2. 2010 BOND PROGRAM UPDATE
TABLE OF CONTENTS
East View High School Phase 2 Additions, Package 1 3
East View High School Phase 2 Additions, Package 2 7
New Warehouse Facility 9
Annie Purl Elementary School Roof and HVAC Modifications 11
Georgetown High School Additions and Renovations 12
Huckabee
Georgetown Independent School District 2
3. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Contract Amount: $5,321,000
Mezzanine
Mechanical
Storage
Weight Room
Junior Varsity Football
Locker Room
Main
B Mech.
Elec.
Storage Meeting Room
D Office Training
C Stor.
Laundry
A
Head AV IDF
Coach Stor. Elec.
A. New Football Field House Secre-
Lockers Jan. Freshman Football
B. New Concession/Restroom Bldg Varsity Football Locker Room tary Coaches Locker Room
C. New Grandstands for 2,500
D. New Field Events
Site Plan Football Field House - Floor Plan
Mechanical Electrical
Storage
Storage Storage
Concession
Women Men
Ticket-
In Out
ing
In Out
Family
RR
Stadium Restroom/Concession - Floor Plan
Conceptual 3D Rendering
Huckabee
Georgetown Independent School District 3
4. 2010 BOND PROGRAM UPDATE General Contractor
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
PROGRESS REPORT
MILESTONE DATES
Concession Building
• Foundation pad is complete Schematic Design Presentation November 11, 2010
• Under slab plumbing is 100 percent complete Architect Signs Documents November 24, 2010
• City of Georgetown inspected the plumbing on March 30 Pre-Proposal Meeting December 8, 2010
• Edge forms for foundation will begin April 11
Proposal Part A Due December 21, 2010
• Substantial completion is scheduled for August 15
Proposal Part B Due December 22, 2010
Field House Proposal Evaluations January 4, 2011
• Foundation pad is complete General Contractor Recommendation to School Board January 10, 2011
• Under slab plumbing began March 30. First Owner/CO Meeting February 15, 2011
• Edge forms for foundation will begin April 14 Construction Start Date February 18, 2011
• Substantial completion is scheduled for August 15
Building Permit Issued March 16, 2011
Substantial Completion (Field/Track and Bleachers) August 1, 2011
Field/Track and Bleachers
• Rough grading is 75 percent complete for the entire site Substantial Completion (Buildings) August 15, 2011
• Carter Construction is scheduled to begin construction of the track
and field in two weeks
• Southern Bleachers is scheduled to begin drilling piers for the
structural columns that support the metal bleachers.
• Substantial completion is scheduled for August 1. Students and
staff may begin using the track and field on this day.
Huckabee
Georgetown Independent School District 4
5. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Field House Building Pad Rough Grading at Main Drive and Parking Lot
Under Slab Plumbing at Concession Building Under Slab Plumbing at Concession Building
Huckabee
Georgetown Independent School District 5
6. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1
Discus and Shot Put Rough Grading at Track and Field
Rock Excavation near Concession Building
Huckabee
Georgetown Independent School District 6
7. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
Budget Amount: $29,735,120
I
New Athletic Addition
I
J
H
H
F
G J
H
J
First Floor
Bid Package 1
A
B J
Existing East View
J High School B
A. New Athletic Addition
B. New Fine Arts Addition New Fine Arts Addition
D
E C. New Academic Addition
C
D. New CTE Building
New Academic Addition
E. New ROTC Addition (Alt.)
CR
10 F. New Tennis Courts
4
ay
29 G. New Tennis Building
hw
Hig H. New Baseball/Softball Fieldhouse,
Bleachers, Lighting & Pressbox
I. New Practice Fields
J. New Parking (1,070 spaces)
New Academic Addition
CTE Building
New CTE Addition
Second Floor
Academic Wing Softball Field House Huckabee
Georgetown Independent School District 7
8. 2010 BOND PROGRAM UPDATE
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2
PROGRESS REPORT
MILESTONE DATES
Schematic Design Presentation January 1, 2011
Architect Signs Documents March 8, 2011
Building Permit Application Submittal March 15, 2011
Site Plan Application Submittal March 17, 2011
Pre-Proposal Meeting March 22, 2011
Tour with General Contractors at East View Ninth Grade Center March 30, 2011
Proposal Part A Due April 5, 2011
Proposal Part B Due April 6, 2011
Proposal Evaluations April 7, 2011
General Contractor Recommendation to School Board April 18, 2011
First Owner/CO Meeting TBD
Construction Start Date April 25, 2011
Substantial Completion June 27, 2012
Huckabee
Georgetown Independent School District 8
9. 2010 BOND PROGRAM UPDATE General Contractor
NEW WAREHOUSE FACILITY
Contract Amount: $641,000
Shed
Existing Support Services
ALTERNATE #2
Warehouse Shop - Floor Plan
Facility
ALTERNATE #1
Warehouse Facility - Floor Plan
Existing Bus Wash Bay
Site Plan Huckabee
Georgetown Independent School District
Georgetown Independent School District 9
9
10. 2010 BOND PROGRAM UPDATE General Contractor
NEW WAREHOUSE FACILITY
PROGRESS REPORT
MILESTONE DATES
Schematic Design Presentation January 10, 2011
Architect Signs Documents January 12, 2011
Building Permit Application Submittal January 25, 2011
Proposal Part A Due February 15, 2011
Proposal Part B Due February 16, 2011
Site Plan Application Submittal February 17, 2011
Proposal Evaluations February 17, 2011
School Board Selects CSS, Inc. as General Contractor March 7, 2011
Job Coordination Meeting March 25, 2011
Construction Start Date April 5, 2011
Substantial Completion August 12, 2011
Huckabee
Georgetown Independent School District 10
11. 2010 BOND PROGRAM UPDATE General Contractor
ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATIONS
Contract Amount: $229,000
MILESTONE DATES
Schematic Design Presentation January 10, 2011
Architect Signs Documents February 3, 2011
A
Pre-Proposal Meeting February 9, 2011
B B
HVAC Unit HVAC Unit
Proposal Part A Due February 22, 2011
Proposal Part B Due February 23, 2011
Proposal Evaluations February 24, 2011
School Board Selects Saratoga as General Contractor March 7, 2011
First Owner/CO Meeting TBD
A. Replace Roof
B. New HVAC Units Construction Start Date June 6, 2011
A A C. New Metal Coping on Parapets
D. New Gutter and Downspouts Substantial Completion August 12, 2011
C
B
HVAC Unit D
A
Roof Plan
Huckabee
Georgetown Independent School District 11
12. 2010 BOND PROGRAM UPDATE
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
Conceptual Floor Plan
Huckabee
Georgetown Independent School District 12
13. 2010 BOND PROGRAM UPDATE
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS
MILESTONE DATES
Design Kick-off Meeting with Librarian, Science Dept.
February 28, 2011
and Nurse
Design Kick-off Meeting with Athletics March 1, 2011
Initial Construction Phasing with Stakeholders March 3, 2011
Design Kick-off Meeting with Special Education March 4, 2011
Design Kick-off Meeting with Administration March 10, 2011
Advertisement for Construction Manager at Risk RFQ March 12, 2011
Received Construction Manager at Risk Step 1
March 29, 2011
(Qualifications)
Evaluation Team Grades and Develops Recommended
March 30, 2011
Short List
School Board Receives Recommended Short List April 4, 2011
Step 2 of RFQ Submitted to Short Listed Contractors
April 5, 2011
(Fees and General Conditions)
Fees and General Conditions due by 3 PM April 8, 2011
Board of Trustees Interview and Select Construction
March 1, 2011
Manager at Risk
Schematic Design Presentation May 2, 2011
Architect Signs Documents August 11, 2011
First Owner/CO Meeting TBD
Construction Start Date October 2011
Substantial Completion July 2013
Huckabee
Georgetown Independent School District 13