Role of the System Requirements Document

Objectives
♦ Capture the vehicle-level capabilities in a set of complete,
  necessary, clear, attainable, traceable, and verifiable statements
  of need (Requirements)                If it is not needed by Cx, it is
    • Should not be unduly restrictive1         not a vehicle-level capability

    • Sets limits that eliminate items outside the boundaries drawn
    • Encourage competition (or alternatives)
    • Capture source and reason of requirement
♦ Establish the verification methods that will lead to product
  acceptance
    • These should be reproducible assessment methods
♦ Allocate requirements to the element-level to facilitate vehicle
  architecture development and integration

    The SRD sets the standards by which the Product will be evaluated
                                                                1MIL-STD-961E   - Reference   2
Where do Requirements Come From?

♦ The Customer
   • One should always listen to the Voice of the Customer when establishing
     what the End Item should be able to do
   • On Altair, we walk through the CARD Allocated Requirements and
     Categorize by:
       −   MOE
       −   Operational
       −   Functional/Performance
       −   Safety/-ilities
♦ Operational Analysis
   • Develop deep understanding of Concept of Operations to identify new End
     Item Capabilities that are required
   • Evaluate operational constraints
♦ Technical Disciplines Best Practices
   • Work with discipline experts to establish capabilities required “to do the job”
♦ Design and Construction Standards
   • Use industry standards to specify how the product is designed
                                                                                       3
Requirements Development Approach

♦ Role of the Project is to validate
  requirements                                    DRM
   • Necessary
                                                 Phase
   • Attainable
   • Traceable                                   Activity
   • Clear and Verifiable
♦ Vehicle Functionality should flow               Event
  from the Concept of Operations
   • How is the vehicle to be                   Functional
      operated?                                  Modes
   • What functionality should be
      on-board to support these
      operations?                             Requirements

   Goal: Ensure Traceability from Missions to Functions to Requirements
                     and Drive for Completeness
                                                                          4
Requirements Development Approach - 2

♦ Required vehicle functionality flows from the concept of operations and
  system of systems architecture.
Prior to Models-Based Systems Engineering (MBSE):
♦ OPSCON articulated our Concept of Operations
    • Captures at the phase/activity-level the general roles of the various systems in
      executing the mission
    • Timeline captures the events that make up these operations with some articulation of
      roles
Implementing MBSE:
♦ OPSModels are flow diagrams that depict operations described in
  OPSCON with an allocation of responsibility of those events
    • Capture discrete events that make up an activity
    • Capture dependencies and data flow that make up those activities
    • Drive traceability of Operational requirements
    • Provide traceability of functionality to vehicle
♦ Traceability comes through linking of data objects, and reports querying
  database depicts this traceability
                                                                                             5
Design Reference Mission: Lunar Sortie Crew
                                        Design Reference Mission: Lunar Sortie Crew
                              EDS                    LOI Burn             LOI Burn              Undock                  ATP for                         Ascent
                             Jettison               Procedures            Sequence             Complete                Lunar Stay                     Preparation
                            Complete                  Begun               Complete                                                                       Start




                                                                                     Pre-Surface                                                                              Lunar
                  TLI                   Trans-Lunar                 LOI              Operations             Altair                        Surface                            Ascent &
               Operations                 Cruise                 Operations           (Docked)             Descent            AND        Operations          AND              RPOD
                                                                                                                                                                            Operations
                 LSC.9                    LSC.10                  LSC.11              LSC.12               LSC.13                         LSC.14
                                                                                                                                                                                LSC.16
 TLI Burn                                                                                                                                                                                    Docking
Prep Start                                                                                                                                                                                   complete
                 Earth
                 Orbit                                                                                                                    Lunar
               Operations                                                                                                                  Orbit
                                                                                                                                        Maintenance                         Post-Surface
                 LSC.8                                                                                                                                                      Operations
                                                                                                                                          LSC.15
Docking                                                                                                                                                                          LSC.17
complete
                                                                                                                                                                                             Altair/LIDS
              LEO RPOD                                                                                                                                                                        Jettison
              Operations
                 LSC.7

 ATP for                                                                                                                                                                    Trans-Earth
Orbit Ops                                                                                                                                                                     Cruise
                  LEO                                                                                                                                                            LSC.18        Final
              Configuration                                                                                                                                                                    Entry
             (Post-Insertion)                                                                                                                                                                  Prep
                                                                                                                                                                                              <EI-12>
                 LSC.6
  Orbit
Insertion
  Burn
                                                                                                                                                                                  Earth
                                                                                                                                                                                 Arrival
                                                                                                                                                                                                            Operational
                                                                                                                                                                                Operations
Complete
                 Ascent                                                                                                                                                          LSC.19                      Hierarchy
                                                                                                                                                                                                SM
                 LSC.5                                                                                                                                                                       Separation
                                                                                                                                                                                                            Terminology
  Liftoff
                                                            Phase
                                                                                                                                                                            Re-entry/Entry
                 Launch                                   (Operation)                                                                                                            LSC.20
                                                                                                                                                                                             Fwd Bay
                                                                                                                                                                                                              DRM
                 LSC.4
                                                                                                                                                                                              Cover
                                                                                                                                                                                              Jettison
LCD CTS

                  Pad
               Operations
                                          Integrated
                                          Operations
                                                                       Stand
                                                                       Alone                                          Post-Flight
                                                                                                                      Processing                  Recovery
                                                                                                                                                                                 Descent
                                                                                                                                                                                   and
                                                                                                                                                                                                             Phase
                                                                     Operations                                                                                                  Landing
                 LSC.3                      LSC.2                                                                      LSC.23                      LSC.22
                                                                       LSC.1                                                                                                     LSC.21


                                                                                                                                                                                                             Activity
                            MLP Hard
                                                        Transport
                                                            to                                             Arrival
                                                                                                                                      Arrival
                                                                                                                                        at                                                        Sub-
                                                       Integration                   DD250                at Refurb                 Post-Flight                     Touchdown
                             Down                        Facility
                                                        Complete
                                                                                                             Site                   Processing
                                                                                                                                      Facility
                                                                                                                                                                                                 Activity
      Trigger                                                                                                                                                                                                 Event
    (Data Item)                                                                                                                                                                     Authoritative Source: CxP 70007, DRMOCD 6
Phase Model – LSC.13 Lunar Descent

                The phase is decomposed into activities that are generally serial.
         Phase
       Transition
                                                           Activity
                         Plane                Plane
 Undock                  Change                                                                     Post DOI
                                                                                                       -                                                                              ATP for
                                              Change                      DOI Burn                   Burn                                                 Touchdown
Complete                                                                                                                        PDI Burn                                             Lunar Stay
                        Procedures            Maneuver                    Initiation                Procedures                  Initiation
                         Initiation           Complete                                              Complete


             Free                  Perform                                                                       Perform                                              Perform
                                    Plane                  Prep for                     Perform                   Lunar                      Perform                    Post
             Flight                                                                                                                          Powered
                                   Change                    DOI                         DOI                     Descent                                              Landing
           Operations                                                                                                                        Descent
                                  Maneuver                                                                        Coast                                               Checkout
           *LSC.13.1*                                    *LSC.13.3*                    *LSC.13.4*
                                   LSC.13.2                                                                    *LSC.13.5*                    *LSC.13.6*               *LSC.13.7*

                                                                                       Abort Required          Abort Required
                                                                                                                                                    LSC.100.12.7
           Abort Required         Abort Required         Abort Required                                                                         G

                                                                           LSC.100.12.4
                                                                      G                                                                                                            DRM

                                                                                                                                                                              Phase

                                                                                                                                                                              Activity

                                                                                                                                                                                 Event
                                                                                                                                                                                                  7
Activity Model – LSC.13.3 Prep for DOI
                         * Crew
                    Activities are
                     the DOI Burn                 Event                                                                      Diagram can be simulated
                    Prep Procedure
                             *
                                                                                                                 Concur
                                    Check
                                                                                                                   with
                      Crew           Altair
                                                                                                                 Execute
           AND   AND               Nav State                                                                                                             AND   AND
                                                                                                                  Burn
                                 LSC.13.3.1
                                                   State                                                        LSC.13.3.2
                                                   Vector
                                                  Accepted                                         Crew Burn
                                   Altair Nav.                                                    Concurrence
                                    State                                                                                          Crew Burn
 Plane                                                                                             Request
                                                                                                                                  Concurrence
Change
Maneuver                                               Compute                    Maneuver                                                                           DOI Burn
                                    Update
Complete             Altair                            DOI Burn                    to Burn                                                                           Initiation
                                   Nav. State
                                                       Solution             AND    Attitude                                                        AND
                                  LSC.13.3.7
                                                      LSC.13.3.3                  LSC.13.3.4
                                                                                                                     Go for DOI
                                                                   Burn Start                                          Burn
                                                                   Time and
                                                                    Final dV
                                                                                      Execute                                           Perform
                                    Altair Nav.                                         DOI                                            Final DOI
                                   State Update                                    Auto-Sequence                                      Countdown

                                                                                     LSC.13.3.5                                       LSC.13.3.6


                                     Send
             Mission                 Altair                                                                     Send Go
             Systems                 Nav.                                                                        for DOI
                                     State                                                                         Burn
                                    Update
                                                                                                                LSC.13.3.9
                                  LSC.13.3.8                                                                                                                     DRM
Goal:
-Capture how the vehicle is operated by the crew                              Phase
    - Show Crew or Other System actions and vehicle response
- Boxes should be Actions that are triggered by:                              Activity
    - Completion of prior task (only solid arrow entering)
    - A signal from another system (dashed arrow w/ data item)                 Event
                                                                                                                                                                                  8
    - Reaching a fixed start time (not shown in diagram, only shown in timeline)
Activity Model – LSC.13.3 Prep for DOI
                         * Crew
                    Activities are
                     the DOI Burn
                    Prep Procedure
                             *
                                                                                                                 Concur
                                    Check
                                                                                                                   with
                      Crew           Altair
                                                                                                                 Execute
           AND   AND               Nav State                                                                                                             AND   AND
                                                                                                                  Burn
                                 LSC.13.3.1
                                                   State                                                        LSC.13.3.2
                                                   Vector
                                                  Accepted                                         Crew Burn
                                   Altair Nav.                                                    Concurrence
                                    State                                                                                          Crew Burn
 Plane                                                                                             Request
                                                                                                                                  Concurrence
Change
Maneuver                                               Compute                    Maneuver                                                                           DOI Burn
                                    Update
Complete             Altair                            DOI Burn                    to Burn                                                                           Initiation
                                   Nav. State
                                                       Solution             AND    Attitude                                                        AND
                                  LSC.13.3.7
                                                      LSC.13.3.3                  LSC.13.3.4
                                                                                                                     Go for DOI
                                                                   Burn Start                                          Burn
                                                                   Time and
                                                                    Final dV
                                                                                      Execute                                           Perform
                                    Altair Nav.                                         DOI                                            Final DOI
                                   State Update                                    Auto-Sequence                                      Countdown

                                                                                     LSC.13.3.5                                       LSC.13.3.6


                                     Send
             Mission                 Altair                                                                     Send Go
             Systems                 Nav.                                                                        for DOI
                                     State                                                                         Burn
                                    Update
                                                                                                                LSC.13.3.9
                                  LSC.13.3.8

   Questions:
   - Is the operational concept complete? Is it Valid?
         - Are there any actions the crew or vehicle need to take to support your
         subsystem or vehicle objectives?
   - What capabilities from your subsystem or other systems are required to
   implement this operational concept?
                                                                                                                                                                                  9
WHAT Do We Want to Specify?
  Treat the Vehicle               Sustain
                                Environment                     Perform
   as a Black Box                                            Communications
  (Inside and Out)      Can the crew live
                              in it?                           Can it interact with
               Provide                                         the outside world?
            Transportation

      Can it carry and
                                                                 Accept and
     service Payload?                                             Execute
                                                                              Can it take
                                                                 Commands
      Provide                                                                 action upon
     Habitability
                                                                              Command?
Can the crew work
    out of it?

                     Perform                     Altair           Manage Vehicle
 Can it move        Maneuvers                                      Performance
                                               Functional
 and follow a                                 Architecture
  trajectory?                                                              Can it assess
                                                                          its own status?
       Establish the purpose of the System; Define Functions and Measures that
                     Implement and Quantify achieving the Purpose
                                                                                            10
The Functional Architecture

♦ A function is a process that takes inputs in and transforms these
  inputs into outputs1
♦ The functional architecture of a system contains a hierarchical
  model of the functions performed by the system1
♦ Functional Architecture
   • Capture required system behavior
   • When someone asks, “What should the Altair be able to do?”, we should be
     able to point to the functional architecture as the sum total of its capabilities
     (independent of the mission)
   • Highest-Level of the architecture developed by grouping Customer
     Functional Requirements
       − Walk through all the Cx requirements and categorize them (CARD, HSIR, C3I)
       − Group those in the category of functional or performance
♦ Functions are need based not discipline based
   • Don’t need a Command and Data Handling System                       C&DH meets
   • Do need to be able to Accept and Execute Commands                  functional need
                                                      1Source   Buede, D. , Engineering Design 11
Example Functions
                Cabin                                       Lander State
              Pressure =
                12 psi

                                                              Generate
                                           Health Request     Health and
 Cabin Pressure     Control                 (multiplexer)      Status      Lander Status
Set-point = 10 psi Pressure     Cabin                                      (Crew Display
                              Pressure =                                    or Downlink)
                                10 psi



            Functional Thread – Perform Rendezvous


          Relative
         Navigation
                                               Manage             Perform
                              Trajectory
                                               Vehicle          Translational
                               Design
          Inertial                             Events            Maneuver
         Navigation
                                                                                       12
Define Subsystem Modes
  A system mode is defined to be a distinct operating capability of the system
  during which some or all of the system's functions may be performed to a full or
  limited degree1
       • Examples: On/Off/Standby or High Data Rate/Low Data Rate
       • Both are an expression of capability

♦ Mode Matrix
   • Should be as concise a representation as possible of total vehicle capability for any
     activity in the mission
♦ Mode Characterizations
   • Mode Names should clearly articulate the level of capability and of what function
        − Status – Active – Capabilities in use; Stndby – Capabilities available but not used; Inactive– No
          capability
   Control Pressure  Automatic Pressure Control  R.EA0703
                     Emergency Pressure Control  R.EA3107/3181
   • Use Mode definitions can tie this to our current understanding of the vehicle
   Passive Cabin Pressure Relief Active  Mechanical positive pressure relief valves (PPRVs) are active, but
      do not require power. They are probably venting in this phase.




                                                                       1Source   Buede, D. , Engineering Design 13
Functional Architecture Modes Matrix
♦ Cross Correlation of sub-                                                                                                                 LSC.13 : Altair Descent :
                                         Altair Functional Relationship
  mode for each scenario                    to Operations via Modes
                                                                                                                                      LSC.13.2 : Perform
                                                                                                               LSC.13.1 : Free Flight Plane Change

   • How much capability in
                                                                                                               Operations :           Maneuver :                          LSC.13.3 : Prep for
                                                                                                               000/01:03:27           000/00:00:00                        DOI : 000/01:34:51




                                              Transportation
     each subsystem is required                                               LNDR.1.3 : Transport Crew




                                                LNDR.1 :
                                                                                                               Crew On-board                 Crew On-board                Crew On-board




                                                 Provide
     execute an activity
♦ Definition of each sub-
                                                                              LNDR.1.5 : Transport EVA
                                                                              Suits                       EVA Suits Donned           EVA Suits Donned           EVA Suits Donned




                                  Habitabilit
                                                                              LNDR.2.1 : Provide exterior




                                  LNDR.2 :
  mode is captured



                                   Provide
                                                                              viewing                     Exterior Viewing Available Exterior Viewing Available Exterior Viewing Available




                                      y
                                                                                                               Reading + Panel Lighting      Reading + Panel Lighting     Reading + Panel Lighting

♦ Capabilities should be met                                                  LNDR.2.2 : Provide Lighting On                                 On                           On




                                             LNDR.3 : Perform
  in total by requirements                                                    LNDR.3.1.1 : Estimate




                                               Maneuvers
                                                                              Inertial State                   Inertial Navigation Active    Inertial Navigation Active   Inertial Navigation Active


♦ In some cases, functions                                                    LNDR.3.2 : Perform
                                                                              Translational Maneuvers                                        Main Engine Burn
  are provided by other                                                       LNDR.3.5 : Perform
                                                                              Trajectory Design                Target Computation Active                                  Target Computation Active
  systems, mode should
                                                                     Environmen
                                                                      LNDR.4 :




                                                                              LNDR.4.1 : Control Cabin         Cabin Pressure Control        Cabin Pressure Control       Cabin Pressure Control
                                                                       Sustain
                                                                        Altair



                                                                              Pressure
  reflect other system is                                                     LNDR.4.2 : Control
                                                                                                               Active
                                                                                                               Temperature Control
                                                                                                                                             Active
                                                                                                                                             Temperature Control
                                                                                                                                                                          Active
                                                                                                                                                                          Temperature Control
                                                                              Temperature
  providing (i.e. Altair on                                                                                    Active                        Active                       Active
                                                     LNDR.5 : Accept




                                                                              LNDR.5.1 : Receive
                                                       and Execute
                                                        Commands




  Orion Power)                                                                Commands from Cx                 Receive Commands Active Receive Commands Active Receive Commands Active



                                                                              LNDR.5.2 : Receive
                                                                              Commands from Crew               Receive Commands Active Receive Commands Active Receive Commands Active
                                   cations Performan
                                  LNDR.7 : LNDR.6 :
                                   Perform Manage
                                  Communi Vehicle




                                                                              LNDR.6.2 : Perform FDIR          Perform FDIR Active           Perform FDIR Active          Perform FDIR Active
                                                                              LNDR.6.4.1: Manage Power
                                                                              Load                             Altair On Internal Power      Altair On Internal Power     Altair On Internal Power



                                                                              LNDR.7.1 : Communicate           RF-High Data Rate             RF-High Data Rate            RF-High Data Rate
                                                                              with Cx Systems                  RF-Low Data Rate              RF-Low Data Rate             RF-Low Data Rate
                                                                                                                                                                                                       14
Requirements linked to Sustain Environment

LNDR.2   Sustain Altair   LNDR.2.1    Control Pressure               R.EA0703   LSAM Cabin       The LSAM shall control cabin pressure to a        This is to facilitate pressure operation from the
         Environment                                                            Pressure         selectable setpoint between 79 (TBR-001-907)      LSAM to Orion operational pressure to the
                                                                                                 kPa (11.4 psia) to 52 (TBR-001-908) kPa (7.5      minimum nominal limit with a 34% oxygen
                                                                                                 psia) with 0.7 (TBR-001-147) kPa (0.1 psia)       materials limit and 17 kPa (2.5 psia) ppO2 crew
                                                                                                 increments for Lunar Sortie and Lunar Outpost     limit. This is to have common approach to cabin
                                                                                                 crew missions.                                    pressure management across Constellation
                                                                                                                                                   Architecture.
                          LNDR.2.2    Control Temperature            R.LNDR.024 Cabin            The Altair shall control cabin temperature per                                                        LNDR.2. Control Cabin
                                                                                Temperature      HSIR 3054 while inhabited except during suited                                                        2.1     Temperature
                                                                                Control          operations.

                          LNDR.2.3    Manage O2 and N2               R.EA3062   LSAM Cabin      The LSAM shall limit the maximum oxygen           This is to keep the oxygen concentration from        LNDR.2. Control
                                                                                Pressure Oxygen concentration within the pressurized cabin to 34% exceeding the materials certification limit. This is 2.2     Component
                                                                                Concentration (TBR-001-038) by volume for Lunar Sortie and to have common approach to cabin pressure                           Temperature
                                                                                Limits          Lunar Outpost crew missions.                      management across Constellation Architecture.

                          LNDR.2.4    Control Humidity
                          LNDR.2.5    Provide Ventilation
                          LNDR.2.6    Control Contamination          R.LNDR.023 Lunar Dust       The Altair shall limit the levels of lunar dust
                                                                                Control          contaminants of less than 10 and equal to or
                                                                                                 greater than 0.1 micron (TBR-006-004) size in
                                                                                                 the internal atmosphere below 0.05 mg/m^3.
                          LNDR.2.7    Provide Fire Detection and     R.EA3139   LSAM Fire        The LSAM shall provide fire detection and       This is to provide cabin fire detection,
                                      Surpression                               Detection and    suppression for the LSAM pressurized volume for notification, and suppression. The type of fire
                                                                                Suppression      Lunar Sortie and Lunar Outpost crew missions. detection and suppression required in the avionics
                                                                                                                                                 bays will be a function of materials selection,
                                                                                                                                                 proximity to ignition sources and oxidizers.

                          LNDR.2.8    Provide Potable Water
                          LNDR.2.9    Remove CO2
                          LNDR.2.10   Provide Waste Collection
                          LNDR.2.11   Provide Galley Service
                          LNDR.2.12   Provide Suit Loop Services
                          LNDR.2.13   Pressurize Docking Vesitbule   R.EA3137   LSAM             The LSAM shall provide not less than two          The responsibility for vestibule pressurization
                                                                                Vestibule        vestibule pressurization cycles per mission for   must be allocated between Orion and LSAM. This
                                                                                Pressurization   Lunar Sortie and Lunar Outpost crew missions.     requirement allocates responsibility for two
                                                                                Cycles                                                             pressurization cycles to LSAM. Primary and
                                                                                                                                                   contingency vestibule pressurization should
                                                                                                                                                   account for each docking in which the crewed
                                                                                                                                                   LSAM is the active vehicle. The LSAM will
                                                                                                                                                   perform the vestibule pressurization when the
                                                                                                                                                   crewed LSAM docks with the Orion.




                                           Linking requirement enforces function
                                                                                                                                                                                                                       15
Requirements Achievability Assessments
             I.D                                                                   Name
  R.EA0062                      LSAM Return Cargo Capability
  Requirement
  The LSAM shall return at least 100 kg (TBR-EARD-037) (220 lbm) of Payload from the lunar surface to the Lunar Rendezvous Orbit (LRO)
  during each crewed lunar mission.
  Rationale
  The LSAM returned mass must include the 100 kg (220 lbm) of Payload specified by ESMD in addition to the crew and Flight Crew
  Equipment. This requirement applies to each crewed lunar mission and is needed to size the LSAM ascent stage.
  Comments
  Quality: Add the following to the rationale "This payload is to be stored in the pressurized environment, with no power / data / thermal
  services provided. The payload may include rocks, ISRU product samples, crew biological samples, failed components, crew personal
  effects. Anything which leaves the lunar surface to be returned to Earth, excluding crew and crew equipment, can be considered payload.
  This allocation is a total return mass allocation that includes containment and interface hardware masses required for transport. Note the
  objective in R.EA6304 is 250 kg."
  This requirement should be a KDR (as listed on the Lunar KDRs for Altair at LCCR).
  KDR        Verification Reqt.             Reqt. Group            SRD POC            Req Status       Reqt.       Criticality      VI Involved
               Method         Type                                                                   Compliance                   Organization
           Analysis        MOE           Provide          Dave McKissock          Agreed          green - High    C1           Altair Flight
                                         Transportation                                           Likelihood of                Systems
                                                                                                  Compliance

♦ Validation (Why a requirement on us?)
      •    Is this philosophically the right requirement to set?                                           r – Low Likelihood of
      •    Is the value achievable/affordable per the results of an analysis task                          Compliance (<50% chance)
♦ Verification (How do we apply it?)                                                                       y – Medium Likelihood of
      •    Is it clear how the customer wants you to measure the value?                                    Compliance (50-80% chance)
      •    How will you know when this requirement is implemented?
                                                                                                           g – High Likelihood of
♦ Achievability (How are we doing against it?)                                                             Compliance (>80% chance)
      •    Is the likelihood of compliance in the final design high/medium/low?
                                                                                                           grey - Unassessed
      •      Choose from: Inherent in current design, captured in T/O, not assessed
               − If not assessed, tied to future task or risk?

          Close the Requirements Development Loop by Assessing
                    Achievability in a Design Concept                                                                                             16
Enablers for MBSE and Streamlining
                 Requirements Development

♦ A relational database for requirements and models
   • Cx Program uses CRADLE to store both requirements and models to
     enable traceability between objects through links
♦ Clear understanding of SRR products
   • Establish upfront how all of the SRR Criteria will be met and how traceability
     will be demonstrated and use these products to drive the process
   • Get comfortable reviewing the raw products within the native environment to
     accelerate development by eliminating post-processing into chart packages
♦ Detailed process definition to eliminate development bottlenecks
   • Develop criteria for generating every product to minimize variability
   • Organize the team for greatest distribution of effort
   • Utilize requirement development metrics and database reports measure
     progress and reinforce lagging areas

  Establishing these business processes as a NASA institutional core
      competency can greatly reduce project start-up resources
                                                                                      17
Robert.bayt

Weitere ähnliche Inhalte

Was ist angesagt?

Standing cxp.panel
Standing cxp.panelStanding cxp.panel
Standing cxp.panelNASAPMC
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbainNASAPMC
 
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...grssieee
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastleNASAPMC
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallengeNASAPMC
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
Unger massey
Unger masseyUnger massey
Unger masseyNASAPMC
 
Crumbley.tim
Crumbley.timCrumbley.tim
Crumbley.timNASAPMC
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont MineHudbay Minerals Inc.
 
Kelly.j.crumbley.t
Kelly.j.crumbley.tKelly.j.crumbley.t
Kelly.j.crumbley.tNASAPMC
 
Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
Robert.ess
Robert.essRobert.ess
Robert.essNASAPMC
 
Stambolianv2
Stambolianv2Stambolianv2
Stambolianv2NASAPMC
 
FME and the Chicago Region Environmental and Transportation Efficiency Program
FME and the Chicago Region Environmental and Transportation Efficiency ProgramFME and the Chicago Region Environmental and Transportation Efficiency Program
FME and the Chicago Region Environmental and Transportation Efficiency ProgramSafe Software
 

Was ist angesagt? (18)

Standing cxp.panel
Standing cxp.panelStanding cxp.panel
Standing cxp.panel
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...TH3.L10.4	 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
TH3.L10.4 - SOIL MOISTURE ACTIVE PASSIVE (SMAP) CALIBRATION AND VALIDATION P...
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastle
 
Dumbacher2012 pmchallenge
Dumbacher2012 pmchallengeDumbacher2012 pmchallenge
Dumbacher2012 pmchallenge
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
9797v00 Boeing Smv Roi
9797v00 Boeing Smv Roi9797v00 Boeing Smv Roi
9797v00 Boeing Smv Roi
 
Unger massey
Unger masseyUnger massey
Unger massey
 
Crumbley.tim
Crumbley.timCrumbley.tim
Crumbley.tim
 
P repetitive
P repetitiveP repetitive
P repetitive
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont Mine
 
Dirks cgsic brief 2012
Dirks cgsic brief 2012Dirks cgsic brief 2012
Dirks cgsic brief 2012
 
Kelly.j.crumbley.t
Kelly.j.crumbley.tKelly.j.crumbley.t
Kelly.j.crumbley.t
 
Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
Robert.ess
Robert.essRobert.ess
Robert.ess
 
Huebner
HuebnerHuebner
Huebner
 
Stambolianv2
Stambolianv2Stambolianv2
Stambolianv2
 
FME and the Chicago Region Environmental and Transportation Efficiency Program
FME and the Chicago Region Environmental and Transportation Efficiency ProgramFME and the Chicago Region Environmental and Transportation Efficiency Program
FME and the Chicago Region Environmental and Transportation Efficiency Program
 

Andere mochten auch

Fuller.david
Fuller.davidFuller.david
Fuller.davidNASAPMC
 
Miller.charles
Miller.charlesMiller.charles
Miller.charlesNASAPMC
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butlerNASAPMC
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karenNASAPMC
 
Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorakNASAPMC
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnershipsNASAPMC
 
Mark wiese
Mark wieseMark wiese
Mark wieseNASAPMC
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.rNASAPMC
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brianNASAPMC
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askinsNASAPMC
 
Ken poole
Ken pooleKen poole
Ken pooleNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgNASAPMC
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathanNASAPMC
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12NASAPMC
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.edNASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michaelNASAPMC
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.claytonNASAPMC
 

Andere mochten auch (20)

Fuller.david
Fuller.davidFuller.david
Fuller.david
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butler
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karen
 
Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
Shinn
ShinnShinn
Shinn
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnerships
 
Mark wiese
Mark wieseMark wiese
Mark wiese
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.r
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brian
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askins
 
Ken poole
Ken pooleKen poole
Ken poole
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathan
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.clayton
 

Ähnlich wie Robert.bayt

Leonard.matthew
Leonard.matthewLeonard.matthew
Leonard.matthewNASAPMC
 
PROSA - Eclipse Is Just What?
PROSA - Eclipse Is Just What?PROSA - Eclipse Is Just What?
PROSA - Eclipse Is Just What?Tonny Madsen
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
Threading Made Easy! A Busy Developer’s Guide to Kotlin Coroutines
Threading Made Easy! A Busy Developer’s Guide to Kotlin CoroutinesThreading Made Easy! A Busy Developer’s Guide to Kotlin Coroutines
Threading Made Easy! A Busy Developer’s Guide to Kotlin CoroutinesLauren Yew
 
L0001 - The Terminology of the Eclipse Platform
L0001 - The Terminology of the Eclipse PlatformL0001 - The Terminology of the Eclipse Platform
L0001 - The Terminology of the Eclipse PlatformTonny Madsen
 
Tech Talk @ Google on Flink Fault Tolerance and HA
Tech Talk @ Google on Flink Fault Tolerance and HATech Talk @ Google on Flink Fault Tolerance and HA
Tech Talk @ Google on Flink Fault Tolerance and HAParis Carbone
 
Graphs: Fabric of DevOps
Graphs: Fabric of DevOpsGraphs: Fabric of DevOps
Graphs: Fabric of DevOpsNeo4j
 
James.lewis
James.lewisJames.lewis
James.lewisNASAPMC
 
Human Exploration Framework Team Presentation
Human Exploration Framework Team PresentationHuman Exploration Framework Team Presentation
Human Exploration Framework Team PresentationBill Duncan
 
Ruszkowski.james
Ruszkowski.jamesRuszkowski.james
Ruszkowski.jamesNASAPMC
 
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...Arthur Berezin
 
OCCI status update
OCCI status updateOCCI status update
OCCI status updatebefreax
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Dave Callen
 
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your applicationjavablend
 
NTTs Journey with Openstack-final
NTTs Journey with Openstack-finalNTTs Journey with Openstack-final
NTTs Journey with Openstack-finalshintaro mizuno
 
Bibhas automation testing
Bibhas automation testingBibhas automation testing
Bibhas automation testingBibhas Senapati
 

Ähnlich wie Robert.bayt (20)

Leonard.matthew
Leonard.matthewLeonard.matthew
Leonard.matthew
 
PROSA - Eclipse Is Just What?
PROSA - Eclipse Is Just What?PROSA - Eclipse Is Just What?
PROSA - Eclipse Is Just What?
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
Threading Made Easy! A Busy Developer’s Guide to Kotlin Coroutines
Threading Made Easy! A Busy Developer’s Guide to Kotlin CoroutinesThreading Made Easy! A Busy Developer’s Guide to Kotlin Coroutines
Threading Made Easy! A Busy Developer’s Guide to Kotlin Coroutines
 
L0001 - The Terminology of the Eclipse Platform
L0001 - The Terminology of the Eclipse PlatformL0001 - The Terminology of the Eclipse Platform
L0001 - The Terminology of the Eclipse Platform
 
Tech Talk @ Google on Flink Fault Tolerance and HA
Tech Talk @ Google on Flink Fault Tolerance and HATech Talk @ Google on Flink Fault Tolerance and HA
Tech Talk @ Google on Flink Fault Tolerance and HA
 
Graphs: Fabric of DevOps
Graphs: Fabric of DevOpsGraphs: Fabric of DevOps
Graphs: Fabric of DevOps
 
James.lewis
James.lewisJames.lewis
James.lewis
 
Eclipse - Single Source;Three Runtimes
Eclipse - Single Source;Three RuntimesEclipse - Single Source;Three Runtimes
Eclipse - Single Source;Three Runtimes
 
Human Exploration Framework Team Presentation
Human Exploration Framework Team PresentationHuman Exploration Framework Team Presentation
Human Exploration Framework Team Presentation
 
Notes for scft
Notes for scftNotes for scft
Notes for scft
 
Ruszkowski.james
Ruszkowski.jamesRuszkowski.james
Ruszkowski.james
 
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...
Kubernetes vs dockers swarm supporting onap oom on multi-cloud multi-stack en...
 
OCCI status update
OCCI status updateOCCI status update
OCCI status update
 
Introducing spring
Introducing springIntroducing spring
Introducing spring
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
 
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application
[Pilarczyk] Adrenaline programing implementing - SOA and BPM in your application
 
2012 11 Openstack China
2012 11 Openstack China2012 11 Openstack China
2012 11 Openstack China
 
NTTs Journey with Openstack-final
NTTs Journey with Openstack-finalNTTs Journey with Openstack-final
NTTs Journey with Openstack-final
 
Bibhas automation testing
Bibhas automation testingBibhas automation testing
Bibhas automation testing
 

Mehr von NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Mehr von NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Kürzlich hochgeladen

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????blackmambaettijean
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 

Kürzlich hochgeladen (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 

Robert.bayt

  • 1. Streamlining Requirements Development through Model-based Systems Engineering Robert Bayt, Ann Christian, Philip Nerren, and Rich DeLoof Altair Project Integration Used with Permission
  • 2. Role of the System Requirements Document Objectives ♦ Capture the vehicle-level capabilities in a set of complete, necessary, clear, attainable, traceable, and verifiable statements of need (Requirements) If it is not needed by Cx, it is • Should not be unduly restrictive1 not a vehicle-level capability • Sets limits that eliminate items outside the boundaries drawn • Encourage competition (or alternatives) • Capture source and reason of requirement ♦ Establish the verification methods that will lead to product acceptance • These should be reproducible assessment methods ♦ Allocate requirements to the element-level to facilitate vehicle architecture development and integration The SRD sets the standards by which the Product will be evaluated 1MIL-STD-961E - Reference 2
  • 3. Where do Requirements Come From? ♦ The Customer • One should always listen to the Voice of the Customer when establishing what the End Item should be able to do • On Altair, we walk through the CARD Allocated Requirements and Categorize by: − MOE − Operational − Functional/Performance − Safety/-ilities ♦ Operational Analysis • Develop deep understanding of Concept of Operations to identify new End Item Capabilities that are required • Evaluate operational constraints ♦ Technical Disciplines Best Practices • Work with discipline experts to establish capabilities required “to do the job” ♦ Design and Construction Standards • Use industry standards to specify how the product is designed 3
  • 4. Requirements Development Approach ♦ Role of the Project is to validate requirements DRM • Necessary Phase • Attainable • Traceable Activity • Clear and Verifiable ♦ Vehicle Functionality should flow Event from the Concept of Operations • How is the vehicle to be Functional operated? Modes • What functionality should be on-board to support these operations? Requirements Goal: Ensure Traceability from Missions to Functions to Requirements and Drive for Completeness 4
  • 5. Requirements Development Approach - 2 ♦ Required vehicle functionality flows from the concept of operations and system of systems architecture. Prior to Models-Based Systems Engineering (MBSE): ♦ OPSCON articulated our Concept of Operations • Captures at the phase/activity-level the general roles of the various systems in executing the mission • Timeline captures the events that make up these operations with some articulation of roles Implementing MBSE: ♦ OPSModels are flow diagrams that depict operations described in OPSCON with an allocation of responsibility of those events • Capture discrete events that make up an activity • Capture dependencies and data flow that make up those activities • Drive traceability of Operational requirements • Provide traceability of functionality to vehicle ♦ Traceability comes through linking of data objects, and reports querying database depicts this traceability 5
  • 6. Design Reference Mission: Lunar Sortie Crew Design Reference Mission: Lunar Sortie Crew EDS LOI Burn LOI Burn Undock ATP for Ascent Jettison Procedures Sequence Complete Lunar Stay Preparation Complete Begun Complete Start Pre-Surface Lunar TLI Trans-Lunar LOI Operations Altair Surface Ascent & Operations Cruise Operations (Docked) Descent AND Operations AND RPOD Operations LSC.9 LSC.10 LSC.11 LSC.12 LSC.13 LSC.14 LSC.16 TLI Burn Docking Prep Start complete Earth Orbit Lunar Operations Orbit Maintenance Post-Surface LSC.8 Operations LSC.15 Docking LSC.17 complete Altair/LIDS LEO RPOD Jettison Operations LSC.7 ATP for Trans-Earth Orbit Ops Cruise LEO LSC.18 Final Configuration Entry (Post-Insertion) Prep <EI-12> LSC.6 Orbit Insertion Burn Earth Arrival Operational Operations Complete Ascent LSC.19 Hierarchy SM LSC.5 Separation Terminology Liftoff Phase Re-entry/Entry Launch (Operation) LSC.20 Fwd Bay DRM LSC.4 Cover Jettison LCD CTS Pad Operations Integrated Operations Stand Alone Post-Flight Processing Recovery Descent and Phase Operations Landing LSC.3 LSC.2 LSC.23 LSC.22 LSC.1 LSC.21 Activity MLP Hard Transport to Arrival Arrival at Sub- Integration DD250 at Refurb Post-Flight Touchdown Down Facility Complete Site Processing Facility Activity Trigger Event (Data Item) Authoritative Source: CxP 70007, DRMOCD 6
  • 7. Phase Model – LSC.13 Lunar Descent The phase is decomposed into activities that are generally serial. Phase Transition Activity Plane Plane Undock Change Post DOI - ATP for Change DOI Burn Burn Touchdown Complete PDI Burn Lunar Stay Procedures Maneuver Initiation Procedures Initiation Initiation Complete Complete Free Perform Perform Perform Plane Prep for Perform Lunar Perform Post Flight Powered Change DOI DOI Descent Landing Operations Descent Maneuver Coast Checkout *LSC.13.1* *LSC.13.3* *LSC.13.4* LSC.13.2 *LSC.13.5* *LSC.13.6* *LSC.13.7* Abort Required Abort Required LSC.100.12.7 Abort Required Abort Required Abort Required G LSC.100.12.4 G DRM Phase Activity Event 7
  • 8. Activity Model – LSC.13.3 Prep for DOI * Crew Activities are the DOI Burn Event Diagram can be simulated Prep Procedure * Concur Check with Crew Altair Execute AND AND Nav State AND AND Burn LSC.13.3.1 State LSC.13.3.2 Vector Accepted Crew Burn Altair Nav. Concurrence State Crew Burn Plane Request Concurrence Change Maneuver Compute Maneuver DOI Burn Update Complete Altair DOI Burn to Burn Initiation Nav. State Solution AND Attitude AND LSC.13.3.7 LSC.13.3.3 LSC.13.3.4 Go for DOI Burn Start Burn Time and Final dV Execute Perform Altair Nav. DOI Final DOI State Update Auto-Sequence Countdown LSC.13.3.5 LSC.13.3.6 Send Mission Altair Send Go Systems Nav. for DOI State Burn Update LSC.13.3.9 LSC.13.3.8 DRM Goal: -Capture how the vehicle is operated by the crew Phase - Show Crew or Other System actions and vehicle response - Boxes should be Actions that are triggered by: Activity - Completion of prior task (only solid arrow entering) - A signal from another system (dashed arrow w/ data item) Event 8 - Reaching a fixed start time (not shown in diagram, only shown in timeline)
  • 9. Activity Model – LSC.13.3 Prep for DOI * Crew Activities are the DOI Burn Prep Procedure * Concur Check with Crew Altair Execute AND AND Nav State AND AND Burn LSC.13.3.1 State LSC.13.3.2 Vector Accepted Crew Burn Altair Nav. Concurrence State Crew Burn Plane Request Concurrence Change Maneuver Compute Maneuver DOI Burn Update Complete Altair DOI Burn to Burn Initiation Nav. State Solution AND Attitude AND LSC.13.3.7 LSC.13.3.3 LSC.13.3.4 Go for DOI Burn Start Burn Time and Final dV Execute Perform Altair Nav. DOI Final DOI State Update Auto-Sequence Countdown LSC.13.3.5 LSC.13.3.6 Send Mission Altair Send Go Systems Nav. for DOI State Burn Update LSC.13.3.9 LSC.13.3.8 Questions: - Is the operational concept complete? Is it Valid? - Are there any actions the crew or vehicle need to take to support your subsystem or vehicle objectives? - What capabilities from your subsystem or other systems are required to implement this operational concept? 9
  • 10. WHAT Do We Want to Specify? Treat the Vehicle Sustain Environment Perform as a Black Box Communications (Inside and Out) Can the crew live in it? Can it interact with Provide the outside world? Transportation Can it carry and Accept and service Payload? Execute Can it take Commands Provide action upon Habitability Command? Can the crew work out of it? Perform Altair Manage Vehicle Can it move Maneuvers Performance Functional and follow a Architecture trajectory? Can it assess its own status? Establish the purpose of the System; Define Functions and Measures that Implement and Quantify achieving the Purpose 10
  • 11. The Functional Architecture ♦ A function is a process that takes inputs in and transforms these inputs into outputs1 ♦ The functional architecture of a system contains a hierarchical model of the functions performed by the system1 ♦ Functional Architecture • Capture required system behavior • When someone asks, “What should the Altair be able to do?”, we should be able to point to the functional architecture as the sum total of its capabilities (independent of the mission) • Highest-Level of the architecture developed by grouping Customer Functional Requirements − Walk through all the Cx requirements and categorize them (CARD, HSIR, C3I) − Group those in the category of functional or performance ♦ Functions are need based not discipline based • Don’t need a Command and Data Handling System C&DH meets • Do need to be able to Accept and Execute Commands functional need 1Source Buede, D. , Engineering Design 11
  • 12. Example Functions Cabin Lander State Pressure = 12 psi Generate Health Request Health and Cabin Pressure Control (multiplexer) Status Lander Status Set-point = 10 psi Pressure Cabin (Crew Display Pressure = or Downlink) 10 psi Functional Thread – Perform Rendezvous Relative Navigation Manage Perform Trajectory Vehicle Translational Design Inertial Events Maneuver Navigation 12
  • 13. Define Subsystem Modes A system mode is defined to be a distinct operating capability of the system during which some or all of the system's functions may be performed to a full or limited degree1 • Examples: On/Off/Standby or High Data Rate/Low Data Rate • Both are an expression of capability ♦ Mode Matrix • Should be as concise a representation as possible of total vehicle capability for any activity in the mission ♦ Mode Characterizations • Mode Names should clearly articulate the level of capability and of what function − Status – Active – Capabilities in use; Stndby – Capabilities available but not used; Inactive– No capability Control Pressure  Automatic Pressure Control  R.EA0703  Emergency Pressure Control  R.EA3107/3181 • Use Mode definitions can tie this to our current understanding of the vehicle Passive Cabin Pressure Relief Active  Mechanical positive pressure relief valves (PPRVs) are active, but do not require power. They are probably venting in this phase. 1Source Buede, D. , Engineering Design 13
  • 14. Functional Architecture Modes Matrix ♦ Cross Correlation of sub- LSC.13 : Altair Descent : Altair Functional Relationship mode for each scenario to Operations via Modes LSC.13.2 : Perform LSC.13.1 : Free Flight Plane Change • How much capability in Operations : Maneuver : LSC.13.3 : Prep for 000/01:03:27 000/00:00:00 DOI : 000/01:34:51 Transportation each subsystem is required LNDR.1.3 : Transport Crew LNDR.1 : Crew On-board Crew On-board Crew On-board Provide execute an activity ♦ Definition of each sub- LNDR.1.5 : Transport EVA Suits EVA Suits Donned EVA Suits Donned EVA Suits Donned Habitabilit LNDR.2.1 : Provide exterior LNDR.2 : mode is captured Provide viewing Exterior Viewing Available Exterior Viewing Available Exterior Viewing Available y Reading + Panel Lighting Reading + Panel Lighting Reading + Panel Lighting ♦ Capabilities should be met LNDR.2.2 : Provide Lighting On On On LNDR.3 : Perform in total by requirements LNDR.3.1.1 : Estimate Maneuvers Inertial State Inertial Navigation Active Inertial Navigation Active Inertial Navigation Active ♦ In some cases, functions LNDR.3.2 : Perform Translational Maneuvers Main Engine Burn are provided by other LNDR.3.5 : Perform Trajectory Design Target Computation Active Target Computation Active systems, mode should Environmen LNDR.4 : LNDR.4.1 : Control Cabin Cabin Pressure Control Cabin Pressure Control Cabin Pressure Control Sustain Altair Pressure reflect other system is LNDR.4.2 : Control Active Temperature Control Active Temperature Control Active Temperature Control Temperature providing (i.e. Altair on Active Active Active LNDR.5 : Accept LNDR.5.1 : Receive and Execute Commands Orion Power) Commands from Cx Receive Commands Active Receive Commands Active Receive Commands Active LNDR.5.2 : Receive Commands from Crew Receive Commands Active Receive Commands Active Receive Commands Active cations Performan LNDR.7 : LNDR.6 : Perform Manage Communi Vehicle LNDR.6.2 : Perform FDIR Perform FDIR Active Perform FDIR Active Perform FDIR Active LNDR.6.4.1: Manage Power Load Altair On Internal Power Altair On Internal Power Altair On Internal Power LNDR.7.1 : Communicate RF-High Data Rate RF-High Data Rate RF-High Data Rate with Cx Systems RF-Low Data Rate RF-Low Data Rate RF-Low Data Rate 14
  • 15. Requirements linked to Sustain Environment LNDR.2 Sustain Altair LNDR.2.1 Control Pressure R.EA0703 LSAM Cabin The LSAM shall control cabin pressure to a This is to facilitate pressure operation from the Environment Pressure selectable setpoint between 79 (TBR-001-907) LSAM to Orion operational pressure to the kPa (11.4 psia) to 52 (TBR-001-908) kPa (7.5 minimum nominal limit with a 34% oxygen psia) with 0.7 (TBR-001-147) kPa (0.1 psia) materials limit and 17 kPa (2.5 psia) ppO2 crew increments for Lunar Sortie and Lunar Outpost limit. This is to have common approach to cabin crew missions. pressure management across Constellation Architecture. LNDR.2.2 Control Temperature R.LNDR.024 Cabin The Altair shall control cabin temperature per LNDR.2. Control Cabin Temperature HSIR 3054 while inhabited except during suited 2.1 Temperature Control operations. LNDR.2.3 Manage O2 and N2 R.EA3062 LSAM Cabin The LSAM shall limit the maximum oxygen This is to keep the oxygen concentration from LNDR.2. Control Pressure Oxygen concentration within the pressurized cabin to 34% exceeding the materials certification limit. This is 2.2 Component Concentration (TBR-001-038) by volume for Lunar Sortie and to have common approach to cabin pressure Temperature Limits Lunar Outpost crew missions. management across Constellation Architecture. LNDR.2.4 Control Humidity LNDR.2.5 Provide Ventilation LNDR.2.6 Control Contamination R.LNDR.023 Lunar Dust The Altair shall limit the levels of lunar dust Control contaminants of less than 10 and equal to or greater than 0.1 micron (TBR-006-004) size in the internal atmosphere below 0.05 mg/m^3. LNDR.2.7 Provide Fire Detection and R.EA3139 LSAM Fire The LSAM shall provide fire detection and This is to provide cabin fire detection, Surpression Detection and suppression for the LSAM pressurized volume for notification, and suppression. The type of fire Suppression Lunar Sortie and Lunar Outpost crew missions. detection and suppression required in the avionics bays will be a function of materials selection, proximity to ignition sources and oxidizers. LNDR.2.8 Provide Potable Water LNDR.2.9 Remove CO2 LNDR.2.10 Provide Waste Collection LNDR.2.11 Provide Galley Service LNDR.2.12 Provide Suit Loop Services LNDR.2.13 Pressurize Docking Vesitbule R.EA3137 LSAM The LSAM shall provide not less than two The responsibility for vestibule pressurization Vestibule vestibule pressurization cycles per mission for must be allocated between Orion and LSAM. This Pressurization Lunar Sortie and Lunar Outpost crew missions. requirement allocates responsibility for two Cycles pressurization cycles to LSAM. Primary and contingency vestibule pressurization should account for each docking in which the crewed LSAM is the active vehicle. The LSAM will perform the vestibule pressurization when the crewed LSAM docks with the Orion. Linking requirement enforces function 15
  • 16. Requirements Achievability Assessments I.D Name R.EA0062 LSAM Return Cargo Capability Requirement The LSAM shall return at least 100 kg (TBR-EARD-037) (220 lbm) of Payload from the lunar surface to the Lunar Rendezvous Orbit (LRO) during each crewed lunar mission. Rationale The LSAM returned mass must include the 100 kg (220 lbm) of Payload specified by ESMD in addition to the crew and Flight Crew Equipment. This requirement applies to each crewed lunar mission and is needed to size the LSAM ascent stage. Comments Quality: Add the following to the rationale "This payload is to be stored in the pressurized environment, with no power / data / thermal services provided. The payload may include rocks, ISRU product samples, crew biological samples, failed components, crew personal effects. Anything which leaves the lunar surface to be returned to Earth, excluding crew and crew equipment, can be considered payload. This allocation is a total return mass allocation that includes containment and interface hardware masses required for transport. Note the objective in R.EA6304 is 250 kg." This requirement should be a KDR (as listed on the Lunar KDRs for Altair at LCCR). KDR Verification Reqt. Reqt. Group SRD POC Req Status Reqt. Criticality VI Involved Method Type Compliance Organization Analysis MOE Provide Dave McKissock Agreed green - High C1 Altair Flight Transportation Likelihood of Systems Compliance ♦ Validation (Why a requirement on us?) • Is this philosophically the right requirement to set? r – Low Likelihood of • Is the value achievable/affordable per the results of an analysis task Compliance (<50% chance) ♦ Verification (How do we apply it?) y – Medium Likelihood of • Is it clear how the customer wants you to measure the value? Compliance (50-80% chance) • How will you know when this requirement is implemented? g – High Likelihood of ♦ Achievability (How are we doing against it?) Compliance (>80% chance) • Is the likelihood of compliance in the final design high/medium/low? grey - Unassessed • Choose from: Inherent in current design, captured in T/O, not assessed − If not assessed, tied to future task or risk? Close the Requirements Development Loop by Assessing Achievability in a Design Concept 16
  • 17. Enablers for MBSE and Streamlining Requirements Development ♦ A relational database for requirements and models • Cx Program uses CRADLE to store both requirements and models to enable traceability between objects through links ♦ Clear understanding of SRR products • Establish upfront how all of the SRR Criteria will be met and how traceability will be demonstrated and use these products to drive the process • Get comfortable reviewing the raw products within the native environment to accelerate development by eliminating post-processing into chart packages ♦ Detailed process definition to eliminate development bottlenecks • Develop criteria for generating every product to minimize variability • Organize the team for greatest distribution of effort • Utilize requirement development metrics and database reports measure progress and reinforce lagging areas Establishing these business processes as a NASA institutional core competency can greatly reduce project start-up resources 17