25 nov pi planning using hdm moldova
1. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Hamid Zarghampour
2010-11-25
Moldova
Planning using HDM
2. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Asset Management today
Set Goals and Objectives
Collect Inventory and Condition Data
Rates of Deterioration
Performance Standards & Measures
Life-Cycle Cost Analysis
Investment Strategies
Programs, Projects, and Practices
Monitoring Feedback and Adjustments
3. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management
Organisation
Information/
Data
Road works
Effect
Road
Deterioration
HDM 4
1 5432
4. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Requirements
Needs
Prioritized needs Programme Annual
Activities
Existing plans, Strategies
Policies
Government, Users, Interested parties, etc.
Needs
PDS
Requirements and
Prioritized Needs
This is what RA
attempt to do
Programme
These are RA’s
modes/Procedures
Action Plan
RA Activities
this year
Management Information PresentationPlanningCompetences
1 5432
Goals and Objectives
“Doing things right”
“Doing right things”
5. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management
Organisation
Information/
Data
Presentation
Technique
Case StudiesHDM 4
1 5432
6. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
Management cycle
HDM 4
Maintenance Management
Management Function and HDM4
Structure of HDM4
Technical analysis tools within HDM 4
Road Engineering from Art to Science
Road Deterioration concept and models in HDM 4
Road Works Classification in HDM 4
Road works Effects
Economy
DHM 4, Economical Indicators
7. Design and Implementation of Road Maintenance Reform. Republic of Moldova
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Important Elements in the plan:
Name of section
Geographical location
Length
Type of works
Cost estimates
Timing of work
Traffic
Packaging appropriate
mix of Road works
with regards to
available budgetV ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä tn in g a v
v ä g y ta n s tills tå n d
S lä n te r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
B ä r ig h e ts m ä tn in g
F a llv ik ts d e f le k t o m e t e r
April- September
August
October
December- March
March - October
September- November
New plan
November- December
August-
October
Road Class
Paved Roads Unpaved Roads
Good Fair Poor Bad Good Poor Bad
National Roads 4 6 8 >8 - - -
Secondary 5 7 9 >9 6 8 10
8. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4, Tool for Road AM
Maintenance Management
Planning:
Estimation of expenditure
Forecasting of various budget vs. road development
Policy making, dialog with financier (Government)
Programming:
Estimation of expenditure for different works and activities
Key aspect of programming is prioritization of work
Find the best use of the constrained budget
Multi-year works and expenditure program
Cost-benefit analysis are required
9. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4, Tool for Road AM
Maintenance Management
Preparation:
Short term planning
Road schemes are packaged for implementation
Designs are refined and prepared in more detail
Bills of quantities and detail costing are made
Detailed cost-benefit is carried out to confirm the feasibility project
Operation:
Refers to the on-going activities
scheduling of works such as monitoring in terms of: labour,
equipment and materials and recording of works completed, etc...
10. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Change in Management Process
Activity Time horizon Spatial Coverage Information Mode of
computer
Operation
Planning Long term
(Strategic)
Network Wide Coarse
Summary Automatic
Programming Medium term
(Tactical)
Network
Sub Network
Preparation Budget Year Scheme Level
Section
Operation Immediate/
Short term
Scheme Level
Sub Section
Fine/detailed Interactive
IQL
11. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Information, Data
What kind of information do we need?
It is always dependent on:
What decisions do we need to make?
What information/data are required to make these decisions?
Can we afford to collect the data?
If it needs updating, can we afford to keep data current over time?
Guiding Principle
Collect only the data you need!
Collect it only when you need to!
The level of detail should be appropriate for the decisions being
made:
Network level data for network level analyses
project level for project level analyses
12. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
13. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
14. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
15. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
16. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Structure of HDM 4
Core Data Objects in HDM 4 are defined in the
following data managers:
HDM-4 Configuration
Defines the default data to be used in the applications
Road Network
Defines the characteristic of road sections
Vehicle fleet
Defines the characteristic of the vehicle fleet
Road works
Defines Maintenance and improvement standards incl. unit costs
17. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Technical analysis within HDM
4 Road Deterioration (RD)
Predicts pavement deterioration for:
Bituminous
Concrete and
Unsealed roads
Works Effects (WE)
Simulates:
The effects of road works on pavement condition
Determine the corresponding costs
18. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Technical analysis within HDM
4.. Road User Effects (RUE)
Determines:
Costs of vehicle operation
Travel time
Road accidents (only in the CBA)
Social and Environment Effects (SEE)
Determines:
The effects of vehicle emissions
Energy consumption
19. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4 processes for analysis
Calculate
Annual effects and
costs
Calculate
Road
deterioration
Calculate
Road
User Effect
VOC, time, etc
Calculate
Social and
Environmental
Effects
Calculate
Road Works
Effect s
Add Exogenous
Costs and
Benefits
Return
20. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
Management cycle
HDM 4
Maintenance Management
Management Function and HDM4
Structure of HDM4
Technical analysis tools within HDM 4
Road Engineering from Art to Science
Road Deterioration concept and models in HDM 4
Road Works Classification in HDM 4
Road works Effects
Economy
DHM 4, Economical Indicators
22. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Engineering from Art to Science
q
Experience
1900-1960
CBR
60-
AASHTO
70-
Mechanistic
approach80-
HDM III
90-
FEM ”Pavement history”
“Homogenous sections”
23. Design and Implementation of Road Maintenance Reform. Republic of Moldova
V ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä t n in g a v
v ä g y t a n s t ills t å n d
S lä n t e r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
F ö r s t ä r k n in g s la g e r
T jä ls s k y d d
U p p f r y s a n d e b lo c k
Ö v e r b y g g n a d
m a t e r ia lv a l o c h d im e n s io n e r in g
T e r r a s s m a t e r ia l
A v v a t t n in g
D r ä n e r in g
B ä r ig h e t s m ä t n in g
F a llv ik t s d e f le k t o m e t e r
Road Construction today
24. Design and Implementation of Road Maintenance Reform. Republic of Moldova
V ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä t n in g a v
v ä g y t a n s t ills t å n d
S lä n t e r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
F ö r s t ä r k n in g s la g e r
T jä ls s k y d d
U p p f r y s a n d e b lo c k
Ö v e r b y g g n a d
m a t e r ia lv a l o c h d im e n s io n e r in g
T e r r a s s m a t e r ia l
A v v a t t n in g
D r ä n e r in g
B ä r ig h e t s m ä t n in g
F a llv ik t s d e f le k t o m e t e r
Climate
Traffic
Design Criterion
Wear
Stability
Deformation, (plastic)
Fatigue
Frost heave action, etc…
Road Construction today
25. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Deterioration concept in HDM 4:
is a function of:
original design
material types
construction quality
traffic volume and axle loading
road geometry
pavement age
environmental condition
maintenance policy pursued
26. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Rate of wear:
is a function of:
Mix design
Material quality (BM value)
Studded tires
Speed
Carriage width
27. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Fatigue:
is mostly caused by:
heavy vehicles
Other reasons:
If it is occurred on early stage after reconstruction, construction
service life is ended
not good enough mix design
inadequate bearing capacity
etc…
35. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM-4 Deterioration Models
36. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Scope of modeling road deterioration
Physical environments
Climatic Zones
Pavement
Rigid concrete
wide range of flexible pavements
Unsealed pavement
Drainage effects
shoulders deterioration, (effects on pavement strength)
37. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Classes of Models
Mechanistic
use sound fundamental theories of soil mechanic to predict pavement
behavior
Empirical
based on statistical analysis of locally deterioration trends
Structural mechanistic-empirical approach
based on identifying the functional form and primary variables from
external sources
statistical techniques to quantify their impact
38. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Pavement Classification System (Bituminous Pavement)
Pavement Type
Asphalt Mix on Asphalt Base
Asphalt Mix on Granular Base
Asphalt Mix on Stabilized Base
Asphalt Mix on Pavement Base
Surface Type
Asphalt Concrete
Hot Rolled Asphalt
Polymer Modified asphalt dressing
Rubberized Asphalt Concrete
Cold Mix
Porous Asphalt
Stone Mastic Asphalt
39. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Pavement Classification System (Bituminous Pavement)
Pavement Type
Surface Treatment on Asphalt Base
Surface Treatment on Granular Base
Surface Treatment on Stabilized Base
Surface Treatment on Pavement Base
Surface Type
Single Bituminous Surface Dressing
Double Bituminous Surface Dressing
Cold Mix
Cape Seal
Slurry Seal
Penetration MacAdam
40. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Modeling Framework
For each pavement type:
a generic model applies to describes the pavement deterioration
After maintenance treatments:
the generic pavement type can change
Pavement Strength:
is characterized by “Adjusted Structural Number” (SNP)
The SNP applies a weighting factor (prevent over-prediction of
pavement strength with increase of depth)
Construction Quality:
Construction Defect Indicators: CDS (surface) and CDB (Base)
CDS: 0.5-1,5 from brittle to soft depending on Binder content
CDB: 0-1,5, No defects or several defects
47. Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
Management cycle
HDM 4
Maintenance Management
Management Function and HDM4
Structure of HDM4
Technical analysis tools within HDM 4
Road Engineering from Art to Science
Road Deterioration concept and models in HDM 4
Road Works Classification in HDM 4
Road works Effects
Economy
DHM 4, Economical Indicators
48. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Works
Bituminous
Pavement
49. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Works classification
Routine Maintenance
Periodic Maintenance
Special Works
Improvement Works
Construction Works
50. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Routine Maintenance
Routine Pavement
Patching
Edge-repair
Crack sealing
Spot-re-gravelling
Shoulders repair, etc.
Drainage
Culvert repairs
Clearing side drains, etc…
Routine Various
Vegetation control
Markings
Sign, etc…
51. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Periodic Maintenance
Preventive Treatment
Fog seal
Rejuvenation
Rehabilitation
Thick overlay
Mill and replace
Inlay
Resurfacing
Surface dressing
Slurry seal
Cape seal
Thin overlay, re-gravelling
Reconstruction
Partial reconstruction
Full pavement
reconstruction
52. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Special
Winter
Snow removal
Salting/gritting, etc…
Emergency
Cleaning debris
Traffic accident removal, etc..
Repairing/washout
53. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Improvement
Widening
Partial widening
Lane addition
Realignment
Horizontal and vertical geometric
improvement
Junction improvement
Off-carriageway
Shoulders addition
Shoulders upgrading
NMT lane addition
Side drain improvement, etc…
54. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Construction
Upgrading
Chang of surface Class
Unsealed surface to Bituminous
Bituminous to Concrete Pavement
New Section
55. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs
Pavement deterioration and road works
Summary of annual pavement condition
Quantities of road works
Details of annual road work costs
Schedule of road works
Road user effects
Summary of Road User Cost
Average traffic speed
Vehicle speed and capacity ratio
Vehicle emission
Energy consumption
56. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs
Economical Indicators
Annual cost streams
Discounted cash flows
Net Present Value (NPV)
Economic Internal Rate of Return (IRR)
Benefit Cost Ration (BCR)
First Year Benefit (FYB)
57. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs…
Net Present Value (NPV)
The higher NPV the higher Benefit
Without budget constrain, shall the alternative with highest NPV be chosen
Comments
Larger investment tends to have higher NPV
NPV is proportional to the project cost if IRR is the same
Economic Internal Rate of Return (IRR)
IRR = the discounted rate at which the NPV is equal to 0
Gives no indications of the size of costs or benefits of an investment
Acts as a guide to the profitability of the investment
The higher the better
If IRR > Discount rate, the investment is said to be economically justified
58. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs…
Benefit Cost Ration (BCR)
Ratio indicating the profitability of one option relative to base option
Gives no indications of the size of costs or benefits of an investment
First Year Benefit (FYB)
FYB is defined as the ratio in present of the net benefit realized in
the first year after construction
Rough guide to project timing
If FYB > discounted rate, the project should go ahead
If FYB < discounted rate the project should be delayed until it satisfies
the criterion
59. Design and Implementation of Road Maintenance Reform. Republic of Moldova
Asset Management today
Set Goals and Objectives
Collect Inventory and Condition Data
Rates of Deterioration
Performance Standards & Measures
Life-Cycle Cost Analysis
Investment Strategies
Programs, Projects, and Practices
Monitoring Feedback and Adjustments
60. Design and Implementation of Road Maintenance Reform. Republic of Moldova
For any kind of planning (programme, Project)!
We need Data/Information:
Road Network
Work standards
Traffic data (Vehicle Fleet)
61. Design and Implementation of Road Maintenance Reform. Republic of Moldova
1 december 2010
We need to prepare
- More than 1? If så:
- SPECIFY
- Visualising section’s conditions
- Map (GIS)
-
-Veify
-Cost estimates
-Maintenance activities
-Routine
-Periodic
- Rehabilitation
- Terminology
- VF available
- Previous studies?
62. Design and Implementation of Road Maintenance Reform. Republic of Moldova
GIS
Data collection
Evaluation
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Systems
Asset Evaluation
Cost-Benefits
Ministry, RA, RU
Condition Data and analysis
Visual inspections
63. Design and Implementation of Road Maintenance Reform. Republic of Moldova
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Condition Data and analysis
Need for Inspection Manual
- Will be recommended
IRI
-For this study:
- 900 km of:
-National and Secondary roads
- Analysis tool
- HDM 4
- Overview next week:
- Programme
- Project
•Modelling RN
•Review results
•Writing report
Next week
Script for selection of
Homogenous sections
is available
Hinweis der Redaktion
While there is no one method that will fit every situation or agency, all asset management structures have certain basic elements in their approach. These include:
-- Setting Goals and Objectives
-- Collecting appropriate data
-- Calculating and analyzing deterioration rates
-- Setting performance standards and measuring progress
-- Use of life-cycle cost analyses
-- Developing investment strategies
-- Selecting programs and projects consistent with the selected strategy
-- Monitoring the results and making adjustments if necessary.
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
So what is driving the move toward asset management?
Our transportation systems are mature ones with many roads and bridges built 30 to 40 years ago. Consequently, we are facing a period of re-investing in existing facilities rather than building new ones. This has been reflected in federal funding where they are moving from strictly capital funding to more flexible funding for preventive maintenance.
Because of the reports I mentioned earlier, the general public expects us to spend their money wisely and efficiently. And they are demanding greater accountability.
We have seen a new breed of leaders coming into transportation. Rather than coming from the engineering field, many of today’s leaders are coming from the political arena or business community. And they are bringing with them a sensitivity to constituents and management concepts and principles that worked in business.
Fourth, there have been vast improvements in computers and technology that make it possible to do things today that we could never do before.
Finally, there is the well-recognized relationship between an efficient, productive transportation system and economic growth.
[GO TO NEXT SLIDE]
In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm.
ARE THERE ANY QUESTIONS?
[GO TO NEXT SLIDE]
While there is no one method that will fit every situation or agency, all asset management structures have certain basic elements in their approach. These include:
-- Setting Goals and Objectives
-- Collecting appropriate data
-- Calculating and analyzing deterioration rates
-- Setting performance standards and measuring progress
-- Use of life-cycle cost analyses
-- Developing investment strategies
-- Selecting programs and projects consistent with the selected strategy
-- Monitoring the results and making adjustments if necessary.
[GO TO NEXT SLIDE]