Angeline Aggarwal, CSPO
Product Owner, Tata Consultancy Services
Scrum Gathering India Regional 2013
July, 2013
: +91 99201 37484
: angelinepp@gmail.com
What and What NOT! - A PO Introspects
2
A Product Owner is born!
Developer for 7 years
Working on RAD methodology; accustomed to
quick turn-around times.
Suddenly Agile – Alice in Wonderland!
One-week sprints were being followed
enterprise wide – Hit the ground running!
In this presentation……
Scrum flow reviewed
At each step identify
 Common mistakes a beginner
makes
 How they impact the end
result
 How to avoid / become better
ENVISION1
4Introspection by Angeline Aggarwal
A vision must be detailed enough to provide clarity…
Why have a vision?
 Guides the team and describes the
essence of the project
 Provides clarity to the stakeholders
that the team has understood what
they have to do!
Attributes of a good vision
 Other Attributes
 Stable
 Clear
 Appealing
 Broad
 Short
 Pass the elevator test
 Demystify the WHO, the WHAT, the
WHY and the HOW
 Who are our customers
 What do they need
 Why do they need
 How we can meet the needs
5Introspection by Angeline Aggarwal
But “Vision” for my first project was woefully incomplete!
Vision for the my first scrum project
To make all finance system applications compliant with new firm wide
change
My Scorecard:
Attributes Score What's the problem?
Who is the
stakeholder
POOR
Team does not know who to turn to, if we run into impediments and
feedback
What are the
customer needs
POOR Unclear: Left open-ended with a catch-all "ALL" systems compliant
Why does the
customer need it
POOR Not identified: Team can't identify with the customers needs
What is the target
time-frame
POOR
Not stated: How do we figure out what resources/time are required and
how much time will be required
Stable POOR The client can go on making continuous changes
Clear POOR Scope left unclear
Short GOOD But its too short, doesn’t cover even the essentials
Broad GOOD Its TOO broad and left open-ended
Engaging POOR Only because it is short
6Introspection by Angeline Aggarwal
This is what the ‘Vision’ should have looked like
Revised Vision
Statement Description
Problem/Opportunity
Statement
 Customer is implementing a new length of employee ids to cater to influx of
new hires
 All downstream applications may not support the increased length
Potential Solution  Test critical applications
 Identify issues
 Fix issues to make the application compliant
Scope of the project  To identify list critical applications which do not have an development team
 Applications which are not to be decommissioned in the next one year
Who is the
stakeholder/Customer
 Program managers (indentified people) for portfolio of applications
Value to the customer  New hires would be able to use applications error free
Timeline  6 months
Success Criteria  Applications should support new length of person id
While it is not short, it is crisp and contains all the relevant information
7Introspection by Angeline Aggarwal
What went wrong
 No clarity on scope / interim
changes
 Not knowing who is involved and in
what capacity
 Not having asked the right questions
Impact
 Improper prioritization of the
requirements/backlog
 Slow the pace in removing
impediments, getting approvals,
requirement clarifications
Doing it right…
 Ask: The more you ask the more you understand. But ask the right questions
 What is more critical
 What needs will it address for the user
 Share the vision with the entire team and make sure the entire team has the
same understanding
 Engage with the sponsor: With the right person at the right time will help in
proper planning and removing most of your impediments in next steps
‘Vision’ - Recap
CREATE A BACKLOG2
9Introspection by Angeline Aggarwal
Step 2: Creating a backlog consisting of epics and stories
 The product owner translates the
vision into a backlog
 Product backlog contains the
following:
o Themes/Epics/Stories,
Technical work and defects.
Attributes of a good Product Backlog
 D E E P
 Detailed Appropriately
 Emergent
 Estimated
 Prioritized
 Visible: Readily available to the
team and stakeholders
What is the backlog
10Introspection by Angeline Aggarwal
How I created my first backlog
In my project:
 Each application became an ‘Epic’
 Disregarded the Iceberg: Aiming to break down all the ‘Epics’ into
detailed ‘Stories’ to get to know the overall size of the project
(Waterfall mindset) - Spent two sprints breaking down half the sprints before
checking course
 Two types of stories
 Standard setup stories common for all applications
 Application Specific Stories
 Started implementation of set up stories for couple of applications and
staffed with team
 Project was set up in ‘Mingle’
11Introspection by Angeline Aggarwal
A backlog in disarray
0 1 2 3 4 5 6 7 8-10 11+
Set up
Mingle
Get
Access
App_1
to 10
App_1
Demo
App_1
Story_1
and 2
App_2
Analyz
e Code
App_2
Confir
m
change
s with
User
App_2
Code
changes
. . .
App_2 –
Identify
Testing
Strategy
App_2
-
Testing
App_2 –
Testing
interfaces
(Dependency
came up)
Get
info
App_1
to App
10
Staff
Team
App_1
and
App_2
App_1
Analyze
code
App_2
Demo
and
Analyze
Code
[App_1
contin
ued on
track]
Adhoc
Develo
pment
work
(Added
subseq
uently)
. . . . .
Adhoc
Development
work (Added
subsequently)
. . .
12Introspection by Angeline Aggarwal
Backlog: What was wrong and what was the impact
 Incorrect Prioritization: Too much upfront effort adding details to ‘Epics’ to be taken up much later
 Impact: Effort wasted and re-planning required, big picture missed due to ‘too many items’
 Activity specific sprints: Application 2 was proceeding like a waterfall model within the agile framework
 Impact: Idle time- Developer idle due to delay from user. No back up work planned
 Interdependencies of applications overlooked:
 Impact: Unforeseen delays due to dependencies on teams handling other application
 Ineffective Planning: Should have identified testing strategy upfront
 Impact: Emergency changes in release planning
 Adhoc development work added to backlog – Team ‘Vision’ was compromised. Cascaded into multiple
change requests and additional work
 Impact: Huge delay. Initial user estimate of 2 months took 3 months despite overworked team
 Neglect backlog Grooming: Specific time not allocated for backlog grooming
 Impact: Could not eliminate unwanted items prior to sprint – backlog not ready for next sprint –
resulting in confusion for the team
Overall impact:
 Non shippable deliverables per sprint
 No sign off from the customer
 Overall release getting delayed by 3 months
13Introspection by Angeline Aggarwal
Backlog: Lessons learnt
 Prioritization
 Take up application with most dependencies initially
 Progressively refine – Impossible to think of everything upfront
 Add details Just-In-Time, not weeks in advance because things
change as new information emerges
 Helps avoid too many backlog items
 Stick to the vision:
 Any adhoc requests not in line with project vision should be treated
like a separate project – with its own backlog and stories
 Backlog Grooming
 Would have set aside Time-boxed period for the entire team to
focus on cleaning up the backlog
ESTIMATE3
15Introspection by Angeline Aggarwal
Estimation 101
The process of quantifying the effort
required in story points or ideal days
involved in implementing the Product
Backlog with the resources available
What is Estimation
The WHEN, WHO And HOW of Estimation
 The When:
 Before the first sprint
 During the first 2 sprints
 On going
 Who: Product Owner + Scrum Master + Team
 The How
 Story points vs. ideal days
 Planning poker
End Result
 Sized Stories
 Results in backlog refinement
16Introspection by Angeline Aggarwal
What were the mistakes Impact How to avoid them
Playing the task master:
• Product owner drives estimate
based on deadline of the
project
• Team estimated 3 weeks I
pushed for 2. It finally took 3
weeks
• OR Team compromises on
Quality
Estimate should be Honest not
influenced:
• Developer should give the
estimate not the product owner
• Scrum master to facilitate
Equating story points to days:
• Each story is considered
individually rather than a
collection to relative estimate
• Failed to see big picture
• Overall deadline slippages
•Play the poker - Its fun!
Trying to estimate the
inestimable!
• Stories are too complex or too
many unknowns/dependencies
to estimate
• Radically different estimates
from team members due to
different interpretations
• Extended planning duration
• Stop and think and break down
further
lUnclear Scale:
lTeam not clear on the scale
being used
• Use a scale which all team
members identify with
• Identify smallest and largest at 2
points and 20 points respectively
Chasing Velocity:
Adjusting estimate to meet
forecasted velocity
• Slippages across sprint
deadlines
• Over-worked team –
unsustainable in the long run
• Velocity gets derived from the
estimates and not the other way
around
Common pitfalls and how to avoid them
17Introspection by Angeline Aggarwal
POs - do not influence the team
USER STORIES EXAMPLES4
19Introspection by Angeline Aggarwal
Backlog consists of multiple USER stories
 Defining the deliverables from a users perspective aligns with goal of the product
 Format: As a <USER>, I want <SOMETHING>, so that <SOME VALUE>
o For Technical stories, user is replaced by the module
Define from a “USERS” perspective
Attributes of a good Story
 I N V E S T
 Independent
 Negotiable
 Valuable
 Estimable
 Small
 Testable
 Should define the WHO, WHAT and WHY
 Story should contain acceptable criteria (for validation) - Sufficient to define
the boundaries of the story
20Introspection by Angeline Aggarwal
Its time to write a story: User Story 1
User Story:
Add a share activity
section to the share
activity report to display
share transactions for a
user
Acceptance criteria:
Display share activity
information in the
following columns, no of
shares, date, activity (Buy
or sell), quantity, value
per share and total
amount
User Story:
As a user, I want to see the share
activity details, for the selected
person for the current financial
year, so that I may view the
details of the share transacted
by that user and compute share
balance
Acceptance criteria:
Display share sale and share
purchase in separate rows with
the following information, no of
shares, date, activity (Buy or
sell), quantity, value per share
and total amount in a user
defined format
Should have
been
21Introspection by Angeline Aggarwal
What were the mistakes Impact How to avoid
mistakes
The
“WHY” is
missing
Story defined from a
developers perspective of what
needs to be done, not the why
Impact: If we knew what we
wanted to use the report for,
we could have added additional
data useful for user (like total
gain in the period, etc)
Could have suggested
displays with additional
data would could have been
meaningful to the user
Potential Additional
revenue lost?
Ask more
questions with
the
stakeholder
and constantly
engage
The WHAT
not
completely
defined
Report pertains to which year –
what test data to retrieve
NOT testable. Boundary
condition missed out.
Involve the
team in story
writing
Not
negotiable
User wanted a different format
for a boundary condition
(shares bought and sold on the
same date in separate columns)
Could not be completed in
simple sprint.
Code had to be re-worked.
Few person days additional
required
Describe by
examples
User could
have pointed
what he
wanted
Analysis of User Story 1
22Introspection by Angeline Aggarwal
Story..continued..: User Story 2
User Story:
As a user, I want to run the
report X for multiple
employees in a given date
range
Acceptance criteria:
 Report should accept
multiple employee
numbers in a comma or
space separated string
 User should be able to
enter start and end date
User Story:
As a user, I want to run the
report X for multiple employees in
a given date range so as to be
able to generate a batch of
reports of all employees under a
partner at one time
Acceptance criteria:
 Report should accept multiple
employee numbers with a
minimum of 750 in a comma or
space separated string
 User should be able to enter
start and end date
 The entire report should be
generated in a maximum of 30
seconds
Should have
been
23Introspection by Angeline Aggarwal
What were the mistakes Impact How to avoid
mistakes
The
“WHY” is
missing
Lead to unclear boundary
condition below
Focus on
discussion
rather than
documentation:
Ask more
questions and
constantly
engage with the
user
ilities and
UI
constraints
Boundary condition not
defined:
User wanted to run report for a
minimum of 750 users at one go
Performance tuning
(optimization) was not
done
Architecture reworked for
optimized performance
Missing
definition
of done
How long should the report
generation take was not listed
The entire report could
not be done in 30 secs as
required by the user, had
to increased up to 2 mins
Analysis of User Story 2
Is it possible to write a complete story upfront and ready for a sprint - NO
ALL ABOUT THE SPRINT5
25Introspection by Angeline Aggarwal
Sprint away!
 A time-boxed period during which the scrum team works to build a potentially
shippable increment to the product
 Both incremental and iterative at the same time
 Iterative - Planning + Execution + Review
 End result: Potentially shippable increment to the project / product
Deliver at end of each sprint: Allows to inspect and seek constructive feedback
SPRINT PLANNING6
27Introspection by Angeline Aggarwal
What is Sprint Planning
 Entire team (Product Owner, Scrum
Master, Developers, etc) participate in
the Sprint planning meeting to discuss
the following
 Sprint goals
 Selection of sprint backlog for the next
sprint (Backlog items that the team
commits to and the tasks they are
broken down into)
 Typical effort of two-four hours per
sprint
What happens during Sprint Planning
Outcome of Sprint Planning
 Defining what the team will achieve in the next
sprint
 Shippable increments
 Behind-the-scenes features
 Just something valuable
 Further break down stories based on new details
 Emergent requirements
28Introspection by Angeline Aggarwal
Sprint Planning Case Study
Top Story Priorities
Stories Points
App_2 Testing (Modules 01 to 10) 3
App_2 Testing (Modules 11 to 20) 3
App_2 Testing (Modules 21 to 30) 3
Test App_2 Interface 1 5
Test App_2 Interface 2 5
Capital Tax Report
(became a 20 pointer
subsequently)
8
App_3 Analyze Code Base 3
App_3 Get Access to Dev Env. 2
App2_Analyze Back end 3
App3_Analyze Import Module 3
App3_Upload 2
App3_Sumbit 3
Chasing too
many points
per sprint
Interface
modules should
have been
prioritized over
• Story too big
to be taken
up and
therefore
broken down
• Task based
break down
into :
Analyze the
requirement,
etc
Detailed plan
for all the
activities put in
place much in
advance
29Introspection by Angeline Aggarwal
Sprint Planning Mistakes Impact How to avoid mistakes
Lacking the big Picture:
• Selecting stories with a
short term goal in mind
• In-correct prioritization
and thereby selection of
sprint
• Start with a prioritized backlog
• Always first take stories which
have maximum
interdependency
Waterfall in Agile
• Planning activity specific
sprints rather than holistic
development of an
increment
• No user specific
deliverable
• Risk of spending too
much time for one
activity which doesn’t
get validated
• AVOID the temptation and
ALWAYS deliver at-least a
testable increment
Chasing Velocity
• Over-committing or
selecting stories that are
too large for the sprint
Planning for overwork
“Need to complete at least
14 story points to maintain
our velocity”
• Overworked team
• Compromise on testing
and quality OR
• Under deliver in next
sprint
• Plan based on what can be
completed end to end
• Selecting the right mix of
stories – not all large, not all
small
• Achievement is not in terms of
velocity – velocity should result
from doing scrum right
Planning for a better finish
30Introspection by Angeline Aggarwal
Sprint Planning Mistakes Impact How to avoid mistakes
Scheduling issues
• PO/ Team member is not
available for the
meeting
• Team members
don’t understand
the sprint goals
• Be flexible with scheduling
• Make the planning meeting
compulsory to all
lPlanning too much into
the future
• Little room for
progressive
adjustments,
• Leads to effort
waste
• Product Owners! Know your backlog
• Plan at the optimal time – one or two
sprints in advance
Starting the new sprint
with planning
• Should be done 2 days
before next sprint starts
• Result in idle team
• Lead time to get
At least 5-10% of team time should be
reserved for planning for the next
sprint
Ignoring Team Ability /
Availability
• Leads to over
committing and
under-delivering
• Avoid assigning story to individuals,
assign story to a team / sub team
• Opt for pair programming where-ever
critical
• Product owner should be aware of
team absences and take that into
account
Think holistically – don’t lose track of the overall vision
SPRINT EXECUTION6
32Introspection by Angeline Aggarwal
Are we getting there? Can you see the goal?
 Team works on the backlog items
committed for the sprint
 Mode of operation:
 Time-boxed daily scrum
 Task boards
 Impediments list
 Changes in boundary conditions –
decide on whether to terminate
the sprint
33Introspection by Angeline Aggarwal
Sprint Execution
Mistakes
Impact How to avoid mistakes
No daily scrum
• Inconsistent meeting
times
• Skipped meetings
• Difficult to understand team
progress
• Individual follow up with team
members – waste of time.
• Team unaware of each others
work and possible impact to
their story
• Disciplined daily scrum
• Fixed meeting time and place
Lack of enthusiasm
• Team not fully
involved
• Meetings from their
desk /
simultaneously doing
other work
• Loose an opportunity to see
overall progress, give and
receive inputs
• Just focused on status updates
• Daily Stand-up done right!
• Time-boxed no lengthy
discussions
• Accounting for time
during DSM rather
than goals and
achievements
• Developer may have spent a
day on the story but achieved
nothing in terms of value
• Updates should be in terms of
what was done and not how
much time was spent on it
Sprinting away from the goal and how to avoid it
34Introspection by Angeline Aggarwal
Sprint Execution
Mistakes
Impact How to avoid mistakes
No mid sprint checks
• Items left for
implementing at the
end – not mid-sprint
checks
• Compromised on scope and
quality
• Maintain Sprint Burn down chart
• Not a time for troubleshooting
• Reduce wasteful effort –
automate where possible
• Don’t leave testing for the end –
it generally gets skipped
• Changing the sprint
goal/sprint backlog
during the sprint
• Hampers the team’s focus
and rhythm
• Leads to hasty and
unplanned activity
• Avoid changes to the sprint goal –
what to do if the priority of
backlog suddenly changes?
lImpediments
• Not raising / handling
impediments
• Delays
• wasted effort
• Slippages
• PO should follow up / force /
beg for team to come up with
impediments
• Make the team comfortable to
escalate issues
Sprinting away from the goal and how to avoid it
REVIEWS AND
RESTROSPECTIVES
6
36Introspection by Angeline Aggarwal
A great finish! – Reviews and Retrospectives
Objectives of the Sprint Review
 1 hour per sprint: Set aside to reflect on
the sprint gone by
 Start, Stop, Change, Continue
 Setup and continually improve best
practices
 No retrospective
 A missed opportunity to learn
 Repeat the same mistakes
 Keep it informal
 10-15 mins per Sprint to Inspect and Adapt
 Highlight team goals and achievements
 Assess the achievements against the sprint
goal and not just completion of backlog
 A natural end to the sprint, not a
distraction requiring preparation time
Retrospective: Learn from the past
37Introspection by Angeline Aggarwal
Maintaining a sustainable pace of development
Pace yourself like a marathon runner;
Get a head start, go steady in between &
Towards the end, give it your all
 Start Small but think Big – never forget the big picture
 Use same length sprints - helps planning and the team works with Rhythm
 Focus on delivery – Definition of done – complete story
 Continuous improvement
 Don’t bank on overtime – it cannot be sustained
 Refine the plan – adjust to accommodate changes in scope, time
 Never compromise on quality
 Maintain agile discipline
APPENDIX6
39Introspection by Angeline Aggarwal
References
 http://agile.dzone.com/news/retrospect-about-sprint
 http://www.slideshare.net/Conscires/sprint-execution-standup-taskboard-etc
 http://www.slideshare.net/romanpichler/product-backlog-tips-and-tricks
 http://www.slideshare.net/dhaval.r.panchal/keeping-product-backlog-healthy
 http://agilepainrelief.com/notesfromatooluser/2012/06/scrummaster-tales-learning-how-
to-estimate.html
 http://colearningbe.wordpress.com/2013/04/01/most-common-mistakes-in-scrum-
ceremonies-27-estimating-stories/
 http://scrummethodology.com/scrum-effort-estimation-and-story-points/
Websites
Book
 ‘Succeeding with Agile’ by Mike Cohn

Weitere ähnliche Inhalte

Was ist angesagt?

Release planning
Release planningRelease planning
Release planningAbhay Kumar
 
What is quality, and how do we build it in
What is quality, and how do we build it in What is quality, and how do we build it in
What is quality, and how do we build it in Maryam Umar
 
Planning and Tracking Agile Projects
Planning and Tracking Agile ProjectsPlanning and Tracking Agile Projects
Planning and Tracking Agile ProjectsMike Cohn
 
ADAPTing to Agile for Continued Success
ADAPTing to Agile for Continued SuccessADAPTing to Agile for Continued Success
ADAPTing to Agile for Continued SuccessMike Cohn
 
Agile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesAgile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesSlideTeam
 
Agile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationAgile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationPrateek Sharma
 
Pptx estimating is not planning
Pptx estimating is not planningPptx estimating is not planning
Pptx estimating is not planningDhaval Panchal
 
Agile project management with scrum
Agile project management with scrumAgile project management with scrum
Agile project management with scrumRasan Samarasinghe
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile developmentPhavadol Srisarnsakul
 
The Role of Quality Assurance in the World of Agile Development and Scrum
The Role of Quality Assurance in the World of Agile Development and ScrumThe Role of Quality Assurance in the World of Agile Development and Scrum
The Role of Quality Assurance in the World of Agile Development and ScrumRussell Pannone
 
Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Harold van Heeringen
 
Story Based Burn Down
Story Based Burn DownStory Based Burn Down
Story Based Burn DownEthan Huang
 
Agile and Scrum for Video Game Development
Agile and Scrum for Video Game DevelopmentAgile and Scrum for Video Game Development
Agile and Scrum for Video Game DevelopmentMike Cohn
 
Operational Excellence Metrics PowerPoint Presentation Slides
Operational Excellence Metrics PowerPoint Presentation SlidesOperational Excellence Metrics PowerPoint Presentation Slides
Operational Excellence Metrics PowerPoint Presentation SlidesSlideTeam
 
Doing agile with an ISO-20000 Telco (AgilePT 2015)
Doing agile with an ISO-20000 Telco (AgilePT 2015)Doing agile with an ISO-20000 Telco (AgilePT 2015)
Doing agile with an ISO-20000 Telco (AgilePT 2015)Manuel Padilha
 
"Hack Your Project" by Andrea Fryrear and David Lesue
"Hack Your Project" by Andrea Fryrear and David Lesue"Hack Your Project" by Andrea Fryrear and David Lesue
"Hack Your Project" by Andrea Fryrear and David LesueMarcus Varner, MBA
 

Was ist angesagt? (20)

Release planning
Release planningRelease planning
Release planning
 
MVP Hacks
MVP HacksMVP Hacks
MVP Hacks
 
What is quality, and how do we build it in
What is quality, and how do we build it in What is quality, and how do we build it in
What is quality, and how do we build it in
 
Planning and Tracking Agile Projects
Planning and Tracking Agile ProjectsPlanning and Tracking Agile Projects
Planning and Tracking Agile Projects
 
ADAPTing to Agile for Continued Success
ADAPTing to Agile for Continued SuccessADAPTing to Agile for Continued Success
ADAPTing to Agile for Continued Success
 
Agile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation SlidesAgile Planning Powerpoint Presentation Slides
Agile Planning Powerpoint Presentation Slides
 
Agile UX
Agile UXAgile UX
Agile UX
 
Agile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management PresentationAgile vs Waterfall Project Management Presentation
Agile vs Waterfall Project Management Presentation
 
Pptx estimating is not planning
Pptx estimating is not planningPptx estimating is not planning
Pptx estimating is not planning
 
Agile project management with scrum
Agile project management with scrumAgile project management with scrum
Agile project management with scrum
 
The Business value of agile development
The Business value of agile developmentThe Business value of agile development
The Business value of agile development
 
The Role of Quality Assurance in the World of Agile Development and Scrum
The Role of Quality Assurance in the World of Agile Development and ScrumThe Role of Quality Assurance in the World of Agile Development and Scrum
The Role of Quality Assurance in the World of Agile Development and Scrum
 
Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...
 
Lean at Yahoo in 2008
Lean at Yahoo in 2008Lean at Yahoo in 2008
Lean at Yahoo in 2008
 
Story Based Burn Down
Story Based Burn DownStory Based Burn Down
Story Based Burn Down
 
Agile and Scrum for Video Game Development
Agile and Scrum for Video Game DevelopmentAgile and Scrum for Video Game Development
Agile and Scrum for Video Game Development
 
Operational Excellence Metrics PowerPoint Presentation Slides
Operational Excellence Metrics PowerPoint Presentation SlidesOperational Excellence Metrics PowerPoint Presentation Slides
Operational Excellence Metrics PowerPoint Presentation Slides
 
Doing agile with an ISO-20000 Telco (AgilePT 2015)
Doing agile with an ISO-20000 Telco (AgilePT 2015)Doing agile with an ISO-20000 Telco (AgilePT 2015)
Doing agile with an ISO-20000 Telco (AgilePT 2015)
 
"Hack Your Project" by Andrea Fryrear and David Lesue
"Hack Your Project" by Andrea Fryrear and David Lesue"Hack Your Project" by Andrea Fryrear and David Lesue
"Hack Your Project" by Andrea Fryrear and David Lesue
 
An agile intro in imago v1 1.pptx
An agile intro in imago v1 1.pptxAn agile intro in imago v1 1.pptx
An agile intro in imago v1 1.pptx
 

Andere mochten auch

Andere mochten auch (9)

Sgin2013 scrum accomplished-mmog-sajitvasudevan
Sgin2013 scrum accomplished-mmog-sajitvasudevanSgin2013 scrum accomplished-mmog-sajitvasudevan
Sgin2013 scrum accomplished-mmog-sajitvasudevan
 
Sudipta lahiri - Kanban Pizza-lets make some pizzas
Sudipta lahiri - Kanban Pizza-lets make some pizzasSudipta lahiri - Kanban Pizza-lets make some pizzas
Sudipta lahiri - Kanban Pizza-lets make some pizzas
 
At2012_pune when_i_had_big_shoes_to_fill_amoliu
At2012_pune when_i_had_big_shoes_to_fill_amoliuAt2012_pune when_i_had_big_shoes_to_fill_amoliu
At2012_pune when_i_had_big_shoes_to_fill_amoliu
 
Sgin2013 keynote-suceeding with scrum-bob hartman
Sgin2013 keynote-suceeding with scrum-bob hartmanSgin2013 keynote-suceeding with scrum-bob hartman
Sgin2013 keynote-suceeding with scrum-bob hartman
 
At2014 Bengaluru karthik_SMs_courage_to_be_wired
At2014 Bengaluru karthik_SMs_courage_to_be_wiredAt2014 Bengaluru karthik_SMs_courage_to_be_wired
At2014 Bengaluru karthik_SMs_courage_to_be_wired
 
At2014 Bengaluru sharad julka_professional growth options for a scrum master
At2014 Bengaluru sharad julka_professional growth options for a scrum masterAt2014 Bengaluru sharad julka_professional growth options for a scrum master
At2014 Bengaluru sharad julka_professional growth options for a scrum master
 
Mahesh Varadharajan Transition from good managers to great leaders
Mahesh Varadharajan Transition from good managers to great leadersMahesh Varadharajan Transition from good managers to great leaders
Mahesh Varadharajan Transition from good managers to great leaders
 
Sgin2013 scrum accomplished-agilemindset-ronenbarnahor
Sgin2013 scrum accomplished-agilemindset-ronenbarnahorSgin2013 scrum accomplished-agilemindset-ronenbarnahor
Sgin2013 scrum accomplished-agilemindset-ronenbarnahor
 
At2011 7 habits_of_highly_effective_agilists
At2011 7 habits_of_highly_effective_agilistsAt2011 7 habits_of_highly_effective_agilists
At2011 7 habits_of_highly_effective_agilists
 

Ähnlich wie Sgin2013 scrum accompllished-whatandwhat not!- apo-introspects-angelineagarwal

Ähnlich wie Sgin2013 scrum accompllished-whatandwhat not!- apo-introspects-angelineagarwal (20)

2 a introduction to agile
2 a introduction to agile2 a introduction to agile
2 a introduction to agile
 
CampusSDN2017 - Jawdat: Product Management and Agile Development
CampusSDN2017 - Jawdat: Product Management and Agile DevelopmentCampusSDN2017 - Jawdat: Product Management and Agile Development
CampusSDN2017 - Jawdat: Product Management and Agile Development
 
Agile and Startups - What can go wrong - a Case study (Presented at ExpoQA 20...
Agile and Startups - What can go wrong - a Case study (Presented at ExpoQA 20...Agile and Startups - What can go wrong - a Case study (Presented at ExpoQA 20...
Agile and Startups - What can go wrong - a Case study (Presented at ExpoQA 20...
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
 
:: Agile Scrum Methodology ::
:: Agile Scrum Methodology :::: Agile Scrum Methodology ::
:: Agile Scrum Methodology ::
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 
Agile
AgileAgile
Agile
 

Mehr von India Scrum Enthusiasts Community

“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...
“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...
“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...India Scrum Enthusiasts Community
 
Software 4.0 : “How” of Building Software Driven Business
Software 4.0 : “How” of Building Software Driven BusinessSoftware 4.0 : “How” of Building Software Driven Business
Software 4.0 : “How” of Building Software Driven BusinessIndia Scrum Enthusiasts Community
 
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...India Scrum Enthusiasts Community
 
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?India Scrum Enthusiasts Community
 

Mehr von India Scrum Enthusiasts Community (20)

Deciphering Agile Big Data
Deciphering Agile Big DataDeciphering Agile Big Data
Deciphering Agile Big Data
 
“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...
“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...
“How We Learnt to Stop Worrying and Live with Uncertainty” – Case Studies fro...
 
Rubber Meets the Road
Rubber Meets the RoadRubber Meets the Road
Rubber Meets the Road
 
Can Agile Enthusiasm See The Organization Through?
Can Agile Enthusiasm See The Organization Through?Can Agile Enthusiasm See The Organization Through?
Can Agile Enthusiasm See The Organization Through?
 
Agile​ ​HR​ ​From​ ​the​ ​trenches
Agile​ ​HR​ ​From​ ​the​ ​trenchesAgile​ ​HR​ ​From​ ​the​ ​trenches
Agile​ ​HR​ ​From​ ​the​ ​trenches
 
Evolutionary Change
Evolutionary ChangeEvolutionary Change
Evolutionary Change
 
Software 4.0 : “How” of Building Software Driven Business
Software 4.0 : “How” of Building Software Driven BusinessSoftware 4.0 : “How” of Building Software Driven Business
Software 4.0 : “How” of Building Software Driven Business
 
Agile Digital Architecture
Agile Digital ArchitectureAgile Digital Architecture
Agile Digital Architecture
 
Governance mechanism to further business agility
Governance mechanism to further business agilityGovernance mechanism to further business agility
Governance mechanism to further business agility
 
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...
Opening the Mainframe world to Mobile Ecosystem in a seamless and beneficial ...
 
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?
Workplace Happiness - Is Business Agility Taking us Towards Happy Workplaces?
 
Wave 2 of Agile: Agile Leadership Redefined
Wave 2 of Agile: Agile Leadership RedefinedWave 2 of Agile: Agile Leadership Redefined
Wave 2 of Agile: Agile Leadership Redefined
 
Agile Engineering Environment – 2017
Agile Engineering Environment – 2017Agile Engineering Environment – 2017
Agile Engineering Environment – 2017
 
Management for Agility and Outcomes
Management for Agility and OutcomesManagement for Agility and Outcomes
Management for Agility and Outcomes
 
Agile Mindset Shifting: Agile For All
Agile Mindset Shifting: Agile For AllAgile Mindset Shifting: Agile For All
Agile Mindset Shifting: Agile For All
 
Agile Engineering Environment – 2017
Agile Engineering Environment – 2017Agile Engineering Environment – 2017
Agile Engineering Environment – 2017
 
Wave 2 of Agile: Agile Leadership Redefined
Wave 2 of Agile: Agile Leadership RedefinedWave 2 of Agile: Agile Leadership Redefined
Wave 2 of Agile: Agile Leadership Redefined
 
Five (Oops!) Six Mistakes You are Making as a Leader
Five (Oops!) Six Mistakes You are Making as a LeaderFive (Oops!) Six Mistakes You are Making as a Leader
Five (Oops!) Six Mistakes You are Making as a Leader
 
Empower the Forbidden Power Players
Empower the Forbidden Power PlayersEmpower the Forbidden Power Players
Empower the Forbidden Power Players
 
Agility in Education System for Digital India
Agility in Education System for Digital IndiaAgility in Education System for Digital India
Agility in Education System for Digital India
 

Kürzlich hochgeladen

TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????blackmambaettijean
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 

Kürzlich hochgeladen (20)

TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 

Sgin2013 scrum accompllished-whatandwhat not!- apo-introspects-angelineagarwal

  • 1. Angeline Aggarwal, CSPO Product Owner, Tata Consultancy Services Scrum Gathering India Regional 2013 July, 2013 : +91 99201 37484 : angelinepp@gmail.com What and What NOT! - A PO Introspects
  • 2. 2 A Product Owner is born! Developer for 7 years Working on RAD methodology; accustomed to quick turn-around times. Suddenly Agile – Alice in Wonderland! One-week sprints were being followed enterprise wide – Hit the ground running! In this presentation…… Scrum flow reviewed At each step identify  Common mistakes a beginner makes  How they impact the end result  How to avoid / become better
  • 4. 4Introspection by Angeline Aggarwal A vision must be detailed enough to provide clarity… Why have a vision?  Guides the team and describes the essence of the project  Provides clarity to the stakeholders that the team has understood what they have to do! Attributes of a good vision  Other Attributes  Stable  Clear  Appealing  Broad  Short  Pass the elevator test  Demystify the WHO, the WHAT, the WHY and the HOW  Who are our customers  What do they need  Why do they need  How we can meet the needs
  • 5. 5Introspection by Angeline Aggarwal But “Vision” for my first project was woefully incomplete! Vision for the my first scrum project To make all finance system applications compliant with new firm wide change My Scorecard: Attributes Score What's the problem? Who is the stakeholder POOR Team does not know who to turn to, if we run into impediments and feedback What are the customer needs POOR Unclear: Left open-ended with a catch-all "ALL" systems compliant Why does the customer need it POOR Not identified: Team can't identify with the customers needs What is the target time-frame POOR Not stated: How do we figure out what resources/time are required and how much time will be required Stable POOR The client can go on making continuous changes Clear POOR Scope left unclear Short GOOD But its too short, doesn’t cover even the essentials Broad GOOD Its TOO broad and left open-ended Engaging POOR Only because it is short
  • 6. 6Introspection by Angeline Aggarwal This is what the ‘Vision’ should have looked like Revised Vision Statement Description Problem/Opportunity Statement  Customer is implementing a new length of employee ids to cater to influx of new hires  All downstream applications may not support the increased length Potential Solution  Test critical applications  Identify issues  Fix issues to make the application compliant Scope of the project  To identify list critical applications which do not have an development team  Applications which are not to be decommissioned in the next one year Who is the stakeholder/Customer  Program managers (indentified people) for portfolio of applications Value to the customer  New hires would be able to use applications error free Timeline  6 months Success Criteria  Applications should support new length of person id While it is not short, it is crisp and contains all the relevant information
  • 7. 7Introspection by Angeline Aggarwal What went wrong  No clarity on scope / interim changes  Not knowing who is involved and in what capacity  Not having asked the right questions Impact  Improper prioritization of the requirements/backlog  Slow the pace in removing impediments, getting approvals, requirement clarifications Doing it right…  Ask: The more you ask the more you understand. But ask the right questions  What is more critical  What needs will it address for the user  Share the vision with the entire team and make sure the entire team has the same understanding  Engage with the sponsor: With the right person at the right time will help in proper planning and removing most of your impediments in next steps ‘Vision’ - Recap
  • 9. 9Introspection by Angeline Aggarwal Step 2: Creating a backlog consisting of epics and stories  The product owner translates the vision into a backlog  Product backlog contains the following: o Themes/Epics/Stories, Technical work and defects. Attributes of a good Product Backlog  D E E P  Detailed Appropriately  Emergent  Estimated  Prioritized  Visible: Readily available to the team and stakeholders What is the backlog
  • 10. 10Introspection by Angeline Aggarwal How I created my first backlog In my project:  Each application became an ‘Epic’  Disregarded the Iceberg: Aiming to break down all the ‘Epics’ into detailed ‘Stories’ to get to know the overall size of the project (Waterfall mindset) - Spent two sprints breaking down half the sprints before checking course  Two types of stories  Standard setup stories common for all applications  Application Specific Stories  Started implementation of set up stories for couple of applications and staffed with team  Project was set up in ‘Mingle’
  • 11. 11Introspection by Angeline Aggarwal A backlog in disarray 0 1 2 3 4 5 6 7 8-10 11+ Set up Mingle Get Access App_1 to 10 App_1 Demo App_1 Story_1 and 2 App_2 Analyz e Code App_2 Confir m change s with User App_2 Code changes . . . App_2 – Identify Testing Strategy App_2 - Testing App_2 – Testing interfaces (Dependency came up) Get info App_1 to App 10 Staff Team App_1 and App_2 App_1 Analyze code App_2 Demo and Analyze Code [App_1 contin ued on track] Adhoc Develo pment work (Added subseq uently) . . . . . Adhoc Development work (Added subsequently) . . .
  • 12. 12Introspection by Angeline Aggarwal Backlog: What was wrong and what was the impact  Incorrect Prioritization: Too much upfront effort adding details to ‘Epics’ to be taken up much later  Impact: Effort wasted and re-planning required, big picture missed due to ‘too many items’  Activity specific sprints: Application 2 was proceeding like a waterfall model within the agile framework  Impact: Idle time- Developer idle due to delay from user. No back up work planned  Interdependencies of applications overlooked:  Impact: Unforeseen delays due to dependencies on teams handling other application  Ineffective Planning: Should have identified testing strategy upfront  Impact: Emergency changes in release planning  Adhoc development work added to backlog – Team ‘Vision’ was compromised. Cascaded into multiple change requests and additional work  Impact: Huge delay. Initial user estimate of 2 months took 3 months despite overworked team  Neglect backlog Grooming: Specific time not allocated for backlog grooming  Impact: Could not eliminate unwanted items prior to sprint – backlog not ready for next sprint – resulting in confusion for the team Overall impact:  Non shippable deliverables per sprint  No sign off from the customer  Overall release getting delayed by 3 months
  • 13. 13Introspection by Angeline Aggarwal Backlog: Lessons learnt  Prioritization  Take up application with most dependencies initially  Progressively refine – Impossible to think of everything upfront  Add details Just-In-Time, not weeks in advance because things change as new information emerges  Helps avoid too many backlog items  Stick to the vision:  Any adhoc requests not in line with project vision should be treated like a separate project – with its own backlog and stories  Backlog Grooming  Would have set aside Time-boxed period for the entire team to focus on cleaning up the backlog
  • 15. 15Introspection by Angeline Aggarwal Estimation 101 The process of quantifying the effort required in story points or ideal days involved in implementing the Product Backlog with the resources available What is Estimation The WHEN, WHO And HOW of Estimation  The When:  Before the first sprint  During the first 2 sprints  On going  Who: Product Owner + Scrum Master + Team  The How  Story points vs. ideal days  Planning poker End Result  Sized Stories  Results in backlog refinement
  • 16. 16Introspection by Angeline Aggarwal What were the mistakes Impact How to avoid them Playing the task master: • Product owner drives estimate based on deadline of the project • Team estimated 3 weeks I pushed for 2. It finally took 3 weeks • OR Team compromises on Quality Estimate should be Honest not influenced: • Developer should give the estimate not the product owner • Scrum master to facilitate Equating story points to days: • Each story is considered individually rather than a collection to relative estimate • Failed to see big picture • Overall deadline slippages •Play the poker - Its fun! Trying to estimate the inestimable! • Stories are too complex or too many unknowns/dependencies to estimate • Radically different estimates from team members due to different interpretations • Extended planning duration • Stop and think and break down further lUnclear Scale: lTeam not clear on the scale being used • Use a scale which all team members identify with • Identify smallest and largest at 2 points and 20 points respectively Chasing Velocity: Adjusting estimate to meet forecasted velocity • Slippages across sprint deadlines • Over-worked team – unsustainable in the long run • Velocity gets derived from the estimates and not the other way around Common pitfalls and how to avoid them
  • 17. 17Introspection by Angeline Aggarwal POs - do not influence the team
  • 19. 19Introspection by Angeline Aggarwal Backlog consists of multiple USER stories  Defining the deliverables from a users perspective aligns with goal of the product  Format: As a <USER>, I want <SOMETHING>, so that <SOME VALUE> o For Technical stories, user is replaced by the module Define from a “USERS” perspective Attributes of a good Story  I N V E S T  Independent  Negotiable  Valuable  Estimable  Small  Testable  Should define the WHO, WHAT and WHY  Story should contain acceptable criteria (for validation) - Sufficient to define the boundaries of the story
  • 20. 20Introspection by Angeline Aggarwal Its time to write a story: User Story 1 User Story: Add a share activity section to the share activity report to display share transactions for a user Acceptance criteria: Display share activity information in the following columns, no of shares, date, activity (Buy or sell), quantity, value per share and total amount User Story: As a user, I want to see the share activity details, for the selected person for the current financial year, so that I may view the details of the share transacted by that user and compute share balance Acceptance criteria: Display share sale and share purchase in separate rows with the following information, no of shares, date, activity (Buy or sell), quantity, value per share and total amount in a user defined format Should have been
  • 21. 21Introspection by Angeline Aggarwal What were the mistakes Impact How to avoid mistakes The “WHY” is missing Story defined from a developers perspective of what needs to be done, not the why Impact: If we knew what we wanted to use the report for, we could have added additional data useful for user (like total gain in the period, etc) Could have suggested displays with additional data would could have been meaningful to the user Potential Additional revenue lost? Ask more questions with the stakeholder and constantly engage The WHAT not completely defined Report pertains to which year – what test data to retrieve NOT testable. Boundary condition missed out. Involve the team in story writing Not negotiable User wanted a different format for a boundary condition (shares bought and sold on the same date in separate columns) Could not be completed in simple sprint. Code had to be re-worked. Few person days additional required Describe by examples User could have pointed what he wanted Analysis of User Story 1
  • 22. 22Introspection by Angeline Aggarwal Story..continued..: User Story 2 User Story: As a user, I want to run the report X for multiple employees in a given date range Acceptance criteria:  Report should accept multiple employee numbers in a comma or space separated string  User should be able to enter start and end date User Story: As a user, I want to run the report X for multiple employees in a given date range so as to be able to generate a batch of reports of all employees under a partner at one time Acceptance criteria:  Report should accept multiple employee numbers with a minimum of 750 in a comma or space separated string  User should be able to enter start and end date  The entire report should be generated in a maximum of 30 seconds Should have been
  • 23. 23Introspection by Angeline Aggarwal What were the mistakes Impact How to avoid mistakes The “WHY” is missing Lead to unclear boundary condition below Focus on discussion rather than documentation: Ask more questions and constantly engage with the user ilities and UI constraints Boundary condition not defined: User wanted to run report for a minimum of 750 users at one go Performance tuning (optimization) was not done Architecture reworked for optimized performance Missing definition of done How long should the report generation take was not listed The entire report could not be done in 30 secs as required by the user, had to increased up to 2 mins Analysis of User Story 2 Is it possible to write a complete story upfront and ready for a sprint - NO
  • 24. ALL ABOUT THE SPRINT5
  • 25. 25Introspection by Angeline Aggarwal Sprint away!  A time-boxed period during which the scrum team works to build a potentially shippable increment to the product  Both incremental and iterative at the same time  Iterative - Planning + Execution + Review  End result: Potentially shippable increment to the project / product Deliver at end of each sprint: Allows to inspect and seek constructive feedback
  • 27. 27Introspection by Angeline Aggarwal What is Sprint Planning  Entire team (Product Owner, Scrum Master, Developers, etc) participate in the Sprint planning meeting to discuss the following  Sprint goals  Selection of sprint backlog for the next sprint (Backlog items that the team commits to and the tasks they are broken down into)  Typical effort of two-four hours per sprint What happens during Sprint Planning Outcome of Sprint Planning  Defining what the team will achieve in the next sprint  Shippable increments  Behind-the-scenes features  Just something valuable  Further break down stories based on new details  Emergent requirements
  • 28. 28Introspection by Angeline Aggarwal Sprint Planning Case Study Top Story Priorities Stories Points App_2 Testing (Modules 01 to 10) 3 App_2 Testing (Modules 11 to 20) 3 App_2 Testing (Modules 21 to 30) 3 Test App_2 Interface 1 5 Test App_2 Interface 2 5 Capital Tax Report (became a 20 pointer subsequently) 8 App_3 Analyze Code Base 3 App_3 Get Access to Dev Env. 2 App2_Analyze Back end 3 App3_Analyze Import Module 3 App3_Upload 2 App3_Sumbit 3 Chasing too many points per sprint Interface modules should have been prioritized over • Story too big to be taken up and therefore broken down • Task based break down into : Analyze the requirement, etc Detailed plan for all the activities put in place much in advance
  • 29. 29Introspection by Angeline Aggarwal Sprint Planning Mistakes Impact How to avoid mistakes Lacking the big Picture: • Selecting stories with a short term goal in mind • In-correct prioritization and thereby selection of sprint • Start with a prioritized backlog • Always first take stories which have maximum interdependency Waterfall in Agile • Planning activity specific sprints rather than holistic development of an increment • No user specific deliverable • Risk of spending too much time for one activity which doesn’t get validated • AVOID the temptation and ALWAYS deliver at-least a testable increment Chasing Velocity • Over-committing or selecting stories that are too large for the sprint Planning for overwork “Need to complete at least 14 story points to maintain our velocity” • Overworked team • Compromise on testing and quality OR • Under deliver in next sprint • Plan based on what can be completed end to end • Selecting the right mix of stories – not all large, not all small • Achievement is not in terms of velocity – velocity should result from doing scrum right Planning for a better finish
  • 30. 30Introspection by Angeline Aggarwal Sprint Planning Mistakes Impact How to avoid mistakes Scheduling issues • PO/ Team member is not available for the meeting • Team members don’t understand the sprint goals • Be flexible with scheduling • Make the planning meeting compulsory to all lPlanning too much into the future • Little room for progressive adjustments, • Leads to effort waste • Product Owners! Know your backlog • Plan at the optimal time – one or two sprints in advance Starting the new sprint with planning • Should be done 2 days before next sprint starts • Result in idle team • Lead time to get At least 5-10% of team time should be reserved for planning for the next sprint Ignoring Team Ability / Availability • Leads to over committing and under-delivering • Avoid assigning story to individuals, assign story to a team / sub team • Opt for pair programming where-ever critical • Product owner should be aware of team absences and take that into account Think holistically – don’t lose track of the overall vision
  • 32. 32Introspection by Angeline Aggarwal Are we getting there? Can you see the goal?  Team works on the backlog items committed for the sprint  Mode of operation:  Time-boxed daily scrum  Task boards  Impediments list  Changes in boundary conditions – decide on whether to terminate the sprint
  • 33. 33Introspection by Angeline Aggarwal Sprint Execution Mistakes Impact How to avoid mistakes No daily scrum • Inconsistent meeting times • Skipped meetings • Difficult to understand team progress • Individual follow up with team members – waste of time. • Team unaware of each others work and possible impact to their story • Disciplined daily scrum • Fixed meeting time and place Lack of enthusiasm • Team not fully involved • Meetings from their desk / simultaneously doing other work • Loose an opportunity to see overall progress, give and receive inputs • Just focused on status updates • Daily Stand-up done right! • Time-boxed no lengthy discussions • Accounting for time during DSM rather than goals and achievements • Developer may have spent a day on the story but achieved nothing in terms of value • Updates should be in terms of what was done and not how much time was spent on it Sprinting away from the goal and how to avoid it
  • 34. 34Introspection by Angeline Aggarwal Sprint Execution Mistakes Impact How to avoid mistakes No mid sprint checks • Items left for implementing at the end – not mid-sprint checks • Compromised on scope and quality • Maintain Sprint Burn down chart • Not a time for troubleshooting • Reduce wasteful effort – automate where possible • Don’t leave testing for the end – it generally gets skipped • Changing the sprint goal/sprint backlog during the sprint • Hampers the team’s focus and rhythm • Leads to hasty and unplanned activity • Avoid changes to the sprint goal – what to do if the priority of backlog suddenly changes? lImpediments • Not raising / handling impediments • Delays • wasted effort • Slippages • PO should follow up / force / beg for team to come up with impediments • Make the team comfortable to escalate issues Sprinting away from the goal and how to avoid it
  • 36. 36Introspection by Angeline Aggarwal A great finish! – Reviews and Retrospectives Objectives of the Sprint Review  1 hour per sprint: Set aside to reflect on the sprint gone by  Start, Stop, Change, Continue  Setup and continually improve best practices  No retrospective  A missed opportunity to learn  Repeat the same mistakes  Keep it informal  10-15 mins per Sprint to Inspect and Adapt  Highlight team goals and achievements  Assess the achievements against the sprint goal and not just completion of backlog  A natural end to the sprint, not a distraction requiring preparation time Retrospective: Learn from the past
  • 37. 37Introspection by Angeline Aggarwal Maintaining a sustainable pace of development Pace yourself like a marathon runner; Get a head start, go steady in between & Towards the end, give it your all  Start Small but think Big – never forget the big picture  Use same length sprints - helps planning and the team works with Rhythm  Focus on delivery – Definition of done – complete story  Continuous improvement  Don’t bank on overtime – it cannot be sustained  Refine the plan – adjust to accommodate changes in scope, time  Never compromise on quality  Maintain agile discipline
  • 39. 39Introspection by Angeline Aggarwal References  http://agile.dzone.com/news/retrospect-about-sprint  http://www.slideshare.net/Conscires/sprint-execution-standup-taskboard-etc  http://www.slideshare.net/romanpichler/product-backlog-tips-and-tricks  http://www.slideshare.net/dhaval.r.panchal/keeping-product-backlog-healthy  http://agilepainrelief.com/notesfromatooluser/2012/06/scrummaster-tales-learning-how- to-estimate.html  http://colearningbe.wordpress.com/2013/04/01/most-common-mistakes-in-scrum- ceremonies-27-estimating-stories/  http://scrummethodology.com/scrum-effort-estimation-and-story-points/ Websites Book  ‘Succeeding with Agile’ by Mike Cohn