Disposition of
Federally Funded
Assets
November 18, 2010
Federal Transit Administration
FTA TRO-02 2
Introduction
Guidelines for Disposition of Project
Property :
REAL PROPERTY
EQUIPMENT, SUPPLIES & ROLLING
STOCK
Definition of Project Property
Definition of Project Property:
Any real property, equipment, supply,
rolling stock or facility purchased or
constructed with Federal funding.
FTA TRO-02 3
FTA TRO-02 4
USE OF PROJECT PROPERTY
Project property is to be used by the grantee in the
program or project for the purpose it was acquired as
long as needed, whether or not the program or project
continues to be supported by Federal funds.
FTA reserves the right in the Grant Agreement to
require the grantee, with FTA, approval, to transfer
title to project property no longer needed or used for
the purposes of the grant to the Federal Gov’t or an
otherwise eligible grantee. (49 CFR 18.32)
When need no longer exists, follow disposition
requirements in FTA Circular 5010.1D Chapter IV,
Subsection 3.1
REAL PROPERTY PENDING DISPOSAL
Follow valuation requirement of 49 CFR
part 24 and obtain an appraisal to
determine property value.
Sale procedure should provide for
competition to the extent possible to yield
highest possible return or at least
appraised fair market value.
FTA TRO-02 5
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 1 of 7
Sell and Reimburse FTA
 Competitively market and sell the property
 Pay FTA the greater of its share of the fair market value
or the straight line depreciated value of the improvement
plus land value
 Note: FTA share is percentage participation in original
grant.
FTA TRO-02 6
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 2 0f 7
Offset
 Sell property and apply net proceeds to cost of
replacement property under SAME program.
 Any excess MUST be returned to FTA (49 CFR
18.31)
FTA TRO-02 7
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 3of 7
Sell and Use Proceeds for Other Capital
Projects.
 Sell and use proceeds to reduce gross cost of
another FTA eligible capital transit project.
 Grantee must record in their accounting system
to show that funds are solely for use in a
subsequent capital project.
 FTA approval required to apply the proceeds to
a subsequent capital grant.
FTA TRO-02 8
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 4 of 7
Sell & Keep Proceeds in Open Project
 Grantee can apply proceeds to the original cost
of the real property which could possibly reduce
Federal Share.
 Grant must still be open to use this option.
FTA TRO-02 9
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 5 of 7
Transfer to Public Agency for Non-Transit
Use
 Competitive process therefore no guarantee on
which public agency will receive property
 Need to be published in Federal Register
 No repayment to FTA required
 Ref. 49 USC 5334(h)(1)-(h)(3)
FTA TRO-02 10
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 6 of 7
Transfer to Other Project
 This option simply involves transferring the
Federal interest to another FTA Eligible project.
 The pro rata share of the FTA interest in the
original property continues in the new project
FTA TRO-02 11
ALTERNATIVE DISPOSITION METHODS
FOR REAL PROPERTY Slide 7 of 7
Retain Title With Buyout
 This option involves compensating FTA in the
amount of the percentage of the original cost.
 Repayment amount is established similar to Sell
and Reimburse option.
FTA TRO-02 12
DISPOSITION of EQUIPMENT,
SUPPLIES & ROLLING STOCK
In order to properly effect disposition of project
property, we first have to establish useful life.
Circular 5010.1D list eight methods acceptable
to FTA for determining useful life:
 GAAP
 Independent Evaluation
 Manufacturer’s estimate of useful life
 IRS Guidelines
 Industry Standards
 Grantee Experience
 Grantee independent auditor
 Proven useful life developed at a Federal test facility
FTA TRO-02 13
USEFUL LIFE
FTA provides recommended useful life for
the following:
 Buses ( 4yrs to 12ys & 100k to 500k miles depending on
type
 Trolleys (15-25 yrs depending on type)
 Rail Vehicles ( minimum 25 yrs)
 Ferries ( 25-60 yrs depending on type & use)
FTA TRO-02 14
USEFUL LIFE
Where a useful life policy has not been
defined by FTA, the grantee, in
consultation with the FTA regional or
metropolitan office shall ‘make the case’
by identifying a useful life period for all
equipment and facilities with an acquisition
value greater than $5000
FTA TRO-02 15
USEFUL LIFE & DISPOSITION
Project property to be disposed must have
achieved at least the minimum useful life
Disposition before the end of useful life
requires prior FTA approval.
FTA TRO-02 16
DISPOSITION AT END of USEFUL LIFE
SLIDE 1 of
10
Retain and Use Elsewhere
 If minimum useful life has been reached,
property can be used for other transit projects or
programs.
 No prior FTA approval required.
 Remaining FTA interest if fair market value is
over $5K
FTA TRO-02 17
DISPOSITION AT END of USEFUL LIFE
SLIDE 2 of
10
Fair Market Value > $5000
 Grantee has the option to retain or sell.
 Need to notify FTA in writing of sale or retention.
 If sold, reimbursement calculated similar to
previously mentioned methods.
 Option for use of proceeds similar to previously
discussed
FTA TRO-02 18
DISPOSITION AT END of USEFUL LIFE
SLIDE 3 of
10
Fair Market Value < $5000
 Grantee has the option to sell or retain
 No prior FTA approval required
 Record of action taken must be retained and
available for review upon request.
FTA TRO-02 19
DISPOSITION AT END of USEFUL LIFE
SLIDE 4 of
10
Like-Kind Exchange Policy
 This type of disposition typically ocurr before the
end of minimum useful life.
 However, whenever a grantee chooses to use
this method, ALL net proceeds from the sale or
trade should be use to acquire a replacement
vehicle of ‘like-kind’ in lieu of returning Federal
funds.
 Special conditions for proceeds less or greater
than Federal share.
FTA TRO-02 20
DISPOSITION AT END of USEFUL LIFE
SLIDE 5 of
10
Transfer of Rolling Stock
 From Grantee to Grantee with prior FTA
approval.
 Coordination between grantees and FTA
regional office plus prerequisites in 5010.1D
Chapter IV
 Desired prior to end of useful life
FTA TRO-02 21
DISPOSITION AT END of USEFUL LIFE
SLIDE 6 of
10
Transfer of Assets No Longer Needed
 Can be used if useful life has not been met and
with prior FTA approval.
 Transfer to a public agency for non-
transportation use.
 Four conditions apply to use this option
FTA TRO-02 22
DISPOSITION AT END of USEFUL LIFE
SLIDE 7 of
10
Sell & Use Proceeds for Other Capital
Project
 Similar option discussed earlier for Real
Property.
 Most important that grantee is expected to
record the proceeds of the transaction in their
accounting system
FTA TRO-02 23
DISPOSITION AT END of USEFUL LIFE
SLIDE 8 of
10
Unused Supplies
This option applies to supplies >$5k for
which there is no transit use.
Grantee is required to compensate FTA
for its share.
FTA TRO-02 24
DISPOSITION AT END of USEFUL LIFE
SLIDE 9 of
10
Casualty, Fire and Natural Disaster
 FMV calculated on the basis of the condition of
the project property just before any of the above,
irrespective of the extent of insurance coverage.
Remit the Federal interest by either:
Like-kind
Returning an amount equal to the interest
FTA TRO-02 25
DISPOSITION AT END of USEFUL LIFE
SLIDE 10 of
10
Insurance Proceeds
 Two option for insurance proceeds received :
Apply to like-kind replacement
Return an amount equal to the Federal interest.
 Please note that the Federal interest is NOT
dependent on the extent of the insurance
coverage or the insurance adjustment received.
FTA TRO-02 26
FTA TRO-02 27
GRANTEE EXPERIENCE
Grantee Input on Disposition Experience
FTA TRO-02 28
Questions and Answers:
Question?
Hans.PointduJour@dot.gov
FTA Region 2 Office
or
Donovan.vincent@dot.gov
FTA Region 2 Office
(212)668-2170

Weitere ähnliche Inhalte

Andere mochten auch

Andere mochten auch (14)

Transportation Industry Roundtable
Transportation Industry RoundtableTransportation Industry Roundtable
Transportation Industry Roundtable
 
MTA Bus Customer Information Systems
MTA Bus Customer Information SystemsMTA Bus Customer Information Systems
MTA Bus Customer Information Systems
 
An Overview of the Changes to Circular 5010.1D Grants Management Requirements
An Overview of the Changes to Circular 5010.1D Grants Management RequirementsAn Overview of the Changes to Circular 5010.1D Grants Management Requirements
An Overview of the Changes to Circular 5010.1D Grants Management Requirements
 
Grant Modifications - Veronica Pelt-Hawkins, Transportation Program Specialis...
Grant Modifications - Veronica Pelt-Hawkins, Transportation Program Specialis...Grant Modifications - Veronica Pelt-Hawkins, Transportation Program Specialis...
Grant Modifications - Veronica Pelt-Hawkins, Transportation Program Specialis...
 
SAFETEA-LU Reauthorization Context & Issues
SAFETEA-LU ReauthorizationContext & IssuesSAFETEA-LU ReauthorizationContext & Issues
SAFETEA-LU Reauthorization Context & Issues
 
NFTA Metro Route Restructuring
NFTA Metro Route RestructuringNFTA Metro Route Restructuring
NFTA Metro Route Restructuring
 
Lessons Learned in Transit Efficiencies, Revenue Generation, and Cost Reductions
Lessons Learned in Transit Efficiencies, Revenue Generation, and Cost ReductionsLessons Learned in Transit Efficiencies, Revenue Generation, and Cost Reductions
Lessons Learned in Transit Efficiencies, Revenue Generation, and Cost Reductions
 
Reinventing Transit: American Communities Finding Smarter, Cleaner, Faster Tr...
Reinventing Transit: American Communities Finding Smarter, Cleaner, Faster Tr...Reinventing Transit: American Communities Finding Smarter, Cleaner, Faster Tr...
Reinventing Transit: American Communities Finding Smarter, Cleaner, Faster Tr...
 
Maintaining and Improving Rural Transit Supply in an Era of Cost-Cutting
Maintaining and Improving Rural Transit Supply in an Era of Cost-CuttingMaintaining and Improving Rural Transit Supply in an Era of Cost-Cutting
Maintaining and Improving Rural Transit Supply in an Era of Cost-Cutting
 
Revitalizing Fatigued Employees - Dr. Dionne Kress, Leadership Coach, D.M. Kr...
Revitalizing Fatigued Employees - Dr. Dionne Kress, Leadership Coach, D.M. Kr...Revitalizing Fatigued Employees - Dr. Dionne Kress, Leadership Coach, D.M. Kr...
Revitalizing Fatigued Employees - Dr. Dionne Kress, Leadership Coach, D.M. Kr...
 
Moving 20 Million People – Best Practices in Transit from Shanghai, China - S...
Moving 20 Million People – Best Practices in Transit from Shanghai, China - S...Moving 20 Million People – Best Practices in Transit from Shanghai, China - S...
Moving 20 Million People – Best Practices in Transit from Shanghai, China - S...
 
A Global Perspective on Public Transit's Current State of Affairs - Stephen D...
A Global Perspective on Public Transit's Current State of Affairs - Stephen D...A Global Perspective on Public Transit's Current State of Affairs - Stephen D...
A Global Perspective on Public Transit's Current State of Affairs - Stephen D...
 
Social Mobility for Seniors
Social Mobility for SeniorsSocial Mobility for Seniors
Social Mobility for Seniors
 
Implementing Contactless Fare Collection Systems - Danielle Pinkus, Instructi...
Implementing Contactless Fare Collection Systems - Danielle Pinkus, Instructi...Implementing Contactless Fare Collection Systems - Danielle Pinkus, Instructi...
Implementing Contactless Fare Collection Systems - Danielle Pinkus, Instructi...
 

Ähnlich wie Disposition of Federally Funded Assets - Donovan Vincent, General Engineer, FTA Region II

Brochure_for_filling_application.pdf
Brochure_for_filling_application.pdfBrochure_for_filling_application.pdf
Brochure_for_filling_application.pdf
AmanDebbarma1
 
Renaissance Infrastructure
Renaissance InfrastructureRenaissance Infrastructure
Renaissance Infrastructure
Jayesh HAryani
 
Variable Pricing Program for Roads | FHWA
Variable Pricing Program for Roads | FHWAVariable Pricing Program for Roads | FHWA
Variable Pricing Program for Roads | FHWA
Texxi Global
 

Ähnlich wie Disposition of Federally Funded Assets - Donovan Vincent, General Engineer, FTA Region II (20)

Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Drilco 2016 1H Drilling Program - Private Placement Memorandum
Drilco 2016 1H Drilling Program - Private Placement MemorandumDrilco 2016 1H Drilling Program - Private Placement Memorandum
Drilco 2016 1H Drilling Program - Private Placement Memorandum
 
Offset obligations in Brazil.ppt
Offset obligations in Brazil.pptOffset obligations in Brazil.ppt
Offset obligations in Brazil.ppt
 
How the gov't buys cap i-tal reps
How the gov't buys   cap i-tal repsHow the gov't buys   cap i-tal reps
How the gov't buys cap i-tal reps
 
Introduction to public procurement
Introduction to public procurement Introduction to public procurement
Introduction to public procurement
 
Pbd.goods
Pbd.goodsPbd.goods
Pbd.goods
 
Brochure_for_filling_application.pdf
Brochure_for_filling_application.pdfBrochure_for_filling_application.pdf
Brochure_for_filling_application.pdf
 
Potential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passedPotential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passed
 
AFCS_PQConference.pdf
AFCS_PQConference.pdfAFCS_PQConference.pdf
AFCS_PQConference.pdf
 
2017 SLA Conference - Government Contracting - King
2017 SLA Conference - Government Contracting - King2017 SLA Conference - Government Contracting - King
2017 SLA Conference - Government Contracting - King
 
Licensing for SHP
Licensing for SHPLicensing for SHP
Licensing for SHP
 
Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184
 
The must have program/project management reporting feature before applying fo...
The must have program/project management reporting feature before applying fo...The must have program/project management reporting feature before applying fo...
The must have program/project management reporting feature before applying fo...
 
Renaissance Infrastructure
Renaissance InfrastructureRenaissance Infrastructure
Renaissance Infrastructure
 
Project Finance Conference Feb 2016
Project Finance Conference Feb 2016Project Finance Conference Feb 2016
Project Finance Conference Feb 2016
 
DBFOT project
DBFOT projectDBFOT project
DBFOT project
 
ActionLine - 2015
ActionLine - 2015ActionLine - 2015
ActionLine - 2015
 
Goods
GoodsGoods
Goods
 
Variable Pricing Program for Roads | FHWA
Variable Pricing Program for Roads | FHWAVariable Pricing Program for Roads | FHWA
Variable Pricing Program for Roads | FHWA
 
Finvision impact series 1 - ed leases - lessee accounting
Finvision   impact series 1 - ed leases - lessee accountingFinvision   impact series 1 - ed leases - lessee accounting
Finvision impact series 1 - ed leases - lessee accounting
 

Mehr von New York Public Transit Association

Mehr von New York Public Transit Association (11)

Cost Cutting through Information Systems: Using Google Transit as a Model
Cost Cutting through Information Systems: Using Google Transit as a ModelCost Cutting through Information Systems: Using Google Transit as a Model
Cost Cutting through Information Systems: Using Google Transit as a Model
 
Best Practices in Sustainability with CDTA
Best Practices in Sustainability with CDTABest Practices in Sustainability with CDTA
Best Practices in Sustainability with CDTA
 
The Future of Transportation in NYS - Mary Ann Crotty
The Future of Transportation in NYS - Mary Ann CrottyThe Future of Transportation in NYS - Mary Ann Crotty
The Future of Transportation in NYS - Mary Ann Crotty
 
Innovative Design Solutions for Urban Intermodal Centers - Don Gray, AIA, LEE...
Innovative Design Solutions for Urban Intermodal Centers - Don Gray, AIA, LEE...Innovative Design Solutions for Urban Intermodal Centers - Don Gray, AIA, LEE...
Innovative Design Solutions for Urban Intermodal Centers - Don Gray, AIA, LEE...
 
Sustainability With CDTA - Odyssey Batteries - Bruce Essig, National Sales Ma...
Sustainability With CDTA - Odyssey Batteries - Bruce Essig, National Sales Ma...Sustainability With CDTA - Odyssey Batteries - Bruce Essig, National Sales Ma...
Sustainability With CDTA - Odyssey Batteries - Bruce Essig, National Sales Ma...
 
Nypta fall 2010
Nypta fall 2010Nypta fall 2010
Nypta fall 2010
 
November 2010 Albany Update - Weingarten, Reid & McNally
November 2010 Albany Update - Weingarten, Reid & McNallyNovember 2010 Albany Update - Weingarten, Reid & McNally
November 2010 Albany Update - Weingarten, Reid & McNally
 
Extra! Extra!: New Circulars and Guidance
Extra! Extra!: New Circulars and GuidanceExtra! Extra!: New Circulars and Guidance
Extra! Extra!: New Circulars and Guidance
 
Fall Conference 2009 Albany Update
Fall Conference 2009 Albany UpdateFall Conference 2009 Albany Update
Fall Conference 2009 Albany Update
 
Using Technology to Enhance Sustainability
Using Technology to Enhance SustainabilityUsing Technology to Enhance Sustainability
Using Technology to Enhance Sustainability
 
Taking the Subway to Copenhagen - How Transit is Essential to Global GHG Red...
Taking the Subway to Copenhagen - How Transit is Essential to Global GHG Red...Taking the Subway to Copenhagen - How Transit is Essential to Global GHG Red...
Taking the Subway to Copenhagen - How Transit is Essential to Global GHG Red...
 

Kürzlich hochgeladen

+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
Health
 
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdfMASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
Cocity Enterprises
 
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammamAbortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
samsungultra782445
 
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnLaw of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
TintoTom3
 

Kürzlich hochgeladen (20)

Test bank for advanced assessment interpreting findings and formulating diffe...
Test bank for advanced assessment interpreting findings and formulating diffe...Test bank for advanced assessment interpreting findings and formulating diffe...
Test bank for advanced assessment interpreting findings and formulating diffe...
 
+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
+971565801893>>SAFE ORIGINAL ABORTION PILLS FOR SALE IN DUBAI,RAK CITY,ABUDHA...
 
Group 8 - Goldman Sachs & 1MDB Case Studies
Group 8 - Goldman Sachs & 1MDB Case StudiesGroup 8 - Goldman Sachs & 1MDB Case Studies
Group 8 - Goldman Sachs & 1MDB Case Studies
 
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai MultipleDubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
Dubai Call Girls Deira O525547819 Dubai Call Girls Bur Dubai Multiple
 
logistics industry development power point ppt.pdf
logistics industry development power point ppt.pdflogistics industry development power point ppt.pdf
logistics industry development power point ppt.pdf
 
Pension dashboards forum 1 May 2024 (1).pdf
Pension dashboards forum 1 May 2024 (1).pdfPension dashboards forum 1 May 2024 (1).pdf
Pension dashboards forum 1 May 2024 (1).pdf
 
Avoidable Errors in Payroll Compliance for Payroll Services Providers - Globu...
Avoidable Errors in Payroll Compliance for Payroll Services Providers - Globu...Avoidable Errors in Payroll Compliance for Payroll Services Providers - Globu...
Avoidable Errors in Payroll Compliance for Payroll Services Providers - Globu...
 
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdfMASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
MASTERING FOREX: STRATEGIES FOR SUCCESS.pdf
 
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsMahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
 
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
 
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammamAbortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
Abortion pills in Saudi Arabia (+919707899604)cytotec pills in dammam
 
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnLaw of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
 
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
In Sharjah ௵(+971)558539980 *_௵abortion pills now available.
 
FE Credit and SMBC Acquisition Case Studies
FE Credit and SMBC Acquisition Case StudiesFE Credit and SMBC Acquisition Case Studies
FE Credit and SMBC Acquisition Case Studies
 
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
 
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
 
Shrambal_Distributors_Newsletter_May-2024.pdf
Shrambal_Distributors_Newsletter_May-2024.pdfShrambal_Distributors_Newsletter_May-2024.pdf
Shrambal_Distributors_Newsletter_May-2024.pdf
 
Stock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdfStock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdf
 
Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...
 

Disposition of Federally Funded Assets - Donovan Vincent, General Engineer, FTA Region II

  • 1. Disposition of Federally Funded Assets November 18, 2010 Federal Transit Administration
  • 2. FTA TRO-02 2 Introduction Guidelines for Disposition of Project Property : REAL PROPERTY EQUIPMENT, SUPPLIES & ROLLING STOCK
  • 3. Definition of Project Property Definition of Project Property: Any real property, equipment, supply, rolling stock or facility purchased or constructed with Federal funding. FTA TRO-02 3
  • 4. FTA TRO-02 4 USE OF PROJECT PROPERTY Project property is to be used by the grantee in the program or project for the purpose it was acquired as long as needed, whether or not the program or project continues to be supported by Federal funds. FTA reserves the right in the Grant Agreement to require the grantee, with FTA, approval, to transfer title to project property no longer needed or used for the purposes of the grant to the Federal Gov’t or an otherwise eligible grantee. (49 CFR 18.32) When need no longer exists, follow disposition requirements in FTA Circular 5010.1D Chapter IV, Subsection 3.1
  • 5. REAL PROPERTY PENDING DISPOSAL Follow valuation requirement of 49 CFR part 24 and obtain an appraisal to determine property value. Sale procedure should provide for competition to the extent possible to yield highest possible return or at least appraised fair market value. FTA TRO-02 5
  • 6. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 1 of 7 Sell and Reimburse FTA  Competitively market and sell the property  Pay FTA the greater of its share of the fair market value or the straight line depreciated value of the improvement plus land value  Note: FTA share is percentage participation in original grant. FTA TRO-02 6
  • 7. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 2 0f 7 Offset  Sell property and apply net proceeds to cost of replacement property under SAME program.  Any excess MUST be returned to FTA (49 CFR 18.31) FTA TRO-02 7
  • 8. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 3of 7 Sell and Use Proceeds for Other Capital Projects.  Sell and use proceeds to reduce gross cost of another FTA eligible capital transit project.  Grantee must record in their accounting system to show that funds are solely for use in a subsequent capital project.  FTA approval required to apply the proceeds to a subsequent capital grant. FTA TRO-02 8
  • 9. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 4 of 7 Sell & Keep Proceeds in Open Project  Grantee can apply proceeds to the original cost of the real property which could possibly reduce Federal Share.  Grant must still be open to use this option. FTA TRO-02 9
  • 10. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 5 of 7 Transfer to Public Agency for Non-Transit Use  Competitive process therefore no guarantee on which public agency will receive property  Need to be published in Federal Register  No repayment to FTA required  Ref. 49 USC 5334(h)(1)-(h)(3) FTA TRO-02 10
  • 11. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 6 of 7 Transfer to Other Project  This option simply involves transferring the Federal interest to another FTA Eligible project.  The pro rata share of the FTA interest in the original property continues in the new project FTA TRO-02 11
  • 12. ALTERNATIVE DISPOSITION METHODS FOR REAL PROPERTY Slide 7 of 7 Retain Title With Buyout  This option involves compensating FTA in the amount of the percentage of the original cost.  Repayment amount is established similar to Sell and Reimburse option. FTA TRO-02 12
  • 13. DISPOSITION of EQUIPMENT, SUPPLIES & ROLLING STOCK In order to properly effect disposition of project property, we first have to establish useful life. Circular 5010.1D list eight methods acceptable to FTA for determining useful life:  GAAP  Independent Evaluation  Manufacturer’s estimate of useful life  IRS Guidelines  Industry Standards  Grantee Experience  Grantee independent auditor  Proven useful life developed at a Federal test facility FTA TRO-02 13
  • 14. USEFUL LIFE FTA provides recommended useful life for the following:  Buses ( 4yrs to 12ys & 100k to 500k miles depending on type  Trolleys (15-25 yrs depending on type)  Rail Vehicles ( minimum 25 yrs)  Ferries ( 25-60 yrs depending on type & use) FTA TRO-02 14
  • 15. USEFUL LIFE Where a useful life policy has not been defined by FTA, the grantee, in consultation with the FTA regional or metropolitan office shall ‘make the case’ by identifying a useful life period for all equipment and facilities with an acquisition value greater than $5000 FTA TRO-02 15
  • 16. USEFUL LIFE & DISPOSITION Project property to be disposed must have achieved at least the minimum useful life Disposition before the end of useful life requires prior FTA approval. FTA TRO-02 16
  • 17. DISPOSITION AT END of USEFUL LIFE SLIDE 1 of 10 Retain and Use Elsewhere  If minimum useful life has been reached, property can be used for other transit projects or programs.  No prior FTA approval required.  Remaining FTA interest if fair market value is over $5K FTA TRO-02 17
  • 18. DISPOSITION AT END of USEFUL LIFE SLIDE 2 of 10 Fair Market Value > $5000  Grantee has the option to retain or sell.  Need to notify FTA in writing of sale or retention.  If sold, reimbursement calculated similar to previously mentioned methods.  Option for use of proceeds similar to previously discussed FTA TRO-02 18
  • 19. DISPOSITION AT END of USEFUL LIFE SLIDE 3 of 10 Fair Market Value < $5000  Grantee has the option to sell or retain  No prior FTA approval required  Record of action taken must be retained and available for review upon request. FTA TRO-02 19
  • 20. DISPOSITION AT END of USEFUL LIFE SLIDE 4 of 10 Like-Kind Exchange Policy  This type of disposition typically ocurr before the end of minimum useful life.  However, whenever a grantee chooses to use this method, ALL net proceeds from the sale or trade should be use to acquire a replacement vehicle of ‘like-kind’ in lieu of returning Federal funds.  Special conditions for proceeds less or greater than Federal share. FTA TRO-02 20
  • 21. DISPOSITION AT END of USEFUL LIFE SLIDE 5 of 10 Transfer of Rolling Stock  From Grantee to Grantee with prior FTA approval.  Coordination between grantees and FTA regional office plus prerequisites in 5010.1D Chapter IV  Desired prior to end of useful life FTA TRO-02 21
  • 22. DISPOSITION AT END of USEFUL LIFE SLIDE 6 of 10 Transfer of Assets No Longer Needed  Can be used if useful life has not been met and with prior FTA approval.  Transfer to a public agency for non- transportation use.  Four conditions apply to use this option FTA TRO-02 22
  • 23. DISPOSITION AT END of USEFUL LIFE SLIDE 7 of 10 Sell & Use Proceeds for Other Capital Project  Similar option discussed earlier for Real Property.  Most important that grantee is expected to record the proceeds of the transaction in their accounting system FTA TRO-02 23
  • 24. DISPOSITION AT END of USEFUL LIFE SLIDE 8 of 10 Unused Supplies This option applies to supplies >$5k for which there is no transit use. Grantee is required to compensate FTA for its share. FTA TRO-02 24
  • 25. DISPOSITION AT END of USEFUL LIFE SLIDE 9 of 10 Casualty, Fire and Natural Disaster  FMV calculated on the basis of the condition of the project property just before any of the above, irrespective of the extent of insurance coverage. Remit the Federal interest by either: Like-kind Returning an amount equal to the interest FTA TRO-02 25
  • 26. DISPOSITION AT END of USEFUL LIFE SLIDE 10 of 10 Insurance Proceeds  Two option for insurance proceeds received : Apply to like-kind replacement Return an amount equal to the Federal interest.  Please note that the Federal interest is NOT dependent on the extent of the insurance coverage or the insurance adjustment received. FTA TRO-02 26
  • 27. FTA TRO-02 27 GRANTEE EXPERIENCE Grantee Input on Disposition Experience
  • 28. FTA TRO-02 28 Questions and Answers: Question? Hans.PointduJour@dot.gov FTA Region 2 Office or Donovan.vincent@dot.gov FTA Region 2 Office (212)668-2170