Radio Active section
1. AWI
Halliburton Project / RA section
1 | P a g e
www.awi.com
Project Name: Halliburton Project / Radio Active section
Site Position: Construction Site Supervisor
Project Start: 14th
November 2013
Project Finished: 18 December 2013
Duration : 34 Days
Work Done :
o Raft Foundation ( 10m x 20m )
o 32 Reinforced Concrete Cellular ( 1m x 1m x 2m )
o Hangar Steel Structure
o Double Fence around the section