SlideShare ist ein Scribd-Unternehmen logo
1 von 33
Modeling the Effect of Budget Constraints
          on Cost and Schedule

                                NASA 2012 PM Challenge


                     Darren Elliott – Tecolote Research, Inc.
                                22 February 2012

                          Los Angeles  Washington, D.C.  Boston  Chantilly  Huntsville  Dayton  Santa Barbara
     Albuquerque  Colorado Springs  Goddard Space Flight Center  Johnson Space Center  Ogden  Patuxent River  Washington Navy Yard
           Ft. Meade  Ft. Monmouth  Dahlgren  Quantico  Cleveland  Montgomery  Silver Spring  San Diego  Tampa  Tacoma
                        Aberdeen  Oklahoma City  Eglin AFB  San Antonio  New Orleans  Denver  Vandenberg AFB

PRT#115 22 February 2012                                 Approved for Public Release
Outline/Agenda

 Background



 Modeling Techniques



 Summary




 PRT#115 22 February 2012   Approved for Public Release                    2
Evolution of Cost/Schedule
                                                          Understanding
     Implementation of cost risk analysis to provide a better gauge of the most likely
      required effort for a project
         NASA established policy to fund at a target cost confidence level
         Reality was that cost risk funds exceeded targeted budget levels
         Led to additional analysis on best techniques for applying reserve and setting up the overall
          project budget
     Recognition that enhanced modeling was needed, as many costs are time-
      dependent (e.g., fixed infrastructure, program support, systems engineering) in
      nature
           Developed methods to address costs based on time behavior (e.g., time-dependent and time-
            independent)
     Enhanced understanding hat additional costs are incurred due to schedule delays
      associated with alignment of work packages
         Developed methodology to integrate cost and schedule risk analysis to determine the joint
          confidence level (percent chance of meeting both cost and schedule objectives)
         NASA established policy to fund projects at a target joint confidence level

     Realization that funding is a major driver to schedule and total cost
         Lack of budget availability stretches schedule
         Currently researching and developing methods to address this problem



    PRT#115 22 February 2012                 Approved for Public Release                                  3
Our Reality is an Integrated System;
                           Where Budget Availability is a Major Input




PRT#115 22 February 2012            Approved for Public Release
Several Tools Have Recently Been Developed
    to Assess Impact of Funding Constraints
     Tool 1: Deterministic Based Approach
         Sponsored by NASA JSC , developed by Tecolote Research, Inc
         Requires identification of major cost elements, breakdown into TD/TI behavior, and notional
          understanding of dependency (serial or parallel) between cost elements
         Uses time-phased cost and budget information
         Runs in Excel


     Tool 2: Cost Risk Based Approach
         Sponsored by NASA HQ, developed by Tecolote Research, Inc
         Requires development of a cost-risk analysis
         Uses cost risk statistics, and time-phased cost and budget information
         Runs in ACE or Excel


     Tool 3: Integrated Cost and Schedule Risk Analysis Approach
         Sponsored by NASA JSC and NASA HQ , developed by Tecolote Research, Inc
         Requires development of an integrated cost and schedule risk analysis, allocation of costs to
          schedule effort, and breakdown of cost into TD/TI behavior
         Uses schedule logic, cost allocation to schedule activities, time-phasing of costs, cost and/or
          schedule statistics, allocation of schedule/cost effort into budget items, time-phased budget
          information, and can incorporate discrete threats
         Runs in Excel /Crystal Ball




    PRT#115 22 February 2012                 Approved for Public Release                                    5
Modeling the Effect of Budget Constraints on Cost and Schedule

   DETERMINISTIC ANALYSIS


PRT#115 22 February 2012    Approved for Public Release             6
Deterministic Analysis Model

 Purpose: Provide program managers and resource
   analysts the ability to assess the effect that budget
   constraints will have on a program
        Requires a simple set of data
        Includes estimated effect on both cost and schedule

 Allows for rapid simulation and comparison of different
   scenarios

 Requires cost plan for major activities/efforts and a
   notional understanding of major effort dependencies (e.g.,
   serial or parallel activities)




 PRT#115 22 February 2012        Approved for Public Release
Model Overview

 The model attaches Time-Independent (TI) and Time-
    Dependent (TD) costs to schedule elements
         TI cost elements: Total cost is constant regardless of duration
         TD cost elements: Total cost increases as duration increases (labor
          rate and resources)


 Budget constraints reduce spending and cause the
    associated schedule elements to extend
         Assumes a constant spend rate within each fiscal year
         The spend rate is determined from the year’s constraint
         TD spend rates are considered fixed, while TI spend rates are
          allowed to vary to fit within the constraint




PRT#115 22 February 2012          Approved for Public Release
Model Overview

                                                                                           Named
      Schedule                Cost      Budget                                            Excursion
      Elements              Elements   Constraint            Budget                        Results
                                          s                 Constraint
                                                             Engine




                                                                                Results
                                                                                Display
                                                                                Engine
                 Schedul
                    e
                 Element
                 Referenc
                    e


                                                             Analyze     Show




                                         User Interface




PRT#115 22 February 2012                 Approved for Public Release
Example Analysis: Baseline Case

 Four budget elements, includes series and parallel events
                               Summary Results Gantt Chart
                                            Date
          10/1/2012    10/1/2013          10/1/2014           10/1/2015           9/30/2016



       Task 1




       Task 2


                                                                                                               Start Date Finish Date
       Task 3
                                                                                               Task 1            10/1/2012 2/13/2016
                                                                                               Task 2             4/1/2013 1/25/2014
       Task 4
                                                                                               Task 3            1/26/2014 6/18/2015
                                                                                               Task 4            1/26/2014 11/25/2015

•      Each task has an associated TI and TD cost, resulting in the
       following spending profile:     Summary Results by Schedule Elements (Constant Year $)
                                                               250


         This example assumed                                  200
         up to $200 was
         available per year, as                                150
                                                                                                                                                Task 4
         demonstrated by the
                                                         $M




                                                                                                                                                Task 3
                                                                                                                                                Task 2
         black line                                            100
                                                                                                                                                Task 1


                                                                50



                                                                 0
                                                                          2011   2012         2013      2014       2015    2016   2017   2018

    PRT#115 22 February 2012                             Approved for Public Release
Example Analysis: Excursion 1

               •   What if the budgets are constrained by 10% each year?
                     –           Because tasks will now begin slipping, it is also necessary to define constraints
                                 in the out-years beyond 2016, this example assumes funding continues at 2016
                                 levels ($180 in this example)
                                  Summary Results Gantt Chart                                                               Summary Results by Schedule Elements (Then Year $)
                                                                                                               200
                                                  Date
   10/1/2012        10/1/2013         10/1/2014          10/1/2015         9/30/2016         9/30/2017         180

                                                                                                               160

Task 1                                                                                                         140

                                                                                                               120
                                                                                                                                                                                        Task 4




                                                                                                          $M
                                                                                                               100                                                                      Task 3
Task 2
                                                                                                                80                                                                      Task 2
                                                                                                                                                                                        Task 1
                                                                                                                60
Task 3
                                                                                                                40

                                                                                                                20
Task 4                                                                                                          0
                                                                                                                     2011     2012   2013   2014   2015   2016   2017   2018     2019




                      Summary Results Gantt Chart - Original Budget
                                                  Date
   10/1/2012         10/1/2013        10/1/2014          10/1/2015         9/30/2016         9/30/2017

                                                                                                                     Original Duration Excursion Duration Original Cost Excursion Cost
Task 1
                                                                                                         Task 1                     1230               1541      $402.64        $453.18
                                                                     311 day slip from                   Task 2                      299                356       $69.35         $72.70
Task 2                                                                    baseline
                                                                                                         Task 3                      508                666       $57.99         $63.28
                                                                                                         Task 4                      668                874      $144.35        $170.78
Task 3




Task 4
               PRT#115 22 February 2012                                                Approved for Public Release
Example Analysis: Comparison

 Excursion has a 12% increase in cost

 All excursion tasks have an increased duration
        Task 1 has the largest increase in duration
        Increases in duration correspond to increased TD costs

 Constraining the budget will avoid cost in those years, but the
   deferred work and presence of fixed costs will result in a net cost
   increase and schedule slip
 How can this information be used? Some examples:
        It is apparent Task 1 is a large cost driver in the new case, prioritizing it at the
         expense of the other, shorter, tasks may result in a total cost savings
        If the goal is a budget reduction, it may be preferable to focus the reduction on only
         one or two years instead of spreading it evenly

 These different scenarios can be run to explore the nature of the
   budget constraint


 PRT#115 22 February 2012               Approved for Public Release
Example Analysis: Excursion 2
    Prioritizing Task 1 allows it to finish earlier, and moves the
           entire project back to the left
                                     Summary Results Gantt Chart
                                                     Date
          10/1/2012      10/1/2013       10/1/2014          10/1/2015     9/30/2016              9/30/2017



       Task 1                                                                                                    Excursion 1 Finish Date

       Task 2
                                                                                                                 Baseline Finish Date
       Task 3
                                                                                                                                     •     Task 1’s earlier
       Task 4
                                                                                                                                           completion frees up
                                                                                                                                           money for Tasks 3 and 4
   •       Final cost in this case: $708                                                                 Summary Results by Schedule Elements (Constant Year $)
                –     Final cost in Excursion 1: $760                                      160


                –     Final cost in Baseline: $674                                         140

                                                                                           120

                                                                                           100
                                                                                                                                                                     Task 1
                                                                                      $M




                                                                                            80                                                                       Task 2
                                                                                                                                                                     Task 3
                                                                                            60
                                                                                                                                                                     Task 4

This is an example of how the tool can be                                                   40



  used to potentially optimize cost and                                                     20

                                                                                            0
   schedule within a budget constraint                                                            2011        2012    2013    2014       2015   2016   2017   2018




    PRT#115 22 February 2012                                            Approved for Public Release
Example Analysis: Excursion 3

   What if some of the budget cuts can be reallocated?
   In this example, we will cause FY2013 to take most of the budget cuts, but
    then increase the budget in the out-years:
                                             2013                  2014                2015            2016           2017
                                           $100.00               $200.00             $200.00         $200.00        $200.00
                                                 Summary Results Gantt Chart
                                                                  Date
                         10/1/2012   10/1/2013       10/1/2014           10/1/2015       9/30/2016      9/30/2017



                      Task 1




                      Task 2




                      Task 3




                      Task 4




•   This example finishes at nearly the same time as the original excursion
      –    Total cost reduced to $743, compared to the excursion 1’s $760




PRT#115 22 February 2012                               Approved for Public Release
Modeling the Effect of Budget Constraints on Cost and Schedule

   COST RISK ANALYSIS


PRT#115 22 February 2012    Approved for Public Release             15
Current Techniques to Align Cost and Schedule
                                 via Uncertainty Analysis
                                                                                                                                           Total - Cost Estimate Uncertainty Analysis Results                                                         BY2010 $M
                                                                                                                    100.0%                                                                                                                                        4.5%

                                                                                                                     90.0%                                                                                                                                        4.0%
                                                                                                                     80.0%                                                                                                                                        3.5%




                                                                                                                                                                                                                                                                         Probability (Histogram)
                                                                                                                     70.0%




                                                                                           Confidence Level (CDF)
                                                                                                                                                                                                                                                                  3.0%
                                                                                                                     60.0%
                                                                                                                                                                                                                                                                  2.5%
                                                                                                                     50.0%
                                                                                                                                                                                                                                                                  2.0%
                                                                                                                     40.0%
                                                                                                                                                                                                                                                                  1.5%
                                                                                                                     30.0%

                                                                                                                     20.0%                    Time Phased - Risk Adjusted Estimate                                                                                1.0%

 Technical                                                                                 $100
                                                                                              10.0%                                                                                                                                                               0.5%


Parameters                                                                                         $90
                                                                                                                     0.0%
                                                                                                                             $75       $215       $356        $497      $638            $778                              $919      $1,060   $1,201   $1,341
                                                                                                                                                                                                                                                                  0.0%

                                                                                                                                                                                                                                                  Allocated Dollars for 70% CL
                                                                                                   $80                                        Probability Histogram                                                              Confidence Level (CDF)
                            CERs                                                                                                                                                                                                                  Point Estimate
                                                                                                   $70                                  Cost Uncertainty Analysis
                                                                                                   $60




                                                                                   TY $M
                                                                                                   $50

                                                                                                   $40

                                                                                                   $30

                                                                                                   $20

                                                                                                   Project Finish Date
                                                                                                   $10
                                                            100.0%                                                                                                                       2.0%
                                                                                                                    $0
                                                             90.0%                                                                                                                       1.8%


                                                             80.0%
                                                                                                                     2006              2007           2008         2009         2010
                                                                                                                                                                                   1.6%
                                                                                                                                                                                                                          2011        2012       2013          2014       2015                     2016
                                                             70.0%                                                                                                                       1.4%




                                                                                                                                                                                                Probability (Histogram)
                                   Confidence Level (CDF)




                                                             60.0%                                                                                                                       1.2%


                                                             50.0%                                                                                                                       1.0%


                                                             40.0%                                                                                                                       0.8%


                                                             30.0%                                                                                                                       0.6%


                                                             20.0%                                                                                                                       0.4%


                                                             10.0%                                                                                                                       0.2%


                                                              0.0%                                                                                                                       0.0%
                                                              24 Mar 2012    24 Dec 2012                                 24 Sep 2013    24 Jun 2014       24 Mar 2015     24 Dec 2015
                                                                            Probability Histogram                                                     Confidence Level (CDF)

         Schedule                                                    Schedule Uncertainty Analysis
 PRT#115 22 February 2012                                             Approved for Public Release
However, Budget Profiles Rarely Match
                                Risk-Adjusted Time-Phased Estimates

              $100

              $90
                                                                             Allocated Dollars for 70% CL
              $80
                                   Shortfall                                 Point Estimate
              $70
                                                                             Project Budget
              $60
      TY $M




              $50

              $40

              $30

              $20

              $10

                $0
                 2006   2007    2008   2009       2010      2011      2012    2013    2014     2015    2016

 Annual budget sufficient to cover estimated point estimate effort

 Shortfall in funding 70% effort for years 2007-2011
                        How Does Shortfall Impact Project?
PRT#115 22 February 2012                      Approved for Public Release
The Concept

 Tecolote Developed a ROM-level analysis technique for NASA to
    gauge the impact of budget availability on a project’s target cost
    confidence level
 The Technique requires:
         Risk adjusted, time-phased cost estimate
         Annual budget information
         User input on how to address multiple items (e.g., penalties, etc)
 The General Approach
         Compare estimated effort (i.e., point estimate, risk adjusted time
          phased results, or annual risk iteration results) to available budget
         Identify and track budget shortfalls
         Rollover unfunded effort, with associated inflation and productivity
          penalties, to future years
         Apply logic to use available budget to fund rollover effort



PRT#115 22 February 2012           Approved for Public Release
General Approach for Three
                                   Different Scenarios




PRT#115 22 February 2012    Approved for Public Release
User Inputs and Controls

 The user has the ability to:
        Select type of analysis to
         conduct
             Point estimate
             Risk-adjusted (e.g., 70%) cost
              estimate
             Dynamic assessment of
              confidence level results
        Specify budget scenarios                      Advanced Considerations
             Extend budget at peak
                                                               Incorporating fixed costs (LOE) into
             Infuse/Reduce funds in specific
                                                                consideration
              year
                                                               Conducting portfolio analysis
      Allow budget carryover
      Incorporate penalties for rollover              Outputs
       effort:                                                 Initial phasing result for Target CL
             Inflation considerations                         Constrained phasing result
             Productivity loss                                Additional years of funding required



PRT#115 22 February 2012                 Approved for Public Release
Example Case – 70% Effort
                                                  Exceeds Available Budget
 Phased budget and point estimate
TY$M        FY 2007     FY 2008       FY 2009     FY 2010      FY 2011                                      FY 2012                    FY 2013               FY 2014                        Total
Budget         $25           $55        $65         $80            $70                                        $60                             $30                  $15                      $400
Cost          $21.8         $51.9      $63.6       $62.4          $52.9                                      $37.8                           $18.9                $1.8                      $311

                                                                                                                    Cost Estimate Uncertainty Analysis Results TY $M
                                                                                              100.0%                                                                                            4.5%


 Cost risk analysis data (TY$M)                                                              90.0%

                                                                                              80.0%
                                                                                                                                                                                                4.0%

                                                                                                                                                                                                3.5%




                                                                                                                                                                                                       Probability (Histogram)
     Point        Confidence                   Standard                                       70.0%




                                                                     Confidence Level (CDF)
                                                                                                                                                                                                3.0%
                                      Mean                   CV                               60.0%
    Estimate        Level                      Deviation                                      50.0%
                                                                                                                                                                                                2.5%

                                                                                                                                                                                                2.0%
                                                                                              40.0%
       $311             42%           $372       $168       0.45                              30.0%
                                                                                                                                                                                                1.5%

                                                                                              20.0%                                                                                             1.0%

                                                                                              10.0%                                                                                             0.5%

                                                                                               0.0%                                                                                             0.0%
                                                                                                      $75    $216   $357        $499         $640   $781   $922   $1,063 $1,205 $1,346

                                                                                                                     Probability Histogram                         Confidence Level (CDF)




 Cost estimate @ 70% confidence level
TY$M          FY 2007       FY 2008    FY 2009     FY 2010      FY 2011                                     FY 2012                          FY 2013              FY 2014                   Total
70% CLE        $29.8         $71.2      $87.1       $85.6          $72.4                                      $51.7                           $25.9                  $2.5                    $426


                         Budget Shortfall to Fund 70% CLE
 PRT#115 22 February 2012                        Approved for Public Release
Understanding the Shortfall – Work
                                                                              Slips to the Right
                                                                                                                                 Budget exceeds
                                                  Budget vs 70% Risk-Adjusted Estimate - Surplus/Shortfall
                                                          Budget vs Pt Estimate - Surplus/Shortfall                              Total Budget
                                                                                                                                  phased point
                                    $25                                                                                           estimate in every year
                                                                                                                                  inadequate to
                                           $26M Total Shortfall -
                                           $89M Budget Surplus                                                                   Limited70% CLE
                                                                                                                                  fund surplus in
                                    $20                                                                                           early years
                                           Funds Available For
                                           Reserve Utilization                                                                
                                                                                                                              
                                                                                                                                  Largeglance seems
                                                                                                                                  At first
                                                                                                                                           shortfall
                                    $15
                                                                                                                                  in early years, if
                                                                                                                                  that enough reserves
Annual Surplus / Shortfall - TY$M




                                                                                                                                  are available for
                                    $10
                                                                                                                                  funds
                                                                                                                                  program cannot
                                                                                                                                  be obtained,
                                     $5
                                     $5                                                                                           effort will slip
                                                                                                                                  into future
                                     $0
                                     $0
                                           2007
                                           2007        2008
                                                       2008      2009
                                                                 2009      2010
                                                                           2010       2011
                                                                                      2011        2012
                                                                                                  2012          2013
                                                                                                                2013   2014
                                                                                                                       2014
                                                                                                                                  periods
                                     -$5
                                     -$5
                                                                                                                                      2007 work
                                                                                                                                       slips to 2008
                                    -$10                                                                                              and so on…
                                                                                                  $50M of work effort            Extended work
                                    -$15
                                                                                                  cannot be done in               carries
                                                                                                  2007-2011                       penalties
                                    -$20

                                                                                                                                      Inflation
                                    -$25                                                                                              Productivity


                                                       What are Possible Budget Scenarios?
                PRT#115 22 February 2012                                          Approved for Public Release
Identifying Budget Scenarios

 Budget Scenario Considerations
        Need to be realistic
            Near-term funds are difficult to obtain
            Annual increase must match capability to ramp up staffing levels and should track
             to required work
            Should not have extreme changes year-to-year
            Difficult to increase beyond peak spending year
        Cannot upset overall portfolio needs
 Potential Options
     Identify infusion of funds into specific years
     Extend funding beyond peak funding year at or near peak value
           $100.000
           $90.000
           $80.000
           $70.000                                                                Project Budget
           $60.000
           $50.000
           $40.000
                                                                                  Budget Extension
                                                                                  at Peak
           $30.000
           $20.000
           $10.000
             $0.000
                      2007   2008   2009    2010     2011     2012         2013   2014      2015

PRT#115 22 February 2012                     Approved for Public Release
Example Case Results – Effort Rollover
                                     Fits Under Budget Constraint

     $100
                                                                                     70% Risk Adjusted Estimate
                                                                                    RolloverEffort
                                                                                      70% Risk Adjusted Estimate
     $90    14
             2
             3                                                                      Budget Funded Effort
                                                                                     BudgetEstimateEffort
                                                                                      Point Funded Effort
                                                                                      Budget Funded
     $80
                                                                                    70% Risk Adjusted Estimate
                                                                                      Project Budget
                                                                                     Extended Budget
     $70                                                                            Extended Budget
     $60
     $50
     $40
     $30
     $20
     $10
      $0
            2007      2008    2009   2010      2011        2012       2013   2014          2015        2016


1.      Initial Conditions indicate budget inadequate to fund 70% CLE
2.      Project funded to budget value
3.      Budget scenario created to extend budget at peak value and 70%
        time-phased estimate funded to extended budget values
4.      Impact of rollover effort funded in out-years

PRT#115 22 February 2012                Approved for Public Release
Modeling the Effect of Budget Constraints on Cost and Schedule

   INTEGRATED COST AND
   SCHEDULE RISK ANALYSIS

PRT#115 22 February 2012    Approved for Public Release             25
Integrated Cost/Schedule Budget
                       Constrained Reserve Phasing Model

 A tool is needed that accurately models the relationships
   between the work to be done, the annual budget available,
   and the overall cost and finish date of a project
 Tool can be used to determine appropriate annual
   budgets and reserve strategies to meet the Joint
   Confidence Level requirement
 The tool is called Budget-Constrained Reserve Phase
   (BCRPhase)




                                                              26
 PRT#115 22 February 2012      Approved for Public Release
High - Level Model Concept

 Schedule Activities from JCL Models (or Project Schedules) are
    Mapped into Budget Organizations (Groupings)
 Links Between Budget Organizations are Identified

 Costs from JCL Models (or Projects Costs/Budget) are Mapped
    into Behavior Buckets within Budget Organizations
 Cost Distributions Obtained from JCL Models (or other Analytical
    Methods) are Defined for Each Element
 Discrete Risks from JCL Models (or Project Risk Lists) are
    Specified
 Annual Values are Identified for Each Budget Organization

 Monte Carlo Simulations are Generated to Determine Effort, Work
    is Adjusted to Fit Effort within Budget Level



PRT#115 22 February 2012      Approved for Public Release            27
Modeling Approach – Enabling
                           via Budget Organization Levels




PRT#115 22 February 2012       Approved for Public Release   28
Example Simple Project Model
                            (5 Budget Organization Items)




  Budget

Effort/Costs


 Schedule




 PRT#115 22 February 2012      Approved for Public Release   29
Model in Action – What Happens When
                                  Effort Exceeds Budget Availability


    Organization 1




    Organization 2




                                             Time
               Time-Driving Costs (Touch Labor, Materials, etc.)               Schedule Activity
               Time-Driving Costs Driven By Schedule Slip                      Milestone
                Level Of Effort Costs                                          Schedule Dependency




PRT#115 22 February 2012                         Approved for Public Release                         30
Modeling the Effect of Budget Constraints on Cost and Schedule

   SUMMARY


PRT#115 22 February 2012    Approved for Public Release             31
Summary

 Understanding connection between cost and schedule is of utmost
   importance for estimators
 Available funds and resources are major items that directly impact
   overall project schedule and end costs
 Tools have been developed and research is continuing to help us
   assess this intricate system

                                                      Budget
                                                                 Duration
                            Technical
        Reqts                                      Work Plan
                             Scope
                                                                   Cost
                                                   Effort Size

 PRT#115 22 February 2012          Approved for Public Release              32
Thank You




PRT#115 22 February 2012     Approved for Public Release   33

Weitere ähnliche Inhalte

Was ist angesagt?

Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michaelNASAPMC
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porterNASAPMC
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tonyNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalleyNASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jeanNASAPMC
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paulNASAPMC
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1NASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Majerowicz
MajerowiczMajerowicz
MajerowiczNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrlaNASAPMC
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvinNASAPMC
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevonNASAPMC
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Esker.linda
Esker.lindaEsker.linda
Esker.lindaNASAPMC
 

Was ist angesagt? (20)

Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jean
 
Solomon.paul
Solomon.paulSolomon.paul
Solomon.paul
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Majerowicz
MajerowiczMajerowicz
Majerowicz
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrla
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
 
Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Esker.linda
Esker.lindaEsker.linda
Esker.linda
 

Andere mochten auch

Fuller.david
Fuller.davidFuller.david
Fuller.davidNASAPMC
 
Miller.charles
Miller.charlesMiller.charles
Miller.charlesNASAPMC
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butlerNASAPMC
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askinsNASAPMC
 
Mark wiese
Mark wieseMark wiese
Mark wieseNASAPMC
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.rNASAPMC
 
Robert.bayt
Robert.baytRobert.bayt
Robert.baytNASAPMC
 
Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgNASAPMC
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karenNASAPMC
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorakNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnershipsNASAPMC
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brianNASAPMC
 
Ken poole
Ken pooleKen poole
Ken pooleNASAPMC
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathanNASAPMC
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.edNASAPMC
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12NASAPMC
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.claytonNASAPMC
 

Andere mochten auch (20)

Fuller.david
Fuller.davidFuller.david
Fuller.david
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
 
Sharyl butler
Sharyl butlerSharyl butler
Sharyl butler
 
Heitzman.askins
Heitzman.askinsHeitzman.askins
Heitzman.askins
 
Mark wiese
Mark wieseMark wiese
Mark wiese
 
Odum.t.averbeck.r
Odum.t.averbeck.rOdum.t.averbeck.r
Odum.t.averbeck.r
 
Robert.bayt
Robert.baytRobert.bayt
Robert.bayt
 
Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
Shinn
ShinnShinn
Shinn
 
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pgGeorgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
Georgi,petra dlr kn-david_implementing a pmo_nasa pm challenge_20120223_pg
 
Mc namara.karen
Mc namara.karenMc namara.karen
Mc namara.karen
 
Daniel.dvorak
Daniel.dvorakDaniel.dvorak
Daniel.dvorak
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Inter succes partnerships
Inter succes partnershipsInter succes partnerships
Inter succes partnerships
 
Muirhead.brian
Muirhead.brianMuirhead.brian
Muirhead.brian
 
Ken poole
Ken pooleKen poole
Ken poole
 
Gilbert.jonathan
Gilbert.jonathanGilbert.jonathan
Gilbert.jonathan
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
 
Yonce.clayton
Yonce.claytonYonce.clayton
Yonce.clayton
 

Ähnlich wie Backup darren elliott

Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframeWesley Opaki
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
First Time IT Project Management Review
First Time IT Project Management ReviewFirst Time IT Project Management Review
First Time IT Project Management Reviewdavidzisu
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Shuchi Joshi
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
Draft CE-74 v03 for MAIN review
Draft CE-74 v03 for MAIN reviewDraft CE-74 v03 for MAIN review
Draft CE-74 v03 for MAIN reviewNesma
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 

Ähnlich wie Backup darren elliott (20)

CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Project m&e & logframe
Project m&e & logframeProject m&e & logframe
Project m&e & logframe
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
First Time IT Project Management Review
First Time IT Project Management ReviewFirst Time IT Project Management Review
First Time IT Project Management Review
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
Draft CE-74 v03 for MAIN review
Draft CE-74 v03 for MAIN reviewDraft CE-74 v03 for MAIN review
Draft CE-74 v03 for MAIN review
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 

Mehr von NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Mehr von NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Kürzlich hochgeladen

DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 

Kürzlich hochgeladen (20)

DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 

Backup darren elliott

  • 1. Modeling the Effect of Budget Constraints on Cost and Schedule NASA 2012 PM Challenge Darren Elliott – Tecolote Research, Inc. 22 February 2012  Los Angeles  Washington, D.C.  Boston  Chantilly  Huntsville  Dayton  Santa Barbara  Albuquerque  Colorado Springs  Goddard Space Flight Center  Johnson Space Center  Ogden  Patuxent River  Washington Navy Yard  Ft. Meade  Ft. Monmouth  Dahlgren  Quantico  Cleveland  Montgomery  Silver Spring  San Diego  Tampa  Tacoma  Aberdeen  Oklahoma City  Eglin AFB  San Antonio  New Orleans  Denver  Vandenberg AFB PRT#115 22 February 2012 Approved for Public Release
  • 2. Outline/Agenda  Background  Modeling Techniques  Summary PRT#115 22 February 2012 Approved for Public Release 2
  • 3. Evolution of Cost/Schedule Understanding  Implementation of cost risk analysis to provide a better gauge of the most likely required effort for a project  NASA established policy to fund at a target cost confidence level  Reality was that cost risk funds exceeded targeted budget levels  Led to additional analysis on best techniques for applying reserve and setting up the overall project budget  Recognition that enhanced modeling was needed, as many costs are time- dependent (e.g., fixed infrastructure, program support, systems engineering) in nature  Developed methods to address costs based on time behavior (e.g., time-dependent and time- independent)  Enhanced understanding hat additional costs are incurred due to schedule delays associated with alignment of work packages  Developed methodology to integrate cost and schedule risk analysis to determine the joint confidence level (percent chance of meeting both cost and schedule objectives)  NASA established policy to fund projects at a target joint confidence level  Realization that funding is a major driver to schedule and total cost  Lack of budget availability stretches schedule  Currently researching and developing methods to address this problem PRT#115 22 February 2012 Approved for Public Release 3
  • 4. Our Reality is an Integrated System; Where Budget Availability is a Major Input PRT#115 22 February 2012 Approved for Public Release
  • 5. Several Tools Have Recently Been Developed to Assess Impact of Funding Constraints  Tool 1: Deterministic Based Approach  Sponsored by NASA JSC , developed by Tecolote Research, Inc  Requires identification of major cost elements, breakdown into TD/TI behavior, and notional understanding of dependency (serial or parallel) between cost elements  Uses time-phased cost and budget information  Runs in Excel  Tool 2: Cost Risk Based Approach  Sponsored by NASA HQ, developed by Tecolote Research, Inc  Requires development of a cost-risk analysis  Uses cost risk statistics, and time-phased cost and budget information  Runs in ACE or Excel  Tool 3: Integrated Cost and Schedule Risk Analysis Approach  Sponsored by NASA JSC and NASA HQ , developed by Tecolote Research, Inc  Requires development of an integrated cost and schedule risk analysis, allocation of costs to schedule effort, and breakdown of cost into TD/TI behavior  Uses schedule logic, cost allocation to schedule activities, time-phasing of costs, cost and/or schedule statistics, allocation of schedule/cost effort into budget items, time-phased budget information, and can incorporate discrete threats  Runs in Excel /Crystal Ball PRT#115 22 February 2012 Approved for Public Release 5
  • 6. Modeling the Effect of Budget Constraints on Cost and Schedule DETERMINISTIC ANALYSIS PRT#115 22 February 2012 Approved for Public Release 6
  • 7. Deterministic Analysis Model  Purpose: Provide program managers and resource analysts the ability to assess the effect that budget constraints will have on a program  Requires a simple set of data  Includes estimated effect on both cost and schedule  Allows for rapid simulation and comparison of different scenarios  Requires cost plan for major activities/efforts and a notional understanding of major effort dependencies (e.g., serial or parallel activities) PRT#115 22 February 2012 Approved for Public Release
  • 8. Model Overview  The model attaches Time-Independent (TI) and Time- Dependent (TD) costs to schedule elements  TI cost elements: Total cost is constant regardless of duration  TD cost elements: Total cost increases as duration increases (labor rate and resources)  Budget constraints reduce spending and cause the associated schedule elements to extend  Assumes a constant spend rate within each fiscal year  The spend rate is determined from the year’s constraint  TD spend rates are considered fixed, while TI spend rates are allowed to vary to fit within the constraint PRT#115 22 February 2012 Approved for Public Release
  • 9. Model Overview Named Schedule Cost Budget Excursion Elements Elements Constraint Budget Results s Constraint Engine Results Display Engine Schedul e Element Referenc e Analyze Show User Interface PRT#115 22 February 2012 Approved for Public Release
  • 10. Example Analysis: Baseline Case  Four budget elements, includes series and parallel events Summary Results Gantt Chart Date 10/1/2012 10/1/2013 10/1/2014 10/1/2015 9/30/2016 Task 1 Task 2 Start Date Finish Date Task 3 Task 1 10/1/2012 2/13/2016 Task 2 4/1/2013 1/25/2014 Task 4 Task 3 1/26/2014 6/18/2015 Task 4 1/26/2014 11/25/2015 • Each task has an associated TI and TD cost, resulting in the following spending profile: Summary Results by Schedule Elements (Constant Year $) 250 This example assumed 200 up to $200 was available per year, as 150 Task 4 demonstrated by the $M Task 3 Task 2 black line 100 Task 1 50 0 2011 2012 2013 2014 2015 2016 2017 2018 PRT#115 22 February 2012 Approved for Public Release
  • 11. Example Analysis: Excursion 1 • What if the budgets are constrained by 10% each year? – Because tasks will now begin slipping, it is also necessary to define constraints in the out-years beyond 2016, this example assumes funding continues at 2016 levels ($180 in this example) Summary Results Gantt Chart Summary Results by Schedule Elements (Then Year $) 200 Date 10/1/2012 10/1/2013 10/1/2014 10/1/2015 9/30/2016 9/30/2017 180 160 Task 1 140 120 Task 4 $M 100 Task 3 Task 2 80 Task 2 Task 1 60 Task 3 40 20 Task 4 0 2011 2012 2013 2014 2015 2016 2017 2018 2019 Summary Results Gantt Chart - Original Budget Date 10/1/2012 10/1/2013 10/1/2014 10/1/2015 9/30/2016 9/30/2017 Original Duration Excursion Duration Original Cost Excursion Cost Task 1 Task 1 1230 1541 $402.64 $453.18 311 day slip from Task 2 299 356 $69.35 $72.70 Task 2 baseline Task 3 508 666 $57.99 $63.28 Task 4 668 874 $144.35 $170.78 Task 3 Task 4 PRT#115 22 February 2012 Approved for Public Release
  • 12. Example Analysis: Comparison  Excursion has a 12% increase in cost  All excursion tasks have an increased duration  Task 1 has the largest increase in duration  Increases in duration correspond to increased TD costs  Constraining the budget will avoid cost in those years, but the deferred work and presence of fixed costs will result in a net cost increase and schedule slip  How can this information be used? Some examples:  It is apparent Task 1 is a large cost driver in the new case, prioritizing it at the expense of the other, shorter, tasks may result in a total cost savings  If the goal is a budget reduction, it may be preferable to focus the reduction on only one or two years instead of spreading it evenly  These different scenarios can be run to explore the nature of the budget constraint PRT#115 22 February 2012 Approved for Public Release
  • 13. Example Analysis: Excursion 2  Prioritizing Task 1 allows it to finish earlier, and moves the entire project back to the left Summary Results Gantt Chart Date 10/1/2012 10/1/2013 10/1/2014 10/1/2015 9/30/2016 9/30/2017 Task 1 Excursion 1 Finish Date Task 2 Baseline Finish Date Task 3 • Task 1’s earlier Task 4 completion frees up money for Tasks 3 and 4 • Final cost in this case: $708 Summary Results by Schedule Elements (Constant Year $) – Final cost in Excursion 1: $760 160 – Final cost in Baseline: $674 140 120 100 Task 1 $M 80 Task 2 Task 3 60 Task 4 This is an example of how the tool can be 40 used to potentially optimize cost and 20 0 schedule within a budget constraint 2011 2012 2013 2014 2015 2016 2017 2018 PRT#115 22 February 2012 Approved for Public Release
  • 14. Example Analysis: Excursion 3  What if some of the budget cuts can be reallocated?  In this example, we will cause FY2013 to take most of the budget cuts, but then increase the budget in the out-years: 2013 2014 2015 2016 2017 $100.00 $200.00 $200.00 $200.00 $200.00 Summary Results Gantt Chart Date 10/1/2012 10/1/2013 10/1/2014 10/1/2015 9/30/2016 9/30/2017 Task 1 Task 2 Task 3 Task 4 • This example finishes at nearly the same time as the original excursion – Total cost reduced to $743, compared to the excursion 1’s $760 PRT#115 22 February 2012 Approved for Public Release
  • 15. Modeling the Effect of Budget Constraints on Cost and Schedule COST RISK ANALYSIS PRT#115 22 February 2012 Approved for Public Release 15
  • 16. Current Techniques to Align Cost and Schedule via Uncertainty Analysis Total - Cost Estimate Uncertainty Analysis Results BY2010 $M 100.0% 4.5% 90.0% 4.0% 80.0% 3.5% Probability (Histogram) 70.0% Confidence Level (CDF) 3.0% 60.0% 2.5% 50.0% 2.0% 40.0% 1.5% 30.0% 20.0% Time Phased - Risk Adjusted Estimate 1.0% Technical $100 10.0% 0.5% Parameters $90 0.0% $75 $215 $356 $497 $638 $778 $919 $1,060 $1,201 $1,341 0.0% Allocated Dollars for 70% CL $80 Probability Histogram Confidence Level (CDF) CERs Point Estimate $70 Cost Uncertainty Analysis $60 TY $M $50 $40 $30 $20 Project Finish Date $10 100.0% 2.0% $0 90.0% 1.8% 80.0% 2006 2007 2008 2009 2010 1.6% 2011 2012 2013 2014 2015 2016 70.0% 1.4% Probability (Histogram) Confidence Level (CDF) 60.0% 1.2% 50.0% 1.0% 40.0% 0.8% 30.0% 0.6% 20.0% 0.4% 10.0% 0.2% 0.0% 0.0% 24 Mar 2012 24 Dec 2012 24 Sep 2013 24 Jun 2014 24 Mar 2015 24 Dec 2015 Probability Histogram Confidence Level (CDF) Schedule Schedule Uncertainty Analysis PRT#115 22 February 2012 Approved for Public Release
  • 17. However, Budget Profiles Rarely Match Risk-Adjusted Time-Phased Estimates $100 $90 Allocated Dollars for 70% CL $80 Shortfall Point Estimate $70 Project Budget $60 TY $M $50 $40 $30 $20 $10 $0 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016  Annual budget sufficient to cover estimated point estimate effort  Shortfall in funding 70% effort for years 2007-2011 How Does Shortfall Impact Project? PRT#115 22 February 2012 Approved for Public Release
  • 18. The Concept  Tecolote Developed a ROM-level analysis technique for NASA to gauge the impact of budget availability on a project’s target cost confidence level  The Technique requires:  Risk adjusted, time-phased cost estimate  Annual budget information  User input on how to address multiple items (e.g., penalties, etc)  The General Approach  Compare estimated effort (i.e., point estimate, risk adjusted time phased results, or annual risk iteration results) to available budget  Identify and track budget shortfalls  Rollover unfunded effort, with associated inflation and productivity penalties, to future years  Apply logic to use available budget to fund rollover effort PRT#115 22 February 2012 Approved for Public Release
  • 19. General Approach for Three Different Scenarios PRT#115 22 February 2012 Approved for Public Release
  • 20. User Inputs and Controls  The user has the ability to:  Select type of analysis to conduct  Point estimate  Risk-adjusted (e.g., 70%) cost estimate  Dynamic assessment of confidence level results  Specify budget scenarios  Advanced Considerations  Extend budget at peak  Incorporating fixed costs (LOE) into  Infuse/Reduce funds in specific consideration year  Conducting portfolio analysis  Allow budget carryover  Incorporate penalties for rollover  Outputs effort:  Initial phasing result for Target CL  Inflation considerations  Constrained phasing result  Productivity loss  Additional years of funding required PRT#115 22 February 2012 Approved for Public Release
  • 21. Example Case – 70% Effort Exceeds Available Budget  Phased budget and point estimate TY$M FY 2007 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Total Budget $25 $55 $65 $80 $70 $60 $30 $15 $400 Cost $21.8 $51.9 $63.6 $62.4 $52.9 $37.8 $18.9 $1.8 $311 Cost Estimate Uncertainty Analysis Results TY $M 100.0% 4.5%  Cost risk analysis data (TY$M) 90.0% 80.0% 4.0% 3.5% Probability (Histogram) Point Confidence Standard 70.0% Confidence Level (CDF) 3.0% Mean CV 60.0% Estimate Level Deviation 50.0% 2.5% 2.0% 40.0% $311 42% $372 $168 0.45 30.0% 1.5% 20.0% 1.0% 10.0% 0.5% 0.0% 0.0% $75 $216 $357 $499 $640 $781 $922 $1,063 $1,205 $1,346 Probability Histogram Confidence Level (CDF)  Cost estimate @ 70% confidence level TY$M FY 2007 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Total 70% CLE $29.8 $71.2 $87.1 $85.6 $72.4 $51.7 $25.9 $2.5 $426 Budget Shortfall to Fund 70% CLE PRT#115 22 February 2012 Approved for Public Release
  • 22. Understanding the Shortfall – Work Slips to the Right  Budget exceeds Budget vs 70% Risk-Adjusted Estimate - Surplus/Shortfall Budget vs Pt Estimate - Surplus/Shortfall  Total Budget phased point $25 estimate in every year inadequate to $26M Total Shortfall - $89M Budget Surplus  Limited70% CLE fund surplus in $20 early years Funds Available For Reserve Utilization   Largeglance seems At first shortfall $15 in early years, if that enough reserves Annual Surplus / Shortfall - TY$M are available for $10 funds program cannot be obtained, $5 $5 effort will slip into future $0 $0 2007 2007 2008 2008 2009 2009 2010 2010 2011 2011 2012 2012 2013 2013 2014 2014 periods -$5 -$5  2007 work slips to 2008 -$10  and so on… $50M of work effort  Extended work -$15 cannot be done in carries 2007-2011 penalties -$20  Inflation -$25  Productivity What are Possible Budget Scenarios? PRT#115 22 February 2012 Approved for Public Release
  • 23. Identifying Budget Scenarios  Budget Scenario Considerations  Need to be realistic  Near-term funds are difficult to obtain  Annual increase must match capability to ramp up staffing levels and should track to required work  Should not have extreme changes year-to-year  Difficult to increase beyond peak spending year  Cannot upset overall portfolio needs  Potential Options  Identify infusion of funds into specific years  Extend funding beyond peak funding year at or near peak value $100.000 $90.000 $80.000 $70.000 Project Budget $60.000 $50.000 $40.000 Budget Extension at Peak $30.000 $20.000 $10.000 $0.000 2007 2008 2009 2010 2011 2012 2013 2014 2015 PRT#115 22 February 2012 Approved for Public Release
  • 24. Example Case Results – Effort Rollover Fits Under Budget Constraint $100 70% Risk Adjusted Estimate RolloverEffort 70% Risk Adjusted Estimate $90 14 2 3 Budget Funded Effort BudgetEstimateEffort Point Funded Effort Budget Funded $80 70% Risk Adjusted Estimate Project Budget Extended Budget $70 Extended Budget $60 $50 $40 $30 $20 $10 $0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 1. Initial Conditions indicate budget inadequate to fund 70% CLE 2. Project funded to budget value 3. Budget scenario created to extend budget at peak value and 70% time-phased estimate funded to extended budget values 4. Impact of rollover effort funded in out-years PRT#115 22 February 2012 Approved for Public Release
  • 25. Modeling the Effect of Budget Constraints on Cost and Schedule INTEGRATED COST AND SCHEDULE RISK ANALYSIS PRT#115 22 February 2012 Approved for Public Release 25
  • 26. Integrated Cost/Schedule Budget Constrained Reserve Phasing Model  A tool is needed that accurately models the relationships between the work to be done, the annual budget available, and the overall cost and finish date of a project  Tool can be used to determine appropriate annual budgets and reserve strategies to meet the Joint Confidence Level requirement  The tool is called Budget-Constrained Reserve Phase (BCRPhase) 26 PRT#115 22 February 2012 Approved for Public Release
  • 27. High - Level Model Concept  Schedule Activities from JCL Models (or Project Schedules) are Mapped into Budget Organizations (Groupings)  Links Between Budget Organizations are Identified  Costs from JCL Models (or Projects Costs/Budget) are Mapped into Behavior Buckets within Budget Organizations  Cost Distributions Obtained from JCL Models (or other Analytical Methods) are Defined for Each Element  Discrete Risks from JCL Models (or Project Risk Lists) are Specified  Annual Values are Identified for Each Budget Organization  Monte Carlo Simulations are Generated to Determine Effort, Work is Adjusted to Fit Effort within Budget Level PRT#115 22 February 2012 Approved for Public Release 27
  • 28. Modeling Approach – Enabling via Budget Organization Levels PRT#115 22 February 2012 Approved for Public Release 28
  • 29. Example Simple Project Model (5 Budget Organization Items) Budget Effort/Costs Schedule PRT#115 22 February 2012 Approved for Public Release 29
  • 30. Model in Action – What Happens When Effort Exceeds Budget Availability Organization 1 Organization 2 Time Time-Driving Costs (Touch Labor, Materials, etc.) Schedule Activity Time-Driving Costs Driven By Schedule Slip Milestone Level Of Effort Costs Schedule Dependency PRT#115 22 February 2012 Approved for Public Release 30
  • 31. Modeling the Effect of Budget Constraints on Cost and Schedule SUMMARY PRT#115 22 February 2012 Approved for Public Release 31
  • 32. Summary  Understanding connection between cost and schedule is of utmost importance for estimators  Available funds and resources are major items that directly impact overall project schedule and end costs  Tools have been developed and research is continuing to help us assess this intricate system Budget Duration Technical Reqts Work Plan Scope Cost Effort Size PRT#115 22 February 2012 Approved for Public Release 32
  • 33. Thank You PRT#115 22 February 2012 Approved for Public Release 33