SlideShare a Scribd company logo
1 of 18
Download to read offline
Managing the Ares I-X First Stage IPT
                     “Life on the Critical Path”




                                    Chris Calfee
                             Ares I-X First Stage Lead
                            Marshall Space Flight Center
                       NASA Project Management Challenge 2010
                                    Galveston, TX
                                 February 9-10, 2010
Used with permission                                            1
Agenda


                  ♦ Introduction to First Stage
                           • Hardware
                           • Mission
                           • Organization
                  ♦ Ares I-X Life-Cycle
                           • Significant Events
                           • Top Level Schedule
                           • Additional Pressure Points
                  ♦ Dealing with the Pressure
                           • Putting the Team Together
                           • Key Decisions Made
                           • Tools Implemented
                  ♦ Conclusions and Lessons
                    Learned




National Aeronautics and Space Administration                      2
First Stage Technical Overview

                                                                ♦ Heritage Hardware
                                                                    • 4 Segment Reusable Solid Rocket Motor
                                                                      (RSRM) w/Nozzle
                                                                    • Thrust Vector Control (TVC)
                                                                    • Flight Termination System (FTS)
                                                                    • Nose Cap w/Thrusters
                                                                    • Booster Separation Motors (BSMs)

                                                                ♦ Modified Heritage
                                                                    • 1st Stage Provided Avionics (Shuttle Derived
                                                                      Avionics) (ISC, RCU, and APUC)
                                                                    • Aft Skirt
                                                                    • T-0

                                                                ♦ New Developments Specifically for AIX
                                                                    •   Fifth Segment Simulator (5SS)
                                                                    •   Forward Skirt (FS)
                                                                    •   Forward Skirt Extension (FSE)
                                                                    •   Main Parachute Support Structure (MPSS)
                                                                    •   Frustum

                                                                ♦ Ares I Designs
                                                                    • Parachutes
                                                                    • FTS Extension to Aft Segment

National Aeronautics and Space Administration                                                                        3
Ares I-X First Stage Major Hardware

    Finished Stage will also include:
    Development Flight Instrumentation Installed
    Systems Tunnel Cables & Covers Installed                         Upper Stage Interface
    Complete Cable & Instrumentation Interfaces
                                                                     Separation and Deceleration
                                                                     System Installed
                                                                     Pad Stabilization Connection Point
                    Insulated and Cast
                 Forward Segment with
                       Igniter Installed
                                                     Forward Assembly


                   Insulated and Cast
              Forward Center Segment                                     Avionics Pallet Installed
                                                                         (all except flight computer & two RRGUs)




                     Insulated and Cast
                    Aft Center Segment
                                                   Fifth Segment Simulator

                   Insulated and Cast
            Aft Segment with Forward
           Nozzle Assembly Installed                                     12 GFP BTMs/BDMs Installed
Modified Systems Tunnel for FTS LSC                                      TVC System (incl. APUC) Installed
                                                                         RRGU Installed
                Aft Exit Cone Assembly                                   Only T-0 Electrical Interface
                                                    Aft Skirt Assembly
                      Four Segment Motor

                                                                                                                    4
Ares I-X First Stage Recovery Sequence
    Re-entry Mass Properties with BDMs, BTMs, and 3654-lb ballast on Aft Skirt
Ares I-X Executive Summary
2006                       2007                                                 2008                                                       2009
O N D     J     F M A M    J    J   A   S O N D          J     F M A M           J    J   A   S O N D              J     F M A M           J     J     A     S O N D                J F
                                                                                                             STS-127
                                                                                                                             STS-125/128                    STS-129
SRR                  PDR                                       CDR 1                 CDR 2                                                       ARR          FS EAR

                                                                                                                                                   FSAR              Post Flight Analysis



       Design
                               Hardware Fabricate & Assemble
                                    Design                             Impl & Mod                                                MLP/VAB/CCC ORR
                                   Ground Systems                                                                                                                   PAD ORR

                                                                 SIL Testing

                                                     Fwd Assy & 5SS Engineering / Fabrication
                                                                                                                      14
                                                                       Fwd Assy & 5SS Processing                 FSAM
                                                                                                                  30 05
                                                                                                      04                RoCS
                                                                                                           USS      29
                                                                                                                         CM/LAS
                                                                                                                            19
                                                                                                                               Motor Segments
                                                                                                                                         11
                                                                                                                              Fwd Assy         5th Seg Sim

                                                 VAB High Bay 4 - Offline Stacking / Config Testing
                                                                                                                                         08
                                                                                                                                              Aft Skirt
                                                                                                                       RPSF Processing
                                                                                                                                                                    20
                                                                               VAB HB 3 - MLP Stacking / Integrated Testing / Closeouts                  Roll to Pad
                                                                                                                                               Pwr On
                                                                                                                              Mate Review 30       LRR 09
                                                                                                                                          FTRR Dry Run 15
                                                                                                                                         Roll Out Review 17
                                                                                                                                                    FTRR 23
                                                                                                                                          L-1 Day Review 26
                                                                                                                                                          Pad Ops
                                                                                                                                                                         Ares I-X Flight
                                                                                                                                                                         Oct 28, 2009
                                                                                                                                                                                        6
Ares I-X First Stage IPT (MSFC)
            Safety & Mission                                     Ares I-X
                                                                                                                                 Chief Engineer
            Assurance ( S& MA                                    First Stage IPT
            )
                                                                                                                                 Mike Phipps
            John Crisler, Lead                                                 Chris Calfee
                                                                                   Lead
             Brent Malone
                                                                               Jay Nichols
                                                                                  Deputy


                                                                                                                  Systems Engineering
                          Business
                                                                                                                  & Integration (SE&I)
                     Janet Crawford               Steve McGraw                                                                 Harry Craft
                         Budget                   Schedules                                                                    LSE
                                                                                                          Bob Williams       Aaron Sumner          David Bath
                                                                                                          Verification       SE Coordination       Verification




                             Fifth Segment                                                                                     Forward
                                                                  Aft Skirt                       RSRM
                             Simulator                                                                                         Assemblies


                                Beth Cook                        Jay Nichols                  Yvonne Villegas                  Bill Claunch




                                                KSC               Recovery
          Structures                                                                           Pyro                Deceleration                SDA (Avionics)
                                                Operations        & Disassembly

    Keith Higginbotham                          Tony Smith          Mike Phipps            Brad Perkins                  Ron King              Robert Cooper



National Aeronautics and Space Administration                                                                                                                     7
Significant Events During the Life Cycle


             ♦ ATP May 2006 (April 15, 2009 Launch)
                     • Motor Delivery 8/8/2008
                     • Forward Assembly/5SS Delivery 1/30/2009
                     • Aft Skirt Delivery 12/12/2008
             ♦ 750 DFI Sensors on Vehicle, 325 on First Stage
             ♦ April 2007 -1st Lean Event and Project Re-Organization
             ♦ August 2007 - Separation Plane Change
                     • Moved Separation Plane from Top of Interstage to Bottom of Frustum
                     • Moved Separation and Tumble Motors to Aft Skirt
                             − Aft Skirt Moved to Critical Path Along with Forward Assemblies

             ♦ Summer of Lean
             ♦ PDR and CDR “Slippages”
                     • 4-10 Months
                     • No Change to Launch Date



National Aeronautics and Space Administration                                                   8
The “Leaning” of First Stage Delivery Dates




                                                       Original Delivery   Evolved
                                                             Dates          Dates
                                      Motor                  8/8/08        7/17/08
                                      Forward
                                      Assembly              1/30/09        12/1/08
                                      5SS                   1/30/09        12/15/08
                                      Aft Skirt             12/12/08       11/19/08


                                      Assumptions:
                                      4/15/09 Launch Date
                                      May 2006 ATP




National Aeronautics and Space Administration                                         9
Ares I-X Major Milestones


                            Launch
                            4/15/09




                                      10
Other Interesting Events
            ♦ Forward Assembly and Fifth Segment Simulator Fabrication
                    • “Small” Shop in Indianapolis, Major Tool & Machine
                    • Centralized Location for All Major FS Fab
                    • Six Major Pieces of Structure
                             − 3 Aluminum
                             − 3 Steel
                    • Shortage of Welders
                    • Lack of Experience with “Flight Hardware”
            ♦ Motor Shipment
                    • Pressure was Applied to Ship the Motor to KSC Before it was Ready
                    • KSC Had No Plan in Place to Complete Instrumentation
                    • First Stage Refused
            ♦ Forward Assembly Processing
                    • KSC Didn’t Approve FA/5SS of Astrotech Processing, Wanted it Done at KSC
            ♦ Harness Issues
                    • Availability
                    • Testing
                    • Aluminum Tape
            ♦ ATK-USA Contract Squabbles
            ♦ Safety Violations

National Aeronautics and Space Administration                                                    11
Adding to the Pressure

          ♦Interactions with MMO
                  • MMO Wanted Schedule Updates from ATK/USA Simultaneously to
                    First Stage Receiving
                           − Didn’t Allow FS to “Manage” the Schedule
                  • Margin Controlled by Mission Manager
                           − Gave the IPTs Limited Flexibility in Managing Schedule

          ♦Interactions with Prime Contractor
                  • Schedule Management was a Significant Weakness Early in Life
                    Cycle
                  • ATK Understood the Pressure the First Stage IPT was Under
                  • Difficult at First
                           − ATK Continually Submitted Updated Schedules with Slippages to Delivery
                             Dates
                           − Multiple Reports Coming from Different Groups




National Aeronautics and Space Administration                                                         12
Dealing with the Pressure

      ♦ Team Makeup
               • Good Mix of “Greybeards” and
                 “Greenies”
               • Selection of the “Right” Personality
               • Worked and Played Well Together
      ♦ Actions Taken
               • Re-Org of First Stage Team
               • On the Floor Presence
               • Ship FA/5SS Structures Directly to KSC
                 for DFI Installation
               • Stop the Mass Distribution of Schedule
                 Updates/Data
      ♦ Tools Implemented
               • “One Pagers”
               • Daily Tracker
               • Milestone Tracking Status




National Aeronautics and Space Administration                               13
AI-X First Stage Tracking Milestones                       25 Mar 09



                                                 Milestone             Last %    Current %
                    Milestone                   Completion   Status   Complete   Complete
                                                                                                              Threats
                                                   Date
                FORWARD ASSEMBLY
               Frustum O/D at
               ARF
                                                   2/20        G       100%        100%
               Main Chute Install
               Complete
                                                   3/13        G       100%        100%
               OFI Cable Testing
               Complete
                                                   3/17        G       100%        100%
               Fwd Skirt DFI
               Sensor Install                      3/26       G
                                                              G         85%        100%      Last 2 Accels Installed 4/2
               Complete
                                                                                             Projection: 4/20 (4/24)
               Fwd Skirt Ready                                                               OFI Harness Testing (6 Harnesses, 34
               to Mate
                                                   4/3         R        82%        85%       connectors)
                                                                                             Return 2 Pyro cables to LMCO for rework
               Frustum DFI                                                                   Projection: 4/11
               Sensor Install
                                                   3/31        R        40%        75%       Peeling Paint inside Frustum

               FSE Ready for
               Mate
                                                   4/8         R        85%        90%       Projection: 4/20

               Frustum Ready
               for Mate
                                                   4/8         R        65%        75%       Projection: 4/22

               FSE/FS Mate                         4/13        R         0           0       Projection: 4/26 (4/30)

               Frustum/FSE
               Mate
                                                   4/20        R         0           0       Projection: 4/30 (5/6)


               Transfer to GO                      5/8         R         0           0       Projection: 522 (5/29)
National Aeronautics and Space Administration                                                                                          14
Forward Assembly Delivery to VAB
                                                                                                                                                                                                                                                                                       Forward Skirt
                                                                                                                                                                                                                                                                                       OFI Harness
          2-Jun-2009                                                                                                                                                                                                                                                                   Testing Impacts

                                                                                                                                                                                                                                                                   Nut Plate
                                                                                                                                                                                                                                                                   Attach
                                                                                                                                                                                                                                                                   Bolts High
        26-May-2009                                                                                                                                                                                                                                                Running
                                                                                                                                                                                                                                                                   Torque


        19-May-2009                                                                                                                                                                                           Ordered
                                                                                                                                                                         Nut                                  Replacement
                                                                                                                                                                         Plate                                Nut Plates                                                                      Nut Plate
                                                                                                                       Harness                                           Failure                                                                                                              Low
        12-May-2009                                                                                                    Testing                                                                                                                                                                Running
                                                                                                                       Directive                                                                                                                                                              Torque


         5-May-2009

                                                                                                                                                                                           MMO Re-
                                                                                                                                                                                           baseline
         28-Apr-2009
                              Harness
                              PR
                              Initiated
         21-Apr-2009                                                                                                                                                                                                                Harness Testing PR                                                          19-Feb
                                                                                                                                                                                                                                    Enabler TIM Re-Baseline                                                     20-Feb
                                                                                                                                                                                                                                    Initial OFI Testing B/L (FSE/AS)                                            5-Mar
         14-Apr-2009                                                                                                                                                                                                                Schedule Re-Baseline                                                        8-Mar
                                                                                                                                                                                                                                    XCB/Davis "no test" Decision                                                12-Mar
                                                                                                                                                                                                                                    CxCB Reversal (Test 5SS Aft)                                                19-Mar
          7-Apr-2009
                              19-Feb
                                       20-Feb
                                                21-Feb
                                                         22-Feb
                                                                  23-Feb
                                                                           24-Feb
                                                                                    25-Feb
                                                                                             26-Feb
                                                                                                      27-Feb
                                                                                                               2-Mar
                                                                                                                        3-Mar
                                                                                                                                4-Mar
                                                                                                                                        5-Mar
                                                                                                                                                6-Mar
                                                                                                                                                        9-Mar




                                                                                                                                                                                                                                                                                                                        2-Apr
                                                                                                                                                                                                                                                                                                                                3-Apr
                                                                                                                                                                10-Mar
                                                                                                                                                                         11-Mar
                                                                                                                                                                                  12-Mar
                                                                                                                                                                                           13-Mar
                                                                                                                                                                                                    16-Mar
                                                                                                                                                                                                             17-Mar
                                                                                                                                                                                                                      18-Mar
                                                                                                                                                                                                                               19-Mar
                                                                                                                                                                                                                                        20-Mar
                                                                                                                                                                                                                                                 23-Mar
                                                                                                                                                                                                                                                          24-Mar
                                                                                                                                                                                                                                                                   25-Mar
                                                                                                                                                                                                                                                                            26-Mar
                                                                                                                                                                                                                                                                                     27-Mar
                                                                                                                                                                                                                                                                                              30-Mar


                                                                                                                                                                                                                                                                                                                1-Apr
                                                                                                                                                                                                                                                                                                       31-Mar
                                                              Current Delivery Projection                                                         FSPO (Calfee) Target                                                         Ares I-X MMO Baseline


National Aeronautics and Space Administration                                                                                                                                                                                                                                                                                           15
First Stage Ares IX 5SS Flow                                                                                                                            As of 3/12/09
                    Nov'08                   Dec'08                      Jan'09                              Feb'09                      Mar'09                         Apr'09                     May'09                     Jun'09             Jul'09
  Forward                            12/11     Receive Fwd O/D @ Astrotech
  Segment                                12/13      12/18 Install TPS          Install DFI
                 11/4                         12/19                            1/15 Finalize
                 7U140176                                               1/16        1/21
                                                                       1/21         Ship to EDO
                                                                                                               Build-up/Inspect, install ladders, cameras
                                                                1/9    1/21                            2/5
                                                                                                               install cable routing brkts, X-port to HB4
                                                               1U110642-
                                                                                               2/5         5SS Fwd Ready to mate

   Center                                                                                2/1         Receive Center O/D @ Astrotech
                                                                                           2/3              2/7 Install TPS
                 11/4                                                                                2/9          2/14 Install DFI
                 7U140175A                                                                                   2/16      2/19 Finalize
                                                                                                               2/19
                                                                                                                 Ship to EDO
                                                                                                                            Build-up/Inspect, install ladders, Temp GSE Platforms,
                                                                                                       2/13
                                                                                                                            Instl cable routing brckts, ECS Doublers, X-port to HB4
                                                                                                     5SS Ctr Ready to mate  3/5

 Aft Segment                                                            1/17     Receive Aft O/D @ Astrotech
                 11/5                                                   1/17              1/26 Install TPS
                 7U140174A                                                        1/27                   2/12 Install DFI
                                                                                                   2/13      2/17 Finalize
                                                                                                                  Internal Mechanical Ops, Shim Install Battery Brkts
                            11/26                                                         2/2               2/16 Install CRD Panel,Cable Routing & Pyro Brkts,
                             7U130488-                                                                            Cmnd Panel, Brkts & Tube Rack Assys, C-Band, Ladde
                                                                                                                 Shim/Install Heater Mod Components
                                                                                                2/10        2/16
                                                                                                                 Install RSS Ant. Cover Plugs, Install Feed thru Pnls
                                                                                                             2/17     Ship to EDO
                                                                                                                                                 External Mech Ops, Install C-Band Doublers
                                                                                                             2/17                               3/16
                                                                                                                                                 S-Band Doubler/Ant, RSS ant, Ord, feed-thru Panels
                                                                                                                                           Systems Tunnel Install, Install Heritage Sys
                                                                                                              2/18                   3/9
                                                                                                                                           Fit check uninsulated tunnel canoe cover, etc..
                                                                                                                      2/26     3/2 Install angle brackets
                                                                                                                                                       Electrical B/U- RSS equip-antenna-cable,
                                                                               7U130488-A            2/2                          3/13           3/23 C-Band antenna- controller- cable- cable Test
                                                                                                                       1U110642-A     3/9              C-Band Xponder
                                                                                                   2/16 Receive FSAM
                                                                                           FSAM Unpack, Inspect, Prep for lift
                                                                                                    2/17                       3/17              3/18 Lift and Mate FSAM to Aft

Final 5SS Mate                                                                                                               3/5                   3/20 Lift & Mate Fwd/Ctr Segments
                                                                                                                                                        Install angle brkts, fitcheck faux cover
                                                                                                                                   3/9            3/19
                                                                                                                                                        DFI Routing and C/O
                                                                                                                                                                    Post FSAM Electrical Opns, DFI Cables/Sensors
                                                                                                                                         3/18                3/31
                                                                                                                                                                    OFI CRD, FSAM Cables, S-Band Cables
                                                                                                                                                       3/31              4/11Lift and Mate Fwd/Ctr to Aft Seg, ECS, Bridge Cover
                                                                                                                                                         4/2             4/11 Final Inspections
                                                                                                                                                                4/11           4/17 Final Xfer Preps-Attach Sling, GSE doors, load, tarp
                                                                                                                                                                       4/17    Ship to HB3
                                                                                                                           3/3                         3/23 Insulate Aft Tunnel Cover
                                                                                                                                         3/19                          4/8    Insulate Fwd/Ctr Tunnel Covers
                                                                                                                                                                       4/17             4/27 Install Insulated Fwd/Ctr tun cvers, bridge cvers
                                                                                                                                                                                 4/28     4/30 Install Insulated Aft tunnel cover, bridge cver
Summary & Lessons Learned
♦ Coming together is a beginning. Keeping together is
  progress. Working together is success. ~Henry Ford
♦ Individual commitment to a group effort - that is what makes
  a team work, a company work, a society work, a civilization
  work. ~Vince Lombardi
♦ Respect your fellow human being, treat them fairly, disagree
  with them honestly, enjoy their friendship, explore your
  thoughts about one another candidly, work together for a
  common goal and help one another achieve it. ~Bill Bradley
♦ Never doubt that a small group of thoughtful, committed
  people can change the world. Indeed, it is the only thing
  that ever has. ~Margaret Meade
♦ Teamwork is the ability to work together toward a common
  vision. The ability to direct individual accomplishment
  toward organizational objectives. It is the fuel that allows
  common people to attain uncommon results. ~Andrew
  Carnegie
♦ If you want to build a ship, don't drum up people together to
  collect wood and don't assign them tasks and work, but
  rather teach them to long for the endless immensity of the
  sea. ~Antoine de Saint-Exupery
♦ None of us is as smart as all of us. ~Ken Blanchard



                                                                  17
18

More Related Content

Viewers also liked

Ward.le roy
Ward.le royWard.le roy
Ward.le royNASAPMC
 
Hembree.mike
Hembree.mikeHembree.mike
Hembree.mikeNASAPMC
 
Poole.eric
Poole.ericPoole.eric
Poole.ericNASAPMC
 
Peddie.cathy
Peddie.cathyPeddie.cathy
Peddie.cathyNASAPMC
 
Moser lightfoot pmc2012pres
Moser lightfoot pmc2012presMoser lightfoot pmc2012pres
Moser lightfoot pmc2012presNASAPMC
 
Gerald.mulenburg
Gerald.mulenburgGerald.mulenburg
Gerald.mulenburgNASAPMC
 
Mackey,william pm challenge 2012
Mackey,william pm challenge 2012Mackey,william pm challenge 2012
Mackey,william pm challenge 2012NASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Amer bill steve
Amer bill steveAmer bill steve
Amer bill steveNASAPMC
 
Glenn.butts mega projects estimates
Glenn.butts   mega projects estimatesGlenn.butts   mega projects estimates
Glenn.butts mega projects estimatesNASAPMC
 
Ryan.richard
Ryan.richardRyan.richard
Ryan.richardNASAPMC
 
Kotnour tim
Kotnour timKotnour tim
Kotnour timNASAPMC
 
D l engyel
D l engyelD l engyel
D l engyelNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Hill.terry
Hill.terryHill.terry
Hill.terryNASAPMC
 
Jeff davis
Jeff davisJeff davis
Jeff davisNASAPMC
 
Crocker lori
Crocker loriCrocker lori
Crocker loriNASAPMC
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deansNASAPMC
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randallNASAPMC
 

Viewers also liked (20)

Ward.le roy
Ward.le royWard.le roy
Ward.le roy
 
Hembree.mike
Hembree.mikeHembree.mike
Hembree.mike
 
Poole.eric
Poole.ericPoole.eric
Poole.eric
 
Palmer
PalmerPalmer
Palmer
 
Peddie.cathy
Peddie.cathyPeddie.cathy
Peddie.cathy
 
Moser lightfoot pmc2012pres
Moser lightfoot pmc2012presMoser lightfoot pmc2012pres
Moser lightfoot pmc2012pres
 
Gerald.mulenburg
Gerald.mulenburgGerald.mulenburg
Gerald.mulenburg
 
Mackey,william pm challenge 2012
Mackey,william pm challenge 2012Mackey,william pm challenge 2012
Mackey,william pm challenge 2012
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Amer bill steve
Amer bill steveAmer bill steve
Amer bill steve
 
Glenn.butts mega projects estimates
Glenn.butts   mega projects estimatesGlenn.butts   mega projects estimates
Glenn.butts mega projects estimates
 
Ryan.richard
Ryan.richardRyan.richard
Ryan.richard
 
Kotnour tim
Kotnour timKotnour tim
Kotnour tim
 
D l engyel
D l engyelD l engyel
D l engyel
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Hill.terry
Hill.terryHill.terry
Hill.terry
 
Jeff davis
Jeff davisJeff davis
Jeff davis
 
Crocker lori
Crocker loriCrocker lori
Crocker lori
 
Sean carter dan_deans
Sean carter dan_deansSean carter dan_deans
Sean carter dan_deans
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
 

Similar to Calfee

Robert.ess
Robert.essRobert.ess
Robert.essNASAPMC
 
Robert.ess
Robert.essRobert.ess
Robert.essNASAPMC
 
Unger massey
Unger masseyUnger massey
Unger masseyNASAPMC
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastleNASAPMC
 
Introduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringIntroduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringArmandHalter
 
Doug.mclennan
Doug.mclennanDoug.mclennan
Doug.mclennanNASAPMC
 
Ann over
Ann overAnn over
Ann overNASAPMC
 
Embedded Systems in Automobile
Embedded Systems in AutomobileEmbedded Systems in Automobile
Embedded Systems in AutomobileAbhishek Sutrave
 
Ares First Stage Development... Igniting the Next Generation of Launch Vehicles
Ares First Stage Development... Igniting the Next Generation of Launch VehiclesAres First Stage Development... Igniting the Next Generation of Launch Vehicles
Ares First Stage Development... Igniting the Next Generation of Launch VehiclesAmerican Astronautical Society
 
Hatfield skip
Hatfield skipHatfield skip
Hatfield skipNASAPMC
 
Xen summit spring2010_tom_woller_amd
Xen summit spring2010_tom_woller_amdXen summit spring2010_tom_woller_amd
Xen summit spring2010_tom_woller_amdThe Linux Foundation
 
Frost.jim
Frost.jimFrost.jim
Frost.jimNASAPMC
 
Mil soft company_overview_2013
Mil soft company_overview_2013Mil soft company_overview_2013
Mil soft company_overview_2013milsoftSDC
 

Similar to Calfee (16)

Robert.ess
Robert.essRobert.ess
Robert.ess
 
Robert.ess
Robert.essRobert.ess
Robert.ess
 
Unger massey
Unger masseyUnger massey
Unger massey
 
Chris.hardcastle
Chris.hardcastleChris.hardcastle
Chris.hardcastle
 
Huebner
HuebnerHuebner
Huebner
 
Huebner
HuebnerHuebner
Huebner
 
Introduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringIntroduction To Sonalysts Engineering
Introduction To Sonalysts Engineering
 
Doug.mclennan
Doug.mclennanDoug.mclennan
Doug.mclennan
 
Ann over
Ann overAnn over
Ann over
 
Embedded Systems in Automobile
Embedded Systems in AutomobileEmbedded Systems in Automobile
Embedded Systems in Automobile
 
Ares First Stage Development... Igniting the Next Generation of Launch Vehicles
Ares First Stage Development... Igniting the Next Generation of Launch VehiclesAres First Stage Development... Igniting the Next Generation of Launch Vehicles
Ares First Stage Development... Igniting the Next Generation of Launch Vehicles
 
Hatfield skip
Hatfield skipHatfield skip
Hatfield skip
 
Advanced Methods for ULS and FLS
Advanced Methods for ULS and FLSAdvanced Methods for ULS and FLS
Advanced Methods for ULS and FLS
 
Xen summit spring2010_tom_woller_amd
Xen summit spring2010_tom_woller_amdXen summit spring2010_tom_woller_amd
Xen summit spring2010_tom_woller_amd
 
Frost.jim
Frost.jimFrost.jim
Frost.jim
 
Mil soft company_overview_2013
Mil soft company_overview_2013Mil soft company_overview_2013
Mil soft company_overview_2013
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Recently uploaded

AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesZilliz
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 

Recently uploaded (20)

AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector Databases
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 

Calfee

  • 1. Managing the Ares I-X First Stage IPT “Life on the Critical Path” Chris Calfee Ares I-X First Stage Lead Marshall Space Flight Center NASA Project Management Challenge 2010 Galveston, TX February 9-10, 2010 Used with permission 1
  • 2. Agenda ♦ Introduction to First Stage • Hardware • Mission • Organization ♦ Ares I-X Life-Cycle • Significant Events • Top Level Schedule • Additional Pressure Points ♦ Dealing with the Pressure • Putting the Team Together • Key Decisions Made • Tools Implemented ♦ Conclusions and Lessons Learned National Aeronautics and Space Administration 2
  • 3. First Stage Technical Overview ♦ Heritage Hardware • 4 Segment Reusable Solid Rocket Motor (RSRM) w/Nozzle • Thrust Vector Control (TVC) • Flight Termination System (FTS) • Nose Cap w/Thrusters • Booster Separation Motors (BSMs) ♦ Modified Heritage • 1st Stage Provided Avionics (Shuttle Derived Avionics) (ISC, RCU, and APUC) • Aft Skirt • T-0 ♦ New Developments Specifically for AIX • Fifth Segment Simulator (5SS) • Forward Skirt (FS) • Forward Skirt Extension (FSE) • Main Parachute Support Structure (MPSS) • Frustum ♦ Ares I Designs • Parachutes • FTS Extension to Aft Segment National Aeronautics and Space Administration 3
  • 4. Ares I-X First Stage Major Hardware Finished Stage will also include: Development Flight Instrumentation Installed Systems Tunnel Cables & Covers Installed Upper Stage Interface Complete Cable & Instrumentation Interfaces Separation and Deceleration System Installed Pad Stabilization Connection Point Insulated and Cast Forward Segment with Igniter Installed Forward Assembly Insulated and Cast Forward Center Segment Avionics Pallet Installed (all except flight computer & two RRGUs) Insulated and Cast Aft Center Segment Fifth Segment Simulator Insulated and Cast Aft Segment with Forward Nozzle Assembly Installed 12 GFP BTMs/BDMs Installed Modified Systems Tunnel for FTS LSC TVC System (incl. APUC) Installed RRGU Installed Aft Exit Cone Assembly Only T-0 Electrical Interface Aft Skirt Assembly Four Segment Motor 4
  • 5. Ares I-X First Stage Recovery Sequence Re-entry Mass Properties with BDMs, BTMs, and 3654-lb ballast on Aft Skirt
  • 6. Ares I-X Executive Summary 2006 2007 2008 2009 O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F STS-127 STS-125/128 STS-129 SRR PDR CDR 1 CDR 2 ARR FS EAR FSAR Post Flight Analysis Design Hardware Fabricate & Assemble Design Impl & Mod MLP/VAB/CCC ORR Ground Systems PAD ORR SIL Testing Fwd Assy & 5SS Engineering / Fabrication 14 Fwd Assy & 5SS Processing FSAM 30 05 04 RoCS USS 29 CM/LAS 19 Motor Segments 11 Fwd Assy 5th Seg Sim VAB High Bay 4 - Offline Stacking / Config Testing 08 Aft Skirt RPSF Processing 20 VAB HB 3 - MLP Stacking / Integrated Testing / Closeouts Roll to Pad Pwr On Mate Review 30 LRR 09 FTRR Dry Run 15 Roll Out Review 17 FTRR 23 L-1 Day Review 26 Pad Ops Ares I-X Flight Oct 28, 2009 6
  • 7. Ares I-X First Stage IPT (MSFC) Safety & Mission Ares I-X Chief Engineer Assurance ( S& MA First Stage IPT ) Mike Phipps John Crisler, Lead Chris Calfee Lead Brent Malone Jay Nichols Deputy Systems Engineering Business & Integration (SE&I) Janet Crawford Steve McGraw Harry Craft Budget Schedules LSE Bob Williams Aaron Sumner David Bath Verification SE Coordination Verification Fifth Segment Forward Aft Skirt RSRM Simulator Assemblies Beth Cook Jay Nichols Yvonne Villegas Bill Claunch KSC Recovery Structures Pyro Deceleration SDA (Avionics) Operations & Disassembly Keith Higginbotham Tony Smith Mike Phipps Brad Perkins Ron King Robert Cooper National Aeronautics and Space Administration 7
  • 8. Significant Events During the Life Cycle ♦ ATP May 2006 (April 15, 2009 Launch) • Motor Delivery 8/8/2008 • Forward Assembly/5SS Delivery 1/30/2009 • Aft Skirt Delivery 12/12/2008 ♦ 750 DFI Sensors on Vehicle, 325 on First Stage ♦ April 2007 -1st Lean Event and Project Re-Organization ♦ August 2007 - Separation Plane Change • Moved Separation Plane from Top of Interstage to Bottom of Frustum • Moved Separation and Tumble Motors to Aft Skirt − Aft Skirt Moved to Critical Path Along with Forward Assemblies ♦ Summer of Lean ♦ PDR and CDR “Slippages” • 4-10 Months • No Change to Launch Date National Aeronautics and Space Administration 8
  • 9. The “Leaning” of First Stage Delivery Dates Original Delivery Evolved Dates Dates Motor 8/8/08 7/17/08 Forward Assembly 1/30/09 12/1/08 5SS 1/30/09 12/15/08 Aft Skirt 12/12/08 11/19/08 Assumptions: 4/15/09 Launch Date May 2006 ATP National Aeronautics and Space Administration 9
  • 10. Ares I-X Major Milestones Launch 4/15/09 10
  • 11. Other Interesting Events ♦ Forward Assembly and Fifth Segment Simulator Fabrication • “Small” Shop in Indianapolis, Major Tool & Machine • Centralized Location for All Major FS Fab • Six Major Pieces of Structure − 3 Aluminum − 3 Steel • Shortage of Welders • Lack of Experience with “Flight Hardware” ♦ Motor Shipment • Pressure was Applied to Ship the Motor to KSC Before it was Ready • KSC Had No Plan in Place to Complete Instrumentation • First Stage Refused ♦ Forward Assembly Processing • KSC Didn’t Approve FA/5SS of Astrotech Processing, Wanted it Done at KSC ♦ Harness Issues • Availability • Testing • Aluminum Tape ♦ ATK-USA Contract Squabbles ♦ Safety Violations National Aeronautics and Space Administration 11
  • 12. Adding to the Pressure ♦Interactions with MMO • MMO Wanted Schedule Updates from ATK/USA Simultaneously to First Stage Receiving − Didn’t Allow FS to “Manage” the Schedule • Margin Controlled by Mission Manager − Gave the IPTs Limited Flexibility in Managing Schedule ♦Interactions with Prime Contractor • Schedule Management was a Significant Weakness Early in Life Cycle • ATK Understood the Pressure the First Stage IPT was Under • Difficult at First − ATK Continually Submitted Updated Schedules with Slippages to Delivery Dates − Multiple Reports Coming from Different Groups National Aeronautics and Space Administration 12
  • 13. Dealing with the Pressure ♦ Team Makeup • Good Mix of “Greybeards” and “Greenies” • Selection of the “Right” Personality • Worked and Played Well Together ♦ Actions Taken • Re-Org of First Stage Team • On the Floor Presence • Ship FA/5SS Structures Directly to KSC for DFI Installation • Stop the Mass Distribution of Schedule Updates/Data ♦ Tools Implemented • “One Pagers” • Daily Tracker • Milestone Tracking Status National Aeronautics and Space Administration 13
  • 14. AI-X First Stage Tracking Milestones 25 Mar 09 Milestone Last % Current % Milestone Completion Status Complete Complete Threats Date FORWARD ASSEMBLY Frustum O/D at ARF 2/20 G 100% 100% Main Chute Install Complete 3/13 G 100% 100% OFI Cable Testing Complete 3/17 G 100% 100% Fwd Skirt DFI Sensor Install 3/26 G G 85% 100% Last 2 Accels Installed 4/2 Complete Projection: 4/20 (4/24) Fwd Skirt Ready OFI Harness Testing (6 Harnesses, 34 to Mate 4/3 R 82% 85% connectors) Return 2 Pyro cables to LMCO for rework Frustum DFI Projection: 4/11 Sensor Install 3/31 R 40% 75% Peeling Paint inside Frustum FSE Ready for Mate 4/8 R 85% 90% Projection: 4/20 Frustum Ready for Mate 4/8 R 65% 75% Projection: 4/22 FSE/FS Mate 4/13 R 0 0 Projection: 4/26 (4/30) Frustum/FSE Mate 4/20 R 0 0 Projection: 4/30 (5/6) Transfer to GO 5/8 R 0 0 Projection: 522 (5/29) National Aeronautics and Space Administration 14
  • 15. Forward Assembly Delivery to VAB Forward Skirt OFI Harness 2-Jun-2009 Testing Impacts Nut Plate Attach Bolts High 26-May-2009 Running Torque 19-May-2009 Ordered Nut Replacement Plate Nut Plates Nut Plate Harness Failure Low 12-May-2009 Testing Running Directive Torque 5-May-2009 MMO Re- baseline 28-Apr-2009 Harness PR Initiated 21-Apr-2009 Harness Testing PR 19-Feb Enabler TIM Re-Baseline 20-Feb Initial OFI Testing B/L (FSE/AS) 5-Mar 14-Apr-2009 Schedule Re-Baseline 8-Mar XCB/Davis "no test" Decision 12-Mar CxCB Reversal (Test 5SS Aft) 19-Mar 7-Apr-2009 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar 9-Mar 2-Apr 3-Apr 10-Mar 11-Mar 12-Mar 13-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 30-Mar 1-Apr 31-Mar Current Delivery Projection FSPO (Calfee) Target Ares I-X MMO Baseline National Aeronautics and Space Administration 15
  • 16. First Stage Ares IX 5SS Flow As of 3/12/09 Nov'08 Dec'08 Jan'09 Feb'09 Mar'09 Apr'09 May'09 Jun'09 Jul'09 Forward 12/11 Receive Fwd O/D @ Astrotech Segment 12/13 12/18 Install TPS Install DFI 11/4 12/19 1/15 Finalize 7U140176 1/16 1/21 1/21 Ship to EDO Build-up/Inspect, install ladders, cameras 1/9 1/21 2/5 install cable routing brkts, X-port to HB4 1U110642- 2/5 5SS Fwd Ready to mate Center 2/1 Receive Center O/D @ Astrotech 2/3 2/7 Install TPS 11/4 2/9 2/14 Install DFI 7U140175A 2/16 2/19 Finalize 2/19 Ship to EDO Build-up/Inspect, install ladders, Temp GSE Platforms, 2/13 Instl cable routing brckts, ECS Doublers, X-port to HB4 5SS Ctr Ready to mate 3/5 Aft Segment 1/17 Receive Aft O/D @ Astrotech 11/5 1/17 1/26 Install TPS 7U140174A 1/27 2/12 Install DFI 2/13 2/17 Finalize Internal Mechanical Ops, Shim Install Battery Brkts 11/26 2/2 2/16 Install CRD Panel,Cable Routing & Pyro Brkts, 7U130488- Cmnd Panel, Brkts & Tube Rack Assys, C-Band, Ladde Shim/Install Heater Mod Components 2/10 2/16 Install RSS Ant. Cover Plugs, Install Feed thru Pnls 2/17 Ship to EDO External Mech Ops, Install C-Band Doublers 2/17 3/16 S-Band Doubler/Ant, RSS ant, Ord, feed-thru Panels Systems Tunnel Install, Install Heritage Sys 2/18 3/9 Fit check uninsulated tunnel canoe cover, etc.. 2/26 3/2 Install angle brackets Electrical B/U- RSS equip-antenna-cable, 7U130488-A 2/2 3/13 3/23 C-Band antenna- controller- cable- cable Test 1U110642-A 3/9 C-Band Xponder 2/16 Receive FSAM FSAM Unpack, Inspect, Prep for lift 2/17 3/17 3/18 Lift and Mate FSAM to Aft Final 5SS Mate 3/5 3/20 Lift & Mate Fwd/Ctr Segments Install angle brkts, fitcheck faux cover 3/9 3/19 DFI Routing and C/O Post FSAM Electrical Opns, DFI Cables/Sensors 3/18 3/31 OFI CRD, FSAM Cables, S-Band Cables 3/31 4/11Lift and Mate Fwd/Ctr to Aft Seg, ECS, Bridge Cover 4/2 4/11 Final Inspections 4/11 4/17 Final Xfer Preps-Attach Sling, GSE doors, load, tarp 4/17 Ship to HB3 3/3 3/23 Insulate Aft Tunnel Cover 3/19 4/8 Insulate Fwd/Ctr Tunnel Covers 4/17 4/27 Install Insulated Fwd/Ctr tun cvers, bridge cvers 4/28 4/30 Install Insulated Aft tunnel cover, bridge cver
  • 17. Summary & Lessons Learned ♦ Coming together is a beginning. Keeping together is progress. Working together is success. ~Henry Ford ♦ Individual commitment to a group effort - that is what makes a team work, a company work, a society work, a civilization work. ~Vince Lombardi ♦ Respect your fellow human being, treat them fairly, disagree with them honestly, enjoy their friendship, explore your thoughts about one another candidly, work together for a common goal and help one another achieve it. ~Bill Bradley ♦ Never doubt that a small group of thoughtful, committed people can change the world. Indeed, it is the only thing that ever has. ~Margaret Meade ♦ Teamwork is the ability to work together toward a common vision. The ability to direct individual accomplishment toward organizational objectives. It is the fuel that allows common people to attain uncommon results. ~Andrew Carnegie ♦ If you want to build a ship, don't drum up people together to collect wood and don't assign them tasks and work, but rather teach them to long for the endless immensity of the sea. ~Antoine de Saint-Exupery ♦ None of us is as smart as all of us. ~Ken Blanchard 17
  • 18. 18