SlideShare ist ein Scribd-Unternehmen logo
1 von 20
Engro Eximp Projects
Report
Year 2013
Prepared By
M Abid
 HSE
 Phase 1
 Phase 2
 Buhler Modification (Mechanical + Automation + Results)
 Project CAPEX-2012 Summary
 Additional Works
 Pending Jobs
 Project Closeout and Demobilization Plan
CONTENTS OF THE PRESENTATION
SAFETY STATISTICS - 2012
PHASE 1 (2011) Compliance %
 TOTAL MANHOURS: 3 Million
 TRIR (LWI:01 MTC:01 RWC:02 ) 0.27 Vs 0.30 ( Projects )
 MSA Compliance 90%
 D-Level Compliance 80%
 MSA Observation Closure 60%
 IR-2 Submission on Time 75%
 IR-2 Recommendation Closure 50%
PHASE 2 (2012)
 TOTAL MANHOURS: (Safe ) 0.6 Million
 TRIR 0.00 Vs 0.30 ( Projects)
 MSA Compliance 100%
 D-Level Compliance 100%
 MSA Observation Closure 90%
 IR-2 Submission on Time 95%
 IR-2 Recommendation Closure 80%
PHASE - 1
Completion
 CDP Lines A,B & C (Partial) Nov 2010
 Admin Building & Infrastructure Dec 2010
 Processing Mill (Line 1 & 2) May 2011
 Parboiling Plant May 2011
 HP Boiler Nov 2011
 Laboratory Sep 2011
 Engineering Warehouse June 2011
 Cooling Tower (Commissioning to be done) Feb 2011
 ETP Plant (Pit Resize to be done) July 2011
 Utilities (Raw Water, RO, Steam Network July 2011
& Instrument Air,Diesel Gensets)
 Fire Water July 2012
PROJECTS COMPLETED
PHASE - 2
Completion Date
 CDP Lines C, D(50TPDH) & E Oct-Nov 2011
 Storage Silos (Qty 10) Oct 2011
 Sampling Bay Oct 2011
 Trucker’s Area Nov 2011
 New Ageing Store Nov 2011
 Worker’s Interface Dec 2011
 Seed Plant (Commissioning to Dec 2011
be done)
PROJECTS COMPLETED
Buhler Modification & Trial Runs
BACKGROUND:
As the CDP Lines were not meeting design parameters in terms of capacity &
quality, improvement project was carried out in collaboration with Buhler and a
series of mechanical & automation modifications were done to meet the desired
results.
Scope of Modifications:
Line A, B & C
Erection of Drum Sieves, Dryers Modification, Airlocks, Structure modification &
Improved chutes & hoppers
Line D & E
Erection of Drum Sieves, Receiving Pit Conveyor , Dryer Modification, Airlocks Structure
modification & Improved chutes & hoppers
 As a result of extensive trial run in August , further modification were done on TAS
Machine , 1st two elevator ‘s buckets & various chutes & hoppers.
 All Modifications were done as per agreed Gantt chart timelines with quality.
MECHANICAL WORKS
Buhler Modification & Trial Runs
AUTOMATION WORKS
Line A, B & C
 New PLC Installation
 Software Rewriting/ WinCos Implementation
 IOs Loop Checking & Sequence Testing
 Addition of New Hardware (Panel, Sensor, Controller & Cable Work)
 FAT/SAT done
Line D & E
 Incorporation of Additional Machines (Drum Sieves, Airlocks) in the
existing software by Avanceon (Allen Bradley).
 IOs Loop Checking & Sequence Testing with additional machines.
 All Jobs done within timelines and as per operation requirement.
 Previously the Processing Lines were running on semi auto mode, and two different
PLCs (Siemens & Allan Bradley) were in operation, Now A,B & C Lines are being
controlled by a Single PLC and running on auto sequence successfully as seen in the
Trial Test
 Previously there was no review of process flow nor Buhler has provided standard
documents on the base of which a software should operate .Therefore all points
incorporated as per new flow diagram.
 Proper Training of the Operators were carried out successfully during trial runs of CDP.
 Series of Trial Runs were carried out in June, August & Sept to improve cleaning &
drying capacities of each line . Each trials resulted in additional modifications .
 Reliability of the drying lines & conveying system tested & improved during trial runs.
 Extensive & detailed maintenance jobs were carried out as per checklist developed by
Buhler.
 As per latest trial run on line A (10-13 Sept), manage to achieve cleaning capacity above
22.5TPH & drying capacity of 23.5 TPH with the input average moisture 25%. Detailed
report issued separately
 Trial Run of Line D is in progress to address & improve the quality issues that were faced
at line A ( 1.85 % of trash in paddy )
Buhler Modification/Trial Run Benefits
CAPEX-2012
STATUS
 Interchanging Conveyor Done
 Head Rice Silo Modification Done
 Manual Bagging System In-Progress (Sep-25)
 Platform & Pit Covers Done
 PSSR Points Phase-1 (Oct 15 )
Phase-2 (Done )
 Brown Rice Pit In-Progress (Sep-30)
 Line 1 & 2 Modifications ( 36 M, 4-5 months)
PROJECTS
ADDITIONAL JOBS
STATUS
 Compressor Jobs Done
 LP Header Modification Done
 Mill Shutdown Jobs Done
 Silo-Trench Conveyors Done
 Transfer Conveyors Done
 Silo Level Sensors Relocation Done
PROJECTS
PENDING JOBS
STATUS
 Steam Turbine Finalization of Spec’s & vendor for
ordering in progress ( July-Aug- 2013 )
 Seed Plant Commissioning of Paddy Separator in
Progress ( October 15 )
 Ash Ponds MOC & Estimations Done (40 MPKR, 4-5 months)
 Line 1 & 2 MOC Done. RFQ raised (local suppliers, 4-5 months )
 HP Boiler Performance test done. Approx. cost 10 M
Suggested improvements in Progress.
 Auto Packing MOC Done.AR approved. ( 2-3 months )
PROJECTS
MV Switch Gear Room Engro Eximp
4MW Steam Turbine Panels
4MW Steam Turbine Panels
Integrated Rice Mill Panels
Integrated Rice project mill
Cleaning Drying Lines Electrical Panels
Award on Best Performance on 4MW
STG Project
Best Safety MSA Award Picture
Thank You..

Weitere ähnliche Inhalte

Was ist angesagt?

Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen Barkwitch
 
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...KBC (A Yokogawa Company)
 
Resume talley 1.5.2016.formatted
Resume talley 1.5.2016.formattedResume talley 1.5.2016.formatted
Resume talley 1.5.2016.formattedDennis Talley
 
Audit Review2014-15
Audit Review2014-15Audit Review2014-15
Audit Review2014-15R Vargis
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationKBC (A Yokogawa Company)
 
Michael Page Resume
Michael Page ResumeMichael Page Resume
Michael Page ResumeMike Page
 
Benzene Emissions - Staying in Compliance as Regulations Change
Benzene Emissions - Staying in Compliance as Regulations ChangeBenzene Emissions - Staying in Compliance as Regulations Change
Benzene Emissions - Staying in Compliance as Regulations ChangeProcess Ecology Inc
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysisMd. Sohag Miah
 
Intelligent Mining: Integrated Mine Planning and Operations
Intelligent Mining: Integrated Mine Planning and OperationsIntelligent Mining: Integrated Mine Planning and Operations
Intelligent Mining: Integrated Mine Planning and OperationsABB Enterprise Software
 
Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Joseph Girouard
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon
 
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...Process Ecology Inc
 

Was ist angesagt? (20)

Stephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioningStephen_Anthony_Barkwitch_CV_-commissioning
Stephen_Anthony_Barkwitch_CV_-commissioning
 
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
Europe User Conference: ADNOC predictive model of gas oil hydrotreater unit f...
 
abid1
abid1abid1
abid1
 
Work Experience
Work ExperienceWork Experience
Work Experience
 
Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 1...
Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 1...Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 1...
Experience from TCM, Olav Falk Pedersen (Gassnova) UK/Norway/Canada Meeting 1...
 
Resume talley 1.5.2016.formatted
Resume talley 1.5.2016.formattedResume talley 1.5.2016.formatted
Resume talley 1.5.2016.formatted
 
Mahesh_Y_Patil
Mahesh_Y_PatilMahesh_Y_Patil
Mahesh_Y_Patil
 
Audit Review2014-15
Audit Review2014-15Audit Review2014-15
Audit Review2014-15
 
Europe User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluationEurope User Conference: GRACE catalyst trial evaluation
Europe User Conference: GRACE catalyst trial evaluation
 
Cold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban AreasCold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban Areas
 
Caltrans Pavement Design Perspective
Caltrans Pavement Design PerspectiveCaltrans Pavement Design Perspective
Caltrans Pavement Design Perspective
 
CV - M. Taj Arain
CV - M. Taj ArainCV - M. Taj Arain
CV - M. Taj Arain
 
Michael Page Resume
Michael Page ResumeMichael Page Resume
Michael Page Resume
 
Benzene Emissions - Staying in Compliance as Regulations Change
Benzene Emissions - Staying in Compliance as Regulations ChangeBenzene Emissions - Staying in Compliance as Regulations Change
Benzene Emissions - Staying in Compliance as Regulations Change
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
Intelligent Mining: Integrated Mine Planning and Operations
Intelligent Mining: Integrated Mine Planning and OperationsIntelligent Mining: Integrated Mine Planning and Operations
Intelligent Mining: Integrated Mine Planning and Operations
 
Girouard.joseph.resume.v5
Girouard.joseph.resume.v5Girouard.joseph.resume.v5
Girouard.joseph.resume.v5
 
Saikaat Saha CV
Saikaat Saha CVSaikaat Saha CV
Saikaat Saha CV
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...
Emission Regulations and Reductions Technology in Western Canada's Oil and Ga...
 

Andere mochten auch

1.andre resume full rev1
1.andre resume  full rev11.andre resume  full rev1
1.andre resume full rev1Andre Sookool
 
Visit to ESP At Aqiu Huarui China
Visit to ESP At Aqiu Huarui ChinaVisit to ESP At Aqiu Huarui China
Visit to ESP At Aqiu Huarui ChinaM Abid Latif
 
Subduction zones Convection currents and continental drift
Subduction zones Convection currents and continental driftSubduction zones Convection currents and continental drift
Subduction zones Convection currents and continental driftAhmed732
 
Shaking our world (Plate boundaries)
Shaking our world (Plate boundaries)Shaking our world (Plate boundaries)
Shaking our world (Plate boundaries)Ahmed732
 
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (2)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (2)FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (2)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (2)M Abid Latif
 
Convection currents and continental drift
Convection currents and continental driftConvection currents and continental drift
Convection currents and continental driftAhmed732
 
Futuristic driverless cars are here now
Futuristic driverless cars are here nowFuturistic driverless cars are here now
Futuristic driverless cars are here nowwebsolutionz
 
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (1)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (1)FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (1)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (1)M Abid Latif
 
Plate boundaries
Plate boundaries Plate boundaries
Plate boundaries Ahmed732
 
Nndt marine profile rev 2
Nndt marine profile rev 2Nndt marine profile rev 2
Nndt marine profile rev 2Andre Sookool
 

Andere mochten auch (14)

Idealconsultant.com
Idealconsultant.comIdealconsultant.com
Idealconsultant.com
 
NovFinished2
NovFinished2NovFinished2
NovFinished2
 
Aprilfinal
AprilfinalAprilfinal
Aprilfinal
 
1.andre resume full rev1
1.andre resume  full rev11.andre resume  full rev1
1.andre resume full rev1
 
Visit to ESP At Aqiu Huarui China
Visit to ESP At Aqiu Huarui ChinaVisit to ESP At Aqiu Huarui China
Visit to ESP At Aqiu Huarui China
 
Subduction zones Convection currents and continental drift
Subduction zones Convection currents and continental driftSubduction zones Convection currents and continental drift
Subduction zones Convection currents and continental drift
 
Nndt marine profile
Nndt marine profileNndt marine profile
Nndt marine profile
 
Shaking our world (Plate boundaries)
Shaking our world (Plate boundaries)Shaking our world (Plate boundaries)
Shaking our world (Plate boundaries)
 
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (2)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (2)FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (2)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (2)
 
Convection currents and continental drift
Convection currents and continental driftConvection currents and continental drift
Convection currents and continental drift
 
Futuristic driverless cars are here now
Futuristic driverless cars are here nowFuturistic driverless cars are here now
Futuristic driverless cars are here now
 
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (1)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (1)FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif  (1)
FAT Pictures of Generator 4MW Steam Turbine conducted by M Abid Latif (1)
 
Plate boundaries
Plate boundaries Plate boundaries
Plate boundaries
 
Nndt marine profile rev 2
Nndt marine profile rev 2Nndt marine profile rev 2
Nndt marine profile rev 2
 

Ähnlich wie Intergrated Rice Plant Progress 2013

Smart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves EnergySmart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves EnergyJim Cahill
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationAmeya Margaj
 
TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docjennbarroga7
 
Calstart fuel cell bus review short v3
Calstart fuel cell bus review short v3Calstart fuel cell bus review short v3
Calstart fuel cell bus review short v3CALSTART
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
Curriculum vitae Bhupat Kanani
Curriculum vitae Bhupat KananiCurriculum vitae Bhupat Kanani
Curriculum vitae Bhupat KananiBhupat Kanani
 
Curriculum vitae_Bhupat Kanani
Curriculum vitae_Bhupat KananiCurriculum vitae_Bhupat Kanani
Curriculum vitae_Bhupat KananiBhupat Kanani
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptxPradeepKumar504728
 
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...LOESCHE
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptxDILIP KUMAR M.Tech (ACT)
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulMuhammad Asad Ullah
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxIESGATEWiz
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011abughaws
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 

Ähnlich wie Intergrated Rice Plant Progress 2013 (20)

SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
 
Smart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves EnergySmart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves Energy
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).doc
 
Calstart fuel cell bus review short v3
Calstart fuel cell bus review short v3Calstart fuel cell bus review short v3
Calstart fuel cell bus review short v3
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
Curriculum vitae Bhupat Kanani
Curriculum vitae Bhupat KananiCurriculum vitae Bhupat Kanani
Curriculum vitae Bhupat Kanani
 
Curriculum vitae_Bhupat Kanani
Curriculum vitae_Bhupat KananiCurriculum vitae_Bhupat Kanani
Curriculum vitae_Bhupat Kanani
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
Increased Pulverizer Performance with Loesche’s High Efficiency Dynamic Class...
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
Leed Modeling
Leed ModelingLeed Modeling
Leed Modeling
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
TA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation OverhaulTA-2015 GE Frame-V Field Instrumentation Overhaul
TA-2015 GE Frame-V Field Instrumentation Overhaul
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011
 
Rahulvikram2016
Rahulvikram2016Rahulvikram2016
Rahulvikram2016
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
 

Intergrated Rice Plant Progress 2013

  • 1. Engro Eximp Projects Report Year 2013 Prepared By M Abid
  • 2.  HSE  Phase 1  Phase 2  Buhler Modification (Mechanical + Automation + Results)  Project CAPEX-2012 Summary  Additional Works  Pending Jobs  Project Closeout and Demobilization Plan CONTENTS OF THE PRESENTATION
  • 3. SAFETY STATISTICS - 2012 PHASE 1 (2011) Compliance %  TOTAL MANHOURS: 3 Million  TRIR (LWI:01 MTC:01 RWC:02 ) 0.27 Vs 0.30 ( Projects )  MSA Compliance 90%  D-Level Compliance 80%  MSA Observation Closure 60%  IR-2 Submission on Time 75%  IR-2 Recommendation Closure 50% PHASE 2 (2012)  TOTAL MANHOURS: (Safe ) 0.6 Million  TRIR 0.00 Vs 0.30 ( Projects)  MSA Compliance 100%  D-Level Compliance 100%  MSA Observation Closure 90%  IR-2 Submission on Time 95%  IR-2 Recommendation Closure 80%
  • 4. PHASE - 1 Completion  CDP Lines A,B & C (Partial) Nov 2010  Admin Building & Infrastructure Dec 2010  Processing Mill (Line 1 & 2) May 2011  Parboiling Plant May 2011  HP Boiler Nov 2011  Laboratory Sep 2011  Engineering Warehouse June 2011  Cooling Tower (Commissioning to be done) Feb 2011  ETP Plant (Pit Resize to be done) July 2011  Utilities (Raw Water, RO, Steam Network July 2011 & Instrument Air,Diesel Gensets)  Fire Water July 2012 PROJECTS COMPLETED
  • 5. PHASE - 2 Completion Date  CDP Lines C, D(50TPDH) & E Oct-Nov 2011  Storage Silos (Qty 10) Oct 2011  Sampling Bay Oct 2011  Trucker’s Area Nov 2011  New Ageing Store Nov 2011  Worker’s Interface Dec 2011  Seed Plant (Commissioning to Dec 2011 be done) PROJECTS COMPLETED
  • 6. Buhler Modification & Trial Runs BACKGROUND: As the CDP Lines were not meeting design parameters in terms of capacity & quality, improvement project was carried out in collaboration with Buhler and a series of mechanical & automation modifications were done to meet the desired results. Scope of Modifications: Line A, B & C Erection of Drum Sieves, Dryers Modification, Airlocks, Structure modification & Improved chutes & hoppers Line D & E Erection of Drum Sieves, Receiving Pit Conveyor , Dryer Modification, Airlocks Structure modification & Improved chutes & hoppers  As a result of extensive trial run in August , further modification were done on TAS Machine , 1st two elevator ‘s buckets & various chutes & hoppers.  All Modifications were done as per agreed Gantt chart timelines with quality. MECHANICAL WORKS
  • 7. Buhler Modification & Trial Runs AUTOMATION WORKS Line A, B & C  New PLC Installation  Software Rewriting/ WinCos Implementation  IOs Loop Checking & Sequence Testing  Addition of New Hardware (Panel, Sensor, Controller & Cable Work)  FAT/SAT done Line D & E  Incorporation of Additional Machines (Drum Sieves, Airlocks) in the existing software by Avanceon (Allen Bradley).  IOs Loop Checking & Sequence Testing with additional machines.  All Jobs done within timelines and as per operation requirement.
  • 8.  Previously the Processing Lines were running on semi auto mode, and two different PLCs (Siemens & Allan Bradley) were in operation, Now A,B & C Lines are being controlled by a Single PLC and running on auto sequence successfully as seen in the Trial Test  Previously there was no review of process flow nor Buhler has provided standard documents on the base of which a software should operate .Therefore all points incorporated as per new flow diagram.  Proper Training of the Operators were carried out successfully during trial runs of CDP.  Series of Trial Runs were carried out in June, August & Sept to improve cleaning & drying capacities of each line . Each trials resulted in additional modifications .  Reliability of the drying lines & conveying system tested & improved during trial runs.  Extensive & detailed maintenance jobs were carried out as per checklist developed by Buhler.  As per latest trial run on line A (10-13 Sept), manage to achieve cleaning capacity above 22.5TPH & drying capacity of 23.5 TPH with the input average moisture 25%. Detailed report issued separately  Trial Run of Line D is in progress to address & improve the quality issues that were faced at line A ( 1.85 % of trash in paddy ) Buhler Modification/Trial Run Benefits
  • 9. CAPEX-2012 STATUS  Interchanging Conveyor Done  Head Rice Silo Modification Done  Manual Bagging System In-Progress (Sep-25)  Platform & Pit Covers Done  PSSR Points Phase-1 (Oct 15 ) Phase-2 (Done )  Brown Rice Pit In-Progress (Sep-30)  Line 1 & 2 Modifications ( 36 M, 4-5 months) PROJECTS
  • 10. ADDITIONAL JOBS STATUS  Compressor Jobs Done  LP Header Modification Done  Mill Shutdown Jobs Done  Silo-Trench Conveyors Done  Transfer Conveyors Done  Silo Level Sensors Relocation Done PROJECTS
  • 11. PENDING JOBS STATUS  Steam Turbine Finalization of Spec’s & vendor for ordering in progress ( July-Aug- 2013 )  Seed Plant Commissioning of Paddy Separator in Progress ( October 15 )  Ash Ponds MOC & Estimations Done (40 MPKR, 4-5 months)  Line 1 & 2 MOC Done. RFQ raised (local suppliers, 4-5 months )  HP Boiler Performance test done. Approx. cost 10 M Suggested improvements in Progress.  Auto Packing MOC Done.AR approved. ( 2-3 months ) PROJECTS
  • 12. MV Switch Gear Room Engro Eximp
  • 17. Cleaning Drying Lines Electrical Panels
  • 18. Award on Best Performance on 4MW STG Project
  • 19. Best Safety MSA Award Picture