International Competitive BiddingBid Opening, Evaluation, and Award of Contract #2 Asian Development Bank Procurement Guidelines
Table of Contents Evaluation and Comparison of Bids Domestic Preferences Extension of Validity of Bids Postqualificationof Bidders Award of Contract Publication of the Award of Contract Rejection of All Bids Debriefing
Extension of Validity of Bids Asian Development Bank Procurement Guidelines
Extension of Validity of Bids Para 2.57  Borrowers shall complete evaluation of bids and award of contract within the initial period of bid validity so that extensions are not necessary.37  An extension of bid validity, if justified by exceptional circumstances, shall be requested in writing from all bidders before the expiration date.  The extension shall be for the minimum period required to complete the evaluation, obtain the necessary approvals, and award the contract.
Extension of Validity of Bids Para 2.57  Whenever an extension of bid validity period is requested, bidders shall not be requested or be permitted to change the price or other conditions of their bid.  Bidders shall have the right to refuse to grant such an extension.  If the bidding documents require a bid security, bidders may exercise their right to refuse to grant such an extension without forfeiting their bid security, but those who are willing to extend the validity of their bid shall be required to provide a suitable extension of bid security.
Postqualification of Bidders Asian Development Bank Procurement Guidelines
Postqualification of Bidders Para 2.58  If bidders have not been prequalified, the borrower shall determine whether the bidder whose bid has been determined to offer the lowest evaluated cost has the capability and resources to effectively carry out the contract as offered in the bid.  The criteria to be met shall be set out in the bidding documents, and if the bidder does not meet them, the bid shall be rejected. In such an event, the borrower shall make a similar determination for the next lowest evaluated bidder.
Award of Contract Asian Development Bank Procurement Guidelines
Award of Contract Para 2.59  The borrower shall award the contract, within the period of the validity of bids, to the bidder who meets the appropriate standards of capability and resources and whose bid has been determined to be substantially responsive to the bidding documents and  to offer the lowest evaluated cost.38  A bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
Publication of the Award of Contract Asian Development Bank Procurement Guidelines
Publication of the Award of Contract Para 2.60  Within two weeks of receiving ADB’s “no objection” to the recommendation of contract award, the borrower shall publish in an English language newspaper or well-known and freely accessible website the results identifying the bid and lot numbers, and the following information:  name of each bidder who submitted a bid;  bid prices as read out at bid opening;  name and evaluated prices of each bid that was evaluated;  name of bidders whose bids were rejected and the reasons for their rejection; and  name of the winning bidder, and the price it offered, as well as the duration and summary scope of the contract awarded.
Publication of the Award of Contract Para 2.60  For contracts subject to post review, the borrower shall publish the results no later than the date of contract award.
Rejection of All Bids Asian Development Bank Procurement Guidelines
Rejection of All Bids Para 2.61  Bidding documents usually provide that borrowers may reject all bids. Rejection of all bids is justified when there is lack of effective competition, or bids are not substantially responsive or when bid prices are substantially higher than existing budget.  Lack of competition shall not be determined solely on the basis of the number of bidders. Even when only one bid is submitted, the bidding process may be considered valid, if the bid was satisfactorily advertised and prices are reasonable in comparison to market values
Rejection of All Bids Para 2.61  Borrowers may, after ADB’s prior approval, reject all bids. If all bids are rejected, the borrower shall review the causes justifying the rejection and consider making revisions to the conditions of contract, design and specifications, scope of the contract, or a combination of these, before inviting new bids.
Rejection of All Bids Para 2.62  If the rejection of all bids is due to lack of competition, wider advertising shall be considered.  If the rejection is due to most or all of the bids being nonresponsive, new bids may be invited from the initially prequalified firms, or with the agreement of ADB from only those that submitted bids in the first instance.
Rejection of All Bids Para 2.63 When all bids have been rejected, a rebidding may be called, and the borrower shall request for new bids from all who were supplied with bidding documents in the first instance. However, if there has been a sufficient number of bids in the initial bidding, the borrower may consider inviting bids only from those who have previously submitted bids.
Rejection of All Bids Para 2.63 Where all bid prices substantially exceed the cost estimates, the borrower may, instead of calling for new bids, and after consultation with ADB, negotiate with the lowest evaluated bidder for a reduction of the bid price. If no satisfactory contract can be concluded and a rebidding is called, modification of the scope of the contract shall be considered.
Rejection of All Bids Para 2.64  ADB’s prior approval shall be obtained before rejecting all bids, soliciting new bids, or entering into negotiations with the lowest evaluated bidder.
Debriefing Asian Development Bank Procurement Guidelines
Para 2.65  In the publication of contract award referred to in paragraph 2.60 the borrower shall specify that any bidder who wishes to ascertain the grounds on which its bid was not selected, should request an explanation from the borrower.  The borrower shall promptly provide an explanation of why such bid was not selected, either in writing and/or in a debriefing meeting, at the option of the borrower. The requesting bidder shall bear all the costs of attending such a debriefing.
Adb procurement guidelines   icb-c2

More Related Content

What's hot

Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb aJoy Irman
 
Tenders , Invitation of tender
Tenders , Invitation of tender Tenders , Invitation of tender
Tenders , Invitation of tender Arpit Sethia
 
Wb appendix 3 guidance to bidders
Wb appendix 3 guidance to biddersWb appendix 3 guidance to bidders
Wb appendix 3 guidance to biddersJoy Irman
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1Joy Irman
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic PrinciplesSHKLaw
 
Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best PracticesSHKLaw
 
Legal rules as to valid acceptance
Legal rules as to valid acceptanceLegal rules as to valid acceptance
Legal rules as to valid acceptanceBhargav Dangar
 
Ppra rules knowledge thirst
Ppra rules  knowledge thirstPpra rules  knowledge thirst
Ppra rules knowledge thirstUnsaSoomro
 
Bid document for Solar Plant in Jharkhand
Bid document for Solar Plant in JharkhandBid document for Solar Plant in Jharkhand
Bid document for Solar Plant in JharkhandHeadway Solar
 
Ipds volume i.35-39
Ipds volume i.35-39Ipds volume i.35-39
Ipds volume i.35-39Sanjay Kumar
 
Haryana Solar Bid Document RFS
Haryana Solar Bid Document RFSHaryana Solar Bid Document RFS
Haryana Solar Bid Document RFSHeadway Solar
 
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...Sazzad Hossain, ITP, MBA, CSCA™
 
Tender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsTender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsIJERA Editor
 
Ppra rules 2004
Ppra rules   2004Ppra rules   2004
Ppra rules 2004dar81b
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 

What's hot (20)

Al huda presentation on stisna1
Al huda presentation on stisna1Al huda presentation on stisna1
Al huda presentation on stisna1
 
Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb a
 
Tenders , Invitation of tender
Tenders , Invitation of tender Tenders , Invitation of tender
Tenders , Invitation of tender
 
Alhuda CIBE - Presentation on Istisna by Mujeeb Baig
Alhuda CIBE - Presentation on Istisna by Mujeeb BaigAlhuda CIBE - Presentation on Istisna by Mujeeb Baig
Alhuda CIBE - Presentation on Istisna by Mujeeb Baig
 
Document samples
Document samplesDocument samples
Document samples
 
Wb appendix 3 guidance to bidders
Wb appendix 3 guidance to biddersWb appendix 3 guidance to bidders
Wb appendix 3 guidance to bidders
 
Advance 1020 1045
Advance 1020 1045Advance 1020 1045
Advance 1020 1045
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic Principles
 
Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best Practices
 
Legal rules as to valid acceptance
Legal rules as to valid acceptanceLegal rules as to valid acceptance
Legal rules as to valid acceptance
 
Ppra rules knowledge thirst
Ppra rules  knowledge thirstPpra rules  knowledge thirst
Ppra rules knowledge thirst
 
Bid document for Solar Plant in Jharkhand
Bid document for Solar Plant in JharkhandBid document for Solar Plant in Jharkhand
Bid document for Solar Plant in Jharkhand
 
Ipds volume i.35-39
Ipds volume i.35-39Ipds volume i.35-39
Ipds volume i.35-39
 
Haryana Solar Bid Document RFS
Haryana Solar Bid Document RFSHaryana Solar Bid Document RFS
Haryana Solar Bid Document RFS
 
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...
IFRS 15 2018 International Financial Reporting Standard 15 Revenue from Contr...
 
Tender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsTender and Bidding in Construction Projects
Tender and Bidding in Construction Projects
 
Public procurement rules 2004
Public procurement rules 2004Public procurement rules 2004
Public procurement rules 2004
 
Ppra rules 2004
Ppra rules   2004Ppra rules   2004
Ppra rules 2004
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 

Similar to Adb procurement guidelines icb-c2

Wb consultant 2c
Wb consultant 2cWb consultant 2c
Wb consultant 2cJoy Irman
 
Appendix 1 adb review of procurement decisions
Appendix 1   adb review of procurement decisionsAppendix 1   adb review of procurement decisions
Appendix 1 adb review of procurement decisionsJoy Irman
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and EvaluationAkshathaBhandary
 
Appendix 3 guidance to bidders
Appendix 3   guidance to biddersAppendix 3   guidance to bidders
Appendix 3 guidance to biddersJoy Irman
 
PowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxPowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxGetachewMekonnen22
 
Instructions to bidders
Instructions to biddersInstructions to bidders
Instructions to biddersRISHARD FAIS
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3Joy Irman
 
Procurement and Subcontractors
Procurement and SubcontractorsProcurement and Subcontractors
Procurement and SubcontractorsSHKLaw
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1Joy Irman
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Joy Irman
 
Adb procurement guidelines introduction1
Adb procurement guidelines   introduction1Adb procurement guidelines   introduction1
Adb procurement guidelines introduction1Joy Irman
 
BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxbenito procia
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2Joy Irman
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTADVj NiroSh
 
16 tender document khawaja fareed university 09112017
16   tender document khawaja fareed university 0911201716   tender document khawaja fareed university 09112017
16 tender document khawaja fareed university 09112017Salman Kharal
 
capaicty buidling program to make nation clean
capaicty buidling program to make nation cleancapaicty buidling program to make nation clean
capaicty buidling program to make nation cleanchiragvyas32
 
Wb procurement icb b2
Wb procurement icb b2Wb procurement icb b2
Wb procurement icb b2Joy Irman
 

Similar to Adb procurement guidelines icb-c2 (20)

Wb consultant 2c
Wb consultant 2cWb consultant 2c
Wb consultant 2c
 
Appendix 1 adb review of procurement decisions
Appendix 1   adb review of procurement decisionsAppendix 1   adb review of procurement decisions
Appendix 1 adb review of procurement decisions
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and Evaluation
 
Appendix 3 guidance to bidders
Appendix 3   guidance to biddersAppendix 3   guidance to bidders
Appendix 3 guidance to bidders
 
PowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxPowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptx
 
Instructions to bidders
Instructions to biddersInstructions to bidders
Instructions to bidders
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3
 
Procurement and Subcontractors
Procurement and SubcontractorsProcurement and Subcontractors
Procurement and Subcontractors
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Adb procurement guidelines introduction1
Adb procurement guidelines   introduction1Adb procurement guidelines   introduction1
Adb procurement guidelines introduction1
 
BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptx
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
 
CIDA SBD 03.pdf
CIDA SBD 03.pdfCIDA SBD 03.pdf
CIDA SBD 03.pdf
 
16 tender document khawaja fareed university 09112017
16   tender document khawaja fareed university 0911201716   tender document khawaja fareed university 09112017
16 tender document khawaja fareed university 09112017
 
capaicty buidling program to make nation clean
capaicty buidling program to make nation cleancapaicty buidling program to make nation clean
capaicty buidling program to make nation clean
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Wb procurement icb b2
Wb procurement icb b2Wb procurement icb b2
Wb procurement icb b2
 

More from Joy Irman

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Joy Irman
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Joy Irman
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - peroranganJoy Irman
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usahaJoy Irman
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankJoy Irman
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingJoy Irman
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansJoy Irman
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Joy Irman
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeriJoy Irman
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkunganJoy Irman
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronikJoy Irman
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaanJoy Irman
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaanJoy Irman
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barangJoy Irman
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelolaJoy Irman
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelolaJoy Irman
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasaJoy Irman
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaanJoy Irman
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaanJoy Irman
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmenJoy Irman
 

More from Joy Irman (20)

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
 

Recently uploaded

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Pitch deck sample detail for New Business Proposal
Pitch deck sample detail for New Business ProposalPitch deck sample detail for New Business Proposal
Pitch deck sample detail for New Business ProposalEvelina300651
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 

Recently uploaded (20)

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Pitch deck sample detail for New Business Proposal
Pitch deck sample detail for New Business ProposalPitch deck sample detail for New Business Proposal
Pitch deck sample detail for New Business Proposal
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 

Adb procurement guidelines icb-c2

  • 1. International Competitive BiddingBid Opening, Evaluation, and Award of Contract #2 Asian Development Bank Procurement Guidelines
  • 2. Table of Contents Evaluation and Comparison of Bids Domestic Preferences Extension of Validity of Bids Postqualificationof Bidders Award of Contract Publication of the Award of Contract Rejection of All Bids Debriefing
  • 3. Extension of Validity of Bids Asian Development Bank Procurement Guidelines
  • 4. Extension of Validity of Bids Para 2.57 Borrowers shall complete evaluation of bids and award of contract within the initial period of bid validity so that extensions are not necessary.37 An extension of bid validity, if justified by exceptional circumstances, shall be requested in writing from all bidders before the expiration date. The extension shall be for the minimum period required to complete the evaluation, obtain the necessary approvals, and award the contract.
  • 5. Extension of Validity of Bids Para 2.57 Whenever an extension of bid validity period is requested, bidders shall not be requested or be permitted to change the price or other conditions of their bid. Bidders shall have the right to refuse to grant such an extension. If the bidding documents require a bid security, bidders may exercise their right to refuse to grant such an extension without forfeiting their bid security, but those who are willing to extend the validity of their bid shall be required to provide a suitable extension of bid security.
  • 6. Postqualification of Bidders Asian Development Bank Procurement Guidelines
  • 7. Postqualification of Bidders Para 2.58 If bidders have not been prequalified, the borrower shall determine whether the bidder whose bid has been determined to offer the lowest evaluated cost has the capability and resources to effectively carry out the contract as offered in the bid. The criteria to be met shall be set out in the bidding documents, and if the bidder does not meet them, the bid shall be rejected. In such an event, the borrower shall make a similar determination for the next lowest evaluated bidder.
  • 8. Award of Contract Asian Development Bank Procurement Guidelines
  • 9. Award of Contract Para 2.59 The borrower shall award the contract, within the period of the validity of bids, to the bidder who meets the appropriate standards of capability and resources and whose bid has been determined to be substantially responsive to the bidding documents and to offer the lowest evaluated cost.38 A bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
  • 10. Publication of the Award of Contract Asian Development Bank Procurement Guidelines
  • 11. Publication of the Award of Contract Para 2.60 Within two weeks of receiving ADB’s “no objection” to the recommendation of contract award, the borrower shall publish in an English language newspaper or well-known and freely accessible website the results identifying the bid and lot numbers, and the following information: name of each bidder who submitted a bid; bid prices as read out at bid opening; name and evaluated prices of each bid that was evaluated; name of bidders whose bids were rejected and the reasons for their rejection; and name of the winning bidder, and the price it offered, as well as the duration and summary scope of the contract awarded.
  • 12. Publication of the Award of Contract Para 2.60 For contracts subject to post review, the borrower shall publish the results no later than the date of contract award.
  • 13. Rejection of All Bids Asian Development Bank Procurement Guidelines
  • 14. Rejection of All Bids Para 2.61 Bidding documents usually provide that borrowers may reject all bids. Rejection of all bids is justified when there is lack of effective competition, or bids are not substantially responsive or when bid prices are substantially higher than existing budget. Lack of competition shall not be determined solely on the basis of the number of bidders. Even when only one bid is submitted, the bidding process may be considered valid, if the bid was satisfactorily advertised and prices are reasonable in comparison to market values
  • 15. Rejection of All Bids Para 2.61 Borrowers may, after ADB’s prior approval, reject all bids. If all bids are rejected, the borrower shall review the causes justifying the rejection and consider making revisions to the conditions of contract, design and specifications, scope of the contract, or a combination of these, before inviting new bids.
  • 16. Rejection of All Bids Para 2.62 If the rejection of all bids is due to lack of competition, wider advertising shall be considered. If the rejection is due to most or all of the bids being nonresponsive, new bids may be invited from the initially prequalified firms, or with the agreement of ADB from only those that submitted bids in the first instance.
  • 17. Rejection of All Bids Para 2.63 When all bids have been rejected, a rebidding may be called, and the borrower shall request for new bids from all who were supplied with bidding documents in the first instance. However, if there has been a sufficient number of bids in the initial bidding, the borrower may consider inviting bids only from those who have previously submitted bids.
  • 18. Rejection of All Bids Para 2.63 Where all bid prices substantially exceed the cost estimates, the borrower may, instead of calling for new bids, and after consultation with ADB, negotiate with the lowest evaluated bidder for a reduction of the bid price. If no satisfactory contract can be concluded and a rebidding is called, modification of the scope of the contract shall be considered.
  • 19. Rejection of All Bids Para 2.64 ADB’s prior approval shall be obtained before rejecting all bids, soliciting new bids, or entering into negotiations with the lowest evaluated bidder.
  • 20. Debriefing Asian Development Bank Procurement Guidelines
  • 21. Para 2.65 In the publication of contract award referred to in paragraph 2.60 the borrower shall specify that any bidder who wishes to ascertain the grounds on which its bid was not selected, should request an explanation from the borrower. The borrower shall promptly provide an explanation of why such bid was not selected, either in writing and/or in a debriefing meeting, at the option of the borrower. The requesting bidder shall bear all the costs of attending such a debriefing.