplish the task you are working on at the moment.

ANSWER NO. 5
•

Long arm excavator

•

Hydraulic pusher arm

•

Balling machine

Weitere ähnliche Inhalte

Was ist angesagt?

OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structuresAnkit Patel
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.Chintan Varia
 
Building demolition techniques and methods
Building demolition techniques and methodsBuilding demolition techniques and methods
Building demolition techniques and methodsmahmoodanas
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingEdwinJacob5
 
DEMOLITION OF BUILDING
DEMOLITION OF BUILDINGDEMOLITION OF BUILDING
DEMOLITION OF BUILDINGshubhajitdua
 
Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Emma Attwood
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler houseAnatoliZ
 
Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan RPNarwade
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAglaia Connect
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Girish Singh
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing buildingKishor Ade
 

Was ist angesagt? (20)

OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
Ch 5 demolition of structures
Ch 5 demolition of structuresCh 5 demolition of structures
Ch 5 demolition of structures
 
Fully Demolition
Fully Demolition Fully Demolition
Fully Demolition
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 
Demolition
 Demolition Demolition
Demolition
 
Building demolition techniques and methods
Building demolition techniques and methodsBuilding demolition techniques and methods
Building demolition techniques and methods
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
DEMOLITION OF BUILDING
DEMOLITION OF BUILDINGDEMOLITION OF BUILDING
DEMOLITION OF BUILDING
 
Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler house
 
Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan
 
Demolition of building
Demolition of building Demolition of building
Demolition of building
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing building
 
Presentation-Demolition-Yıkım
Presentation-Demolition-YıkımPresentation-Demolition-Yıkım
Presentation-Demolition-Yıkım
 

Andere mochten auch

Building services chapter 1
Building services chapter 1Building services chapter 1
Building services chapter 1Noor Lida Jusoh
 
Building Service Chapter 2
Building Service Chapter 2Building Service Chapter 2
Building Service Chapter 2Izam Lukman
 
Building Service Chapter 6
Building Service Chapter 6Building Service Chapter 6
Building Service Chapter 6Izam Lukman
 
Building Service Chapter 1
Building Service Chapter 1Building Service Chapter 1
Building Service Chapter 1Izam Lukman
 
amalan Bismillah 20,9,6,5
amalan Bismillah 20,9,6,5amalan Bismillah 20,9,6,5
amalan Bismillah 20,9,6,5Natalie Ulza
 
miraculous discovery
miraculous discoverymiraculous discovery
miraculous discoveryNatalie Ulza
 
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)Natalie Ulza
 
Sistem Pengagihan
Sistem PengagihanSistem Pengagihan
Sistem Pengagihanaman zaki
 
Building Service Chapter 5
Building Service Chapter 5Building Service Chapter 5
Building Service Chapter 5Izam Lukman
 
enviromental pollution & air pollution
enviromental pollution & air pollutionenviromental pollution & air pollution
enviromental pollution & air pollutionsarkawtn
 

Andere mochten auch (20)

Bs bab 2
Bs bab 2Bs bab 2
Bs bab 2
 
Bs bab 3
Bs bab 3Bs bab 3
Bs bab 3
 
Bs bab 1
Bs bab 1Bs bab 1
Bs bab 1
 
Air cond
Air condAir cond
Air cond
 
Eskalator
EskalatorEskalator
Eskalator
 
Building services chapter 1
Building services chapter 1Building services chapter 1
Building services chapter 1
 
Lift
LiftLift
Lift
 
Building Service Chapter 2
Building Service Chapter 2Building Service Chapter 2
Building Service Chapter 2
 
Building Service Chapter 6
Building Service Chapter 6Building Service Chapter 6
Building Service Chapter 6
 
Building Service Chapter 1
Building Service Chapter 1Building Service Chapter 1
Building Service Chapter 1
 
Building services
Building servicesBuilding services
Building services
 
amalan Bismillah 20,9,6,5
amalan Bismillah 20,9,6,5amalan Bismillah 20,9,6,5
amalan Bismillah 20,9,6,5
 
miraculous discovery
miraculous discoverymiraculous discovery
miraculous discovery
 
BOD TEST
BOD TESTBOD TEST
BOD TEST
 
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)
PANDUAN LAPORAN AKHIR LATIHAN INDUSTRI 2014 (PMM)
 
TURBIDITY TEST
TURBIDITY TESTTURBIDITY TEST
TURBIDITY TEST
 
Sistem Pengagihan
Sistem PengagihanSistem Pengagihan
Sistem Pengagihan
 
Escalator
EscalatorEscalator
Escalator
 
Building Service Chapter 5
Building Service Chapter 5Building Service Chapter 5
Building Service Chapter 5
 
enviromental pollution & air pollution
enviromental pollution & air pollutionenviromental pollution & air pollution
enviromental pollution & air pollution
 

Ähnlich wie Bs bab 4

Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptxAnanthakumar75
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATAbhinav Rawat
 
BUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTBUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTemily9199
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAnimesh1714013
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKKHUSHBU SHAH
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHA Makwana
 
demolition of building
demolition of buildingdemolition of building
demolition of buildingtushar garg
 
Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction reportClara Lee
 
Building Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERINGBuilding Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERINGCESatvirSingh1
 
Construction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesConstruction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesMuizz Anibire
 
civil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfcivil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfpramodKumarsahani1
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and ControlsAbbas Tahir
 

Ähnlich wie Bs bab 4 (20)

Dempolition notes Part 1.pdf
Dempolition notes Part 1.pdfDempolition notes Part 1.pdf
Dempolition notes Part 1.pdf
 
Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptx
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
 
Rishabh kumar
Rishabh kumarRishabh kumar
Rishabh kumar
 
BUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORTBUILDING CONSTRUCTION REPORT
BUILDING CONSTRUCTION REPORT
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
Demolition.pptx
Demolition.pptxDemolition.pptx
Demolition.pptx
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 
Demolition of Structure ppt.pptx
Demolition of Structure ppt.pptxDemolition of Structure ppt.pptx
Demolition of Structure ppt.pptx
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
demolition of building
demolition of buildingdemolition of building
demolition of building
 
Buildng construction report
Buildng construction reportBuildng construction report
Buildng construction report
 
13
1313
13
 
Building Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERINGBuilding Industrial Training report for CIVIL ENGINEERING
Building Industrial Training report for CIVIL ENGINEERING
 
Construction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesConstruction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using Explosives
 
civil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdfcivil DEMOLITION OF BUILDING ppt.pdf
civil DEMOLITION OF BUILDING ppt.pdf
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and Controls
 

Mehr von Natalie Ulza

4.1 planning schedulling
4.1 planning schedulling4.1 planning schedulling
4.1 planning schedullingNatalie Ulza
 
3.6 understand of construction policies
3.6 understand of construction policies3.6 understand of construction policies
3.6 understand of construction policiesNatalie Ulza
 
3.3.1 planking strutting
3.3.1 planking strutting3.3.1 planking strutting
3.3.1 planking struttingNatalie Ulza
 
3.2.3 site diary dan lawatan tapak
3.2.3 site diary dan lawatan tapak3.2.3 site diary dan lawatan tapak
3.2.3 site diary dan lawatan tapakNatalie Ulza
 
3.1 the usage of bar chart
3.1 the usage of bar chart3.1 the usage of bar chart
3.1 the usage of bar chartNatalie Ulza
 
2.2 resources of project management
2.2 resources of project management2.2 resources of project management
2.2 resources of project managementNatalie Ulza
 
2.1 concept of leader ship
2.1 concept of leader ship2.1 concept of leader ship
2.1 concept of leader shipNatalie Ulza
 
1.1.4 interpret project manager
1.1.4 interpret  project manager1.1.4 interpret  project manager
1.1.4 interpret project managerNatalie Ulza
 
1.1 concepr of management
1.1 concepr of management1.1 concepr of management
1.1 concepr of managementNatalie Ulza
 
Microsoft project 1
Microsoft project 1Microsoft project 1
Microsoft project 1Natalie Ulza
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1Natalie Ulza
 
Center of pressure and hydrostatic force on a submerged body rev
Center of pressure and hydrostatic force on a submerged body revCenter of pressure and hydrostatic force on a submerged body rev
Center of pressure and hydrostatic force on a submerged body revNatalie Ulza
 
environment pollution topic 2-water pollution 2
environment pollution topic 2-water pollution 2environment pollution topic 2-water pollution 2
environment pollution topic 2-water pollution 2Natalie Ulza
 
environment pollution topic 1-public health
environment pollution topic 1-public healthenvironment pollution topic 1-public health
environment pollution topic 1-public healthNatalie Ulza
 

Mehr von Natalie Ulza (20)

PENEMUAN AJAIB
PENEMUAN AJAIBPENEMUAN AJAIB
PENEMUAN AJAIB
 
4.1 planning schedulling
4.1 planning schedulling4.1 planning schedulling
4.1 planning schedulling
 
3.6 understand of construction policies
3.6 understand of construction policies3.6 understand of construction policies
3.6 understand of construction policies
 
3.4 scaffolding
3.4 scaffolding3.4 scaffolding
3.4 scaffolding
 
3.3.1 planking strutting
3.3.1 planking strutting3.3.1 planking strutting
3.3.1 planking strutting
 
3.2.3 site diary dan lawatan tapak
3.2.3 site diary dan lawatan tapak3.2.3 site diary dan lawatan tapak
3.2.3 site diary dan lawatan tapak
 
3.1 the usage of bar chart
3.1 the usage of bar chart3.1 the usage of bar chart
3.1 the usage of bar chart
 
2.2 resources of project management
2.2 resources of project management2.2 resources of project management
2.2 resources of project management
 
2.1 concept of leader ship
2.1 concept of leader ship2.1 concept of leader ship
2.1 concept of leader ship
 
1.1.4 interpret project manager
1.1.4 interpret  project manager1.1.4 interpret  project manager
1.1.4 interpret project manager
 
1.1 concepr of management
1.1 concepr of management1.1 concepr of management
1.1 concepr of management
 
Microsoft project 1
Microsoft project 1Microsoft project 1
Microsoft project 1
 
Hydrostatic force
Hydrostatic forceHydrostatic force
Hydrostatic force
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Center of pressure and hydrostatic force on a submerged body rev
Center of pressure and hydrostatic force on a submerged body revCenter of pressure and hydrostatic force on a submerged body rev
Center of pressure and hydrostatic force on a submerged body rev
 
Mangan test
Mangan testMangan test
Mangan test
 
JET JAR TEST
JET JAR TESTJET JAR TEST
JET JAR TEST
 
FERUM TEST
FERUM TESTFERUM TEST
FERUM TEST
 
environment pollution topic 2-water pollution 2
environment pollution topic 2-water pollution 2environment pollution topic 2-water pollution 2
environment pollution topic 2-water pollution 2
 
environment pollution topic 1-public health
environment pollution topic 1-public healthenvironment pollution topic 1-public health
environment pollution topic 1-public health
 

Kürzlich hochgeladen

3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptxmary850239
 
Vani Magazine - Quarterly Magazine of Seshadripuram Educational Trust
Vani Magazine - Quarterly Magazine of Seshadripuram Educational TrustVani Magazine - Quarterly Magazine of Seshadripuram Educational Trust
Vani Magazine - Quarterly Magazine of Seshadripuram Educational TrustSavipriya Raghavendra
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapitolTechU
 
Diploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfDiploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfMohonDas
 
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfP4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfYu Kanazawa / Osaka University
 
The Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsThe Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsEugene Lysak
 
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRATanmoy Mishra
 
10 Topics For MBA Project Report [HR].pdf
10 Topics For MBA Project Report [HR].pdf10 Topics For MBA Project Report [HR].pdf
10 Topics For MBA Project Report [HR].pdfJayanti Pande
 
Protein Structure - threading Protein modelling pptx
Protein Structure - threading Protein modelling pptxProtein Structure - threading Protein modelling pptx
Protein Structure - threading Protein modelling pptxvidhisharma994099
 
In - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxIn - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxAditiChauhan701637
 
Quality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICEQuality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICESayali Powar
 
How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17Celine George
 
How to Add Existing Field in One2Many Tree View in Odoo 17
How to Add Existing Field in One2Many Tree View in Odoo 17How to Add Existing Field in One2Many Tree View in Odoo 17
How to Add Existing Field in One2Many Tree View in Odoo 17Celine George
 
Department of Health Compounder Question ‍Solution 2022.pdf
Department of Health Compounder Question ‍Solution 2022.pdfDepartment of Health Compounder Question ‍Solution 2022.pdf
Department of Health Compounder Question ‍Solution 2022.pdfMohonDas
 
How to Make a Field read-only in Odoo 17
How to Make a Field read-only in Odoo 17How to Make a Field read-only in Odoo 17
How to Make a Field read-only in Odoo 17Celine George
 
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptxClinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptxraviapr7
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17Celine George
 
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...M56BOOKSTORE PRODUCT/SERVICE
 

Kürzlich hochgeladen (20)

3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx3.26.24 Race, the Draft, and the Vietnam War.pptx
3.26.24 Race, the Draft, and the Vietnam War.pptx
 
Prelims of Kant get Marx 2.0: a general politics quiz
Prelims of Kant get Marx 2.0: a general politics quizPrelims of Kant get Marx 2.0: a general politics quiz
Prelims of Kant get Marx 2.0: a general politics quiz
 
Vani Magazine - Quarterly Magazine of Seshadripuram Educational Trust
Vani Magazine - Quarterly Magazine of Seshadripuram Educational TrustVani Magazine - Quarterly Magazine of Seshadripuram Educational Trust
Vani Magazine - Quarterly Magazine of Seshadripuram Educational Trust
 
CapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptxCapTechU Doctoral Presentation -March 2024 slides.pptx
CapTechU Doctoral Presentation -March 2024 slides.pptx
 
Diploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdfDiploma in Nursing Admission Test Question Solution 2023.pdf
Diploma in Nursing Admission Test Question Solution 2023.pdf
 
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdfP4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
P4C x ELT = P4ELT: Its Theoretical Background (Kanazawa, 2024 March).pdf
 
The Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George WellsThe Stolen Bacillus by Herbert George Wells
The Stolen Bacillus by Herbert George Wells
 
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRADUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
DUST OF SNOW_BY ROBERT FROST_EDITED BY_ TANMOY MISHRA
 
10 Topics For MBA Project Report [HR].pdf
10 Topics For MBA Project Report [HR].pdf10 Topics For MBA Project Report [HR].pdf
10 Topics For MBA Project Report [HR].pdf
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Protein Structure - threading Protein modelling pptx
Protein Structure - threading Protein modelling pptxProtein Structure - threading Protein modelling pptx
Protein Structure - threading Protein modelling pptx
 
In - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptxIn - Vivo and In - Vitro Correlation.pptx
In - Vivo and In - Vitro Correlation.pptx
 
Quality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICEQuality Assurance_GOOD LABORATORY PRACTICE
Quality Assurance_GOOD LABORATORY PRACTICE
 
How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17How to Add a New Field in Existing Kanban View in Odoo 17
How to Add a New Field in Existing Kanban View in Odoo 17
 
How to Add Existing Field in One2Many Tree View in Odoo 17
How to Add Existing Field in One2Many Tree View in Odoo 17How to Add Existing Field in One2Many Tree View in Odoo 17
How to Add Existing Field in One2Many Tree View in Odoo 17
 
Department of Health Compounder Question ‍Solution 2022.pdf
Department of Health Compounder Question ‍Solution 2022.pdfDepartment of Health Compounder Question ‍Solution 2022.pdf
Department of Health Compounder Question ‍Solution 2022.pdf
 
How to Make a Field read-only in Odoo 17
How to Make a Field read-only in Odoo 17How to Make a Field read-only in Odoo 17
How to Make a Field read-only in Odoo 17
 
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptxClinical Pharmacy  Introduction to Clinical Pharmacy, Concept of clinical pptx
Clinical Pharmacy Introduction to Clinical Pharmacy, Concept of clinical pptx
 
How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17How to Show Error_Warning Messages in Odoo 17
How to Show Error_Warning Messages in Odoo 17
 
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...KARNAADA.pptx  made by -  saransh dwivedi ( SD ) -  SHALAKYA TANTRA - ENT - 4...
KARNAADA.pptx made by - saransh dwivedi ( SD ) - SHALAKYA TANTRA - ENT - 4...
 

Bs bab 4

  • 1. DEMOLITION WORKS General Objective C3001 / UNIT 4 / 1 : To understand demolition works in a safe and economical manner Specific Objectives : At the end of this unit you should be able to: • understand demolition processes. • explain demolition methods. • describe safety precautions taken in demolition of building. • recognize machineries used in demolition.
  • 2. DEMOLITION WORKS 4.0 C3001 / UNIT 4 / 2 INTRODUCTION DO YOU KNOW? With the increased number of fatal accidents caused by demolition of high rise buildings, safety in demolition works becomes a great concern to both the Government and the public. The reasons leading to such horrible accidents are many, of which the lack of planning and supervision are the major ones. Following the issuance of various practice notes to Authorized Persons, Registered Structural Engineers and Contractors, regarding the safety measures for demolition works for the protection of the Public, the Building Department has recently prepared a draft of the Code of Practice for Demolition of Building.
  • 3. DEMOLITION WORKS C3001 / UNIT 4 / 3 It is intended to be followed by specialist demolition contractors for the demolition of various building works in Malaysia, aiming at minimizing the risks of injury to persons and damage to properties, the risks of endangering the health and safety of site personnel and damage to the environment in the vicinity. The Code sets out the guidelines for demolition of the buildings from roof level to ground level and the demolition of basement, underground tanks, as well ascertain common civil engineering structures, but not major civil engineering works such as underpinning, excavation, highway bridges, dams and nuclear reactors. General guidelines are also given for the design of temporary works and checking of temporary structures. The code covers common methods typically used in the demolition of buildings in Malaysia, but exhaustive guidelines for all methods are not given. The code does not intend to discourage any other demolition methods, which may be used subject to approval. The content of the unit includes the following topics: • Demolition Processes • Demolition Methods • Machinery used in demolition
  • 4. Based on the Oxford Fajar dictionary demolition means to “ pull to or knock down a building ”, and another meaning for demolition is a “ highly skilled and dangerous activity in terms of damage to life and property”. 4.1 Rina , what is the meaning of “Demolition” ? Demolition Tariffs And Reasons For Demolition C3001 / UNIT 4 / 4 DEMOLITION WORKS
  • 5. DEMOLITION WORKS C3001 / UNIT 4 / 5 Does anybody know the causes of demolition? ?????? No…sir 4.2 Causes Of Demolition It’s ok, let me tell you about the causes of demolition, the example are: Commercials Aesthetic Human health Human safety Building new buildings Renovation Structure problems Environment ( near slopes ) Population density Adjacent buildings Traffic
  • 6. DEMOLITION WORKS C3001 / UNIT 4 / 6 Let us list together the demolition processes Demolition Processes 1. Before demolition a. identify site locations, special site restrictions and impact of special buildings b. identify buildings/structures to be demolished c. verify dimensions of site and building d. identify hoardings requirements e. verify building construction, types of materials f. verify existing fixtures g. verify the building use h. verify utilities location i. prepare demolition schedule j. test and remove hazardous materials
  • 7. DEMOLITION WORKS C3001 / UNIT 4 / 7 k. identify the safety measures for protection of the public l. arrange for debris handling m. prepare demolition plan n. prepare stability report with calculations o. apply consent (also submit supervision plan, names and details of Technically Competent Persons. 2. During demolition a. install site precautionary measures b. remove hazardous materials c. inform site personnel the specifics and precautionary measures d. establish emergency access e. establish line of communication to supervisor f. progress work in accordance with method statements approved. g. remove debris to avoid accumulation h. control dust emission i. adequate supervision j. protect party walls k. ensure workers follow safety procedures l. ensure machines and equipment are well maintained. m. provide security n. schedule regular inspection and maintenance of scaffolding.
  • 8. DEMOLITION WORKS C3001 / UNIT 4 / 8 3. After demolition a. clear debris and level site b. secure boundaries c. protect all excavations d. for sloping site and/or site with retaining wall i. seal ground surface ii. provide surface drainage iii. provide demolition plan to the foundation contractor for maintaining the supports. Let’s answer the questions in the next activity to test our knowledge.
  • 9. DEMOLITION WORKS C3001 / UNIT 4 / 9 State whether the following questions are True or False. 1. Commercials, aesthetic, human health, human safety, build new building are the example of the causes of demolition. 2. Demolition processes have 3 situations; it is before, during and after. 3. Demolition means to “ pull to or knock down a building ”, and another meaning for demolition is a “ highly skilled and dangerous activity in terms of damage to life and property”.
  • 11. DEMOLITION WORKS C3001 / UNIT 4 / 11 1. 2. True 3. 4.2 True True Types And Ways Of Demolition In many circumstances, buildings and structures should be demolished in the reverse order to their erection; although where partial demolition is involved a more careful evaluation of the nature of the effects of the demolition is necessary. Normally, the demolition contractor is able to adopt a method of work which:-
  • 12. DEMOLITION WORKS  C3001 / UNIT 4 / 12 gradually reduces the height of the building; or arranges the deliberate controlled collapse of the building or structure so that work can be completed at ground level. The choice of demolition technique will depend on the nature of the building or structure and its environment. Risks to the public, operatives involved in the demolition process and adjacent structures and buildings should be considered. Demolition techniques may be categorized as:• Piecemeal demolition, using hand-held tools or machines, to reduce the height of the building or structure gradually; • Deliberate controlled collapse, demolition to be completed at ground level. 4.2.1 Manual Demolition of buildings or structure by hand-held tools such as electric or pneumatic breakers, sometimes as a preliminary to using other methods, should be carried out, where practicable, in the reverse order to the original construction sequence. Lifting appliances may be necessary to hold larger structural members during cutting and for lowering severed structural members and other debris. Chutes may be used to
  • 13. DEMOLITION WORKS C3001 / UNIT 4 / 13 discharge debris into a vehicle or hopper. Foundations would normally be grubbed up by excavation machines. Figure 4.1 demolition by hand 4.2.2 Machinery’s Components Simple roof structures supported on wall plates should normally be demolished to the level of wall plates by hand, but if this may involve unsafe working, then demolition totally by machine may be appropriate.
  • 14. DEMOLITION WORKS C3001 / UNIT 4 / 14 Where a building that is to be demolished by machine is attached to another structure, the two properties should be separated by the use of hand methods before the main demolition process begins. When any part of a building is being demolished by a balling machine, pusher arm or similar equipment, only the machine operator and banks man should be allowed close to the working area. The cabs of all machines should be strong enough to protect the operator against the fall of debris. In particular, the windscreen and roof light should be of shatterproof material and guarded by a grille of steel bars or a substantial mesh. Figure 4.2 4.3.2.1 Demolition by machinery’s components Balling machine Balling machines generally comprise a drag-line type crawler chassis fitted with a lattice crane jib. The demolition ball, with a steel anti-spin device, is suspended from the lifting rope and swung by the drag rope.
  • 15. DEMOLITION WORKS C3001 / UNIT 4 / 15 Balling should only be carried out by skilled operatives under the control of experienced supervisors using well maintained machines adequate for the proposed duty and standing on a firm, level base. The manufacturer should be consulted before a machine is used for balling to establish any restrictions on the type or length of jib or the weight of the ball. Balling operations subject cranes to dynamic stresses and wear, and the ball chosen should have the minimum weight necessary for effective use. In many cases, demolition balls of quite light weight will be adequate. Floors should be demolished by dropping the ball on the highest remaining floor and allowing the debris to fall inside the building. The debris should be removed regularly to prevent excessive weight accumulating on the lower floors. Walls or columns can be demolished either by swinging the ball in line with the stationary jib, using the drag rope, or by slewing the jib. The ball should not swing by derricking the jib.
  • 16. DEMOLITION WORKS C3001 / UNIT 4 / 16 Figure 4.3 Demolition ball Figure 4.4 Demolition ball
  • 17. DEMOLITION WORKS C3001 / UNIT 4 / 17 Figure 4.5 Ball crane Figure 4.6 Ball crane Figure 4.7 Ball crane
  • 18. DEMOLITION WORKS 4.3.2.2 C3001 / UNIT 4 / 18 Hydraulic pusher arm Articulated, hydraulically-powered pusher-arm machines are normally mounted on a tracked or wheeled chassis, and have a toothed plate or hook for applying for applying a horizontal force to a wall. The machine should stand on a firm level base and apply force by a controlled movement of the pusher arm. Figure 4.8 Figure 4.9 Mini Hydraulic Breaker Hydraulic Breaker Figure 4.10 Hydraulic Mobile crane ( 20 T - 200 T )
  • 19. DEMOLITION WORKS 4.3.2.3 C3001 / UNIT 4 / 19 Long arm excavator Figure 4.11 Long Arm Excavator Figure 4.12 Long Arm Excavator
  • 20. DEMOLITION WORKS 4.3.2.4 C3001 / UNIT 4 / 20 Dynamite If explosives are to be used for demolition, the planning and execution, include pre-weakening, should be under the control of a person competent in these techniques. For large demolition, the competent person is likely to be an experienced explosive engineer; for smaller work, a shot-firer may be sufficient. When the use of explosives is contemplated, it is usual to employ a technique that will ensure the total demolition of the whole building by staging a controlled collapse. The explosive charges are set and fired in a sequence that will weaken the structure in such a way that the building collapses in upon itself. Although we tend to think of explosives as devices producing spectacular bomblike explosions, the use of non-explosive "explosives" is now at an advanced stage. These non-explosive techniques are essentially expanding charges that achieve the same results as explosives but without the noise and initial devastating blast. “Did you understand all the information in this unit? If you have difficulties go through the notes again. Now let us answer the question in the next activity”.
  • 21. DEMOLITION WORKS C3001 / UNIT 4 / 21 Complete the sentences below by providing the correct answers. 1. Demolition means………………….. 2. Demolition techniques may be categorized as ……………… 3. Manual and Machinery components are ……………………… 4. List the machinery’s components. Write your answers in the space below. a) …………………………. b) …………………………. c) ………………………….. d) ………………………….. 5. Who should be allowed close to the working area?
  • 22. DEMOLITION WORKS C3001 / UNIT 4 / 22 1. Based on the Oxford Fajar dictionary Demolition means to “pull or knock down a building”, and another meaning for demolition is a “highly skilled and dangerous activity in terms of damage to life and property”. 2. Demolition techniques may be categorized as:Piecemeal demolition, using hand-held tools or machines, to reduce the height of the building or structure gradually; • • Deliberate controlled collapse, completed at ground level. demolition to be
  • 23. DEMOLITION WORKS 3. Manual and machinery components are ways of demolition 4. a) balling machine b) hydraulic pusher arm long arm excavator dynamite 5. The machine operator and banks man should be allowed closed to the working area C3001 / UNIT 4 / 23
  • 24. DEMOLITION WORKS C3001 / UNIT 4 / 24 Answer the following questions: 1. Give FIVE of the most important safety precautions which must be taken into account before starting a demolition project to prevent your actions from undermining the structural integrity of the building? 2. Give THREE proper attire and tools needed to ensure a safe environment in a demolition project? 3. Give FIVE steps that need to be taken to ensure the homeowner’s safety. 4. Explain how to schedule the best time to start a demolition project. 5. List three examples of Machinery’s Components.
  • 25. DEMOLITION WORKS C3001 / UNIT 4 / 25 ANSWER NO. 1 • Always know exactly what it is you're about to remove. Before you move or remove anything, always check to see what's behind it, below it and what it might support. • Never assume that a structural member you're about to remove doesn't support anything • When removing framing that is near electrical wiring, shut off the electricity, even if you're not removing the wiring. Do the same for any plumbing or gas lines. A single nick with a saw blade or a drill can cause disastrous results. • When removing electrical wiring, turn off the circuit breaker or remove the fuse controlling the circuit you're working on, and then post a note on the electrical panel warning others not to turn it back on. • Never attempt to work on a gas or water line without first making certain it has been shut off. Also, do not assume that a shutoff valve works - after closing the valve, test the line to be absolutely sure it's off.
  • 26. DEMOLITION WORKS C3001 / UNIT 4 / 26 ANSWER NO. 2 • Use only the proper tool that is designed for a particular task - don't improvise. If you are prying up a board, use a heavy pry, not a big screwdriver. On the other hand, use a screwdriver to remove a screw; don't yank it out with a pry bar. • If you don't have the proper tool for the job, don't proceed until you are able to buy or rent one. If you need a jack to lift a heavy beam, get one - don't try to rig up a couple of 2 X 4 as a lever. If scaffolding is required to work safely at a given height, get some and take the time to set it up correctly - balancing a 2 X 12 on a couple of ladders is an invitation for disaster. • Wear the appropriate clothings. Demolition work requires long pants, a heavy shirt, and solid shoes - allowing your crew to work in shorts and tennis hoes can net you a serious fine. Wear gloves, and always wear eye protection. If anyone is working above you, or if there is any potential for falling objects, make hard hats mandatory.
  • 27. DEMOLITION WORKS C3001 / UNIT 4 / 27 ANSWER NO. 3 • Secure all tools at lunchtime, at the end of the day, and during absence from the job site, cords need to be unplugged and sharp tools placed in a safe and secure enclosure. Remember that children are fascinated with construction sites, and this curiosity can lead to serious injuries. • Motorized equipment needs to be securely locked and the keys placed in a safe locked area. • Take down ladders at the end of the day. This includes covering holes in the floor and placing temporary barricades over window and door openings. • If you cannot cover or otherwise close off an area - such as an open trench that is still in use - ring the area with caution tape and place lighted barricades at regular intervals as a warning. • Cover holes and other danger spots.
  • 28. DEMOLITION WORKS C3001 / UNIT 4 / 28 ANSWER NO. 4 • In most cases, demolition work is best left until the last possible moment in order to help avoid weather and security problems. The addition should be completely framed, roofed, and enclosed with siding, and exterior windows and doors should be installed, before the walls connecting the addition with the existing house should be removed. • Try to work in stages as much as possible, again doing only as much demolition work as necessary for a particular phase of the construction. You may, for example, need to remove a small section of siding at the base of the wall in order to align the new foundation with the old one, or perhaps take down some drywall to line up the new ceiling joints. • Even if it's all coming down eventually, it's best to remove only what you need to accomplish the task you are working on at the moment. ANSWER NO. 5 • Long arm excavator • Hydraulic pusher arm • Balling machine