18. Objectives with Vital Signs
• Bring
visibility
into
all
5
project
levers
• Simple,
quan9ta9ve,
near-‐real
9me
metrics
• Publish
to
charts
in
full
public
display
• Where
possible
include
history
and
trends
19. Project Vital Signs
1) Scope Burn Up
2) Current State of Delivery
3) Budget Burn Down
4) Delivery Quality
5) Team Dynamics
63. What is the Current State
of the Project?
Not going to make it.
64. What is the Diagnosis?
The team is firing on all cylinders.
Quality is good.
Not enough time to deliver the full
backlog for the September 9th release.
Not enough money to carry us through
the warranty period ending September
23rd.
65. What is the Treatment?
Release on Aug 26th instead of Sep 9th.
Includes 35 stories that are ready for,
currently in or have passed QA.
Remaining 20 stories to be included
in a future release, budgeted for
at a later time.