Design and Implementation of Road Maintenance Reform. Republic of Moldova
Hamid Zarghampour
2010-11-25
Moldova
Planning using HDM
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Asset Management today
 Set Goals and Objectives
 Collect Inventory and Condition Data
 Rates of Deterioration
 Performance Standards & Measures
 Life-Cycle Cost Analysis
 Investment Strategies
 Programs, Projects, and Practices
 Monitoring Feedback and Adjustments
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management
Organisation
Information/
Data
Road works
Effect
Road
Deterioration
HDM 4
1 5432
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Requirements
Needs
Prioritized needs Programme Annual
Activities
Existing plans, Strategies
Policies
Government, Users, Interested parties, etc.
Needs
PDS
Requirements and
Prioritized Needs
This is what RA
attempt to do
Programme
These are RA’s
modes/Procedures
Action Plan
RA Activities
this year
Management Information PresentationPlanningCompetences
1 5432
Goals and Objectives
“Doing things right”
“Doing right things”
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management
Organisation
Information/
Data
Presentation
Technique
Case StudiesHDM 4
1 5432
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
 Management cycle
 HDM 4
­ Maintenance Management
­ Management Function and HDM4
­ Structure of HDM4
­ Technical analysis tools within HDM 4
 Road Engineering from Art to Science
­ Road Deterioration concept and models in HDM 4
­ Road Works Classification in HDM 4
­ Road works Effects
 Economy
­ DHM 4, Economical Indicators
Design and Implementation of Road Maintenance Reform. Republic of Moldova
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Important Elements in the plan:
 Name of section
 Geographical location
 Length
Type of works
 Cost estimates
 Timing of work
Traffic
Packaging appropriate
mix of Road works
with regards to
available budgetV ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä tn in g a v
v ä g y ta n s tills tå n d
S lä n te r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
B ä r ig h e ts m ä tn in g
F a llv ik ts d e f le k t o m e t e r
April- September
August
October
December- March
March - October
September- November
New plan
November- December
August-
October
Road Class
Paved Roads Unpaved Roads
Good Fair Poor Bad Good Poor Bad
National Roads 4 6 8 >8 - - -
Secondary 5 7 9 >9 6 8 10
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4, Tool for Road AM
 Maintenance Management
 Planning:
 Estimation of expenditure
 Forecasting of various budget vs. road development
 Policy making, dialog with financier (Government)
 Programming:
 Estimation of expenditure for different works and activities
 Key aspect of programming is prioritization of work
 Find the best use of the constrained budget
 Multi-year works and expenditure program
 Cost-benefit analysis are required
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4, Tool for Road AM
 Maintenance Management
 Preparation:
 Short term planning
 Road schemes are packaged for implementation
 Designs are refined and prepared in more detail
 Bills of quantities and detail costing are made
 Detailed cost-benefit is carried out to confirm the feasibility project
 Operation:
 Refers to the on-going activities
 scheduling of works such as monitoring in terms of: labour,
equipment and materials and recording of works completed, etc...
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Change in Management Process
Activity Time horizon Spatial Coverage Information Mode of
computer
Operation
Planning Long term
(Strategic)
Network Wide Coarse
Summary Automatic
Programming Medium term
(Tactical)
Network
Sub Network
Preparation Budget Year Scheme Level
Section
Operation Immediate/
Short term
Scheme Level
Sub Section
Fine/detailed Interactive
IQL
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Information, Data
 What kind of information do we need?
 It is always dependent on:
­ What decisions do we need to make?
­ What information/data are required to make these decisions?
­ Can we afford to collect the data?
­ If it needs updating, can we afford to keep data current over time?
 Guiding Principle
 Collect only the data you need!
 Collect it only when you need to!
 The level of detail should be appropriate for the decisions being
made:
­ Network level data for network level analyses
­ project level for project level analyses
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Management function and HDM 4
Management
Function
Common description HDM 4 Application
Planning - Strategic Analysis System
- Network Planning
- Pavement Management System
- Programme analysis System
HDM 4
Strategy Analysis
Programming -Pavement Management System
-Budgeting System
HDM 4
Programme Analysis
Preparation - Project Analysis System
. Pavement Management System
- Pavement/Overlay design System
- Contract procurement System
HDM 4
Project Analysis
Operation - Project Management System
- Maintenance Management System
- Equipment Management System
- Financial Management/Accounting System
Not addressed by
HDM
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Structure of HDM 4
 Core Data Objects in HDM 4 are defined in the
following data managers:
 HDM-4 Configuration
 Defines the default data to be used in the applications
 Road Network
 Defines the characteristic of road sections
 Vehicle fleet
 Defines the characteristic of the vehicle fleet
 Road works
 Defines Maintenance and improvement standards incl. unit costs
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Technical analysis within HDM
4 Road Deterioration (RD)
 Predicts pavement deterioration for:
 Bituminous
 Concrete and
 Unsealed roads
 Works Effects (WE)
 Simulates:
 The effects of road works on pavement condition
 Determine the corresponding costs
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Technical analysis within HDM
4.. Road User Effects (RUE)
 Determines:
 Costs of vehicle operation
 Travel time
 Road accidents (only in the CBA)
 Social and Environment Effects (SEE)
 Determines:
 The effects of vehicle emissions
 Energy consumption
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4 processes for analysis
Calculate
Annual effects and
costs
Calculate
Road
deterioration
Calculate
Road
User Effect
VOC, time, etc
Calculate
Social and
Environmental
Effects
Calculate
Road Works
Effect s
Add Exogenous
Costs and
Benefits
Return
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
 Management cycle
 HDM 4
­ Maintenance Management
­ Management Function and HDM4
­ Structure of HDM4
­ Technical analysis tools within HDM 4
 Road Engineering from Art to Science
­ Road Deterioration concept and models in HDM 4
­ Road Works Classification in HDM 4
­ Road works Effects
 Economy
­ DHM 4, Economical Indicators
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Deterioration
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Engineering from Art to Science
q
Experience
1900-1960
CBR
60-
AASHTO
70-
Mechanistic
approach80-
HDM III
90-
FEM ”Pavement history”
“Homogenous sections”
Design and Implementation of Road Maintenance Reform. Republic of Moldova
V ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä t n in g a v
v ä g y t a n s t ills t å n d
S lä n t e r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
F ö r s t ä r k n in g s la g e r
T jä ls s k y d d
U p p f r y s a n d e b lo c k
Ö v e r b y g g n a d
m a t e r ia lv a l o c h d im e n s io n e r in g
T e r r a s s m a t e r ia l
A v v a t t n in g
D r ä n e r in g
B ä r ig h e t s m ä t n in g
F a llv ik t s d e f le k t o m e t e r
Road Construction today
Design and Implementation of Road Maintenance Reform. Republic of Moldova
V ä g m a r k e r in g
V ä g t r u m m o r
B e r g a r b e t e n , b o r r n in g
s p r ä n g n in gM ä t n in g a v
v ä g y t a n s t ills t å n d
S lä n t e r
E r o s io n s s k y d d
B e lä g g n in g
B ä r la g e r
F ö r s t ä r k n in g s la g e r
T jä ls s k y d d
U p p f r y s a n d e b lo c k
Ö v e r b y g g n a d
m a t e r ia lv a l o c h d im e n s io n e r in g
T e r r a s s m a t e r ia l
A v v a t t n in g
D r ä n e r in g
B ä r ig h e t s m ä t n in g
F a llv ik t s d e f le k t o m e t e r
Climate
Traffic
 Design Criterion
­ Wear
­ Stability
­ Deformation, (plastic)
­ Fatigue
­ Frost heave action, etc…
Road Construction today
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Deterioration concept in HDM 4:
 is a function of:
 original design
 material types
 construction quality
 traffic volume and axle loading
 road geometry
 pavement age
 environmental condition
 maintenance policy pursued
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Rate of wear:
 is a function of:
 Mix design
 Material quality (BM value)
 Studded tires
 Speed
 Carriage width
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Fatigue:
 is mostly caused by:
 heavy vehicles
 Other reasons:
 If it is occurred on early stage after reconstruction, construction
­ service life is ended
­ not good enough mix design
­ inadequate bearing capacity
­ etc…
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Frost heave action
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Bearing Capacity
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Plastic deformation
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Bleeding
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Ravelling
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Cracking
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Separation
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM-4 Deterioration Models
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Scope of modeling road deterioration
 Physical environments
 Climatic Zones
 Pavement
 Rigid concrete
 wide range of flexible pavements
 Unsealed pavement
 Drainage effects
 shoulders deterioration, (effects on pavement strength)
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Classes of Models
 Mechanistic
 use sound fundamental theories of soil mechanic to predict pavement
behavior
 Empirical
 based on statistical analysis of locally deterioration trends
 Structural mechanistic-empirical approach
 based on identifying the functional form and primary variables from
external sources
­ statistical techniques to quantify their impact
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Pavement Classification System (Bituminous Pavement)
 Pavement Type
 Asphalt Mix on Asphalt Base
 Asphalt Mix on Granular Base
 Asphalt Mix on Stabilized Base
 Asphalt Mix on Pavement Base
 Surface Type
 Asphalt Concrete
 Hot Rolled Asphalt
 Polymer Modified asphalt dressing
 Rubberized Asphalt Concrete
 Cold Mix
 Porous Asphalt
 Stone Mastic Asphalt
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Pavement Classification System (Bituminous Pavement)
 Pavement Type
 Surface Treatment on Asphalt Base
 Surface Treatment on Granular Base
 Surface Treatment on Stabilized Base
 Surface Treatment on Pavement Base
 Surface Type
 Single Bituminous Surface Dressing
 Double Bituminous Surface Dressing
 Cold Mix
 Cape Seal
 Slurry Seal
 Penetration MacAdam
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Modeling Framework
 For each pavement type:
 a generic model applies to describes the pavement deterioration
 After maintenance treatments:
 the generic pavement type can change
 Pavement Strength:
 is characterized by “Adjusted Structural Number” (SNP)
 The SNP applies a weighting factor (prevent over-prediction of
pavement strength with increase of depth)
 Construction Quality:
 Construction Defect Indicators: CDS (surface) and CDB (Base)
­ CDS: 0.5-1,5 from brittle to soft depending on Binder content
­ CDB: 0-1,5, No defects or several defects
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Concrete
Joint spalling
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Concrete
Joint spalling
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Concrete
Joint spalling
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Design and Implementation of Road Maintenance Reform. Republic of Moldova
HDM 4
 Management cycle
 HDM 4
­ Maintenance Management
­ Management Function and HDM4
­ Structure of HDM4
­ Technical analysis tools within HDM 4
 Road Engineering from Art to Science
­ Road Deterioration concept and models in HDM 4
­ Road Works Classification in HDM 4
­ Road works Effects
 Economy
­ DHM 4, Economical Indicators
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Works
Bituminous
Pavement
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Road Works classification
 Routine Maintenance
 Periodic Maintenance
 Special Works
 Improvement Works
 Construction Works
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Routine Maintenance
 Routine Pavement
 Patching
 Edge-repair
 Crack sealing
 Spot-re-gravelling
 Shoulders repair, etc.
 Drainage
 Culvert repairs
 Clearing side drains, etc…
 Routine Various
 Vegetation control
 Markings
 Sign, etc…
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Periodic Maintenance
 Preventive Treatment
 Fog seal
 Rejuvenation
 Rehabilitation
 Thick overlay
 Mill and replace
 Inlay
 Resurfacing
 Surface dressing
 Slurry seal
 Cape seal
 Thin overlay, re-gravelling
 Reconstruction
 Partial reconstruction
 Full pavement
reconstruction
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Special
 Winter
 Snow removal
 Salting/gritting, etc…
 Emergency
 Cleaning debris
 Traffic accident removal, etc..
 Repairing/washout
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Improvement
 Widening
 Partial widening
 Lane addition
 Realignment
 Horizontal and vertical geometric
improvement
 Junction improvement
 Off-carriageway
 Shoulders addition
 Shoulders upgrading
 NMT lane addition
 Side drain improvement, etc…
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Construction
 Upgrading
 Chang of surface Class
­ Unsealed surface to Bituminous
­ Bituminous to Concrete Pavement
 New Section
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs
 Pavement deterioration and road works
 Summary of annual pavement condition
 Quantities of road works
 Details of annual road work costs
 Schedule of road works
 Road user effects
 Summary of Road User Cost
 Average traffic speed
 Vehicle speed and capacity ratio
 Vehicle emission
 Energy consumption
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs
 Economical Indicators
 Annual cost streams
 Discounted cash flows
 Net Present Value (NPV)
 Economic Internal Rate of Return (IRR)
 Benefit Cost Ration (BCR)
 First Year Benefit (FYB)
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs…
 Net Present Value (NPV)
 The higher NPV the higher Benefit
 Without budget constrain, shall the alternative with highest NPV be chosen
 Comments
 Larger investment tends to have higher NPV
 NPV is proportional to the project cost if IRR is the same
 Economic Internal Rate of Return (IRR)
 IRR = the discounted rate at which the NPV is equal to 0
 Gives no indications of the size of costs or benefits of an investment
 Acts as a guide to the profitability of the investment
 The higher the better
 If IRR > Discount rate, the investment is said to be economically justified
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Outputs…
 Benefit Cost Ration (BCR)
 Ratio indicating the profitability of one option relative to base option
 Gives no indications of the size of costs or benefits of an investment
 First Year Benefit (FYB)
 FYB is defined as the ratio in present of the net benefit realized in
the first year after construction
 Rough guide to project timing
 If FYB > discounted rate, the project should go ahead
 If FYB < discounted rate the project should be delayed until it satisfies
the criterion
Design and Implementation of Road Maintenance Reform. Republic of Moldova
Asset Management today
 Set Goals and Objectives
 Collect Inventory and Condition Data
 Rates of Deterioration
 Performance Standards & Measures
 Life-Cycle Cost Analysis
 Investment Strategies
 Programs, Projects, and Practices
 Monitoring Feedback and Adjustments
Design and Implementation of Road Maintenance Reform. Republic of Moldova
For any kind of planning (programme, Project)!
We need Data/Information:
Road Network
Work standards
Traffic data (Vehicle Fleet)
Design and Implementation of Road Maintenance Reform. Republic of Moldova
1 december 2010
We need to prepare
- More than 1? If så:
- SPECIFY
- Visualising section’s conditions
- Map (GIS)
-
-Veify
-Cost estimates
-Maintenance activities
-Routine
-Periodic
- Rehabilitation
- Terminology
- VF available
- Previous studies?
Design and Implementation of Road Maintenance Reform. Republic of Moldova
GIS
Data collection
Evaluation
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Systems
Asset Evaluation
Cost-Benefits
Ministry, RA, RU
Condition Data and analysis
Visual inspections
Design and Implementation of Road Maintenance Reform. Republic of Moldova
0-500 500-1500 1500-4000 4000-7000 7000-
0
20
40
60
80
100
120
Condition Data and analysis
Need for Inspection Manual
- Will be recommended
IRI
-For this study:
- 900 km of:
-National and Secondary roads
- Analysis tool
- HDM 4
- Overview next week:
- Programme
- Project
•Modelling RN
•Review results
•Writing report
Next week
Script for selection of
Homogenous sections
is available

Weitere ähnliche Inhalte

Andere mochten auch

Andere mochten auch (9)

ANTREC Moldova (eng)
ANTREC Moldova (eng)ANTREC Moldova (eng)
ANTREC Moldova (eng)
 
Moldova
MoldovaMoldova
Moldova
 
Moldávia
MoldáviaMoldávia
Moldávia
 
Prezentare Moldova
Prezentare MoldovaPrezentare Moldova
Prezentare Moldova
 
Republic of Moldova
Republic of MoldovaRepublic of Moldova
Republic of Moldova
 
Moldova
Moldova Moldova
Moldova
 
Proiect de lectie lb engleza
Proiect de lectie lb englezaProiect de lectie lb engleza
Proiect de lectie lb engleza
 
Moldova tourist destination
Moldova tourist destinationMoldova tourist destination
Moldova tourist destination
 
Republic of Moldova
Republic of MoldovaRepublic of Moldova
Republic of Moldova
 

Ähnlich wie 25 nov pi planning using hdm moldova

2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Studypyoungkyova
 
11. NECS 2016 _Current status and the way ahead for road development in the ...
11.  NECS 2016 _Current status and the way ahead for road development in the ...11.  NECS 2016 _Current status and the way ahead for road development in the ...
11. NECS 2016 _Current status and the way ahead for road development in the ...FICCINorthEast
 
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal ho
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal hoPavement Management, PMS, Asset Management, Road Maintenance planningfinal ho
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal hoHamid62
 
How Are Route Planning and Route Optimisation Not The Same?.pdf
How Are Route Planning and Route Optimisation Not The Same?.pdfHow Are Route Planning and Route Optimisation Not The Same?.pdf
How Are Route Planning and Route Optimisation Not The Same?.pdfTrackobit
 
Performance Measures for Highway Capacity Decision Making
Performance Measures forHighway Capacity Decision MakingPerformance Measures forHighway Capacity Decision Making
Performance Measures for Highway Capacity Decision Makingpyoungkyova
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Sok-Tharath CHREUNG
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvkGlenn Van_kooijk
 
Flour Presentation MEED MENA 2014
Flour Presentation MEED MENA 2014Flour Presentation MEED MENA 2014
Flour Presentation MEED MENA 2014Ibrahim Al-Hudhaif
 
EU ITS-2452 - The Why, Where, What and How of ITS Egypt Case Study Final
EU ITS-2452  - The Why, Where, What and How of ITS Egypt Case Study FinalEU ITS-2452  - The Why, Where, What and How of ITS Egypt Case Study Final
EU ITS-2452 - The Why, Where, What and How of ITS Egypt Case Study FinalBarry Moore MSc CEng MIET
 
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Avinash Shabade
 
IAQM AGM 2016 - Dr Beth Conlan, Ricardo
IAQM AGM 2016 - Dr Beth Conlan, RicardoIAQM AGM 2016 - Dr Beth Conlan, Ricardo
IAQM AGM 2016 - Dr Beth Conlan, RicardoIES / IAQM
 
Clear Air Zones – What are Local Authorities Proposing? - Nigel Bellamy
Clear Air Zones – What are Local Authorities Proposing? - Nigel BellamyClear Air Zones – What are Local Authorities Proposing? - Nigel Bellamy
Clear Air Zones – What are Local Authorities Proposing? - Nigel BellamyIES / IAQM
 
The Road Efficiency Group: Transforming Transportation Asset Management
The Road Efficiency Group: Transforming Transportation Asset ManagementThe Road Efficiency Group: Transforming Transportation Asset Management
The Road Efficiency Group: Transforming Transportation Asset ManagementWaugh Infrastructure Management Ltd.
 

Ähnlich wie 25 nov pi planning using hdm moldova (20)

Una introducción a HDM-4
Una introducción a HDM-4Una introducción a HDM-4
Una introducción a HDM-4
 
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
 
11. NECS 2016 _Current status and the way ahead for road development in the ...
11.  NECS 2016 _Current status and the way ahead for road development in the ...11.  NECS 2016 _Current status and the way ahead for road development in the ...
11. NECS 2016 _Current status and the way ahead for road development in the ...
 
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal ho
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal hoPavement Management, PMS, Asset Management, Road Maintenance planningfinal ho
Pavement Management, PMS, Asset Management, Road Maintenance planningfinal ho
 
How Are Route Planning and Route Optimisation Not The Same?.pdf
How Are Route Planning and Route Optimisation Not The Same?.pdfHow Are Route Planning and Route Optimisation Not The Same?.pdf
How Are Route Planning and Route Optimisation Not The Same?.pdf
 
Performance Measures for Highway Capacity Decision Making
Performance Measures forHighway Capacity Decision MakingPerformance Measures forHighway Capacity Decision Making
Performance Measures for Highway Capacity Decision Making
 
April 12, 2021 TPC Virtual Workshop
April 12, 2021 TPC Virtual WorkshopApril 12, 2021 TPC Virtual Workshop
April 12, 2021 TPC Virtual Workshop
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106
 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvk
 
9 pilot projects rs final
9 pilot projects rs final9 pilot projects rs final
9 pilot projects rs final
 
Pkrmmp phase 2 ntb workshop final ty-session 1
Pkrmmp phase 2 ntb workshop final  ty-session 1Pkrmmp phase 2 ntb workshop final  ty-session 1
Pkrmmp phase 2 ntb workshop final ty-session 1
 
Flour Presentation MEED MENA 2014
Flour Presentation MEED MENA 2014Flour Presentation MEED MENA 2014
Flour Presentation MEED MENA 2014
 
PTOLEMUS in a nutshell
PTOLEMUS in a nutshellPTOLEMUS in a nutshell
PTOLEMUS in a nutshell
 
EU ITS-2452 - The Why, Where, What and How of ITS Egypt Case Study Final
EU ITS-2452  - The Why, Where, What and How of ITS Egypt Case Study FinalEU ITS-2452  - The Why, Where, What and How of ITS Egypt Case Study Final
EU ITS-2452 - The Why, Where, What and How of ITS Egypt Case Study Final
 
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
 
Level of Service F for Grade A Streets
Level of Service F for Grade A StreetsLevel of Service F for Grade A Streets
Level of Service F for Grade A Streets
 
IAQM AGM 2016 - Dr Beth Conlan, Ricardo
IAQM AGM 2016 - Dr Beth Conlan, RicardoIAQM AGM 2016 - Dr Beth Conlan, Ricardo
IAQM AGM 2016 - Dr Beth Conlan, Ricardo
 
ITS Maryland
ITS MarylandITS Maryland
ITS Maryland
 
Clear Air Zones – What are Local Authorities Proposing? - Nigel Bellamy
Clear Air Zones – What are Local Authorities Proposing? - Nigel BellamyClear Air Zones – What are Local Authorities Proposing? - Nigel Bellamy
Clear Air Zones – What are Local Authorities Proposing? - Nigel Bellamy
 
The Road Efficiency Group: Transforming Transportation Asset Management
The Road Efficiency Group: Transforming Transportation Asset ManagementThe Road Efficiency Group: Transforming Transportation Asset Management
The Road Efficiency Group: Transforming Transportation Asset Management
 

Kürzlich hochgeladen

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdftbatkhuu1
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 

Kürzlich hochgeladen (20)

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdf
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

25 nov pi planning using hdm moldova

  • 1. Design and Implementation of Road Maintenance Reform. Republic of Moldova Hamid Zarghampour 2010-11-25 Moldova Planning using HDM
  • 2. Design and Implementation of Road Maintenance Reform. Republic of Moldova Asset Management today  Set Goals and Objectives  Collect Inventory and Condition Data  Rates of Deterioration  Performance Standards & Measures  Life-Cycle Cost Analysis  Investment Strategies  Programs, Projects, and Practices  Monitoring Feedback and Adjustments
  • 3. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management Organisation Information/ Data Road works Effect Road Deterioration HDM 4 1 5432
  • 4. Design and Implementation of Road Maintenance Reform. Republic of Moldova Requirements Needs Prioritized needs Programme Annual Activities Existing plans, Strategies Policies Government, Users, Interested parties, etc. Needs PDS Requirements and Prioritized Needs This is what RA attempt to do Programme These are RA’s modes/Procedures Action Plan RA Activities this year Management Information PresentationPlanningCompetences 1 5432 Goals and Objectives “Doing things right” “Doing right things”
  • 5. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management Organisation Information/ Data Presentation Technique Case StudiesHDM 4 1 5432
  • 6. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4  Management cycle  HDM 4 ­ Maintenance Management ­ Management Function and HDM4 ­ Structure of HDM4 ­ Technical analysis tools within HDM 4  Road Engineering from Art to Science ­ Road Deterioration concept and models in HDM 4 ­ Road Works Classification in HDM 4 ­ Road works Effects  Economy ­ DHM 4, Economical Indicators
  • 7. Design and Implementation of Road Maintenance Reform. Republic of Moldova 0-500 500-1500 1500-4000 4000-7000 7000- 0 20 40 60 80 100 120 Important Elements in the plan:  Name of section  Geographical location  Length Type of works  Cost estimates  Timing of work Traffic Packaging appropriate mix of Road works with regards to available budgetV ä g m a r k e r in g V ä g t r u m m o r B e r g a r b e t e n , b o r r n in g s p r ä n g n in gM ä tn in g a v v ä g y ta n s tills tå n d S lä n te r E r o s io n s s k y d d B e lä g g n in g B ä r la g e r B ä r ig h e ts m ä tn in g F a llv ik ts d e f le k t o m e t e r April- September August October December- March March - October September- November New plan November- December August- October Road Class Paved Roads Unpaved Roads Good Fair Poor Bad Good Poor Bad National Roads 4 6 8 >8 - - - Secondary 5 7 9 >9 6 8 10
  • 8. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4, Tool for Road AM  Maintenance Management  Planning:  Estimation of expenditure  Forecasting of various budget vs. road development  Policy making, dialog with financier (Government)  Programming:  Estimation of expenditure for different works and activities  Key aspect of programming is prioritization of work  Find the best use of the constrained budget  Multi-year works and expenditure program  Cost-benefit analysis are required
  • 9. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4, Tool for Road AM  Maintenance Management  Preparation:  Short term planning  Road schemes are packaged for implementation  Designs are refined and prepared in more detail  Bills of quantities and detail costing are made  Detailed cost-benefit is carried out to confirm the feasibility project  Operation:  Refers to the on-going activities  scheduling of works such as monitoring in terms of: labour, equipment and materials and recording of works completed, etc...
  • 10. Design and Implementation of Road Maintenance Reform. Republic of Moldova Change in Management Process Activity Time horizon Spatial Coverage Information Mode of computer Operation Planning Long term (Strategic) Network Wide Coarse Summary Automatic Programming Medium term (Tactical) Network Sub Network Preparation Budget Year Scheme Level Section Operation Immediate/ Short term Scheme Level Sub Section Fine/detailed Interactive IQL
  • 11. Design and Implementation of Road Maintenance Reform. Republic of Moldova Information, Data  What kind of information do we need?  It is always dependent on: ­ What decisions do we need to make? ­ What information/data are required to make these decisions? ­ Can we afford to collect the data? ­ If it needs updating, can we afford to keep data current over time?  Guiding Principle  Collect only the data you need!  Collect it only when you need to!  The level of detail should be appropriate for the decisions being made: ­ Network level data for network level analyses ­ project level for project level analyses
  • 12. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management function and HDM 4 Management Function Common description HDM 4 Application Planning - Strategic Analysis System - Network Planning - Pavement Management System - Programme analysis System HDM 4 Strategy Analysis Programming -Pavement Management System -Budgeting System HDM 4 Programme Analysis Preparation - Project Analysis System . Pavement Management System - Pavement/Overlay design System - Contract procurement System HDM 4 Project Analysis Operation - Project Management System - Maintenance Management System - Equipment Management System - Financial Management/Accounting System Not addressed by HDM
  • 13. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management function and HDM 4 Management Function Common description HDM 4 Application Planning - Strategic Analysis System - Network Planning - Pavement Management System - Programme analysis System HDM 4 Strategy Analysis Programming -Pavement Management System -Budgeting System HDM 4 Programme Analysis Preparation - Project Analysis System . Pavement Management System - Pavement/Overlay design System - Contract procurement System HDM 4 Project Analysis Operation - Project Management System - Maintenance Management System - Equipment Management System - Financial Management/Accounting System Not addressed by HDM
  • 14. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management function and HDM 4 Management Function Common description HDM 4 Application Planning - Strategic Analysis System - Network Planning - Pavement Management System - Programme analysis System HDM 4 Strategy Analysis Programming -Pavement Management System -Budgeting System HDM 4 Programme Analysis Preparation - Project Analysis System . Pavement Management System - Pavement/Overlay design System - Contract procurement System HDM 4 Project Analysis Operation - Project Management System - Maintenance Management System - Equipment Management System - Financial Management/Accounting System Not addressed by HDM
  • 15. Design and Implementation of Road Maintenance Reform. Republic of Moldova Management function and HDM 4 Management Function Common description HDM 4 Application Planning - Strategic Analysis System - Network Planning - Pavement Management System - Programme analysis System HDM 4 Strategy Analysis Programming -Pavement Management System -Budgeting System HDM 4 Programme Analysis Preparation - Project Analysis System . Pavement Management System - Pavement/Overlay design System - Contract procurement System HDM 4 Project Analysis Operation - Project Management System - Maintenance Management System - Equipment Management System - Financial Management/Accounting System Not addressed by HDM
  • 16. Design and Implementation of Road Maintenance Reform. Republic of Moldova Structure of HDM 4  Core Data Objects in HDM 4 are defined in the following data managers:  HDM-4 Configuration  Defines the default data to be used in the applications  Road Network  Defines the characteristic of road sections  Vehicle fleet  Defines the characteristic of the vehicle fleet  Road works  Defines Maintenance and improvement standards incl. unit costs
  • 17. Design and Implementation of Road Maintenance Reform. Republic of Moldova Technical analysis within HDM 4 Road Deterioration (RD)  Predicts pavement deterioration for:  Bituminous  Concrete and  Unsealed roads  Works Effects (WE)  Simulates:  The effects of road works on pavement condition  Determine the corresponding costs
  • 18. Design and Implementation of Road Maintenance Reform. Republic of Moldova Technical analysis within HDM 4.. Road User Effects (RUE)  Determines:  Costs of vehicle operation  Travel time  Road accidents (only in the CBA)  Social and Environment Effects (SEE)  Determines:  The effects of vehicle emissions  Energy consumption
  • 19. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4 processes for analysis Calculate Annual effects and costs Calculate Road deterioration Calculate Road User Effect VOC, time, etc Calculate Social and Environmental Effects Calculate Road Works Effect s Add Exogenous Costs and Benefits Return
  • 20. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4  Management cycle  HDM 4 ­ Maintenance Management ­ Management Function and HDM4 ­ Structure of HDM4 ­ Technical analysis tools within HDM 4  Road Engineering from Art to Science ­ Road Deterioration concept and models in HDM 4 ­ Road Works Classification in HDM 4 ­ Road works Effects  Economy ­ DHM 4, Economical Indicators
  • 21. Design and Implementation of Road Maintenance Reform. Republic of Moldova Road Deterioration
  • 22. Design and Implementation of Road Maintenance Reform. Republic of Moldova Road Engineering from Art to Science q Experience 1900-1960 CBR 60- AASHTO 70- Mechanistic approach80- HDM III 90- FEM ”Pavement history” “Homogenous sections”
  • 23. Design and Implementation of Road Maintenance Reform. Republic of Moldova V ä g m a r k e r in g V ä g t r u m m o r B e r g a r b e t e n , b o r r n in g s p r ä n g n in gM ä t n in g a v v ä g y t a n s t ills t å n d S lä n t e r E r o s io n s s k y d d B e lä g g n in g B ä r la g e r F ö r s t ä r k n in g s la g e r T jä ls s k y d d U p p f r y s a n d e b lo c k Ö v e r b y g g n a d m a t e r ia lv a l o c h d im e n s io n e r in g T e r r a s s m a t e r ia l A v v a t t n in g D r ä n e r in g B ä r ig h e t s m ä t n in g F a llv ik t s d e f le k t o m e t e r Road Construction today
  • 24. Design and Implementation of Road Maintenance Reform. Republic of Moldova V ä g m a r k e r in g V ä g t r u m m o r B e r g a r b e t e n , b o r r n in g s p r ä n g n in gM ä t n in g a v v ä g y t a n s t ills t å n d S lä n t e r E r o s io n s s k y d d B e lä g g n in g B ä r la g e r F ö r s t ä r k n in g s la g e r T jä ls s k y d d U p p f r y s a n d e b lo c k Ö v e r b y g g n a d m a t e r ia lv a l o c h d im e n s io n e r in g T e r r a s s m a t e r ia l A v v a t t n in g D r ä n e r in g B ä r ig h e t s m ä t n in g F a llv ik t s d e f le k t o m e t e r Climate Traffic  Design Criterion ­ Wear ­ Stability ­ Deformation, (plastic) ­ Fatigue ­ Frost heave action, etc… Road Construction today
  • 25. Design and Implementation of Road Maintenance Reform. Republic of Moldova Road Deterioration concept in HDM 4:  is a function of:  original design  material types  construction quality  traffic volume and axle loading  road geometry  pavement age  environmental condition  maintenance policy pursued
  • 26. Design and Implementation of Road Maintenance Reform. Republic of Moldova Rate of wear:  is a function of:  Mix design  Material quality (BM value)  Studded tires  Speed  Carriage width
  • 27. Design and Implementation of Road Maintenance Reform. Republic of Moldova Fatigue:  is mostly caused by:  heavy vehicles  Other reasons:  If it is occurred on early stage after reconstruction, construction ­ service life is ended ­ not good enough mix design ­ inadequate bearing capacity ­ etc…
  • 28. Design and Implementation of Road Maintenance Reform. Republic of Moldova Frost heave action
  • 29. Design and Implementation of Road Maintenance Reform. Republic of Moldova Bearing Capacity
  • 30. Design and Implementation of Road Maintenance Reform. Republic of Moldova Plastic deformation
  • 31. Design and Implementation of Road Maintenance Reform. Republic of Moldova Bleeding
  • 32. Design and Implementation of Road Maintenance Reform. Republic of Moldova Ravelling
  • 33. Design and Implementation of Road Maintenance Reform. Republic of Moldova Cracking
  • 34. Design and Implementation of Road Maintenance Reform. Republic of Moldova Separation
  • 35. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM-4 Deterioration Models
  • 36. Design and Implementation of Road Maintenance Reform. Republic of Moldova Scope of modeling road deterioration  Physical environments  Climatic Zones  Pavement  Rigid concrete  wide range of flexible pavements  Unsealed pavement  Drainage effects  shoulders deterioration, (effects on pavement strength)
  • 37. Design and Implementation of Road Maintenance Reform. Republic of Moldova Classes of Models  Mechanistic  use sound fundamental theories of soil mechanic to predict pavement behavior  Empirical  based on statistical analysis of locally deterioration trends  Structural mechanistic-empirical approach  based on identifying the functional form and primary variables from external sources ­ statistical techniques to quantify their impact
  • 38. Design and Implementation of Road Maintenance Reform. Republic of Moldova Pavement Classification System (Bituminous Pavement)  Pavement Type  Asphalt Mix on Asphalt Base  Asphalt Mix on Granular Base  Asphalt Mix on Stabilized Base  Asphalt Mix on Pavement Base  Surface Type  Asphalt Concrete  Hot Rolled Asphalt  Polymer Modified asphalt dressing  Rubberized Asphalt Concrete  Cold Mix  Porous Asphalt  Stone Mastic Asphalt
  • 39. Design and Implementation of Road Maintenance Reform. Republic of Moldova Pavement Classification System (Bituminous Pavement)  Pavement Type  Surface Treatment on Asphalt Base  Surface Treatment on Granular Base  Surface Treatment on Stabilized Base  Surface Treatment on Pavement Base  Surface Type  Single Bituminous Surface Dressing  Double Bituminous Surface Dressing  Cold Mix  Cape Seal  Slurry Seal  Penetration MacAdam
  • 40. Design and Implementation of Road Maintenance Reform. Republic of Moldova Modeling Framework  For each pavement type:  a generic model applies to describes the pavement deterioration  After maintenance treatments:  the generic pavement type can change  Pavement Strength:  is characterized by “Adjusted Structural Number” (SNP)  The SNP applies a weighting factor (prevent over-prediction of pavement strength with increase of depth)  Construction Quality:  Construction Defect Indicators: CDS (surface) and CDB (Base) ­ CDS: 0.5-1,5 from brittle to soft depending on Binder content ­ CDB: 0-1,5, No defects or several defects
  • 41. Design and Implementation of Road Maintenance Reform. Republic of Moldova
  • 42. Design and Implementation of Road Maintenance Reform. Republic of Moldova
  • 43. Design and Implementation of Road Maintenance Reform. Republic of Moldova Concrete Joint spalling
  • 44. Design and Implementation of Road Maintenance Reform. Republic of Moldova Concrete Joint spalling
  • 45. Design and Implementation of Road Maintenance Reform. Republic of Moldova Concrete Joint spalling
  • 46. Design and Implementation of Road Maintenance Reform. Republic of Moldova
  • 47. Design and Implementation of Road Maintenance Reform. Republic of Moldova HDM 4  Management cycle  HDM 4 ­ Maintenance Management ­ Management Function and HDM4 ­ Structure of HDM4 ­ Technical analysis tools within HDM 4  Road Engineering from Art to Science ­ Road Deterioration concept and models in HDM 4 ­ Road Works Classification in HDM 4 ­ Road works Effects  Economy ­ DHM 4, Economical Indicators
  • 48. Design and Implementation of Road Maintenance Reform. Republic of Moldova Road Works Bituminous Pavement
  • 49. Design and Implementation of Road Maintenance Reform. Republic of Moldova Road Works classification  Routine Maintenance  Periodic Maintenance  Special Works  Improvement Works  Construction Works
  • 50. Design and Implementation of Road Maintenance Reform. Republic of Moldova Routine Maintenance  Routine Pavement  Patching  Edge-repair  Crack sealing  Spot-re-gravelling  Shoulders repair, etc.  Drainage  Culvert repairs  Clearing side drains, etc…  Routine Various  Vegetation control  Markings  Sign, etc…
  • 51. Design and Implementation of Road Maintenance Reform. Republic of Moldova Periodic Maintenance  Preventive Treatment  Fog seal  Rejuvenation  Rehabilitation  Thick overlay  Mill and replace  Inlay  Resurfacing  Surface dressing  Slurry seal  Cape seal  Thin overlay, re-gravelling  Reconstruction  Partial reconstruction  Full pavement reconstruction
  • 52. Design and Implementation of Road Maintenance Reform. Republic of Moldova Special  Winter  Snow removal  Salting/gritting, etc…  Emergency  Cleaning debris  Traffic accident removal, etc..  Repairing/washout
  • 53. Design and Implementation of Road Maintenance Reform. Republic of Moldova Improvement  Widening  Partial widening  Lane addition  Realignment  Horizontal and vertical geometric improvement  Junction improvement  Off-carriageway  Shoulders addition  Shoulders upgrading  NMT lane addition  Side drain improvement, etc…
  • 54. Design and Implementation of Road Maintenance Reform. Republic of Moldova Construction  Upgrading  Chang of surface Class ­ Unsealed surface to Bituminous ­ Bituminous to Concrete Pavement  New Section
  • 55. Design and Implementation of Road Maintenance Reform. Republic of Moldova Outputs  Pavement deterioration and road works  Summary of annual pavement condition  Quantities of road works  Details of annual road work costs  Schedule of road works  Road user effects  Summary of Road User Cost  Average traffic speed  Vehicle speed and capacity ratio  Vehicle emission  Energy consumption
  • 56. Design and Implementation of Road Maintenance Reform. Republic of Moldova Outputs  Economical Indicators  Annual cost streams  Discounted cash flows  Net Present Value (NPV)  Economic Internal Rate of Return (IRR)  Benefit Cost Ration (BCR)  First Year Benefit (FYB)
  • 57. Design and Implementation of Road Maintenance Reform. Republic of Moldova Outputs…  Net Present Value (NPV)  The higher NPV the higher Benefit  Without budget constrain, shall the alternative with highest NPV be chosen  Comments  Larger investment tends to have higher NPV  NPV is proportional to the project cost if IRR is the same  Economic Internal Rate of Return (IRR)  IRR = the discounted rate at which the NPV is equal to 0  Gives no indications of the size of costs or benefits of an investment  Acts as a guide to the profitability of the investment  The higher the better  If IRR > Discount rate, the investment is said to be economically justified
  • 58. Design and Implementation of Road Maintenance Reform. Republic of Moldova Outputs…  Benefit Cost Ration (BCR)  Ratio indicating the profitability of one option relative to base option  Gives no indications of the size of costs or benefits of an investment  First Year Benefit (FYB)  FYB is defined as the ratio in present of the net benefit realized in the first year after construction  Rough guide to project timing  If FYB > discounted rate, the project should go ahead  If FYB < discounted rate the project should be delayed until it satisfies the criterion
  • 59. Design and Implementation of Road Maintenance Reform. Republic of Moldova Asset Management today  Set Goals and Objectives  Collect Inventory and Condition Data  Rates of Deterioration  Performance Standards & Measures  Life-Cycle Cost Analysis  Investment Strategies  Programs, Projects, and Practices  Monitoring Feedback and Adjustments
  • 60. Design and Implementation of Road Maintenance Reform. Republic of Moldova For any kind of planning (programme, Project)! We need Data/Information: Road Network Work standards Traffic data (Vehicle Fleet)
  • 61. Design and Implementation of Road Maintenance Reform. Republic of Moldova 1 december 2010 We need to prepare - More than 1? If så: - SPECIFY - Visualising section’s conditions - Map (GIS) - -Veify -Cost estimates -Maintenance activities -Routine -Periodic - Rehabilitation - Terminology - VF available - Previous studies?
  • 62. Design and Implementation of Road Maintenance Reform. Republic of Moldova GIS Data collection Evaluation 0-500 500-1500 1500-4000 4000-7000 7000- 0 20 40 60 80 100 120 Systems Asset Evaluation Cost-Benefits Ministry, RA, RU Condition Data and analysis Visual inspections
  • 63. Design and Implementation of Road Maintenance Reform. Republic of Moldova 0-500 500-1500 1500-4000 4000-7000 7000- 0 20 40 60 80 100 120 Condition Data and analysis Need for Inspection Manual - Will be recommended IRI -For this study: - 900 km of: -National and Secondary roads - Analysis tool - HDM 4 - Overview next week: - Programme - Project •Modelling RN •Review results •Writing report Next week Script for selection of Homogenous sections is available

Hinweis der Redaktion

  1. While there is no one method that will fit every situation or agency, all asset management structures have certain basic elements in their approach. These include: -- Setting Goals and Objectives -- Collecting appropriate data -- Calculating and analyzing deterioration rates -- Setting performance standards and measuring progress -- Use of life-cycle cost analyses -- Developing investment strategies -- Selecting programs and projects consistent with the selected strategy -- Monitoring the results and making adjustments if necessary. [GO TO NEXT SLIDE]
  2. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  3. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  4. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  5. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  6. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  7. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  8. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  9. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  10. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  11. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  12. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  13. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  14. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  15. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  16. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  17. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  18. So what is driving the move toward asset management? Our transportation systems are mature ones with many roads and bridges built 30 to 40 years ago. Consequently, we are facing a period of re-investing in existing facilities rather than building new ones. This has been reflected in federal funding where they are moving from strictly capital funding to more flexible funding for preventive maintenance. Because of the reports I mentioned earlier, the general public expects us to spend their money wisely and efficiently. And they are demanding greater accountability. We have seen a new breed of leaders coming into transportation. Rather than coming from the engineering field, many of today’s leaders are coming from the political arena or business community. And they are bringing with them a sensitivity to constituents and management concepts and principles that worked in business. Fourth, there have been vast improvements in computers and technology that make it possible to do things today that we could never do before. Finally, there is the well-recognized relationship between an efficient, productive transportation system and economic growth. [GO TO NEXT SLIDE]
  19. In closing this second module this slide shows some of the key differences between the old way of doing business and the new paradigm. ARE THERE ANY QUESTIONS? [GO TO NEXT SLIDE]
  20. While there is no one method that will fit every situation or agency, all asset management structures have certain basic elements in their approach. These include: -- Setting Goals and Objectives -- Collecting appropriate data -- Calculating and analyzing deterioration rates -- Setting performance standards and measuring progress -- Use of life-cycle cost analyses -- Developing investment strategies -- Selecting programs and projects consistent with the selected strategy -- Monitoring the results and making adjustments if necessary. [GO TO NEXT SLIDE]