Journal of Economic & Administrative Sciences

Vol. 24, No. 2, December 2008 (35 - 53)

An Empirical Approach for Identifying Critical Time-Ovrerun
Risk Factors in Kuwait’s Construction Projects
Dr. Hassan Al Zubaidi
Kuwait-Maastricht Business
School

Mr. Srour Al Otaibi
Construction Team leader
Ministry of Public Work
Kuwait

Abstract
Risk identification is an integral part of overall risk management
framework of projects. The risks associated with projects and their response
planning differs according to the country and the sector specific environment
in which they are being implemented. In this paper, the study is carried out
to identify the critical risk factors causing delay in Kuwait’s building and
infrastructure projects. The preparation of a preliminary list of risks and risk
factors is outlined, questionnaire development and survey details are
explained, and analysis of survey responses for the identification of delay
risk factors in Kuwait is presented. A case study analysis with respect to
time-overrun/delay of about 28 building and infrastructure projects executed
in Kuwait is also presented to validate the survey results. Survey and case
study results show that the frequency of time-overrun in Kuwait’s
construction projects is very high. The five most critical time-overrun factors
identified in Kuwait’s infrastructure and building projects are: delay in
government approvals/permits, delay in preparation and approval in
variation orders, client induced additional work beyond the original scope,
changed engineering conditions from the contract document and decreased
labor productivity due to extreme climatic conditions. All the above risk
factors are rated as moderately critical to very critical in Kuwait.
Introduction
Availability of adequate infrastructure facilities at reasonable cost is a
prerequisite for the economic development of a country. In recent decades
the Middle East States in general have experienced a boom in the
construction and infrastructure industry and experienced substantial growth
after escalated oil prices brought cash pouring into their economies. Global
economic research on Kuwait has indicated of exuberant growth for Kuwaiti
economy with a Nominal GDP surge of 19.3% from 2003 to 2004, which
was one of the highest in the world. (Kuwait Economic and Strategic
Outlook, 2005). Robust economic conditions and increased private spending
as well as a strong pick up in gross capital formation driven by several
capital projects in Kuwait is anticipated to help the economy to sustain the
double digit growth rate further. Along with the oil and gas sector, the civil
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

infrastructure and services-led non-oil sector in Kuwait are also anticipated
to exhibit a matching growth trends. After a recession in the late 1990s,
Kuwait is rejuvenating itself for higher investment in Civil Infrastructures. It
is expected that in Kuwait, for the next five years the private sector will
invest up to US$8bn in the construction sector, in addition US$3bn in
government investment.
Most of the large-scale construction projects are operated in complex and
dynamic conditions and is constantly confronted with various risks and
uncertainties. Kartam et al (2001) have studied the significance/contribution
of risk factors towards project delay and their preference of risk allocation
among major contractors in the Kuwait’s construction industry. The
significant risk factors identified are financial failure of contractors or
subcontractors, defective design, and delayed dispute resolution. In a study
of analyzing eight (8) Kuwaiti construction projects, Al-Sabah et al (2002)
found that, arbitration tribunal awarded KD31 million on contract price of
KD100 million (at 1980 price level). Many of the past construction projects
executed in Kuwait had time- and cost-overrun problems (Koushki et al.,
2005). Major Government contracts for construction in Kuwait are let as
lump sum projects (Design-Build), which are often encountered with
construction disputes resulting, claims induced delay and cost-overrun.
Many of the projects exceed completion time by 100% in addition to
exceeding their budget.
Project Risks and their Characterization
In the context of project management, Chapman et al (1983) and Perry et
al (1985) have expressed risk as an exposure to economic loss or gain
arriving from involvement in the construction process, whereas Wideman
(1986) have viewed risk as an exposure to loss only. Al-Bahar (1989)
characterized risk with three components: risk event, the uncertainty of the
event and the potential loss or gain. In general, risks in a project can be
either viewed as an opportunity for greater potential of return or as hazards
or threats, which affects the goal and the economic performance of the
organization that is promoting the project. It is manifested through the
occurrences of various risk events.
In this research, “risk” is used to indicate threat/hazard to the project from
one or more events of a particular category/nature or origin, for example,
Time-overrun risk. Risk Event is a specific event that could occur during the
project life cycle, which has a probability of occurrence and an adverse
impact on the project objectives. The key attributes of risk events are the
probability of occurrence and the impact of occurrence (RAMP, 2000). A
36
Journal of Economic & Administrative Sciences

December 2008

Risk Factor is a factor, which could lead to the occurrence of one or more
risk events and is characterized by the probability of occurrence. Risk factors
do not affect project objectives directly but do so through risk events
(indirect impact). It is assumed that the realization of respective risk factors
will contribute to the risk/risk event (under which it is classified) with
varying degrees of influences (Thomas et al; 2006). The research seeks to
identify and evaluate the critical risk factors contributing to time-overrun in
both the public and private sectors. The main hypothesis this paper is trying
to test is “Is there a difference in criticality rating by different category of
respondents.
Research Methodology
The risks associated with construction projects differ according to the
country and the sector specific environment in which they are being
implemented. The political, legal, economic and regulatory environments in
Kuwait are different from other countries and risk management strategies
carried out in other project environments may not be directly suitable for the
Kuwait infrastructure and construction environment. One of the aims of this
research is to identify the critical risk factors causing time-overrun in the
building and infrastructure projects implemented in Kuwait. The process of
identification of critical risk factors was done in two stages and summarized
in Table 1.
Table 1: Process of Risk Factor Identification
Stage
1

Process
Preparation of
preliminary list of
risk factors

2

Identification of
critical risk factors

Details
 Study of literature including research papers and
case study reports.
 Discussions with project participants.
 Unstructured interviews/discussions with project
participants for consolidation of risk factors and
their classification.
 Content validation of list/questionnaire through
locally available experts.
 Questionnaire survey among senior project
participants in Kuwait Construction Industry.
The survey responses were statistically analysed
for identifying critical risk factors. Validation of
survey results through case studies

A mixed approach of questionnaire survey followed by case study was
used for the research (Assaf et al, 1995; Chan et al, 1997; Odeh et al, 2000;
37
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Kartam et al, 2001; Aibinu et al, 2002). A preliminary list of various timeoverrun risk factors associated with building and infrastructure projects in
general and unique to the middle east and Kuwait construction project
environment was prepared based on desk based literature review and
discussions with project participants of Kuwait’s construction industry.
The preliminary list of risk factors causing time-overrun thus prepared
was further filtered out through unstructured interviews with locally
available project experts/participants. Thirty-three risk factors causing timeoverrun were short listed for including in the questionnaire. The short listed
risk factors that included in the questionnaire are given in Appendix 1.
Survey Approach
Due to the non-availability of organized information relating to the
occurrence of risk factors and risk management in Kuwait’s construction
industry, a mail questionnaire survey approach was considered. This
approach is well recognized and widely used in both social sciences and
management research studies. In the area of construction management,
many researchers have used this approach (Assaf et al, 1995; Chan et al,
1997; Odeh et al, 2000; Kartam et al, 2001; El-Dash et al, 2004; Assaf et al,
2006). Some of the advantages of mail questionnaire approaches are low
cost, greater anonymity, reduction in bias and wider geographic coverage.
Criteria for Risk Identification
In this research, “Criticality Index CI” is used as the criteria for
identifying the critical risk factors. The degree of impact of each risk factor
was included in the questionnaire under the heading “significance”. As
mentioned earlier, criticality of risk factor is assumed to be the combined
effect of probability (frequency of occurrence) and impact (significance) of
occurrence of the risk. Assaf et al, (1995) and Falqi, (2004) have used a
similar criterion. Both studies had used severity/significance of risk factors
and frequency of risk factors for evaluation of importance index as a
function of two attributes.
Survey Questionnaire
The questionnaire for the survey was designed with the main objective of
identifying the most critical risks factors causing time-overrun in Kuwait’s
building and infrastructure projects. The preliminary questionnaire was
circulated among locally available experts in the field and their suggestions
with respect to contents, structure, and format were incorporated in the final
questionnaire. Questions Q.1 to Q.5 were factual questions, which elicit
38
Journal of Economic & Administrative Sciences

December 2008

information from the respondents regarding their background, experience
and category and also the overall time-overrun risk exposure of construction
projects in Kuwait.
Questions for Identification of Critical Risk Factors: Thirty-three risk
factors causing time-overrun in construction projects were given in the
questionnaire and respondents were asked to indicate the significance of
each risk factor on a five point Likert scale, response scale ranging from “not
significant” (1) to “extremely significant” (5). The questionnaire was
designed to examine the respondent’s observation and judgment in
determining the relative significance of risk factors.
Although the degree of impact of risk factors varies from project to
project, the questions were designed to elicit a general assessment of the
significance of risk factors. The respondents were also asked about the
frequency of occurrence of that risk factor according to their judgment and
local working experience in Kuwait construction industry on a three point
Likert scale, response scale ranging from “low” (1) to “high” (3).
Survey Responses
In order to identify critical risk factors causing time-overrun in Kuwait’s
building and infrastructure construction environment, a survey was carried
out among the various stakeholders: Government representatives, builder/
contractors, clients, consultants, project managers and architects. The survey
was administrated during the period August 2006 to October 2006. Since
the responses from clients, project managers and architects were very few in
numbers; their responses were clubbed with other categories. Clients and
project managers were included in contractor/ builder category whereas
architects were included in the consultant’s category.
Out of 100 questionnaires sent, 84 responses were received out of which
4 were incomplete and discarded. The response rate of 80 percent is
considered to be very good for this kind of a mail survey. The methodology
adopted for increasing the response rate was regular email and telephonic
follow-ups. The reliability of the survey results is expected to be high
because all the respondents are top-level experienced management officials
in their organizations.
The summary of the survey responses concerning category and
experience is given in Table 2. The majority of the survey respondents were
having very good experience in Kuwait’s construction environment. About
ninety four percent of the respondents have at least 10 years of experience in
the area construction projects.
39
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Table 2: Distribution of Respondents by Category and Experience
Experience in Construction Projects, in years
Total

Category

Government
Engineers
Builders/
Contractors
Consultants
Total
(%)

> 20

15-19

10-14

5-9

<5

5

7

10

3

0

17

7

3

1

0

21

5

0

0

1

43
(54%)

19
(24%)

13
(16%)

4
(5%)

1
(1%)

(%)
25
(31%)
28
(35%)
27
(34%)
80
(100%)

Time-Over run in Kuwait’s Construction Projects
Respondents of the survey were asked to evaluate the overall timeoverrun risk exposure of construction projects in Kuwait. The responses to
Q.4 “How often have time-overrun problems occurred in the projects you
have undertaken in Kuwait?” were statistically analyzed and summarized in
Table 3, which shows that the percentage of time-overrun in Kuwait’s
construction projects is ranging from 20-80%.
Table 3: Frequency of Time-overrun in Kuwait’s Construction Projects
Percentage of Projects
Category

< 20%

20-50%

50-80%

80-100%

Government
Engineers

3

10

12

0

Builders/
Contractors

11

8

7

2

Consultants

12

10

3

2

26
(32.5)

28
(35)

22
(27.5)

4
(5)

Total
(%)

About 93% of the respondents to Q.5 “Which type of construction
projects undertaken in Kuwait has had the highest case of time-overrun
problems?” stated that government projects executed in Kuwait have the
highest time-overrun problems. The remaining 6% mentioned private
developers’ projects.
40
Journal of Economic & Administrative Sciences

December 2008

Identification of Critical Risk Factors
The survey responses were stored in a database and the SPSS software
was used to perform the statistical analysis. For the purpose of this research
the responses were sorted based on category of respondents (Government
Engineers, Builders/Contractors and Consultants). Based on the significance
rating and frequency rating on each risk factor, the average score of the
Significance Index (SI) and Frequency Index (FI) was calculated for the
combined as well as for each category of respondents. The average scores of
SI and FI were calculated for each risk factor by the following formulae:
5
5
(1)
SI
i 1 S i Pi /
i 1 Pi

FI

3
j 1

F j Pj /

3
j 1

(2)

Pj

where
Si is the significance weight (1, 2, 3, 4 or 5) assigned to option i
Pi is the number of participants who responded to option i
Fj is the frequency weight (1, 2 or 3) assigned to option j
Pj is the number of participants who responded to option j
The calculation of the criticality index (CI) was determined through two
steps; first, identifying the score for every possible answer as shown in the
Table 4.
Table 4: Significance-Frequency Combination Matrix
Frequency (F)
1
Significance (S)

3

1
2
3
4
5

1
2
3
4
5

2
2
4
6
7
9

3
6
8
10
11

Since the weight of significance was considered on a 5-point scale
whereas that of frequency was considered on a 3-point scale, the score of
integrating S and F will run from 1 to 11. The Criticality index (CI) for each
cause was calculated as follows:
15
CI
F )k P k / 15 1 P k ,
(3)
k 1( S
k
where (S F )k is the conjunction (1, 2, …., or 11) in the matrix shown in
Table 4 and Pk is the number of participants who responded to option k.
41
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Based on the criticality rating of each category of respondents, the mean
criticality index was evaluated for each risk factor. Analysis of Variance
(ANOVA) using the F-test was carried out to compare the mean criticality
rating among different categories of respondents (Mendenhall, 1971; Levin
and Rubin, 1998). In the ANOVA F-test, the samples are assumed to have
been randomly selected from the population in an independent manner. The
population is assumed to be normally distributed. Moderate departure from
these assumptions will not seriously affect the properties of the test
(Mendenhall, 1971).
Overall F-tests only determine whether any significant difference exists
among the means. For cases where the F-test is statistically significant, the
Post-Hoc Tukey HSD test was carried out. This test compares sets of two
means at a time in order to determine specifically, where the significant
difference lies. The Spearman’s rank correlation technique was also used to
compare the risk criticality ranking of the three different categories of
respondents. This technique is widely used in various psychological, socioeconomic and complex environmental problems to measure the association
between two ranked variables.
Identification of Critical Time-overrun Risk Factors: Survey Results
The mean criticality index (CI) for each time-overrun risk factor was
calculated based on the rating given by the government engineers,
builders/contractors and consultants and are summarized in Appendix 2.
One-way ANOVA F-tests (2- tailed) were carried out for each risk factor
and showed that there was a high degree of agreement in risk criticality
rating (at 0.05 significance level) for the majority of the time-overrun risk
factors except TO.4 (Client induced additional work beyond the original
scope) and TO.27 (Inadequate design team experience). Post-Hoc Tukey
HSD tests were carried out for the TO.4 and TO.27 risk factors. The results
appear in Table 5, which reveals significant differences between Consultants
and Government Engineers. The criticality ratings of TO.4 and TO.27 risk
factors for Consultants were lower in comparison to others.
The high degree of agreement on risk factor criticality rating and ranking
(except two risk factors) shows that the respondents have a common
understanding of the risks in Kuwait construction project environment and
the reliability of their ratings are likely to be high. Since the criticality rating
of different categories of respondents were not significantly different for
thirty one risk factors out of thirty three, the critical time-overrun risk factors
for Kuwait were identified based on the combined rating of all categories.
The risk ranking based on criticality index (CI) is given in Appendix 3.
42
Journal of Economic & Administrative Sciences

December 2008

Table 5: Multiple Comparisons (Tukey HSD)
Risk
Factor

Dependent Variables
(I)

Mean Std.
diff. Error

Significance

(J)

TO.4

Consultants
Contractors/Builders
Consultants
Govt. Engineers
Govt. Engineers
Builders/Contractors
TO.27 Consultants
Builders/Contractors
Consultants
Govt. Engineers
Govt. Engineers
Builders/Contractors
* S ignificant at the 0.05 level

3.11
3.39
0.28
1.70
3.82
2.12

1.14
1.17
1.16
1.13
1.17
1.16

0.021*
0.013*
0.969
0.296
0.004*
0.66

There is also a high correlation among different categories of respondents
in overall ranking of different risk factors. The spearman’s rank correlation
for risk factor criticality is also considered. The results show that there is
relatively good agreement between each two categories in ranking timeoverrun risk factors with the highest degree of agreement (0.87) between
Government Engineers and consultants, while the lowest degree of
agreement is between Builders and consultants (0.81). Such a relatively high
agreement demonstrates the reliability of the results.
Based on the risk criticality index analysis, most critical time-overrun risk
factors in Kuwait’s construction projects identified are given in Table 6,
which also gives the results of similar analyses for significance as well as
frequency of occurrence of critical risk factors in Kuwait.
The five highest rankings are “Delay in government approvals/permits
related to project”, “Delay in preparation and approval in variation orders”,
“Client induced additional work beyond the original scope”, “Changed
engineering conditions from the contract document”, “Decreased labor
productivity due to extreme climatic conditions”. Among these five most
critical time-overrun risk factors, the values of the criticality index (CI) of
first three risk factors are around 8-8.75 whereas the values for the fourth
and fifth factors are around 6.5. Since the highest possible criticality index in
the adopted scale is 11, the range 6 to 8.75 can be treated as moderately to
very critical risk factors. None of the time-overrun risk factors are in the
range of extremely critical in Kuwait. The values of the relative criticality
index for the five most critical risk factors are shown in Figure 1.

43
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Table 6: The Most Critical Time-overrun Risk Factors in Kuwait
Risk
Factor No.
TO.29

TO.11

TO.4

TO.2

TO.30

Significance Frequency
Rank
Rank

Risk Factor
Delay in Government
approvals/permits related
to project
Delay in preparation and
approval in variation
orders
Client induced additional
work beyond the original
scope
Changed engineering
conditions from the
contract document
Decreased labor
productivity due to
extreme climatic
conditions

Criticality
Rank

1

1

1

2

2

2

3

3

3

4

4

4

5

5

5

Figure 1: Criticality Index of Most Critical Time-overrun Risk Factors
The most critical problem identified is “Delay in government
approvals/permits related to project”. This is a global problem especially for
44
Journal of Economic & Administrative Sciences

December 2008

infrastructure construction projects. Depending on the type of projects, the
clearance/approval required from government agencies can adversely affect
the completion time. Careful observations of most critical time-overrun risk
factors reveal that all project stakeholders are equally responsible for project
delay. Government delay, delay in variation orders, additional works beyond
scope are client induced risk factors. Contractors with proper planning and
scheduling can better address problems related to change engineering
condition and labor productivity issues. Though earlier studies in some other
Middle East counties and Kuwait identified that delayed payment and
working capital shortage is a potential reason for time-overrun, such
problems are not very critical in Kuwait now. The survey result reveals that
“social and cultural problems (TO.24)” and “Accidents during construction
(TO.25)” are the least critical time-overrun factors in Kuwait.
Risk Factors Identification - Case Study Approach
In order to continue the survey based criticality assessment, twenty eight
infrastructure and Building projects executed in Kuwait were studied for
actual time-overrun occurrence and the major contributing risk factors. The
case study analysis revealed that 23 out of the 28 projects had time-overrun
problems. The case study results substantiated the survey findings of
frequent time problems of Kuwait’s building and infrastructure projects. The
average time-overrun in Kuwait’s projects (calculated from the case study) is
38%. In case of Management & Operation of Um-El haiman STP project,
the time-overrun recorded was 174%, which is the maximum among all
projects studied.
One of the main objectives of the case study research was to check how
far the critical risk factors (identified through the survey research) have
adversely affected the projects. The percentages of projects incurring timeoverrun with their critical risk factors are summarized in Table 7.
The most critical time-overrun factors like “delay in government
approvals/permits related to project (TO.29)”, “delay in preparation and
approval in variation orders (TO.11)”, “client induced additional work
beyond the original scope (TO.4)” and “changed engineering conditions
from the contract document (TO.2)” were major time-overrun reasons for the
majority of projects. More than 65% of projects had time-overrun due to
above problems. However, in contrary to the survey results, “decreased labor
productivity due to extreme climatic conditions (TO.30)” was not a major
time-overrun issue in Kuwait. Only 9% of projects studied had extreme
climatic conditions as a reason for delay. “Third party delays (TO.33)” and
45
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

“insufficient information of constructability (TO.3)” have delayed about
30% and 39% of the projects.
Table 7: Occurrence of Time- overrun Risk Factors in Kuwait’s
Projects
Time-overrun Risk Factors
Delay in Government approvals/permits related to project
Delay in preparation and approval in variation orders
Client induced additional work beyond the original scope
Changed engineering conditions from the contract document
Decreased labor productivity due to extreme climatic conditions
Third party delays *
Insufficient information of constructability *
* Additional critical risk factors

% of projects
incurring
Time-overrun
78
74
87
65
9
39
30

Conclusions
In comparison to private and corporate body projects, government
projects executed in Kuwait have the highest time-overrun problems. On an
average, about 20-50% projects executed in Kuwait have time-overrun
problems.
There is a high degree of agreement on criticality ratings among various
respondents for all risk factors causing time-overrun in construction projects
executed in Kuwait. There is a significant difference in risk criticality rating
between the government engineers and the consultants with respect to two
time-overrun risk factors: “Client induced additional work beyond the
original scope” and “Inadequate design team experience”.
The five most critical time-overrun risk factors in Kuwait’s construction
projects are: “Delay in Government approvals/permits related to project”,
“Delay in preparation and approval in variation orders”, “Client induced
additional work beyond the original scope”, “Changed engineering
conditions from the contract document”, and “Decreased labor productivity
due to extreme climatic conditions”.
Client induced additional work beyond the original scope and subsequent
design changes can lead to time-overrun and in turn cost-overrun. Such risk
factors will ultimately end up in aggressive claims by the contractor.
All the short-listed time-overrun risk factors can be treated as moderately
critical to very critical risk factors. None of the time-overrun risk factors is
in the range of extremely critical in Kuwait.
46
Journal of Economic & Administrative Sciences

December 2008

There was a fair degree of agreement between survey based risk
assessment and the actual risk impact in construction projects examined
through the case study. The average time-overrun in Kuwait’s project
(calculated from the case study) is 38%.
Limitations & Scope for Further Work
The scope of the present work was limited to specific risks, i.e., timeoverrun risks. The research can be extended for other construction related
risk categories like cost-overrun, political risks, legal risks, financial risk,
etc. The risk identification study carried out for building and infrastructure
projects in Kuwait can be extended and or focused on specific infrastructure
sectors like power, ports, telecommunication, etc.

47
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

References
Aibinu, A. A. and Jagboro, G. O (2002) “The Effects of Construction Delays
on Project Delivery in Nigerian Construction Industry”, International
Journal of Project Management, 20, 593-599.
Al-Bahar, J. F. (1989) “Risk Management in Construction Projects: A
Systemic Analytical Approach for Contractors”, PhD Thesis, University
of California, Berkeley, 1989.
Al-Sabah, S. J, S. M. Fereig and D. J. Hoare (2002) “Construction Claims:
Result from Major Tribunal Findings in Kuwait”, The journal of
Chartered Institute of Arbitrators, 68 (1), February.
Assef, S.A. and S. Al-Hejji (2006) “Causes of Delay in Large Construction
Projects”, International Journal of Project Management, 24, 349-357. Assaf, S.
A., M. Al-Khalil, and Al-Hazmi (1995) “Causes of Delay in Large
Construction Building Projects”, Journal of Management in Engineering,
March-April, 45-50.
Chan, D. W. M. and M. M. Kumaraswamy (1997) “A Comparative Study of
Causes of Time-overrun in Hong Kong Construction Projects”,
International Journal of Project Management, 15(1), 55-63.
Chapman, C. B. and D. F. Cooper (1983) “Risk analysis: testing some
prejudices”. European Journal of Operational Research, 14, 238-247.
EI- Dadh, K. and M. A. Monem (2004) “Potential Risks in Civil
Infrastructure Projects in Egypt”. Proceedings of III IPMA-ICEC
International Expert Seminar, Bilbao, Spain, 6-8 October 2004.
Falki, I. I. (2004) “Delay in Project Completion: A Comparative Study of
Construction Delay Factors in Saudi Arabia and the United Kingdom”.
Master Thesis, Heriot-Watt University.
Kartam, N. A. and S. A. Kartam (2001) “Risk and its management in the
Kuwaiti Construction Industry: a Contractors Perspective, Project
Management”, International Journal of Project Management, 19, 325335.
Koushki, P. A. and K. Al Rashid , N. Kartam (2005) “Delays and cost
increases in the construction of private residential projects in Kuwait”,
Construction Management & Economics, Volume 23, Number 3.
Kuwait Economic and Strategic Outlook-VIII (2005), Global Investment
House (KSCC), December.
Levin, I. R. and D. S. Rubin (1998) “Data Analysis for Management”,
Prentice Hall of India Pvt. Ltd., New Delhi, 1998.
Mendenhall, W. (1971) “Introduction to Probability and Statistics” (3rd Ed.),
Duxbury Press, Belmount, California , 1971.
48
Journal of Economic & Administrative Sciences

December 2008

Odeh, A. M. and H. T Battaineh (2002) “Causes of Construction Delays:
Traditional Contracts”, International Journal of Project Management, 20,
67-73.
Perry, J. G. and R. W. Hayes (1985) “Risk and its management in
construction projects.” Proceedings of the Institute of Civil Engineering,
78(1), 499-521.
RAMP. (2000) “Risk Analysis and Management of Projects”, Thomas
Telford Publishing, London, 2000.
Thomas, A. V., S. N. Kalidindi and L. S. Ganesh (2006) “Modelling and
Assessment of Critical Risks in BOT Road Projects.” Construction
Management and Economics, 24, 407-424.
Wideman, R. M. (1986) “Risk management”. Project Management Journal,
9, 20-26

49
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Appendix 1: Risk Factors Causing Time-Overrun
Risk
Factor No.
TO.1
TO.2
TO.3
TO.4
TO.5
TO.6
TO.7
TO.8
TO.9
TO.10
TO.11
TO.12
TO.13
TO.14
TO.15
TO.16
TO.17
TO.18
TO.19
TO.20
TO.21
TO.22
TO.23
TO.24
TO.25
TO.26
TO.27
TO.28
TO.29
TO.30
TO.31
TO.32
TO.33

Time-overrun Risk factors
Unrealistic design development periods
Changed engineering conditions from the contract document
Insufficient information of constructability
Client induced additional work beyond the original scope
Rework due to errors/omissions during construction (quantity & quality)
Error in the estimated activity completion time
Noncompliance with conditions of contract
Delay in contractors payment of completing work
Consultant/Engineer driven frequent changes in design and materials
Lack of co-ordination between design team and contractor
Delay in preparation and approval in variation orders
Unplanned Maintenance of Plant & Machinery
Lack of construction experience of client
Capacity problem of Contractor (handling many sites at a time)
Shortage and slow delivery of construction materials
Shortage of skilled labour in Kuwait
Working capital shortage of contractor
Selection of improper project delivery system (Design-build/turnkey…)
Shortage of utilities at site
Conflict between Contractor and subcontractors
Joint ownership problems of project
Improper scheduling/sequencing of project
Legal disputes between project participants
Social and cultural problems
Accidents during construction
Inappropriate organizational structure to link project participants
Inadequate design team experience
Periodic regulatory changes
Delay in Government approvals/permits related to project
Decreased labor productivity due to extreme climatic conditions
Inadequate contractor experience
Change in standards and specifications
Third party delays

50
Journal of Economic & Administrative Sciences

December 2008

Appendix 2: Risk Factor Criticality Rating for Time-Overruns
Risk
Factors

Government
Engineers

Builders/
Contractors

Consultants

ANOVA

Combined

CI

SD

CI

SD

CI

SD

F

Sig.

CI

SD

TO.1

7.20

4.11

6.32

2.98

5.78

2.91

1.18

0.31

6.41

3.36

TO.2

8.08

5.07

6.18

4.24

5.48

4.60

2.17

0.12

6.54

4.70

TO.3

6.44

3.75

6.14

4.41

4.11

3.12

2.95

0.06

5.55

3.90

TO.4

9.24

4.22

8.96

4.37

5.85

4.04

5.33

0.01*

8.00

4.44

TO.5

5.36

3.72

4.43

3.23

4.26

3.81

0.70

0.50

4.66

3.57

TO.6

6.64

4.40

5.46

4.10

5.22

4.17

0.83

0.44

5.75

4.21

TO.7

6.32

3.65

4.71

3.23

4.11

2.79

3.22

0.05

5.01

3.32

TO.8

5.20

4.10

4.61

3.36

4.07

4.03

0.56

0.57

4.61

3.81

TO.9

4.72

4.26

4.86

3.97

3.19

3.21

1.58

0.21

4.25

3.86

TO.10

6.40

4.22

6.18

4.44

4.81

4.02

1.09

0.34

5.79

4.24

TO.11

9.08

4.29

9.25

4.46

7.04

4.30

2.16

0.12

8.45

4.42

TO.12

4.68

3.70

3.00

2.39

3.37

2.57

2.38

0.10

3.65

2.97

TO.13

6.04

4.38

4.07

3.21

4.93

3.91

1.74

0.18

4.98

3.88

TO.14

6.56

4.05

4.61

3.30

5.30

4.33

1.68

0.19

5.45

3.94

TO.15

5.80

4.07

5.14

3.44

4.37

3.54

0.98

0.38

5.09

3.68

TO.16

6.84

5.19

4.89

3.90

5.37

4.40

1.32

0.27

5.66

4.52

TO.17

5.32

4.48

4.57

3.54

3.96

3.46

0.81

0.45

4.60

3.82

TO.18

3.72

3.23

3.71

2.57

3.67

2.47

0.00

1.00

3.70

2.73

TO.19

3.44

3.08

3.11

2.36

3.89

3.50

0.47

0.63

3.48

2.99

TO.20

6.68

4.71

4.18

3.40

5.30

4.45

2.34

0.10

5.34

4.28

TO.21

6.00

4.57

4.14

2.99

4.26

3.40

2.06

0.13

4.76

3.73

TO.22

7.28

3.39

6.04

3.49

5.15

3.03

2.71

0.07

6.13

3.38

TO.23

4.56

3.87

3.11

1.99

3.41

2.58

1.84

0.17

3.66

2.91

TO.24

2.00

1.47

1.82

1.12

1.67

0.88

0.52

0.59

1.83

1.17

TO.25

3.00

2.89

2.29

1.38

2.78

2.47

0.67

0.51

2.68

2.30

TO.26

4.52

3.69

4.36

3.14

3.48

2.91

0.78

0.46

4.11

3.24

TO.27

8.12

4.85

6.00

3.93

4.30

3.82

5.37

0.01*

6.09

4.43

TO.28

3.92

2.98

4.00

2.80

3.33

2.90

0.43

0.65

3.75

2.87

TO.29

9.64

3.68

8.07

3.98

8.67

4.12

1.06

0.35

8.76

3.94

TO.30

6.32

3.29

6.32

3.17

6.74

4.18

0.12

0.88

6.46

3.54

TO.31

7.20

4.19

6.00

3.70

5.74

3.13

1.15

0.32

6.29

3.69

TO.32

5.24

4.22

3.71

2.65

3.00

2.79

3.18

0.05

3.95

3.35

TO.33

5.32

3.46

4.71

3.47

4.96

4.37

0.17

0.84

4.99

3.76

* Significant at the 0.05 level
SD: Standard Deviation

51
Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi

December 2008

Appendix 3: Time-overrun Risk Factors’ Ranking Based on Criticality
Risk
Factors

Government Eng.

Builders/Contractors

Consultants

Combined

CI

Rank

CI

Rank

CI

Rank

CI

Rank

TO.1

7.20

7

6.32

4

5.78

5

6.41

6

TO.2

8.08

5

6.18

6

5.48

7

6.54

4

TO.3

6.44

13

6.14

8

4.11

20

5.55

13

TO.4

9.24

2

8.96

2

5.85

4

8.00

3

TO.5

5.36

20

4.43

21

4.26

18

4.66

21

TO.6

6.64

11

5.46

12

5.22

11

5.75

11

TO.7

6.32

15

4.71

16

4.11

21

5.01

17

TO.8

5.20

24

4.61

18

4.07

22

4.61

22

TO.9

4.72

25

4.86

15

3.19

30

4.25

24

TO.10

6.40

14

6.18

7

4.81

15

5.79

10

TO.11

9.08

3

9.25

1

7.04

2

8.45

2

TO.12

4.68

26

3.00

31

3.37

28

3.65

30

TO.13

6.04

17

4.07

25

4.93

14

4.98

19

TO.14

6.56

12

4.61

19

5.30

9

5.45

14

TO.15

5.80

19

5.14

13

4.37

16

5.09

16

TO.16

6.84

9

4.89

14

5.37

8

5.66

12

TO.17

5.32

21

4.57

20

3.96

23

4.60

23

TO.18

3.72

30

3.71

27

3.67

25

3.70

28

TO.19

3.44

31

3.11

29

3.89

24

3.48

31

TO.20

6.68

10

4.18

23

5.30

10

5.34

15

TO.21

6.00

18

4.14

24

4.26

19

4.76

20

TO.22

7.28

6

6.04

9

5.15

12

6.13

8

TO.23

4.56

27

3.11

30

3.41

27

3.66

29

TO.24

2.00

33

1.82

33

1.67

33

1.83

33

TO.25

3.00

32

2.29

32

2.78

32

2.68

32

TO.26

4.52

28

4.36

22

3.48

26

4.11

25

TO.27

8.12

4

6.00

10

4.30

17

6.09

9

TO.28

3.92

29

4.00

26

3.33

29

3.75

27

TO.29

9.64

1

8.07

3

8.67

1

8.76

1

TO.30

6.32

16

6.32

5

6.74

3

6.46

5

TO.31

7.20

8

6.00

11

5.74

6

6.29

7

TO.32

5.24

23

3.71

28

3.00

31

3.95

26

TO.33

5.32

22

4.71

17

4.96

13

4.99

18

52
Journal of Economic & Administrative Sciences

December 2008

28

53
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Weitere ähnliche Inhalte

Was ist angesagt?

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...IRJET Journal
 
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...IRJET Journal
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...IAEME Publication
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building vivatechijri
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesIJERA Editor
 
Theoretical risk identification within
Theoretical risk identification withinTheoretical risk identification within
Theoretical risk identification withincivej
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...A Makwana
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET Journal
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 

Was ist angesagt? (19)

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing Countries
 
Theoretical risk identification within
Theoretical risk identification withinTheoretical risk identification within
Theoretical risk identification within
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 

Andere mochten auch

Template cpsu child_protection_policy
Template cpsu child_protection_policyTemplate cpsu child_protection_policy
Template cpsu child_protection_policyPortia Ponteras Balsa
 
Kelly ruggles financial advice to secure finances for retirement
Kelly ruggles   financial advice to secure finances for retirementKelly ruggles   financial advice to secure finances for retirement
Kelly ruggles financial advice to secure finances for retirementKellyRuggels
 
Developing the curriculum chapter 10
Developing the curriculum chapter 10Developing the curriculum chapter 10
Developing the curriculum chapter 10GrigsbyB
 
Developing the curriculum chapter 11
Developing the curriculum chapter 11Developing the curriculum chapter 11
Developing the curriculum chapter 11GrigsbyB
 
Developing the curriculum chapter 8
Developing the curriculum chapter 8Developing the curriculum chapter 8
Developing the curriculum chapter 8GrigsbyB
 
Developing the curriculum chapter 1
Developing the curriculum chapter 1Developing the curriculum chapter 1
Developing the curriculum chapter 1GrigsbyB
 

Andere mochten auch (14)

English cg grade 1 10 01.30.2014(1)
English cg grade 1 10 01.30.2014(1)English cg grade 1 10 01.30.2014(1)
English cg grade 1 10 01.30.2014(1)
 
rpmsGetting started
rpmsGetting startedrpmsGetting started
rpmsGetting started
 
Template cpsu child_protection_policy
Template cpsu child_protection_policyTemplate cpsu child_protection_policy
Template cpsu child_protection_policy
 
Ultimate Clean Flyer
Ultimate Clean FlyerUltimate Clean Flyer
Ultimate Clean Flyer
 
1rstenglish 140801111732-phpapp01
1rstenglish 140801111732-phpapp011rstenglish 140801111732-phpapp01
1rstenglish 140801111732-phpapp01
 
Business plan on buttermilk
Business plan on buttermilkBusiness plan on buttermilk
Business plan on buttermilk
 
Presentation sports coaching
Presentation   sports coachingPresentation   sports coaching
Presentation sports coaching
 
Kelly ruggles financial advice to secure finances for retirement
Kelly ruggles   financial advice to secure finances for retirementKelly ruggles   financial advice to secure finances for retirement
Kelly ruggles financial advice to secure finances for retirement
 
Mathematics grade3 curriculum_guide
Mathematics grade3 curriculum_guideMathematics grade3 curriculum_guide
Mathematics grade3 curriculum_guide
 
Developing the curriculum chapter 10
Developing the curriculum chapter 10Developing the curriculum chapter 10
Developing the curriculum chapter 10
 
Developing the curriculum chapter 11
Developing the curriculum chapter 11Developing the curriculum chapter 11
Developing the curriculum chapter 11
 
Developing the curriculum chapter 8
Developing the curriculum chapter 8Developing the curriculum chapter 8
Developing the curriculum chapter 8
 
Developing the curriculum chapter 1
Developing the curriculum chapter 1Developing the curriculum chapter 1
Developing the curriculum chapter 1
 
Harshad mehta final
Harshad mehta finalHarshad mehta final
Harshad mehta final
 

Ähnlich wie مهم جدا جدا An empirical approach for identifying critical time ovrerun risk factors in kuwait’s construction projects

ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ IAEME Publication
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - FinalRifan Fhazi
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
B0363010015
B0363010015B0363010015
B0363010015theijes
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projectstheijes
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdfRidaShahid36
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassanOyeniyi Samuel
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...Amy Cernava
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSFredy Kurniawan
 

Ähnlich wie مهم جدا جدا An empirical approach for identifying critical time ovrerun risk factors in kuwait’s construction projects (20)

ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
ESTABLISHING RISK MANAGEMENT FACTORS FOR CONSTRUCTION PROJECTS IN IRAQ
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
B0363010015
B0363010015B0363010015
B0363010015
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...
Assessment Of Risk Management And Evaluate The Level Of Risk In Construction ...
 
C1303032126
C1303032126C1303032126
C1303032126
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
 

Kürzlich hochgeladen

Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsIntellect Design Arena Ltd
 
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxChapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxesiyasmengesha
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Lviv Startup Club
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...AustraliaChapterIIBA
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyHanna Klim
 
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...Brian Solis
 
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003believeminhh
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaEricBonilla13
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access
 
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfGraham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfAnhNguyen97152
 
Intellectual Property Licensing Examples
Intellectual Property Licensing ExamplesIntellectual Property Licensing Examples
Intellectual Property Licensing Examplesamberjiles31
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access
 
Scrum Events & How to run them effectively
Scrum Events & How to run them effectivelyScrum Events & How to run them effectively
Scrum Events & How to run them effectivelyMarianna Nakou
 
MC Heights construction company in Jhang
MC Heights construction company in JhangMC Heights construction company in Jhang
MC Heights construction company in Jhangmcgroupjeya
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfCharles Cotter, PhD
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toumarfarooquejamali32
 
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHelene Heckrotte
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarNathanielSchmuck
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsWristbands Ireland
 

Kürzlich hochgeladen (20)

Investment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV IndustriesInvestment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV Industries
 
Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking Applications
 
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxChapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agency
 
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
 
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
The Vietnam Believer Newsletter_MARCH 25, 2024_EN_Vol. 003
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric Bonilla
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024
 
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfGraham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
 
Intellectual Property Licensing Examples
Intellectual Property Licensing ExamplesIntellectual Property Licensing Examples
Intellectual Property Licensing Examples
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024
 
Scrum Events & How to run them effectively
Scrum Events & How to run them effectivelyScrum Events & How to run them effectively
Scrum Events & How to run them effectively
 
MC Heights construction company in Jhang
MC Heights construction company in JhangMC Heights construction company in Jhang
MC Heights construction company in Jhang
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb to
 
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptxHELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
HELENE HECKROTTE'S PROFESSIONAL PORTFOLIO.pptx
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry Webinar
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and Festivals
 

مهم جدا جدا An empirical approach for identifying critical time ovrerun risk factors in kuwait’s construction projects

  • 1. Journal of Economic & Administrative Sciences Vol. 24, No. 2, December 2008 (35 - 53) An Empirical Approach for Identifying Critical Time-Ovrerun Risk Factors in Kuwait’s Construction Projects Dr. Hassan Al Zubaidi Kuwait-Maastricht Business School Mr. Srour Al Otaibi Construction Team leader Ministry of Public Work Kuwait Abstract Risk identification is an integral part of overall risk management framework of projects. The risks associated with projects and their response planning differs according to the country and the sector specific environment in which they are being implemented. In this paper, the study is carried out to identify the critical risk factors causing delay in Kuwait’s building and infrastructure projects. The preparation of a preliminary list of risks and risk factors is outlined, questionnaire development and survey details are explained, and analysis of survey responses for the identification of delay risk factors in Kuwait is presented. A case study analysis with respect to time-overrun/delay of about 28 building and infrastructure projects executed in Kuwait is also presented to validate the survey results. Survey and case study results show that the frequency of time-overrun in Kuwait’s construction projects is very high. The five most critical time-overrun factors identified in Kuwait’s infrastructure and building projects are: delay in government approvals/permits, delay in preparation and approval in variation orders, client induced additional work beyond the original scope, changed engineering conditions from the contract document and decreased labor productivity due to extreme climatic conditions. All the above risk factors are rated as moderately critical to very critical in Kuwait. Introduction Availability of adequate infrastructure facilities at reasonable cost is a prerequisite for the economic development of a country. In recent decades the Middle East States in general have experienced a boom in the construction and infrastructure industry and experienced substantial growth after escalated oil prices brought cash pouring into their economies. Global economic research on Kuwait has indicated of exuberant growth for Kuwaiti economy with a Nominal GDP surge of 19.3% from 2003 to 2004, which was one of the highest in the world. (Kuwait Economic and Strategic Outlook, 2005). Robust economic conditions and increased private spending as well as a strong pick up in gross capital formation driven by several capital projects in Kuwait is anticipated to help the economy to sustain the double digit growth rate further. Along with the oil and gas sector, the civil
  • 2. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 infrastructure and services-led non-oil sector in Kuwait are also anticipated to exhibit a matching growth trends. After a recession in the late 1990s, Kuwait is rejuvenating itself for higher investment in Civil Infrastructures. It is expected that in Kuwait, for the next five years the private sector will invest up to US$8bn in the construction sector, in addition US$3bn in government investment. Most of the large-scale construction projects are operated in complex and dynamic conditions and is constantly confronted with various risks and uncertainties. Kartam et al (2001) have studied the significance/contribution of risk factors towards project delay and their preference of risk allocation among major contractors in the Kuwait’s construction industry. The significant risk factors identified are financial failure of contractors or subcontractors, defective design, and delayed dispute resolution. In a study of analyzing eight (8) Kuwaiti construction projects, Al-Sabah et al (2002) found that, arbitration tribunal awarded KD31 million on contract price of KD100 million (at 1980 price level). Many of the past construction projects executed in Kuwait had time- and cost-overrun problems (Koushki et al., 2005). Major Government contracts for construction in Kuwait are let as lump sum projects (Design-Build), which are often encountered with construction disputes resulting, claims induced delay and cost-overrun. Many of the projects exceed completion time by 100% in addition to exceeding their budget. Project Risks and their Characterization In the context of project management, Chapman et al (1983) and Perry et al (1985) have expressed risk as an exposure to economic loss or gain arriving from involvement in the construction process, whereas Wideman (1986) have viewed risk as an exposure to loss only. Al-Bahar (1989) characterized risk with three components: risk event, the uncertainty of the event and the potential loss or gain. In general, risks in a project can be either viewed as an opportunity for greater potential of return or as hazards or threats, which affects the goal and the economic performance of the organization that is promoting the project. It is manifested through the occurrences of various risk events. In this research, “risk” is used to indicate threat/hazard to the project from one or more events of a particular category/nature or origin, for example, Time-overrun risk. Risk Event is a specific event that could occur during the project life cycle, which has a probability of occurrence and an adverse impact on the project objectives. The key attributes of risk events are the probability of occurrence and the impact of occurrence (RAMP, 2000). A 36
  • 3. Journal of Economic & Administrative Sciences December 2008 Risk Factor is a factor, which could lead to the occurrence of one or more risk events and is characterized by the probability of occurrence. Risk factors do not affect project objectives directly but do so through risk events (indirect impact). It is assumed that the realization of respective risk factors will contribute to the risk/risk event (under which it is classified) with varying degrees of influences (Thomas et al; 2006). The research seeks to identify and evaluate the critical risk factors contributing to time-overrun in both the public and private sectors. The main hypothesis this paper is trying to test is “Is there a difference in criticality rating by different category of respondents. Research Methodology The risks associated with construction projects differ according to the country and the sector specific environment in which they are being implemented. The political, legal, economic and regulatory environments in Kuwait are different from other countries and risk management strategies carried out in other project environments may not be directly suitable for the Kuwait infrastructure and construction environment. One of the aims of this research is to identify the critical risk factors causing time-overrun in the building and infrastructure projects implemented in Kuwait. The process of identification of critical risk factors was done in two stages and summarized in Table 1. Table 1: Process of Risk Factor Identification Stage 1 Process Preparation of preliminary list of risk factors 2 Identification of critical risk factors Details  Study of literature including research papers and case study reports.  Discussions with project participants.  Unstructured interviews/discussions with project participants for consolidation of risk factors and their classification.  Content validation of list/questionnaire through locally available experts.  Questionnaire survey among senior project participants in Kuwait Construction Industry. The survey responses were statistically analysed for identifying critical risk factors. Validation of survey results through case studies A mixed approach of questionnaire survey followed by case study was used for the research (Assaf et al, 1995; Chan et al, 1997; Odeh et al, 2000; 37
  • 4. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Kartam et al, 2001; Aibinu et al, 2002). A preliminary list of various timeoverrun risk factors associated with building and infrastructure projects in general and unique to the middle east and Kuwait construction project environment was prepared based on desk based literature review and discussions with project participants of Kuwait’s construction industry. The preliminary list of risk factors causing time-overrun thus prepared was further filtered out through unstructured interviews with locally available project experts/participants. Thirty-three risk factors causing timeoverrun were short listed for including in the questionnaire. The short listed risk factors that included in the questionnaire are given in Appendix 1. Survey Approach Due to the non-availability of organized information relating to the occurrence of risk factors and risk management in Kuwait’s construction industry, a mail questionnaire survey approach was considered. This approach is well recognized and widely used in both social sciences and management research studies. In the area of construction management, many researchers have used this approach (Assaf et al, 1995; Chan et al, 1997; Odeh et al, 2000; Kartam et al, 2001; El-Dash et al, 2004; Assaf et al, 2006). Some of the advantages of mail questionnaire approaches are low cost, greater anonymity, reduction in bias and wider geographic coverage. Criteria for Risk Identification In this research, “Criticality Index CI” is used as the criteria for identifying the critical risk factors. The degree of impact of each risk factor was included in the questionnaire under the heading “significance”. As mentioned earlier, criticality of risk factor is assumed to be the combined effect of probability (frequency of occurrence) and impact (significance) of occurrence of the risk. Assaf et al, (1995) and Falqi, (2004) have used a similar criterion. Both studies had used severity/significance of risk factors and frequency of risk factors for evaluation of importance index as a function of two attributes. Survey Questionnaire The questionnaire for the survey was designed with the main objective of identifying the most critical risks factors causing time-overrun in Kuwait’s building and infrastructure projects. The preliminary questionnaire was circulated among locally available experts in the field and their suggestions with respect to contents, structure, and format were incorporated in the final questionnaire. Questions Q.1 to Q.5 were factual questions, which elicit 38
  • 5. Journal of Economic & Administrative Sciences December 2008 information from the respondents regarding their background, experience and category and also the overall time-overrun risk exposure of construction projects in Kuwait. Questions for Identification of Critical Risk Factors: Thirty-three risk factors causing time-overrun in construction projects were given in the questionnaire and respondents were asked to indicate the significance of each risk factor on a five point Likert scale, response scale ranging from “not significant” (1) to “extremely significant” (5). The questionnaire was designed to examine the respondent’s observation and judgment in determining the relative significance of risk factors. Although the degree of impact of risk factors varies from project to project, the questions were designed to elicit a general assessment of the significance of risk factors. The respondents were also asked about the frequency of occurrence of that risk factor according to their judgment and local working experience in Kuwait construction industry on a three point Likert scale, response scale ranging from “low” (1) to “high” (3). Survey Responses In order to identify critical risk factors causing time-overrun in Kuwait’s building and infrastructure construction environment, a survey was carried out among the various stakeholders: Government representatives, builder/ contractors, clients, consultants, project managers and architects. The survey was administrated during the period August 2006 to October 2006. Since the responses from clients, project managers and architects were very few in numbers; their responses were clubbed with other categories. Clients and project managers were included in contractor/ builder category whereas architects were included in the consultant’s category. Out of 100 questionnaires sent, 84 responses were received out of which 4 were incomplete and discarded. The response rate of 80 percent is considered to be very good for this kind of a mail survey. The methodology adopted for increasing the response rate was regular email and telephonic follow-ups. The reliability of the survey results is expected to be high because all the respondents are top-level experienced management officials in their organizations. The summary of the survey responses concerning category and experience is given in Table 2. The majority of the survey respondents were having very good experience in Kuwait’s construction environment. About ninety four percent of the respondents have at least 10 years of experience in the area construction projects. 39
  • 6. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Table 2: Distribution of Respondents by Category and Experience Experience in Construction Projects, in years Total Category Government Engineers Builders/ Contractors Consultants Total (%) > 20 15-19 10-14 5-9 <5 5 7 10 3 0 17 7 3 1 0 21 5 0 0 1 43 (54%) 19 (24%) 13 (16%) 4 (5%) 1 (1%) (%) 25 (31%) 28 (35%) 27 (34%) 80 (100%) Time-Over run in Kuwait’s Construction Projects Respondents of the survey were asked to evaluate the overall timeoverrun risk exposure of construction projects in Kuwait. The responses to Q.4 “How often have time-overrun problems occurred in the projects you have undertaken in Kuwait?” were statistically analyzed and summarized in Table 3, which shows that the percentage of time-overrun in Kuwait’s construction projects is ranging from 20-80%. Table 3: Frequency of Time-overrun in Kuwait’s Construction Projects Percentage of Projects Category < 20% 20-50% 50-80% 80-100% Government Engineers 3 10 12 0 Builders/ Contractors 11 8 7 2 Consultants 12 10 3 2 26 (32.5) 28 (35) 22 (27.5) 4 (5) Total (%) About 93% of the respondents to Q.5 “Which type of construction projects undertaken in Kuwait has had the highest case of time-overrun problems?” stated that government projects executed in Kuwait have the highest time-overrun problems. The remaining 6% mentioned private developers’ projects. 40
  • 7. Journal of Economic & Administrative Sciences December 2008 Identification of Critical Risk Factors The survey responses were stored in a database and the SPSS software was used to perform the statistical analysis. For the purpose of this research the responses were sorted based on category of respondents (Government Engineers, Builders/Contractors and Consultants). Based on the significance rating and frequency rating on each risk factor, the average score of the Significance Index (SI) and Frequency Index (FI) was calculated for the combined as well as for each category of respondents. The average scores of SI and FI were calculated for each risk factor by the following formulae: 5 5 (1) SI i 1 S i Pi / i 1 Pi FI 3 j 1 F j Pj / 3 j 1 (2) Pj where Si is the significance weight (1, 2, 3, 4 or 5) assigned to option i Pi is the number of participants who responded to option i Fj is the frequency weight (1, 2 or 3) assigned to option j Pj is the number of participants who responded to option j The calculation of the criticality index (CI) was determined through two steps; first, identifying the score for every possible answer as shown in the Table 4. Table 4: Significance-Frequency Combination Matrix Frequency (F) 1 Significance (S) 3 1 2 3 4 5 1 2 3 4 5 2 2 4 6 7 9 3 6 8 10 11 Since the weight of significance was considered on a 5-point scale whereas that of frequency was considered on a 3-point scale, the score of integrating S and F will run from 1 to 11. The Criticality index (CI) for each cause was calculated as follows: 15 CI F )k P k / 15 1 P k , (3) k 1( S k where (S F )k is the conjunction (1, 2, …., or 11) in the matrix shown in Table 4 and Pk is the number of participants who responded to option k. 41
  • 8. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Based on the criticality rating of each category of respondents, the mean criticality index was evaluated for each risk factor. Analysis of Variance (ANOVA) using the F-test was carried out to compare the mean criticality rating among different categories of respondents (Mendenhall, 1971; Levin and Rubin, 1998). In the ANOVA F-test, the samples are assumed to have been randomly selected from the population in an independent manner. The population is assumed to be normally distributed. Moderate departure from these assumptions will not seriously affect the properties of the test (Mendenhall, 1971). Overall F-tests only determine whether any significant difference exists among the means. For cases where the F-test is statistically significant, the Post-Hoc Tukey HSD test was carried out. This test compares sets of two means at a time in order to determine specifically, where the significant difference lies. The Spearman’s rank correlation technique was also used to compare the risk criticality ranking of the three different categories of respondents. This technique is widely used in various psychological, socioeconomic and complex environmental problems to measure the association between two ranked variables. Identification of Critical Time-overrun Risk Factors: Survey Results The mean criticality index (CI) for each time-overrun risk factor was calculated based on the rating given by the government engineers, builders/contractors and consultants and are summarized in Appendix 2. One-way ANOVA F-tests (2- tailed) were carried out for each risk factor and showed that there was a high degree of agreement in risk criticality rating (at 0.05 significance level) for the majority of the time-overrun risk factors except TO.4 (Client induced additional work beyond the original scope) and TO.27 (Inadequate design team experience). Post-Hoc Tukey HSD tests were carried out for the TO.4 and TO.27 risk factors. The results appear in Table 5, which reveals significant differences between Consultants and Government Engineers. The criticality ratings of TO.4 and TO.27 risk factors for Consultants were lower in comparison to others. The high degree of agreement on risk factor criticality rating and ranking (except two risk factors) shows that the respondents have a common understanding of the risks in Kuwait construction project environment and the reliability of their ratings are likely to be high. Since the criticality rating of different categories of respondents were not significantly different for thirty one risk factors out of thirty three, the critical time-overrun risk factors for Kuwait were identified based on the combined rating of all categories. The risk ranking based on criticality index (CI) is given in Appendix 3. 42
  • 9. Journal of Economic & Administrative Sciences December 2008 Table 5: Multiple Comparisons (Tukey HSD) Risk Factor Dependent Variables (I) Mean Std. diff. Error Significance (J) TO.4 Consultants Contractors/Builders Consultants Govt. Engineers Govt. Engineers Builders/Contractors TO.27 Consultants Builders/Contractors Consultants Govt. Engineers Govt. Engineers Builders/Contractors * S ignificant at the 0.05 level 3.11 3.39 0.28 1.70 3.82 2.12 1.14 1.17 1.16 1.13 1.17 1.16 0.021* 0.013* 0.969 0.296 0.004* 0.66 There is also a high correlation among different categories of respondents in overall ranking of different risk factors. The spearman’s rank correlation for risk factor criticality is also considered. The results show that there is relatively good agreement between each two categories in ranking timeoverrun risk factors with the highest degree of agreement (0.87) between Government Engineers and consultants, while the lowest degree of agreement is between Builders and consultants (0.81). Such a relatively high agreement demonstrates the reliability of the results. Based on the risk criticality index analysis, most critical time-overrun risk factors in Kuwait’s construction projects identified are given in Table 6, which also gives the results of similar analyses for significance as well as frequency of occurrence of critical risk factors in Kuwait. The five highest rankings are “Delay in government approvals/permits related to project”, “Delay in preparation and approval in variation orders”, “Client induced additional work beyond the original scope”, “Changed engineering conditions from the contract document”, “Decreased labor productivity due to extreme climatic conditions”. Among these five most critical time-overrun risk factors, the values of the criticality index (CI) of first three risk factors are around 8-8.75 whereas the values for the fourth and fifth factors are around 6.5. Since the highest possible criticality index in the adopted scale is 11, the range 6 to 8.75 can be treated as moderately to very critical risk factors. None of the time-overrun risk factors are in the range of extremely critical in Kuwait. The values of the relative criticality index for the five most critical risk factors are shown in Figure 1. 43
  • 10. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Table 6: The Most Critical Time-overrun Risk Factors in Kuwait Risk Factor No. TO.29 TO.11 TO.4 TO.2 TO.30 Significance Frequency Rank Rank Risk Factor Delay in Government approvals/permits related to project Delay in preparation and approval in variation orders Client induced additional work beyond the original scope Changed engineering conditions from the contract document Decreased labor productivity due to extreme climatic conditions Criticality Rank 1 1 1 2 2 2 3 3 3 4 4 4 5 5 5 Figure 1: Criticality Index of Most Critical Time-overrun Risk Factors The most critical problem identified is “Delay in government approvals/permits related to project”. This is a global problem especially for 44
  • 11. Journal of Economic & Administrative Sciences December 2008 infrastructure construction projects. Depending on the type of projects, the clearance/approval required from government agencies can adversely affect the completion time. Careful observations of most critical time-overrun risk factors reveal that all project stakeholders are equally responsible for project delay. Government delay, delay in variation orders, additional works beyond scope are client induced risk factors. Contractors with proper planning and scheduling can better address problems related to change engineering condition and labor productivity issues. Though earlier studies in some other Middle East counties and Kuwait identified that delayed payment and working capital shortage is a potential reason for time-overrun, such problems are not very critical in Kuwait now. The survey result reveals that “social and cultural problems (TO.24)” and “Accidents during construction (TO.25)” are the least critical time-overrun factors in Kuwait. Risk Factors Identification - Case Study Approach In order to continue the survey based criticality assessment, twenty eight infrastructure and Building projects executed in Kuwait were studied for actual time-overrun occurrence and the major contributing risk factors. The case study analysis revealed that 23 out of the 28 projects had time-overrun problems. The case study results substantiated the survey findings of frequent time problems of Kuwait’s building and infrastructure projects. The average time-overrun in Kuwait’s projects (calculated from the case study) is 38%. In case of Management & Operation of Um-El haiman STP project, the time-overrun recorded was 174%, which is the maximum among all projects studied. One of the main objectives of the case study research was to check how far the critical risk factors (identified through the survey research) have adversely affected the projects. The percentages of projects incurring timeoverrun with their critical risk factors are summarized in Table 7. The most critical time-overrun factors like “delay in government approvals/permits related to project (TO.29)”, “delay in preparation and approval in variation orders (TO.11)”, “client induced additional work beyond the original scope (TO.4)” and “changed engineering conditions from the contract document (TO.2)” were major time-overrun reasons for the majority of projects. More than 65% of projects had time-overrun due to above problems. However, in contrary to the survey results, “decreased labor productivity due to extreme climatic conditions (TO.30)” was not a major time-overrun issue in Kuwait. Only 9% of projects studied had extreme climatic conditions as a reason for delay. “Third party delays (TO.33)” and 45
  • 12. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 “insufficient information of constructability (TO.3)” have delayed about 30% and 39% of the projects. Table 7: Occurrence of Time- overrun Risk Factors in Kuwait’s Projects Time-overrun Risk Factors Delay in Government approvals/permits related to project Delay in preparation and approval in variation orders Client induced additional work beyond the original scope Changed engineering conditions from the contract document Decreased labor productivity due to extreme climatic conditions Third party delays * Insufficient information of constructability * * Additional critical risk factors % of projects incurring Time-overrun 78 74 87 65 9 39 30 Conclusions In comparison to private and corporate body projects, government projects executed in Kuwait have the highest time-overrun problems. On an average, about 20-50% projects executed in Kuwait have time-overrun problems. There is a high degree of agreement on criticality ratings among various respondents for all risk factors causing time-overrun in construction projects executed in Kuwait. There is a significant difference in risk criticality rating between the government engineers and the consultants with respect to two time-overrun risk factors: “Client induced additional work beyond the original scope” and “Inadequate design team experience”. The five most critical time-overrun risk factors in Kuwait’s construction projects are: “Delay in Government approvals/permits related to project”, “Delay in preparation and approval in variation orders”, “Client induced additional work beyond the original scope”, “Changed engineering conditions from the contract document”, and “Decreased labor productivity due to extreme climatic conditions”. Client induced additional work beyond the original scope and subsequent design changes can lead to time-overrun and in turn cost-overrun. Such risk factors will ultimately end up in aggressive claims by the contractor. All the short-listed time-overrun risk factors can be treated as moderately critical to very critical risk factors. None of the time-overrun risk factors is in the range of extremely critical in Kuwait. 46
  • 13. Journal of Economic & Administrative Sciences December 2008 There was a fair degree of agreement between survey based risk assessment and the actual risk impact in construction projects examined through the case study. The average time-overrun in Kuwait’s project (calculated from the case study) is 38%. Limitations & Scope for Further Work The scope of the present work was limited to specific risks, i.e., timeoverrun risks. The research can be extended for other construction related risk categories like cost-overrun, political risks, legal risks, financial risk, etc. The risk identification study carried out for building and infrastructure projects in Kuwait can be extended and or focused on specific infrastructure sectors like power, ports, telecommunication, etc. 47
  • 14. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 References Aibinu, A. A. and Jagboro, G. O (2002) “The Effects of Construction Delays on Project Delivery in Nigerian Construction Industry”, International Journal of Project Management, 20, 593-599. Al-Bahar, J. F. (1989) “Risk Management in Construction Projects: A Systemic Analytical Approach for Contractors”, PhD Thesis, University of California, Berkeley, 1989. Al-Sabah, S. J, S. M. Fereig and D. J. Hoare (2002) “Construction Claims: Result from Major Tribunal Findings in Kuwait”, The journal of Chartered Institute of Arbitrators, 68 (1), February. Assef, S.A. and S. Al-Hejji (2006) “Causes of Delay in Large Construction Projects”, International Journal of Project Management, 24, 349-357. Assaf, S. A., M. Al-Khalil, and Al-Hazmi (1995) “Causes of Delay in Large Construction Building Projects”, Journal of Management in Engineering, March-April, 45-50. Chan, D. W. M. and M. M. Kumaraswamy (1997) “A Comparative Study of Causes of Time-overrun in Hong Kong Construction Projects”, International Journal of Project Management, 15(1), 55-63. Chapman, C. B. and D. F. Cooper (1983) “Risk analysis: testing some prejudices”. European Journal of Operational Research, 14, 238-247. EI- Dadh, K. and M. A. Monem (2004) “Potential Risks in Civil Infrastructure Projects in Egypt”. Proceedings of III IPMA-ICEC International Expert Seminar, Bilbao, Spain, 6-8 October 2004. Falki, I. I. (2004) “Delay in Project Completion: A Comparative Study of Construction Delay Factors in Saudi Arabia and the United Kingdom”. Master Thesis, Heriot-Watt University. Kartam, N. A. and S. A. Kartam (2001) “Risk and its management in the Kuwaiti Construction Industry: a Contractors Perspective, Project Management”, International Journal of Project Management, 19, 325335. Koushki, P. A. and K. Al Rashid , N. Kartam (2005) “Delays and cost increases in the construction of private residential projects in Kuwait”, Construction Management & Economics, Volume 23, Number 3. Kuwait Economic and Strategic Outlook-VIII (2005), Global Investment House (KSCC), December. Levin, I. R. and D. S. Rubin (1998) “Data Analysis for Management”, Prentice Hall of India Pvt. Ltd., New Delhi, 1998. Mendenhall, W. (1971) “Introduction to Probability and Statistics” (3rd Ed.), Duxbury Press, Belmount, California , 1971. 48
  • 15. Journal of Economic & Administrative Sciences December 2008 Odeh, A. M. and H. T Battaineh (2002) “Causes of Construction Delays: Traditional Contracts”, International Journal of Project Management, 20, 67-73. Perry, J. G. and R. W. Hayes (1985) “Risk and its management in construction projects.” Proceedings of the Institute of Civil Engineering, 78(1), 499-521. RAMP. (2000) “Risk Analysis and Management of Projects”, Thomas Telford Publishing, London, 2000. Thomas, A. V., S. N. Kalidindi and L. S. Ganesh (2006) “Modelling and Assessment of Critical Risks in BOT Road Projects.” Construction Management and Economics, 24, 407-424. Wideman, R. M. (1986) “Risk management”. Project Management Journal, 9, 20-26 49
  • 16. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Appendix 1: Risk Factors Causing Time-Overrun Risk Factor No. TO.1 TO.2 TO.3 TO.4 TO.5 TO.6 TO.7 TO.8 TO.9 TO.10 TO.11 TO.12 TO.13 TO.14 TO.15 TO.16 TO.17 TO.18 TO.19 TO.20 TO.21 TO.22 TO.23 TO.24 TO.25 TO.26 TO.27 TO.28 TO.29 TO.30 TO.31 TO.32 TO.33 Time-overrun Risk factors Unrealistic design development periods Changed engineering conditions from the contract document Insufficient information of constructability Client induced additional work beyond the original scope Rework due to errors/omissions during construction (quantity & quality) Error in the estimated activity completion time Noncompliance with conditions of contract Delay in contractors payment of completing work Consultant/Engineer driven frequent changes in design and materials Lack of co-ordination between design team and contractor Delay in preparation and approval in variation orders Unplanned Maintenance of Plant & Machinery Lack of construction experience of client Capacity problem of Contractor (handling many sites at a time) Shortage and slow delivery of construction materials Shortage of skilled labour in Kuwait Working capital shortage of contractor Selection of improper project delivery system (Design-build/turnkey…) Shortage of utilities at site Conflict between Contractor and subcontractors Joint ownership problems of project Improper scheduling/sequencing of project Legal disputes between project participants Social and cultural problems Accidents during construction Inappropriate organizational structure to link project participants Inadequate design team experience Periodic regulatory changes Delay in Government approvals/permits related to project Decreased labor productivity due to extreme climatic conditions Inadequate contractor experience Change in standards and specifications Third party delays 50
  • 17. Journal of Economic & Administrative Sciences December 2008 Appendix 2: Risk Factor Criticality Rating for Time-Overruns Risk Factors Government Engineers Builders/ Contractors Consultants ANOVA Combined CI SD CI SD CI SD F Sig. CI SD TO.1 7.20 4.11 6.32 2.98 5.78 2.91 1.18 0.31 6.41 3.36 TO.2 8.08 5.07 6.18 4.24 5.48 4.60 2.17 0.12 6.54 4.70 TO.3 6.44 3.75 6.14 4.41 4.11 3.12 2.95 0.06 5.55 3.90 TO.4 9.24 4.22 8.96 4.37 5.85 4.04 5.33 0.01* 8.00 4.44 TO.5 5.36 3.72 4.43 3.23 4.26 3.81 0.70 0.50 4.66 3.57 TO.6 6.64 4.40 5.46 4.10 5.22 4.17 0.83 0.44 5.75 4.21 TO.7 6.32 3.65 4.71 3.23 4.11 2.79 3.22 0.05 5.01 3.32 TO.8 5.20 4.10 4.61 3.36 4.07 4.03 0.56 0.57 4.61 3.81 TO.9 4.72 4.26 4.86 3.97 3.19 3.21 1.58 0.21 4.25 3.86 TO.10 6.40 4.22 6.18 4.44 4.81 4.02 1.09 0.34 5.79 4.24 TO.11 9.08 4.29 9.25 4.46 7.04 4.30 2.16 0.12 8.45 4.42 TO.12 4.68 3.70 3.00 2.39 3.37 2.57 2.38 0.10 3.65 2.97 TO.13 6.04 4.38 4.07 3.21 4.93 3.91 1.74 0.18 4.98 3.88 TO.14 6.56 4.05 4.61 3.30 5.30 4.33 1.68 0.19 5.45 3.94 TO.15 5.80 4.07 5.14 3.44 4.37 3.54 0.98 0.38 5.09 3.68 TO.16 6.84 5.19 4.89 3.90 5.37 4.40 1.32 0.27 5.66 4.52 TO.17 5.32 4.48 4.57 3.54 3.96 3.46 0.81 0.45 4.60 3.82 TO.18 3.72 3.23 3.71 2.57 3.67 2.47 0.00 1.00 3.70 2.73 TO.19 3.44 3.08 3.11 2.36 3.89 3.50 0.47 0.63 3.48 2.99 TO.20 6.68 4.71 4.18 3.40 5.30 4.45 2.34 0.10 5.34 4.28 TO.21 6.00 4.57 4.14 2.99 4.26 3.40 2.06 0.13 4.76 3.73 TO.22 7.28 3.39 6.04 3.49 5.15 3.03 2.71 0.07 6.13 3.38 TO.23 4.56 3.87 3.11 1.99 3.41 2.58 1.84 0.17 3.66 2.91 TO.24 2.00 1.47 1.82 1.12 1.67 0.88 0.52 0.59 1.83 1.17 TO.25 3.00 2.89 2.29 1.38 2.78 2.47 0.67 0.51 2.68 2.30 TO.26 4.52 3.69 4.36 3.14 3.48 2.91 0.78 0.46 4.11 3.24 TO.27 8.12 4.85 6.00 3.93 4.30 3.82 5.37 0.01* 6.09 4.43 TO.28 3.92 2.98 4.00 2.80 3.33 2.90 0.43 0.65 3.75 2.87 TO.29 9.64 3.68 8.07 3.98 8.67 4.12 1.06 0.35 8.76 3.94 TO.30 6.32 3.29 6.32 3.17 6.74 4.18 0.12 0.88 6.46 3.54 TO.31 7.20 4.19 6.00 3.70 5.74 3.13 1.15 0.32 6.29 3.69 TO.32 5.24 4.22 3.71 2.65 3.00 2.79 3.18 0.05 3.95 3.35 TO.33 5.32 3.46 4.71 3.47 4.96 4.37 0.17 0.84 4.99 3.76 * Significant at the 0.05 level SD: Standard Deviation 51
  • 18. Dr. Hassan Al Zubaiadi, Mr. Srour Al Otaibi December 2008 Appendix 3: Time-overrun Risk Factors’ Ranking Based on Criticality Risk Factors Government Eng. Builders/Contractors Consultants Combined CI Rank CI Rank CI Rank CI Rank TO.1 7.20 7 6.32 4 5.78 5 6.41 6 TO.2 8.08 5 6.18 6 5.48 7 6.54 4 TO.3 6.44 13 6.14 8 4.11 20 5.55 13 TO.4 9.24 2 8.96 2 5.85 4 8.00 3 TO.5 5.36 20 4.43 21 4.26 18 4.66 21 TO.6 6.64 11 5.46 12 5.22 11 5.75 11 TO.7 6.32 15 4.71 16 4.11 21 5.01 17 TO.8 5.20 24 4.61 18 4.07 22 4.61 22 TO.9 4.72 25 4.86 15 3.19 30 4.25 24 TO.10 6.40 14 6.18 7 4.81 15 5.79 10 TO.11 9.08 3 9.25 1 7.04 2 8.45 2 TO.12 4.68 26 3.00 31 3.37 28 3.65 30 TO.13 6.04 17 4.07 25 4.93 14 4.98 19 TO.14 6.56 12 4.61 19 5.30 9 5.45 14 TO.15 5.80 19 5.14 13 4.37 16 5.09 16 TO.16 6.84 9 4.89 14 5.37 8 5.66 12 TO.17 5.32 21 4.57 20 3.96 23 4.60 23 TO.18 3.72 30 3.71 27 3.67 25 3.70 28 TO.19 3.44 31 3.11 29 3.89 24 3.48 31 TO.20 6.68 10 4.18 23 5.30 10 5.34 15 TO.21 6.00 18 4.14 24 4.26 19 4.76 20 TO.22 7.28 6 6.04 9 5.15 12 6.13 8 TO.23 4.56 27 3.11 30 3.41 27 3.66 29 TO.24 2.00 33 1.82 33 1.67 33 1.83 33 TO.25 3.00 32 2.29 32 2.78 32 2.68 32 TO.26 4.52 28 4.36 22 3.48 26 4.11 25 TO.27 8.12 4 6.00 10 4.30 17 6.09 9 TO.28 3.92 29 4.00 26 3.33 29 3.75 27 TO.29 9.64 1 8.07 3 8.67 1 8.76 1 TO.30 6.32 16 6.32 5 6.74 3 6.46 5 TO.31 7.20 8 6.00 11 5.74 6 6.29 7 TO.32 5.24 23 3.71 28 3.00 31 3.95 26 TO.33 5.32 22 4.71 17 4.96 13 4.99 18 52
  • 19. Journal of Economic & Administrative Sciences December 2008 28 53
  • 20. Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.