Green Intelligence at your side




            Rooftop Solar PV projects for
              landlords and investors
                                        What you should know
                                  prior to meeting a solar salesman


                                        Last Updated August, 2012
Agenda
• Ontario FIT2.0 program
• Property requirements for a solar PV
  project
• Different ownership models – roof
  lease, system ownership & ownership with
  development
• An overview of project progression from
  idea to commissioning
• Aspects of solar PV technology that affect
  property owner – financing and taxation


                         Copyright GreenQ Partners Inc   2
FIT Program Overview
• Program started with the Green Energy Act in May 2009. New
  Rules were introduced in August 2012.
• Established rules under which businesses can sell to the grid
  electricity produced with renewable energy generation
  technologies, such as solar PV, wind, bio-energy
• Electricity is bought by the OPA on the basis of a 20-year fixed
  price contract




                            Copyright GreenQ Partners Inc            3
Ontario FIT Rates for PV
 Project Size      Rooftop, C$/kWh               Ground, C$/kWh
   ≤10 kW                         0.549               0.445
> 10 ≤ 100 kW                     0.548               0.388

> 100 ≤ 500 kW                    0.539               0.388

  > 500 kW                        0.487          0.35 (up to 5MW)
                                                 0.347 (over 5MW




                 Copyright GreenQ Partners Inc                      4
FIT Program Requirements
To qualify for FIT rates project must:
• Be located in Ontario
• Pass the transmission/distribution availability test
• 60% of implied project cost* should be incurred in Ontario
• Meet OPA’s size requirements per kW


* While determining compliance with domestic content requirement OPA assigns
                                                      FIT
  portions of costs to project activities and materials regardless of actual costs.



                                     Copyright GreenQ Partners Inc                    5
Site suitability

                              Electrical
Roof
                                Room

       Location



        Copyright GreenQ Partners Inc      6
Suite Suitability - Roof
• Orientation
   – South or South-West
• Roof space
   – 40,000 sq ft => 250kW system
   – Other equipment may use up roof space
• Shading
   – None or very little
• Roof condition
   – Membrane should last at least for 20 years (ideally)
• Structural capacity
   – Roof structure must allow for additional 3-7 psf load to accommodate dead
     and wind load and possible additional snow accumulation


                                  Copyright GreenQ Partners Inc                  7
How it looks



  Ballasted mounting from Unirac




                                                         Example of a penetrating mounting system




Ballasted mounting from SolarDock


                                       Copyright GreenQ Partners Inc                                8
Costs of Roof Imperfections
• Not true south orientation
   – 10o off => 0.2% less energy
   – 25o off => 1.5% less energy

• Below optimal tilt (<30o)
   – 20o => 2.3% less energy
   – 10o => 6.3% less energy
   – Flat => 12.1% less energy (may lower costs)

• Dirt & snow on panels
   – Higher tilt allows for better self cleaning


                               Copyright GreenQ Partners Inc   9
Site Suitability - Electrical
• Electrical room
   – Space for inverter, connector box,
     meter, disconnects, etc
   – Equipment weight
   – Equipment delivery constraints

• Sufficient distribution line to your
       building


                                                            Images are property of Satcom (top) and Xantrex.




                            Copyright GreenQ Partners Inc                                                      10
Site Suitability - Location
• LDC capacity availability
   – Pre-application consultation with LDC is required to determine if
     project can be connected

• Local weather conditions
   – Snow belt area will have higher losses than Toronto

• Air cleanliness & dirt accumulation
   – You only harness the sun that gets to the panels




                               Copyright GreenQ Partners Inc             11
How involved do you want to be?

Greater involvement
leads to greater:                                        Develop & Own
                                                           the system
• Required investment
• Return on investment                                   Own the system

• Risks
                                                              Lease
                                                               roof




                         Copyright GreenQ Partners Inc                    12
“Lease” Option
You invite a company to install, own and operate a solar
system on your roof and charge them fixed lease payment.
• Investment required
   – No capital investment
   – Legal and organisational costs, pre-application assessments

• Expected revenues:
   – Around $0.5 per sq ft of used roof per year

• Risks
   – Roof: Leakage, structural damage, roof traffic, conflicting use during 20 years
     of contract,
   – Default of your solar tenant


                                   Copyright GreenQ Partners Inc                       13
“Own” Option
You invite a company to develop and install a system; you
collect payments for produced electricity from the OPA.
• Investment required
   – Around $4,500 per kW of installed system, capital and preparation costs

• Expected revenues
   – $450-500 per kW pa on a commercial scale system (100-500kW AC)
   – 11% IRR (100% equity financing)

• Risks
   – Roof risks, same as in “lease” option
   – Performance risks, maintenance risks

                                 Copyright GreenQ Partners Inc                 14
Owning a system:
                      Performance Factors
PV technology                                             Inverter
 • c-Si panels produce more kWh/sft of roof                   • Efficiency, Cooling, Life expectancy
 • Thin film panels are more tolerant to high                 • Reliability, warranty, service
   temperatures, but less productive
 • “Shadow resistant” panel designs help                  System design
   avoid some losses
                                                              • Losses in cables, due to panel
Mounting                                                        heating, overshadowing, service
                                                                needs, panel mismatch, etc
 • Orientation: ideal is true South and 30° tilt              • Need for cleaning
 • Best performance tilt may be not cost                      • Downtime
   effective due to wind load                                 • Array capacity vs. inverter capacity
 • Higher tilt => more roof space
   required, lower tilt => lower wind load                Local conditions
 • Roof warranty and mounting warranty
 • Ease of temporary relocation                               • Local sun access conditions
                                                                (shadow, smoke, dust, steam, etc)

                                          Copyright GreenQ Partners Inc                                15
“Develop & Own” Option
You develop an in-house team that can procure and install
the system. The rest is the same as in Own Option.
This option is most viable for owners of multiple rooftops.
• Investment required
   – Cost to setup in-house facility + per-system costs lower than in “own” option

• Expected revenues
   – $450-500 per kW pa on a commercial scale system
   – 11% IRR (100% equity financing) on system

• Risks
   – Roof risks and Performance risks as in Own option
   – Design and procurement (parts) risks


                                  Copyright GreenQ Partners Inc                      16
Sample Project
For a 40,000 sq ft, problem-free roof one can expect:
• System size of 250kW DC
• Investments:
   – Feasibility & Organizational costs - $10-30K (depending on project
     complexity)
   – System cost (“own” option) - $1M
• Revenues
   – “Lease” revenue - $20,000 pa
   – “Own” revenue - $110,000 - $120,000 pa
• Bonus for “own” option – 50% depreciation rate on solar
  equipment; can used against other profits

                                Copyright GreenQ Partners Inc             17
Project Progression
1. Project Assessment
   – Evaluation of site suitability
   – How involved do you want to be?

2. Project setup
   – OPA Contract                              Highest impact decisions are made
                                                  at project assessment stage
   – Developer Selection
   – Project Financing

3. Construction & Operation


                           Copyright GreenQ Partners Inc                           18
Project Setup - OPA Contract
• The party that owns roof access rights should apply
  for OPA contract
   – The application fee is 0.5$ per kW (up to $5,000)
   – Application security of $20 per kW is also required. Refundable
     if project goes into construction

• LDC approval for future system is required
• Contracts are granted based on priority points
• The processing time for an application varies, with
  “OPA target” of 60 days

                            Copyright GreenQ Partners Inc              19
Project Setup - Developer Selection
• Free assessment is never free and never unbiased

• Look at IRR and risks; not just cost or performance

• Warranties: for roof, equipment and performance; is developer worth
  the offered warranty? How is warranty going to work?

• Maintenance schedule: who, when, how



        The decision you are making
     will be binding for at least 20 years




                                  Copyright GreenQ Partners Inc         20
Project Financing
• Debt and equity financing is available from different
  sources
• CEPP Funding for Ontario organizations can be used
  to cover soft costs
• Bank loans may be obtained only for projects using
  bankable equipment
   – Banks will typically finance up to 70% of cost for projects that
     meet their criteria
   – Will require adequate project structure and documentation


                             Copyright GreenQ Partners Inc              21
Other Aspects of Project Setup
• Internal team set-up
   – Technical and technology advisors
   – Legal advisor
   – Financial advisor
• Establishing project schedule and its impact on other
  activities
• DBF or DBFM approach



                           Copyright GreenQ Partners Inc   22
Construction – Major Concerns
• Who is responsible for damages to roof? To system?
   – Cooperation with roofing company

• Permitting and unexpected fees
• Construction financing
• Interference with primary business
   – Length of construction
   – Scheduling




                              Copyright GreenQ Partners Inc   23
Operation – Major Concerns
• Roof warranties during operation
   – Cooperation with roofer during construction
• Roof repairs
   – Contractual provisions

• System repair and maintenance
   – Defined maintenance plan
   – Problem response – timing & warranties
   – Value of monitoring system



                              Copyright GreenQ Partners Inc   24
Taxation Considerations
• Income tax
  – System costs are subject to 50% depreciation
  – In some cases depreciation can be used against other
    income

• Property taxes
  – System should be treated as “equipment”
  – Rooftop PV should not affect property taxes




                         Copyright GreenQ Partners Inc     25
Conclusion
For a landlord a solar PV project should not
differ much from any other investment project:
   • All investment rules apply
   • No need to be a pro in solar to benefit from it
   • To maximize return – stay within core competence and
     assign direct solar risks to solar developer, who can
     manage them at a lower cost

               When done right, solar PV
                investment is like bond,
                   but with 11% IRR



                                 Copyright GreenQ Partners Inc   26
Questions




 Copyright GreenQ Partners Inc   27

Weitere ähnliche Inhalte

Was ist angesagt?

Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Engineering Limited
 
Ozone - Corporate Profile Detailed
Ozone - Corporate Profile DetailedOzone - Corporate Profile Detailed
Ozone - Corporate Profile DetailedSetu Goyal
 
Rooftop Solar & Benefits of Net Metering
Rooftop Solar & Benefits of Net MeteringRooftop Solar & Benefits of Net Metering
Rooftop Solar & Benefits of Net MeteringUday Doshi
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installationAmitesh Kumar
 
Epc service proposal for setting up solar power project standard template
Epc service proposal for setting up solar power project standard templateEpc service proposal for setting up solar power project standard template
Epc service proposal for setting up solar power project standard templateSaurabh Parihar
 
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects Gensol Engineering Limited
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Engineering Limited
 
performance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterperformance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterAshish Verma
 
Grid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at siliconGrid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at siliconNavneet Das
 
Rooftop PV System Shubham Gaurav
Rooftop PV System Shubham GauravRooftop PV System Shubham Gaurav
Rooftop PV System Shubham GauravShubham Gaurav
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...sdchrosis
 
Solar Driven Asia Proposal
Solar Driven Asia Proposal Solar Driven Asia Proposal
Solar Driven Asia Proposal Maurice Williams
 
How solar rooftop system works
How solar rooftop system worksHow solar rooftop system works
How solar rooftop system worksHardik Parmar
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
 

Was ist angesagt? (20)

Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Group Profile  - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)
 
Gensol Permits Procurement Services
Gensol Permits Procurement ServicesGensol Permits Procurement Services
Gensol Permits Procurement Services
 
Ozone - Corporate Profile Detailed
Ozone - Corporate Profile DetailedOzone - Corporate Profile Detailed
Ozone - Corporate Profile Detailed
 
Rooftop Solar & Benefits of Net Metering
Rooftop Solar & Benefits of Net MeteringRooftop Solar & Benefits of Net Metering
Rooftop Solar & Benefits of Net Metering
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installation
 
Epc service proposal for setting up solar power project standard template
Epc service proposal for setting up solar power project standard templateEpc service proposal for setting up solar power project standard template
Epc service proposal for setting up solar power project standard template
 
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
 
Rooftop Solar Benefits: Net Metering
Rooftop Solar Benefits: Net MeteringRooftop Solar Benefits: Net Metering
Rooftop Solar Benefits: Net Metering
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality Management
 
performance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverterperformance optimization of Solar pv plant through Micro inverter
performance optimization of Solar pv plant through Micro inverter
 
Grid Connected Roof Top Solar Power Generation: A Review
Grid Connected Roof Top Solar Power Generation: A ReviewGrid Connected Roof Top Solar Power Generation: A Review
Grid Connected Roof Top Solar Power Generation: A Review
 
Project solar
Project solar Project solar
Project solar
 
Jakson_report_Final
Jakson_report_FinalJakson_report_Final
Jakson_report_Final
 
Grid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at siliconGrid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at silicon
 
Rooftop PV System Shubham Gaurav
Rooftop PV System Shubham GauravRooftop PV System Shubham Gaurav
Rooftop PV System Shubham Gaurav
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
 
Gensol Lender's Engineer Services
Gensol Lender's Engineer ServicesGensol Lender's Engineer Services
Gensol Lender's Engineer Services
 
Solar Driven Asia Proposal
Solar Driven Asia Proposal Solar Driven Asia Proposal
Solar Driven Asia Proposal
 
How solar rooftop system works
How solar rooftop system worksHow solar rooftop system works
How solar rooftop system works
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
 

Andere mochten auch

The GIS for the Solar Projects Development
The GIS for the Solar Projects DevelopmentThe GIS for the Solar Projects Development
The GIS for the Solar Projects DevelopmentEsri
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projectsalejolop
 
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing FinalDenysStephens
 
Performance Presentation - NREL March 2010
Performance Presentation - NREL March 2010Performance Presentation - NREL March 2010
Performance Presentation - NREL March 2010Jacob McKee
 
EPRI Q3 2014 Meeting - Batteries & Power Optimizers
EPRI Q3 2014 Meeting - Batteries & Power OptimizersEPRI Q3 2014 Meeting - Batteries & Power Optimizers
EPRI Q3 2014 Meeting - Batteries & Power OptimizersJacob McKee
 
Interior Lighting for Local Governments - LED vs. Incumbents
Interior Lighting for Local Governments - LED vs. IncumbentsInterior Lighting for Local Governments - LED vs. Incumbents
Interior Lighting for Local Governments - LED vs. IncumbentsCenter for Sustainable Energy
 
Lighting Efficiency Measures
Lighting Efficiency Measures Lighting Efficiency Measures
Lighting Efficiency Measures haroldtaylor1113
 
Day 2: Energy Audit of Air Conditioning And Cooling Systems
Day 2: Energy Audit of Air Conditioning And Cooling Systems Day 2: Energy Audit of Air Conditioning And Cooling Systems
Day 2: Energy Audit of Air Conditioning And Cooling Systems RCREEE
 
Lighting systems 2014
Lighting systems 2014Lighting systems 2014
Lighting systems 2014ahmed salman
 
Distribution of electricity in a large or medium
Distribution of electricity in a large or mediumDistribution of electricity in a large or medium
Distribution of electricity in a large or mediumIqbal Nurfariq
 
Main findings Working Group 3: Mitigation of Climate Change
Main findings Working Group 3: Mitigation of Climate ChangeMain findings Working Group 3: Mitigation of Climate Change
Main findings Working Group 3: Mitigation of Climate ChangeAndy Dabydeen
 
Innovation in Building presentation 12 Sept 2014
Innovation in Building presentation 12 Sept 2014Innovation in Building presentation 12 Sept 2014
Innovation in Building presentation 12 Sept 2014Simon McGuinness
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYAmeen San
 
Climate Change Mitigation &amp; Adaptation
Climate Change  Mitigation &amp; AdaptationClimate Change  Mitigation &amp; Adaptation
Climate Change Mitigation &amp; AdaptationLaurence Mills
 
New Product Development PPT on Solar Tanning Printer
New Product Development PPT on Solar Tanning PrinterNew Product Development PPT on Solar Tanning Printer
New Product Development PPT on Solar Tanning PrinterBibekananda Swain
 
New product development (solar base mobile)
New product development (solar base mobile)New product development (solar base mobile)
New product development (solar base mobile)Muhammad Fahim
 
Project development new1
Project development new1Project development new1
Project development new1David mbwiga
 

Andere mochten auch (20)

The GIS for the Solar Projects Development
The GIS for the Solar Projects DevelopmentThe GIS for the Solar Projects Development
The GIS for the Solar Projects Development
 
Developing Solar Projects
Developing Solar ProjectsDeveloping Solar Projects
Developing Solar Projects
 
Respond! Clare Presentation 2015 A
Respond! Clare Presentation 2015 ARespond! Clare Presentation 2015 A
Respond! Clare Presentation 2015 A
 
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final
11128 Denys Stephens Penwith Ha Gshps In Low Income Housing Final
 
Performance Presentation - NREL March 2010
Performance Presentation - NREL March 2010Performance Presentation - NREL March 2010
Performance Presentation - NREL March 2010
 
EPRI Q3 2014 Meeting - Batteries & Power Optimizers
EPRI Q3 2014 Meeting - Batteries & Power OptimizersEPRI Q3 2014 Meeting - Batteries & Power Optimizers
EPRI Q3 2014 Meeting - Batteries & Power Optimizers
 
Interior Lighting for Local Governments - LED vs. Incumbents
Interior Lighting for Local Governments - LED vs. IncumbentsInterior Lighting for Local Governments - LED vs. Incumbents
Interior Lighting for Local Governments - LED vs. Incumbents
 
Lighting Efficiency Measures
Lighting Efficiency Measures Lighting Efficiency Measures
Lighting Efficiency Measures
 
Day 2: Energy Audit of Air Conditioning And Cooling Systems
Day 2: Energy Audit of Air Conditioning And Cooling Systems Day 2: Energy Audit of Air Conditioning And Cooling Systems
Day 2: Energy Audit of Air Conditioning And Cooling Systems
 
Lighting systems 2014
Lighting systems 2014Lighting systems 2014
Lighting systems 2014
 
Distribution of electricity in a large or medium
Distribution of electricity in a large or mediumDistribution of electricity in a large or medium
Distribution of electricity in a large or medium
 
Main findings Working Group 3: Mitigation of Climate Change
Main findings Working Group 3: Mitigation of Climate ChangeMain findings Working Group 3: Mitigation of Climate Change
Main findings Working Group 3: Mitigation of Climate Change
 
Innovation in Building presentation 12 Sept 2014
Innovation in Building presentation 12 Sept 2014Innovation in Building presentation 12 Sept 2014
Innovation in Building presentation 12 Sept 2014
 
ELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGYELECTRICAL DISTRIBUTION TECHNOLOGY
ELECTRICAL DISTRIBUTION TECHNOLOGY
 
Climate Change Mitigation &amp; Adaptation
Climate Change  Mitigation &amp; AdaptationClimate Change  Mitigation &amp; Adaptation
Climate Change Mitigation &amp; Adaptation
 
Light
LightLight
Light
 
New Product Development PPT on Solar Tanning Printer
New Product Development PPT on Solar Tanning PrinterNew Product Development PPT on Solar Tanning Printer
New Product Development PPT on Solar Tanning Printer
 
New product development (solar base mobile)
New product development (solar base mobile)New product development (solar base mobile)
New product development (solar base mobile)
 
Project development new1
Project development new1Project development new1
Project development new1
 
Artificial lighting
Artificial lightingArtificial lighting
Artificial lighting
 

Ähnlich wie Solar PV project development

Local Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyLocal Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyTransGrid AU
 
Ninth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar ProposalNinth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar Proposalninthavenue
 
Metal Bulletin IFA Prague 2015
Metal Bulletin IFA Prague 2015Metal Bulletin IFA Prague 2015
Metal Bulletin IFA Prague 2015Lou Parous
 
Small Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped SectorSmall Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped Sectorallearthrenewables
 
Challenges at project level for microgrid solutions lisbon 2016
Challenges at project level for microgrid solutions lisbon 2016Challenges at project level for microgrid solutions lisbon 2016
Challenges at project level for microgrid solutions lisbon 2016Trevor De Vries
 
Kenergy Infrapresentation(Aravind Format) (1)
Kenergy Infrapresentation(Aravind Format) (1)Kenergy Infrapresentation(Aravind Format) (1)
Kenergy Infrapresentation(Aravind Format) (1)anjumehrotra
 
D0 1 ricardo_infrastructure &amp; service delivery
D0 1 ricardo_infrastructure &amp; service deliveryD0 1 ricardo_infrastructure &amp; service delivery
D0 1 ricardo_infrastructure &amp; service deliveryRicardo Energy & Environment
 
Ozone - Solar Business
Ozone - Solar BusinessOzone - Solar Business
Ozone - Solar BusinessSetu Goyal
 
Barrier Electric Commercial Solar
Barrier Electric Commercial SolarBarrier Electric Commercial Solar
Barrier Electric Commercial SolarSolarAndy67
 
Standard Solar - Corporate Overview
Standard Solar - Corporate OverviewStandard Solar - Corporate Overview
Standard Solar - Corporate OverviewAndrew Maus
 
Natural group corporate profile 2013
Natural group corporate profile 2013Natural group corporate profile 2013
Natural group corporate profile 2013Ritesh Pothan
 
20161020_ASA Beyond The Panel (1)
20161020_ASA Beyond The Panel (1)20161020_ASA Beyond The Panel (1)
20161020_ASA Beyond The Panel (1)Browning Rockwell
 
Solar Energy Choices Magazine3
Solar Energy Choices Magazine3Solar Energy Choices Magazine3
Solar Energy Choices Magazine3comF5
 
Infrastructure Solutions for Commercial Properties and Developers
Infrastructure Solutions for Commercial Properties and DevelopersInfrastructure Solutions for Commercial Properties and Developers
Infrastructure Solutions for Commercial Properties and DevelopersMestizo Enterprises
 
EDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding PresentationEDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding PresentationNorbi Hegedus
 
Rooftop Solar: The eco-friendly way to cut your electricity bill
Rooftop Solar: The eco-friendly way to cut your electricity billRooftop Solar: The eco-friendly way to cut your electricity bill
Rooftop Solar: The eco-friendly way to cut your electricity billADDA
 

Ähnlich wie Solar PV project development (20)

Cymi Ecourja
Cymi EcourjaCymi Ecourja
Cymi Ecourja
 
Local Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyLocal Generation Workshop - Powering Sydney
Local Generation Workshop - Powering Sydney
 
projdoc(1).docx
projdoc(1).docxprojdoc(1).docx
projdoc(1).docx
 
Ninth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar ProposalNinth Avenue Terminal Solar Proposal
Ninth Avenue Terminal Solar Proposal
 
Metal Bulletin IFA Prague 2015
Metal Bulletin IFA Prague 2015Metal Bulletin IFA Prague 2015
Metal Bulletin IFA Prague 2015
 
Small Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped SectorSmall Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped Sector
 
Challenges at project level for microgrid solutions lisbon 2016
Challenges at project level for microgrid solutions lisbon 2016Challenges at project level for microgrid solutions lisbon 2016
Challenges at project level for microgrid solutions lisbon 2016
 
Kenergy Infrapresentation(Aravind Format) (1)
Kenergy Infrapresentation(Aravind Format) (1)Kenergy Infrapresentation(Aravind Format) (1)
Kenergy Infrapresentation(Aravind Format) (1)
 
D0 1 ricardo_infrastructure &amp; service delivery
D0 1 ricardo_infrastructure &amp; service deliveryD0 1 ricardo_infrastructure &amp; service delivery
D0 1 ricardo_infrastructure &amp; service delivery
 
Ozone - Solar Business
Ozone - Solar BusinessOzone - Solar Business
Ozone - Solar Business
 
Barrier Electric Commercial Solar
Barrier Electric Commercial SolarBarrier Electric Commercial Solar
Barrier Electric Commercial Solar
 
Standard Solar - Corporate Overview
Standard Solar - Corporate OverviewStandard Solar - Corporate Overview
Standard Solar - Corporate Overview
 
Natural group corporate profile 2013
Natural group corporate profile 2013Natural group corporate profile 2013
Natural group corporate profile 2013
 
20161020_ASA Beyond The Panel (1)
20161020_ASA Beyond The Panel (1)20161020_ASA Beyond The Panel (1)
20161020_ASA Beyond The Panel (1)
 
Solar Energy Choices Magazine3
Solar Energy Choices Magazine3Solar Energy Choices Magazine3
Solar Energy Choices Magazine3
 
Infrastructure Solutions for Commercial Properties and Developers
Infrastructure Solutions for Commercial Properties and DevelopersInfrastructure Solutions for Commercial Properties and Developers
Infrastructure Solutions for Commercial Properties and Developers
 
MARG-OPENACCESS
MARG-OPENACCESSMARG-OPENACCESS
MARG-OPENACCESS
 
Distributed Generation Feasibility
Distributed Generation FeasibilityDistributed Generation Feasibility
Distributed Generation Feasibility
 
EDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding PresentationEDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding Presentation
 
Rooftop Solar: The eco-friendly way to cut your electricity bill
Rooftop Solar: The eco-friendly way to cut your electricity billRooftop Solar: The eco-friendly way to cut your electricity bill
Rooftop Solar: The eco-friendly way to cut your electricity bill
 

Kürzlich hochgeladen

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 

Kürzlich hochgeladen (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 

Solar PV project development

  • 1. Green Intelligence at your side Rooftop Solar PV projects for landlords and investors What you should know prior to meeting a solar salesman Last Updated August, 2012
  • 2. Agenda • Ontario FIT2.0 program • Property requirements for a solar PV project • Different ownership models – roof lease, system ownership & ownership with development • An overview of project progression from idea to commissioning • Aspects of solar PV technology that affect property owner – financing and taxation Copyright GreenQ Partners Inc 2
  • 3. FIT Program Overview • Program started with the Green Energy Act in May 2009. New Rules were introduced in August 2012. • Established rules under which businesses can sell to the grid electricity produced with renewable energy generation technologies, such as solar PV, wind, bio-energy • Electricity is bought by the OPA on the basis of a 20-year fixed price contract Copyright GreenQ Partners Inc 3
  • 4. Ontario FIT Rates for PV Project Size Rooftop, C$/kWh Ground, C$/kWh ≤10 kW 0.549 0.445 > 10 ≤ 100 kW 0.548 0.388 > 100 ≤ 500 kW 0.539 0.388 > 500 kW 0.487 0.35 (up to 5MW) 0.347 (over 5MW Copyright GreenQ Partners Inc 4
  • 5. FIT Program Requirements To qualify for FIT rates project must: • Be located in Ontario • Pass the transmission/distribution availability test • 60% of implied project cost* should be incurred in Ontario • Meet OPA’s size requirements per kW * While determining compliance with domestic content requirement OPA assigns FIT portions of costs to project activities and materials regardless of actual costs. Copyright GreenQ Partners Inc 5
  • 6. Site suitability Electrical Roof Room Location Copyright GreenQ Partners Inc 6
  • 7. Suite Suitability - Roof • Orientation – South or South-West • Roof space – 40,000 sq ft => 250kW system – Other equipment may use up roof space • Shading – None or very little • Roof condition – Membrane should last at least for 20 years (ideally) • Structural capacity – Roof structure must allow for additional 3-7 psf load to accommodate dead and wind load and possible additional snow accumulation Copyright GreenQ Partners Inc 7
  • 8. How it looks Ballasted mounting from Unirac Example of a penetrating mounting system Ballasted mounting from SolarDock Copyright GreenQ Partners Inc 8
  • 9. Costs of Roof Imperfections • Not true south orientation – 10o off => 0.2% less energy – 25o off => 1.5% less energy • Below optimal tilt (<30o) – 20o => 2.3% less energy – 10o => 6.3% less energy – Flat => 12.1% less energy (may lower costs) • Dirt & snow on panels – Higher tilt allows for better self cleaning Copyright GreenQ Partners Inc 9
  • 10. Site Suitability - Electrical • Electrical room – Space for inverter, connector box, meter, disconnects, etc – Equipment weight – Equipment delivery constraints • Sufficient distribution line to your building Images are property of Satcom (top) and Xantrex. Copyright GreenQ Partners Inc 10
  • 11. Site Suitability - Location • LDC capacity availability – Pre-application consultation with LDC is required to determine if project can be connected • Local weather conditions – Snow belt area will have higher losses than Toronto • Air cleanliness & dirt accumulation – You only harness the sun that gets to the panels Copyright GreenQ Partners Inc 11
  • 12. How involved do you want to be? Greater involvement leads to greater: Develop & Own the system • Required investment • Return on investment Own the system • Risks Lease roof Copyright GreenQ Partners Inc 12
  • 13. “Lease” Option You invite a company to install, own and operate a solar system on your roof and charge them fixed lease payment. • Investment required – No capital investment – Legal and organisational costs, pre-application assessments • Expected revenues: – Around $0.5 per sq ft of used roof per year • Risks – Roof: Leakage, structural damage, roof traffic, conflicting use during 20 years of contract, – Default of your solar tenant Copyright GreenQ Partners Inc 13
  • 14. “Own” Option You invite a company to develop and install a system; you collect payments for produced electricity from the OPA. • Investment required – Around $4,500 per kW of installed system, capital and preparation costs • Expected revenues – $450-500 per kW pa on a commercial scale system (100-500kW AC) – 11% IRR (100% equity financing) • Risks – Roof risks, same as in “lease” option – Performance risks, maintenance risks Copyright GreenQ Partners Inc 14
  • 15. Owning a system: Performance Factors PV technology Inverter • c-Si panels produce more kWh/sft of roof • Efficiency, Cooling, Life expectancy • Thin film panels are more tolerant to high • Reliability, warranty, service temperatures, but less productive • “Shadow resistant” panel designs help System design avoid some losses • Losses in cables, due to panel Mounting heating, overshadowing, service needs, panel mismatch, etc • Orientation: ideal is true South and 30° tilt • Need for cleaning • Best performance tilt may be not cost • Downtime effective due to wind load • Array capacity vs. inverter capacity • Higher tilt => more roof space required, lower tilt => lower wind load Local conditions • Roof warranty and mounting warranty • Ease of temporary relocation • Local sun access conditions (shadow, smoke, dust, steam, etc) Copyright GreenQ Partners Inc 15
  • 16. “Develop & Own” Option You develop an in-house team that can procure and install the system. The rest is the same as in Own Option. This option is most viable for owners of multiple rooftops. • Investment required – Cost to setup in-house facility + per-system costs lower than in “own” option • Expected revenues – $450-500 per kW pa on a commercial scale system – 11% IRR (100% equity financing) on system • Risks – Roof risks and Performance risks as in Own option – Design and procurement (parts) risks Copyright GreenQ Partners Inc 16
  • 17. Sample Project For a 40,000 sq ft, problem-free roof one can expect: • System size of 250kW DC • Investments: – Feasibility & Organizational costs - $10-30K (depending on project complexity) – System cost (“own” option) - $1M • Revenues – “Lease” revenue - $20,000 pa – “Own” revenue - $110,000 - $120,000 pa • Bonus for “own” option – 50% depreciation rate on solar equipment; can used against other profits Copyright GreenQ Partners Inc 17
  • 18. Project Progression 1. Project Assessment – Evaluation of site suitability – How involved do you want to be? 2. Project setup – OPA Contract Highest impact decisions are made at project assessment stage – Developer Selection – Project Financing 3. Construction & Operation Copyright GreenQ Partners Inc 18
  • 19. Project Setup - OPA Contract • The party that owns roof access rights should apply for OPA contract – The application fee is 0.5$ per kW (up to $5,000) – Application security of $20 per kW is also required. Refundable if project goes into construction • LDC approval for future system is required • Contracts are granted based on priority points • The processing time for an application varies, with “OPA target” of 60 days Copyright GreenQ Partners Inc 19
  • 20. Project Setup - Developer Selection • Free assessment is never free and never unbiased • Look at IRR and risks; not just cost or performance • Warranties: for roof, equipment and performance; is developer worth the offered warranty? How is warranty going to work? • Maintenance schedule: who, when, how The decision you are making will be binding for at least 20 years Copyright GreenQ Partners Inc 20
  • 21. Project Financing • Debt and equity financing is available from different sources • CEPP Funding for Ontario organizations can be used to cover soft costs • Bank loans may be obtained only for projects using bankable equipment – Banks will typically finance up to 70% of cost for projects that meet their criteria – Will require adequate project structure and documentation Copyright GreenQ Partners Inc 21
  • 22. Other Aspects of Project Setup • Internal team set-up – Technical and technology advisors – Legal advisor – Financial advisor • Establishing project schedule and its impact on other activities • DBF or DBFM approach Copyright GreenQ Partners Inc 22
  • 23. Construction – Major Concerns • Who is responsible for damages to roof? To system? – Cooperation with roofing company • Permitting and unexpected fees • Construction financing • Interference with primary business – Length of construction – Scheduling Copyright GreenQ Partners Inc 23
  • 24. Operation – Major Concerns • Roof warranties during operation – Cooperation with roofer during construction • Roof repairs – Contractual provisions • System repair and maintenance – Defined maintenance plan – Problem response – timing & warranties – Value of monitoring system Copyright GreenQ Partners Inc 24
  • 25. Taxation Considerations • Income tax – System costs are subject to 50% depreciation – In some cases depreciation can be used against other income • Property taxes – System should be treated as “equipment” – Rooftop PV should not affect property taxes Copyright GreenQ Partners Inc 25
  • 26. Conclusion For a landlord a solar PV project should not differ much from any other investment project: • All investment rules apply • No need to be a pro in solar to benefit from it • To maximize return – stay within core competence and assign direct solar risks to solar developer, who can manage them at a lower cost When done right, solar PV investment is like bond, but with 11% IRR Copyright GreenQ Partners Inc 26
  • 27. Questions Copyright GreenQ Partners Inc 27