SlideShare ist ein Scribd-Unternehmen logo
1 von 32
Capital ProjectsRisk Development and ManagementChristiane KampschulteParsons Brinckerhoff16th August 2010	2:30-3:15pm The most comprehensive Oracle applications & technology content under one roof
Introduction The presentation addresses Risk management in terms of quantitative Risk Management not qualitative scoring methods. The presentation compares two projects. To validate the effectiveness of Risk Management statistically we require more examples and case studies. None of the Project are as per “Best Practice” which is dealt with at the end.
Introduction There are a number of uncertainties in every project that have a potential to affect the outcome.  Commonly, the provision for these uncertainties is taken care of by adding a percentage of costs as contingency to the cost estimate and adding a time contingency at the end of the longest path.
Introduction The paper compares 2 similar projects and: Highlights the importance of calculating and documenting a meaningful cost and schedule contingency.  Illustrates the benefits of project cost and time estimate range reviews.
CASE STUDY A : Mining Infrastructure Project  in Western Australia
Rail Construction TD-Graph  Capping Tracklaying Bridges Commissioning Activities Target Track Actual Track Layed Hand Lay2 Hand layed Cloud Break PORT  250 COMMISSIONING &  Stockpiling Target No Later then  date 220 190 Bridge 8 Chainage (km) 160 Bridge 7 Bridge 6 Bridge 5 130 100 Bridge 4 Bridge 3 70 Bridge 2 40 Bridge 1 Actual Track  10 Layed Hand layed Loop 16-Nov-07 21-Sep-07 11-Jan-08 27-Jun-08 2-May-08 27-Jul-07 7-Mar-08 1-Jun-07 6-Apr-07 -20 CASE STUDIES
Cost and time estimates were based on information given by Engineering Design Team. The project started with a single point cost and time estimate. The single point estimate resulted in a contingency linked to the time and cost estimate. This was a fixed percentage added to the cost estimate and a fixed number of days added to the project programme. Case A
Execution phase risk management workshops were conducted  at regular intervals but inputs were taken from a Safety perspective and  risk were not quantified. The contractors were required to submit a time scaled detailed network program, hours spent and forecasts. No alliance partner's forecast showed schedule or cost overrun. Schedule updates always showed a date within the required dates.  Case A
Variations were approved while the cost value did not surpass the project single point estimate. No other number than the original estimate was ever communicated for time and cost. Case A
The project was being built in a Cyclone prone area and was under a high cyclone danger zone. A cyclone hit the area and one of the 3 worker accommodation camps a was damaged.  Case A
This incident triggered the intensive review of the project’s time estimate and cost estimate with focus on the assumptions made for calculating the contingency.  The finding were that the scope hat deviated from the initial estimate.  The assumptions made for the calculation of time and cost contingency were not treaceableso couldn’t not be evaluated for their adequateness. Case A
CASE STUDY B : Coal Terminal Project  in New South Wales
A Range Analysis Workshop (RAW) was held to identify and quantify all risks and uncertainties that could cause a deviation to the estimate.  Particular attention was paid to the facilitation of this workshop where project participants were encouraged to come up with extreme outcomes of the uncertainties.  Case B
Examples for risk sources considered in the RAW were: Availability of area or facility, staff availability and major equipment. Uncertainty over productivity level on the project. Adverse environmental conditions Specific risks identified for the project that have the potential to impact the project like geotechnical conditions, Industrial Relations, Quality. Case B – Risk sources
For awarded contracts, capital cost sources that were considered were  uncertainty associated with variations that have been submitted,  uncertainty with forecast variation and  uncertainty associated with emerging trends. Case B - Risk sources
	Capital cost inputs that were considered for un-awarded contracts typically included  variations in project scope that were being developed at that stage,  variations in unit rates considering the time lag between feasibility study and project execution,  variations in quantities-both materials and work hours which are impacted by the stage of the design process and  risk events specific to the project.  Case B - Risk sources
The schedule risk profile was developed through a summary risk schedule developed from the project schedule that captured the key milestones and the associated near critical activities. Duration ranges were developed for these activities in a facilitated workshop. These ranges were defined by the minimum case, maximum case, P10, P90 scenarios and probability of achieving or improving the task duration.  The ranges were then used to develop a probability distribution for the activity. Correlations between the ranged schedule activities were also included. Case B – Schedule range analysis
Case B – Schedule range analysis Key Drivers of the Project completion milestone
Awarded contracts – models cost uncertainty due to variations. Un-awarded contracts – modeled uncertainty associated with the estimate of these contracts. Owners – models uncertainty associated with owner’s costs. Project Risks – models the risks that have been identified. Project Scope – models potential scope changes for the project. Schedule – models the time variable uncertainty associated with schedule duration risk.    Case B – CAPEX range analysis
Case B - CAPEX Range analysis Schedule range analysis Cost range analysis
Case B - Risk model Mean P95 P5 Capital Cost Key Capital risk drivers
Differences
One definition of an estimate is that it is the expected value of a complex equation of probabilistic elements, each subject to random variation within defined ranges. Ref: Larry R.Dysert, CCE. Skills and Knowledge of Cost Engineering. 5th Edition Revised p 9.21, AACE International, 2007 ,[object Object],What do the cases illustrate?
Integrated cost-schedule risk analysis The purpose of this is to estimate the appropriate level of cost contingency reserve on projects and also to include the impact of schedule risk on cost risk.  Best Practice (as per AACE recommendation)
Start with a “good” logic driven schedule (summary schedule) Assign cost loaded resources to the activities in the schedule Take a risk driven approach. Use the “Risk Register”. Collect good risk data from facilitated workshop or one to one interview with stakeholders or project participants.  Derive contingency reserve of time and cost, prioritize the risks and mitigating them in steps. Best Practice
Risks are identified during a qualitative risk analysis of the project. This leads to a list of prioritized risks which are characterized by their probability and impact ranges. A best practice project schedule which is resource loaded. The “Neat Estimate” (an estimate without contingency) assigned to the activities in the schedule. Best Practice - Inputs
From the inputs, a risk model would be created in a readily available software like “Primavera Risk Analysis V8” (Pertmaster) ready to run a number of iterations simulating the project Risk # 01 – P50% Factors 0.95,1.05,1.15 Activity A Activity B Best Practice - Model
Outputs
Answers we get  Which risks are most important to the achievement of the project schedule and cost estimate?  How likely are the project plan’s cost and schedule targets to be met - taking into account the risk that may affect that plan?  How much contingency of time and cost needs to be provided to meet the risk threshold of the project management or other stakeholders? 
Tell us what you think… http://feedback.insync10.com.au Questions to : adatta_project@yahoo.comc.kampschulte@gmx.de

Weitere ähnliche Inhalte

Was ist angesagt?

Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisIntaver Insititute
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementMike Tulkoff
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisAsaman Patnaik
 
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleProject Controls Expo
 
Simplifying effort estimation based on use case points
Simplifying effort estimation based on use case pointsSimplifying effort estimation based on use case points
Simplifying effort estimation based on use case pointsAbdulrhman Shaheen
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaPankaj K Sinha
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis Shereef Sabri
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Drmarshallpmp
 
112 risk- metrics for risk reduction
112 risk- metrics for risk reduction112 risk- metrics for risk reduction
112 risk- metrics for risk reductionDr Fereidoun Dejahang
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...p6academy
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Anakinzs
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJavier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJ. García - Verdugo
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsMartin van Vliet
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityPMA Consultants
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2ahsanrabbani
 

Was ist angesagt? (20)

Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Project mgt
Project mgtProject mgt
Project mgt
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk Analysis
 
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
 
Simplifying effort estimation based on use case points
Simplifying effort estimation based on use case pointsSimplifying effort estimation based on use case points
Simplifying effort estimation based on use case points
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2
 
112 risk- metrics for risk reduction
112 risk- metrics for risk reduction112 risk- metrics for risk reduction
112 risk- metrics for risk reduction
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJavier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 

Andere mochten auch

Buscamos distribuidores
Buscamos distribuidoresBuscamos distribuidores
Buscamos distribuidoresjuansalas
 
Non verbal communication in norway and malaysia
Non verbal communication in norway and malaysiaNon verbal communication in norway and malaysia
Non verbal communication in norway and malaysiadragon888
 
Seminar On Non verbal communication
Seminar On Non verbal communication Seminar On Non verbal communication
Seminar On Non verbal communication Pradip Kumar
 
Silence communicate
Silence communicateSilence communicate
Silence communicateLê Hoàng
 

Andere mochten auch (8)

Buscamos distribuidores
Buscamos distribuidoresBuscamos distribuidores
Buscamos distribuidores
 
Cs fy
Cs fyCs fy
Cs fy
 
Communication Dispatch Centers
Communication Dispatch CentersCommunication Dispatch Centers
Communication Dispatch Centers
 
Non verbal communication in norway and malaysia
Non verbal communication in norway and malaysiaNon verbal communication in norway and malaysia
Non verbal communication in norway and malaysia
 
05gdall
05gdall05gdall
05gdall
 
Seminar On Non verbal communication
Seminar On Non verbal communication Seminar On Non verbal communication
Seminar On Non verbal communication
 
Methods of communication
Methods of communicationMethods of communication
Methods of communication
 
Silence communicate
Silence communicateSilence communicate
Silence communicate
 

Ähnlich wie C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Cost Engineering Financing and Risk Management in Upstream Oil & Gas Projects
Cost Engineering Financing and Risk Management in Upstream Oil & Gas ProjectsCost Engineering Financing and Risk Management in Upstream Oil & Gas Projects
Cost Engineering Financing and Risk Management in Upstream Oil & Gas ProjectspetroEDGE
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educCicelyBourqueju
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educChantellPantoja184
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty ParadoxHKA
 
Cost management
Cost managementCost management
Cost managementshkadry
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...HIMADRI BANERJI
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 

Ähnlich wie C:\documents and settings\ckampschulte\desktop\in sync risk range analysis (20)

CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Unit 2.pptx
Unit 2.pptxUnit 2.pptx
Unit 2.pptx
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Cost Engineering Financing and Risk Management in Upstream Oil & Gas Projects
Cost Engineering Financing and Risk Management in Upstream Oil & Gas ProjectsCost Engineering Financing and Risk Management in Upstream Oil & Gas Projects
Cost Engineering Financing and Risk Management in Upstream Oil & Gas Projects
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ
 
1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ1312021 Project Procurementhttpsleocontent.umgc.educ
1312021 Project Procurementhttpsleocontent.umgc.educ
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty Paradox
 
Cost management
Cost managementCost management
Cost management
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
H1303055462
H1303055462H1303055462
H1303055462
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 

Mehr von InSync Conference

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11InSync Conference
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economyInSync Conference
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreInSync Conference
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On OracleInSync Conference
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsInSync Conference
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalInSync Conference
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalInSync Conference
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationInSync Conference
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationInSync Conference
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInSync Conference
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better DecisionsInSync Conference
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationInSync Conference
 

Mehr von InSync Conference (20)

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economy
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution Centre
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On Oracle
 
P6 r8
P6 r8P6 r8
P6 r8
 
P6 analytics
P6 analyticsP6 analytics
P6 analytics
 
Upk presentation insync
Upk presentation insync Upk presentation insync
Upk presentation insync
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD Edwards
 
In sync10 grc_suite
In sync10 grc_suiteIn sync10 grc_suite
In sync10 grc_suite
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-final
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-final
 
Mnod linsync10 oba
Mnod linsync10 obaMnod linsync10 oba
Mnod linsync10 oba
 
D linsync10 ofa5yrs
D linsync10 ofa5yrsD linsync10 ofa5yrs
D linsync10 ofa5yrs
 
D linsync10 fusaapps
D linsync10 fusaappsD linsync10 fusaapps
D linsync10 fusaapps
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentation
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer Presentation
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed Announcement
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better Decisions
 
Life after upgrading to r12
Life after upgrading to r12Life after upgrading to r12
Life after upgrading to r12
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementation
 

Kürzlich hochgeladen

Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一diploma 1
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxmapanig881
 
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一Fi L
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree ttt fff
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证nhjeo1gg
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...katerynaivanenko1
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,Aginakm1
 

Kürzlich hochgeladen (20)

Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptx
 
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
 

C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

  • 1. Capital ProjectsRisk Development and ManagementChristiane KampschulteParsons Brinckerhoff16th August 2010 2:30-3:15pm The most comprehensive Oracle applications & technology content under one roof
  • 2. Introduction The presentation addresses Risk management in terms of quantitative Risk Management not qualitative scoring methods. The presentation compares two projects. To validate the effectiveness of Risk Management statistically we require more examples and case studies. None of the Project are as per “Best Practice” which is dealt with at the end.
  • 3. Introduction There are a number of uncertainties in every project that have a potential to affect the outcome. Commonly, the provision for these uncertainties is taken care of by adding a percentage of costs as contingency to the cost estimate and adding a time contingency at the end of the longest path.
  • 4. Introduction The paper compares 2 similar projects and: Highlights the importance of calculating and documenting a meaningful cost and schedule contingency. Illustrates the benefits of project cost and time estimate range reviews.
  • 5. CASE STUDY A : Mining Infrastructure Project in Western Australia
  • 6. Rail Construction TD-Graph Capping Tracklaying Bridges Commissioning Activities Target Track Actual Track Layed Hand Lay2 Hand layed Cloud Break PORT 250 COMMISSIONING & Stockpiling Target No Later then date 220 190 Bridge 8 Chainage (km) 160 Bridge 7 Bridge 6 Bridge 5 130 100 Bridge 4 Bridge 3 70 Bridge 2 40 Bridge 1 Actual Track 10 Layed Hand layed Loop 16-Nov-07 21-Sep-07 11-Jan-08 27-Jun-08 2-May-08 27-Jul-07 7-Mar-08 1-Jun-07 6-Apr-07 -20 CASE STUDIES
  • 7. Cost and time estimates were based on information given by Engineering Design Team. The project started with a single point cost and time estimate. The single point estimate resulted in a contingency linked to the time and cost estimate. This was a fixed percentage added to the cost estimate and a fixed number of days added to the project programme. Case A
  • 8. Execution phase risk management workshops were conducted at regular intervals but inputs were taken from a Safety perspective and risk were not quantified. The contractors were required to submit a time scaled detailed network program, hours spent and forecasts. No alliance partner's forecast showed schedule or cost overrun. Schedule updates always showed a date within the required dates. Case A
  • 9. Variations were approved while the cost value did not surpass the project single point estimate. No other number than the original estimate was ever communicated for time and cost. Case A
  • 10. The project was being built in a Cyclone prone area and was under a high cyclone danger zone. A cyclone hit the area and one of the 3 worker accommodation camps a was damaged. Case A
  • 11. This incident triggered the intensive review of the project’s time estimate and cost estimate with focus on the assumptions made for calculating the contingency. The finding were that the scope hat deviated from the initial estimate. The assumptions made for the calculation of time and cost contingency were not treaceableso couldn’t not be evaluated for their adequateness. Case A
  • 12. CASE STUDY B : Coal Terminal Project in New South Wales
  • 13.
  • 14. A Range Analysis Workshop (RAW) was held to identify and quantify all risks and uncertainties that could cause a deviation to the estimate. Particular attention was paid to the facilitation of this workshop where project participants were encouraged to come up with extreme outcomes of the uncertainties. Case B
  • 15. Examples for risk sources considered in the RAW were: Availability of area or facility, staff availability and major equipment. Uncertainty over productivity level on the project. Adverse environmental conditions Specific risks identified for the project that have the potential to impact the project like geotechnical conditions, Industrial Relations, Quality. Case B – Risk sources
  • 16. For awarded contracts, capital cost sources that were considered were uncertainty associated with variations that have been submitted, uncertainty with forecast variation and uncertainty associated with emerging trends. Case B - Risk sources
  • 17. Capital cost inputs that were considered for un-awarded contracts typically included variations in project scope that were being developed at that stage, variations in unit rates considering the time lag between feasibility study and project execution, variations in quantities-both materials and work hours which are impacted by the stage of the design process and risk events specific to the project. Case B - Risk sources
  • 18. The schedule risk profile was developed through a summary risk schedule developed from the project schedule that captured the key milestones and the associated near critical activities. Duration ranges were developed for these activities in a facilitated workshop. These ranges were defined by the minimum case, maximum case, P10, P90 scenarios and probability of achieving or improving the task duration. The ranges were then used to develop a probability distribution for the activity. Correlations between the ranged schedule activities were also included. Case B – Schedule range analysis
  • 19. Case B – Schedule range analysis Key Drivers of the Project completion milestone
  • 20. Awarded contracts – models cost uncertainty due to variations. Un-awarded contracts – modeled uncertainty associated with the estimate of these contracts. Owners – models uncertainty associated with owner’s costs. Project Risks – models the risks that have been identified. Project Scope – models potential scope changes for the project. Schedule – models the time variable uncertainty associated with schedule duration risk.   Case B – CAPEX range analysis
  • 21. Case B - CAPEX Range analysis Schedule range analysis Cost range analysis
  • 22. Case B - Risk model Mean P95 P5 Capital Cost Key Capital risk drivers
  • 24.
  • 25. Integrated cost-schedule risk analysis The purpose of this is to estimate the appropriate level of cost contingency reserve on projects and also to include the impact of schedule risk on cost risk. Best Practice (as per AACE recommendation)
  • 26. Start with a “good” logic driven schedule (summary schedule) Assign cost loaded resources to the activities in the schedule Take a risk driven approach. Use the “Risk Register”. Collect good risk data from facilitated workshop or one to one interview with stakeholders or project participants. Derive contingency reserve of time and cost, prioritize the risks and mitigating them in steps. Best Practice
  • 27. Risks are identified during a qualitative risk analysis of the project. This leads to a list of prioritized risks which are characterized by their probability and impact ranges. A best practice project schedule which is resource loaded. The “Neat Estimate” (an estimate without contingency) assigned to the activities in the schedule. Best Practice - Inputs
  • 28. From the inputs, a risk model would be created in a readily available software like “Primavera Risk Analysis V8” (Pertmaster) ready to run a number of iterations simulating the project Risk # 01 – P50% Factors 0.95,1.05,1.15 Activity A Activity B Best Practice - Model
  • 29.
  • 31. Answers we get Which risks are most important to the achievement of the project schedule and cost estimate? How likely are the project plan’s cost and schedule targets to be met - taking into account the risk that may affect that plan?  How much contingency of time and cost needs to be provided to meet the risk threshold of the project management or other stakeholders? 
  • 32. Tell us what you think… http://feedback.insync10.com.au Questions to : adatta_project@yahoo.comc.kampschulte@gmx.de