National Guard
Black Belt Training
     Module 17

     Takt Time
UNCLASSIFIED / FOUO




CPI Roadmap – Measure
                                                             8-STEP PROCESS
                                                                                                       6. See
   1.Validate          2. Identify           3. Set          4. Determine          5. Develop                           7. Confirm    8. Standardize
                                                                                                      Counter-
      the             Performance         Improvement            Root               Counter-                             Results        Successful
                                                                                                      Measures
    Problem               Gaps              Targets              Cause             Measures                             & Process        Processes
                                                                                                      Through

        Define                Measure                         Analyze                           Improve                        Control


                                                                       TOOLS
                                                                  •Process Mapping
                                    ACTIVITIES
                  •   Map Current Process / Go & See              •Process Cycle Efficiency/TOC
                  •   Identify Key Input, Process, Output Metrics •Little’s Law
                  •   Develop Operational Definitions             •Operational Definitions
                  •   Develop Data Collection Plan                •Data Collection Plan
                  •   Validate Measurement System                 •Statistical Sampling
                  •   Collect Baseline Data                       •Measurement System Analysis
                  •   Identify Performance Gaps                   •TPM
                  •   Estimate Financial/Operational Benefits     •Generic Pull
                  •   Determine Process Stability/Capability      •Setup Reduction
                  •   Complete Measure Tollgate                   •Control Charts
                                                                  •Histograms
                                                                  •Constraint Identification
                                                                  •Process Capability                                                              2


                       Note: Activities and tools vary by project. Lists provided here are not necessarily all-inclusive.    UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Objectives

          Understand the following:
            – Takt Time
            – Theoretical minimum staffing levels
            – Takt Time, Cycle Time Bar Charts
            – How all of these concepts assist in
              understanding and improving a process




                                                                            3


                                                      UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Definition of Takt Time
          Time required to produce a component or set of
           components to meet customer demand

                                        Operating Time
                      Takt Time =
                                    Customer Requirements




          Subject to change – depending on demand from
           the customer
          Determines rate of production
          Key to determining resource requirements
                                                                                  4


                                                            UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takt Time Example – Step 1
    Step 1: Determine available time

     Aircrew Flight Equipment (AFE) has 1 hour a day to test life
      vests
           52 (weeks) * 5 (days/week) * 1 hour = 260 hours

     Convert to minutes
          260 hours * 60 minutes/hour = 15,600 minutes


    Answer: 15,600 minutes is the total available operating time
      per year

                                                                             5


                                                       UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takt Time Example – Step 2

      Step 2: Determine Customer Requirement
        – Average daily customer demand
        – Get this anyway you can
           • Advance orders
           • Forecasts
           • Historical data
           • Best guess!
        – For this example, AFE has 3,120 life vests to maintain
            3,120 units per year is the customer requirement


                                                                            6


                                                      UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takt Time Example – Step 3

          Divide operating time by demand

                  15600 minutes/year divided by 3,120 units/year

          Takt time =          5 minutes (300 seconds)

          This is the time that each process step CANNOT
           exceed in order to meet customer demand using
           single piece flow!


                                                                                 7


                                                           UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takt Time vs. Cycle Time

      Cycle time is the time for an operator to do a prescribed
       task and return to his or her original stance
      Don’t confuse cycle time and Takt Time!!


        WHAT’S WRONG WITH THIS QUOTE ??
        “Those people have Takt time down to a science! Their Takt time
         is 54 seconds. They make a car in 54 seconds and every step in
          the process takes 54 seconds. And they have a plan to reduce
        their Takt time to 52 seconds through constantly improving every
                                 job! Amazing!!!”

                                                                                   8


                                                             UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takt Time & Theoretical Minimum Staffing

     If we:
     • Understand the Total Cycle Time required to
       produce a unit, and we have
     • Calculated the Takt Time of this unit

      We can calculate the theoretical minimum staffing
     required. This is calculated as:

     TOTAL CYCLE TIME
                            = MINIMUM STAFF REQUIRED
       TAKT TIME


                                                                           9


                                                     UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Theoretical Minimum Staffing - Example
      If the Total Cycle Time of all the operators combined =
                            720 seconds
                                AND
                    The Takt Time is 300 seconds

      WHAT IS THE MINIMUM STAFFING REQUIREMENT
                FOR LIFE VESTS IN AFE?

                      720 sec/300 sec = 2.4 …so 3 People
          In your experience, what are some of the practical issues
              that make it difficult to hit this minimum staffing??
                                                                               10


                                                         UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Cycle Time Bar Charts
     Takt Time – Cycle Time Bar Charts enable us to visualize a
     production line with data and determine some of its
     operating characteristics
                               Operator Cycle Time in
                                   Seconds/Part
                                                     Let’s look at a sample chart
                      80     70
                                         Takt Time = 60 Sec
                      60
                                                     45
                                    40
                      40                                      30

                      20                   15

                      0
                           Oper.1 Oper.2 Oper.3 Oper.4 Oper.5
                                                                                           11


                                                                     UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Cycle Time Bar Chart - After
                              Operator Cycle Time in
                                  Seconds/Part

                      80
                                                    Takt Time = 60 Sec
                             60       60       60
                      60

                      40
                                                           20
                      20

                      0
                           Oper.1   Oper.2   Oper.3     Oper.4
                                                                                               12


                                                                         UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Cycle Time Bar Chart - Final
                              Operator Cycle Time in
                                  Seconds/Part

                      80
                                                      Takt Time = 60 Sec
                             60       60       60
                      60

                      40

                      20

                      0
                           Oper.1   Oper.2   Oper.3

                                                                                           13


                                                                     UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




Takeaways

          Takt Time is based on customer demand – it is
           the time in which a task must be completed to
           meet the customer requirements
          Cycle time is the time it takes to actually
           complete the task
          Use takt time and cycle time to determine
           theoretical minimum staffing levels
          Visually display staffing levels using Cycle Time
           Bar Charts to help improve the process

                                                                            14


                                                      UNCLASSIFIED / FOUO
UNCLASSIFIED / FOUO




        What other comments or questions
                  do you have?




                                                         15


                                   UNCLASSIFIED / FOUO

More Related Content

What's hot

NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project CharterLeanleaders.org
 
NG BB 47 Basic Design of Experiments
NG BB 47 Basic Design of ExperimentsNG BB 47 Basic Design of Experiments
NG BB 47 Basic Design of ExperimentsLeanleaders.org
 
NG BB 49 Risk Assessment
NG BB 49 Risk AssessmentNG BB 49 Risk Assessment
NG BB 49 Risk AssessmentLeanleaders.org
 
NG BB 43 Standardized Work
NG BB 43 Standardized WorkNG BB 43 Standardized Work
NG BB 43 Standardized WorkLeanleaders.org
 
NG BB 13 Voice of Customer
NG BB 13 Voice of CustomerNG BB 13 Voice of Customer
NG BB 13 Voice of CustomerLeanleaders.org
 
NG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapNG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapLeanleaders.org
 
NG BB 09 Project Management
NG BB 09 Project ManagementNG BB 09 Project Management
NG BB 09 Project ManagementLeanleaders.org
 
NG BB 40 Solution Selection
NG BB 40 Solution SelectionNG BB 40 Solution Selection
NG BB 40 Solution SelectionLeanleaders.org
 
NG BB 46 Mistake Proofing
NG BB 46 Mistake ProofingNG BB 46 Mistake Proofing
NG BB 46 Mistake ProofingLeanleaders.org
 
NG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessNG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessLeanleaders.org
 
NG BB 36 Simple Linear Regression
NG BB 36 Simple Linear RegressionNG BB 36 Simple Linear Regression
NG BB 36 Simple Linear RegressionLeanleaders.org
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapLeanleaders.org
 
NG BB 37 Multiple Regression
NG BB 37 Multiple RegressionNG BB 37 Multiple Regression
NG BB 37 Multiple RegressionLeanleaders.org
 
NG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventNG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventLeanleaders.org
 
NG BB 45 Quick Change Over
NG BB 45 Quick Change OverNG BB 45 Quick Change Over
NG BB 45 Quick Change OverLeanleaders.org
 
NG BB 20 Data Collection
NG BB 20 Data CollectionNG BB 20 Data Collection
NG BB 20 Data CollectionLeanleaders.org
 

What's hot (18)

NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project Charter
 
NG BB 47 Basic Design of Experiments
NG BB 47 Basic Design of ExperimentsNG BB 47 Basic Design of Experiments
NG BB 47 Basic Design of Experiments
 
NG BB 49 Risk Assessment
NG BB 49 Risk AssessmentNG BB 49 Risk Assessment
NG BB 49 Risk Assessment
 
NG BB 43 Standardized Work
NG BB 43 Standardized WorkNG BB 43 Standardized Work
NG BB 43 Standardized Work
 
NG BB 13 Voice of Customer
NG BB 13 Voice of CustomerNG BB 13 Voice of Customer
NG BB 13 Voice of Customer
 
NG BB 26 Control Charts
NG BB 26 Control ChartsNG BB 26 Control Charts
NG BB 26 Control Charts
 
NG BB 12 High-Level Process Map
NG BB 12 High-Level Process MapNG BB 12 High-Level Process Map
NG BB 12 High-Level Process Map
 
NG BB 11 Power Steering
NG BB 11 Power SteeringNG BB 11 Power Steering
NG BB 11 Power Steering
 
NG BB 09 Project Management
NG BB 09 Project ManagementNG BB 09 Project Management
NG BB 09 Project Management
 
NG BB 40 Solution Selection
NG BB 40 Solution SelectionNG BB 40 Solution Selection
NG BB 40 Solution Selection
 
NG BB 46 Mistake Proofing
NG BB 46 Mistake ProofingNG BB 46 Mistake Proofing
NG BB 46 Mistake Proofing
 
NG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the ProcessNG BB 19 Document and Analyze the Process
NG BB 19 Document and Analyze the Process
 
NG BB 36 Simple Linear Regression
NG BB 36 Simple Linear RegressionNG BB 36 Simple Linear Regression
NG BB 36 Simple Linear Regression
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE Roadmap
 
NG BB 37 Multiple Regression
NG BB 37 Multiple RegressionNG BB 37 Multiple Regression
NG BB 37 Multiple Regression
 
NG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement EventNG BB 50 Rapid Improvement Event
NG BB 50 Rapid Improvement Event
 
NG BB 45 Quick Change Over
NG BB 45 Quick Change OverNG BB 45 Quick Change Over
NG BB 45 Quick Change Over
 
NG BB 20 Data Collection
NG BB 20 Data CollectionNG BB 20 Data Collection
NG BB 20 Data Collection
 

Viewers also liked (20)

OEE
OEEOEE
OEE
 
OEE
OEEOEE
OEE
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
Oee guide
Oee guideOee guide
Oee guide
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
OEE
OEEOEE
OEE
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
 
Total Productive Maintenance - TPM
Total Productive Maintenance - TPM Total Productive Maintenance - TPM
Total Productive Maintenance - TPM
 
Tpm Presentation
Tpm PresentationTpm Presentation
Tpm Presentation
 
TPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARANTPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARAN
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
 
tpm presentation
tpm presentationtpm presentation
tpm presentation
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Takt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line BalancingTakt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line Balancing
 
Value stream mapping ppt
Value stream mapping pptValue stream mapping ppt
Value stream mapping ppt
 
Value stream mapping training
Value stream mapping trainingValue stream mapping training
Value stream mapping training
 

Similar to NG BB 17 Takt Time

NG BB 27 Process Capability
NG BB 27 Process CapabilityNG BB 27 Process Capability
NG BB 27 Process CapabilityLeanleaders.org
 
NG BB 27 Process Capability
NG BB 27 Process CapabilityNG BB 27 Process Capability
NG BB 27 Process CapabilityLeanleaders.org
 
NG BB 45 Quick Change Over
NG BB 45 Quick Change OverNG BB 45 Quick Change Over
NG BB 45 Quick Change OverLeanleaders.org
 
NG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - IntroductionNG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - IntroductionLeanleaders.org
 
NG BB 15 MEASURE Roadmap
NG BB 15 MEASURE RoadmapNG BB 15 MEASURE Roadmap
NG BB 15 MEASURE RoadmapLeanleaders.org
 
NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]Leanleaders.org
 
Production and material management
Production and material managementProduction and material management
Production and material managementsksbatish
 
NG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeNG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeLeanleaders.org
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapLeanleaders.org
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation managementSaravanan Murugan
 
NG BB 24 Measurement System Analysis - Continuous
NG BB 24 Measurement System Analysis - ContinuousNG BB 24 Measurement System Analysis - Continuous
NG BB 24 Measurement System Analysis - ContinuousLeanleaders.org
 
Tool Box Talk - World Class Maintenance Edited
Tool Box Talk - World Class Maintenance   EditedTool Box Talk - World Class Maintenance   Edited
Tool Box Talk - World Class Maintenance EditedRicky Smith CMRP, CMRT
 

Similar to NG BB 17 Takt Time (20)

NG BB 27 Process Capability
NG BB 27 Process CapabilityNG BB 27 Process Capability
NG BB 27 Process Capability
 
NG BB 27 Process Capability
NG BB 27 Process CapabilityNG BB 27 Process Capability
NG BB 27 Process Capability
 
NG BB 45 Quick Change Over
NG BB 45 Quick Change OverNG BB 45 Quick Change Over
NG BB 45 Quick Change Over
 
NG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - IntroductionNG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - Introduction
 
NG BB 15 MEASURE Roadmap
NG BB 15 MEASURE RoadmapNG BB 15 MEASURE Roadmap
NG BB 15 MEASURE Roadmap
 
NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]NG BB 53 Process Control [Compatibility Mode]
NG BB 53 Process Control [Compatibility Mode]
 
Production and material management
Production and material managementProduction and material management
Production and material management
 
NG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - AttributeNG BB 25 Measurement System Analysis - Attribute
NG BB 25 Measurement System Analysis - Attribute
 
NG BB 52 CONTROL Roadmap
NG BB 52 CONTROL RoadmapNG BB 52 CONTROL Roadmap
NG BB 52 CONTROL Roadmap
 
Standard work
Standard workStandard work
Standard work
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 
Basic of work study
Basic of work studyBasic of work study
Basic of work study
 
NG BB 24 Measurement System Analysis - Continuous
NG BB 24 Measurement System Analysis - ContinuousNG BB 24 Measurement System Analysis - Continuous
NG BB 24 Measurement System Analysis - Continuous
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
 
4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx4th-IE-BSS.pptx.pptx
4th-IE-BSS.pptx.pptx
 
Motion & time study
Motion & time studyMotion & time study
Motion & time study
 
Management tools
Management toolsManagement tools
Management tools
 
Tool Box Talk - World Class Maintenance Edited
Tool Box Talk - World Class Maintenance   EditedTool Box Talk - World Class Maintenance   Edited
Tool Box Talk - World Class Maintenance Edited
 

More from Leanleaders.org

More from Leanleaders.org (20)

Variation and mistake proofing
Variation and mistake proofingVariation and mistake proofing
Variation and mistake proofing
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
Blankgage.MTW
Blankgage.MTWBlankgage.MTW
Blankgage.MTW
 
Chi-sq GOF Calculator.xls
Chi-sq GOF Calculator.xlsChi-sq GOF Calculator.xls
Chi-sq GOF Calculator.xls
 
D04 Why6Sigma
D04 Why6SigmaD04 Why6Sigma
D04 Why6Sigma
 
D10 Project Management
D10 Project ManagementD10 Project Management
D10 Project Management
 
Attrib R&R.xls
Attrib R&R.xlsAttrib R&R.xls
Attrib R&R.xls
 
Blank Logo LEAN template
Blank Logo LEAN templateBlank Logo LEAN template
Blank Logo LEAN template
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
NG BB 36 Simple Linear Regression
NG BB 36 Simple Linear RegressionNG BB 36 Simple Linear Regression
NG BB 36 Simple Linear Regression
 
ANG_AFSO21_Awareness_Training_(DULUTH)
ANG_AFSO21_Awareness_Training_(DULUTH)ANG_AFSO21_Awareness_Training_(DULUTH)
ANG_AFSO21_Awareness_Training_(DULUTH)
 
Cause and Effect Tree.vst
Cause and Effect Tree.vstCause and Effect Tree.vst
Cause and Effect Tree.vst
 
LEAN template
LEAN templateLEAN template
LEAN template
 
I07 Simulation
I07 SimulationI07 Simulation
I07 Simulation
 
NG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE RoadmapNG BB 39 IMPROVE Roadmap
NG BB 39 IMPROVE Roadmap
 
D01 Define Spacer
D01 Define SpacerD01 Define Spacer
D01 Define Spacer
 
Attribute Process Capability Calculator.xls
Attribute Process Capability Calculator.xlsAttribute Process Capability Calculator.xls
Attribute Process Capability Calculator.xls
 
A05 Continuous One Variable Stat Tests
A05 Continuous One Variable Stat TestsA05 Continuous One Variable Stat Tests
A05 Continuous One Variable Stat Tests
 
XY Matrix.xls
XY Matrix.xlsXY Matrix.xls
XY Matrix.xls
 
NG BB 11 Power Steering
NG BB 11 Power SteeringNG BB 11 Power Steering
NG BB 11 Power Steering
 

Recently uploaded

Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 

Recently uploaded (20)

Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 

NG BB 17 Takt Time

  • 1. National Guard Black Belt Training Module 17 Takt Time
  • 2. UNCLASSIFIED / FOUO CPI Roadmap – Measure 8-STEP PROCESS 6. See 1.Validate 2. Identify 3. Set 4. Determine 5. Develop 7. Confirm 8. Standardize Counter- the Performance Improvement Root Counter- Results Successful Measures Problem Gaps Targets Cause Measures & Process Processes Through Define Measure Analyze Improve Control TOOLS •Process Mapping ACTIVITIES • Map Current Process / Go & See •Process Cycle Efficiency/TOC • Identify Key Input, Process, Output Metrics •Little’s Law • Develop Operational Definitions •Operational Definitions • Develop Data Collection Plan •Data Collection Plan • Validate Measurement System •Statistical Sampling • Collect Baseline Data •Measurement System Analysis • Identify Performance Gaps •TPM • Estimate Financial/Operational Benefits •Generic Pull • Determine Process Stability/Capability •Setup Reduction • Complete Measure Tollgate •Control Charts •Histograms •Constraint Identification •Process Capability 2 Note: Activities and tools vary by project. Lists provided here are not necessarily all-inclusive. UNCLASSIFIED / FOUO
  • 3. UNCLASSIFIED / FOUO Objectives  Understand the following: – Takt Time – Theoretical minimum staffing levels – Takt Time, Cycle Time Bar Charts – How all of these concepts assist in understanding and improving a process 3 UNCLASSIFIED / FOUO
  • 4. UNCLASSIFIED / FOUO Definition of Takt Time  Time required to produce a component or set of components to meet customer demand Operating Time Takt Time = Customer Requirements  Subject to change – depending on demand from the customer  Determines rate of production  Key to determining resource requirements 4 UNCLASSIFIED / FOUO
  • 5. UNCLASSIFIED / FOUO Takt Time Example – Step 1 Step 1: Determine available time  Aircrew Flight Equipment (AFE) has 1 hour a day to test life vests 52 (weeks) * 5 (days/week) * 1 hour = 260 hours  Convert to minutes 260 hours * 60 minutes/hour = 15,600 minutes Answer: 15,600 minutes is the total available operating time per year 5 UNCLASSIFIED / FOUO
  • 6. UNCLASSIFIED / FOUO Takt Time Example – Step 2  Step 2: Determine Customer Requirement – Average daily customer demand – Get this anyway you can • Advance orders • Forecasts • Historical data • Best guess! – For this example, AFE has 3,120 life vests to maintain 3,120 units per year is the customer requirement 6 UNCLASSIFIED / FOUO
  • 7. UNCLASSIFIED / FOUO Takt Time Example – Step 3  Divide operating time by demand 15600 minutes/year divided by 3,120 units/year  Takt time = 5 minutes (300 seconds)  This is the time that each process step CANNOT exceed in order to meet customer demand using single piece flow! 7 UNCLASSIFIED / FOUO
  • 8. UNCLASSIFIED / FOUO Takt Time vs. Cycle Time  Cycle time is the time for an operator to do a prescribed task and return to his or her original stance  Don’t confuse cycle time and Takt Time!! WHAT’S WRONG WITH THIS QUOTE ?? “Those people have Takt time down to a science! Their Takt time is 54 seconds. They make a car in 54 seconds and every step in the process takes 54 seconds. And they have a plan to reduce their Takt time to 52 seconds through constantly improving every job! Amazing!!!” 8 UNCLASSIFIED / FOUO
  • 9. UNCLASSIFIED / FOUO Takt Time & Theoretical Minimum Staffing If we: • Understand the Total Cycle Time required to produce a unit, and we have • Calculated the Takt Time of this unit  We can calculate the theoretical minimum staffing required. This is calculated as: TOTAL CYCLE TIME = MINIMUM STAFF REQUIRED TAKT TIME 9 UNCLASSIFIED / FOUO
  • 10. UNCLASSIFIED / FOUO Theoretical Minimum Staffing - Example If the Total Cycle Time of all the operators combined = 720 seconds AND The Takt Time is 300 seconds WHAT IS THE MINIMUM STAFFING REQUIREMENT FOR LIFE VESTS IN AFE? 720 sec/300 sec = 2.4 …so 3 People In your experience, what are some of the practical issues that make it difficult to hit this minimum staffing?? 10 UNCLASSIFIED / FOUO
  • 11. UNCLASSIFIED / FOUO Cycle Time Bar Charts Takt Time – Cycle Time Bar Charts enable us to visualize a production line with data and determine some of its operating characteristics Operator Cycle Time in Seconds/Part Let’s look at a sample chart 80 70 Takt Time = 60 Sec 60 45 40 40 30 20 15 0 Oper.1 Oper.2 Oper.3 Oper.4 Oper.5 11 UNCLASSIFIED / FOUO
  • 12. UNCLASSIFIED / FOUO Cycle Time Bar Chart - After Operator Cycle Time in Seconds/Part 80 Takt Time = 60 Sec 60 60 60 60 40 20 20 0 Oper.1 Oper.2 Oper.3 Oper.4 12 UNCLASSIFIED / FOUO
  • 13. UNCLASSIFIED / FOUO Cycle Time Bar Chart - Final Operator Cycle Time in Seconds/Part 80 Takt Time = 60 Sec 60 60 60 60 40 20 0 Oper.1 Oper.2 Oper.3 13 UNCLASSIFIED / FOUO
  • 14. UNCLASSIFIED / FOUO Takeaways  Takt Time is based on customer demand – it is the time in which a task must be completed to meet the customer requirements  Cycle time is the time it takes to actually complete the task  Use takt time and cycle time to determine theoretical minimum staffing levels  Visually display staffing levels using Cycle Time Bar Charts to help improve the process 14 UNCLASSIFIED / FOUO
  • 15. UNCLASSIFIED / FOUO What other comments or questions do you have? 15 UNCLASSIFIED / FOUO