2. Time Study Analysis Report
The rework required in some cases takes one day usually for its completion.
The pieces after inspection which are found to be defected are sent for rework in the
previous level of machining to attain the desire level of satisfaction and requirements.
After the boil test the pieces which are found to be defected are sent to the passivation
chamber for the treatment and then after that these pieces are Re-boiled to check
whether they meet the level of satisfaction or not. For this Treatment of the defected
pieces, it requires at least a day to proceed for next level.
The operations which require more time than others include Heat Treatment, Boil Test,
Polishing and Filing.
Delay in these operations may result into delay in production lot.
These operations must be performed carefully and accurately so that no or less defected
pieces are produced and more time can be saved. Time saving activity ultimately results
in more production level, delivery on time therefore more profit generation.
Packing of the products involves three major steps which include oiling, cleaning and
then packing.
It takes approximately 28 days for the completion of 1 lot (200 pieces) of scissor in that
case when there is no rework and no other item is being manufactured and processes
are continuous.
In case of rework and other factors it can take more than 28 days for its production,
depending upon the situation of production line.
The product which is selected is of stock, having lot no DF-26-388 which is Metzenbaum-
Nelson Dissecting Scissor.
As there is batch production process in Dr.frigz, therefore it can take around 30 days for
the production of 200 pieces of nelson Dissecting Scissor.