Summary of Downtown Charlotte Amalie Revitalization Projects as of September 2012.
Presented by Dept. of Public Works at DRI's Forum on Main Street and Waterfront Enhancements on October 2012
http://www.downtownrevitalizationinc.com
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Summary of Downtown Charlotte Amalie Revitalization Projects as of September 2012
1. DOWNTOWN CHARLOTTE AMALIE REVITALIZATION PROJECTS
4. FIRE STATION/HOTEL COMPANY 8. DOWNTOWN SIDE STREETS
Design is 99% Involves work on Nye
1. ROTHSCHILD FRANCIS “MARKET SQUARE” complete. Project Gade, Stor Tove Gade
REHABILITATION PROJECT went to FHWA for and Back Street.
authorization in Estimated cost at $1.8
July 2012. FHWA million. Initial funding
is paying for 73% from Department of
of the project Interior grant.
cost. Project is To be put out to bid.
programmed
in FY2012 TTIP. DOI and local Funds. 9. WAPA ELECTRIC UNDERGROUND
Project is currently in construction. Estimated Construction to start 1Q FY2013. (Main Street)
completion date is April 2013. Project is 34% Installation of
complete. 5. FORT CHRISTIAN underground
2. VETERANS DRIVE - PHASE I Contract has been duct bank with
terminated. Project is electrical manholes,
currently in litigation, communication
which is being manhole, pad-
handled by DOJ. mounted transformers.
Seeking funding. Project cost funded by
FEMA Hazard Mitigation Grant at $2.1 million.
Design is now 60%
6. FORT CHRISTIAN PARKING LOT Estimated completion FQ FY2013.
complete. CZM
application submitted June 7, 2012, and RFP is being
drafted for 10. THE TOWN’S BLUEPRINT
deemed complete September 14, 2012. The first step in creating a new Form-Based
Programmed in FY2013 TTIP. Start 2Q FY2013. issuance in the
1Q FY2013. Code (“FBC”) District
within the historic core
3. VETERANS DRIVE - PHASE II of Charlotte Amalie
Design is more than 30% complete. 7. MAIN STREET ENHANCEMENT
as the initial area of
First citizen advisory group The design is
focus. The FBC will be
meeting held on June 14, 2012 90% complete.
a special component
to provide Project went
of the zoning and
comments to FHWA for
subdivision update.
on project authorization in
aesthetics. July 2012. Project 11. HARBOR TRANSPORTATION
Environmental is programmed Development of water
document is for FY2013 TTIP. transportation apparatus in
currently being Construction the port of Charlotte Amalie
updated. Design to be completed May/June to start in 3Q under the auspices of VITRAN.
2013. Seek funding 2Q FY2013. FY2013. Currently awaiting utilities. An RFP for a consultant has
been issued by DPW.
2. PROJECTED COMPLETION SCHEDULE
PROJECT Name of Actual/ Estimated Amount Expended Actual/ Estimated
NO. FUNDED AMOUNTS AGENCY
DESCRIPTION Contractors Total Fund Budget To Date Project Start Date
MARKET SQAURE
1 Island Roads $5,499,620.00 $5,499,620.00 FHWA $1,857,311.50 34% Sep-11
REHABILITATION
VETERANS DRIVE Parsons Phase 1/ Feb-13
2&3 $63,518,699.00 $23,518,699.00 FHWA $4,741,622.19 7%
PHASE I & 2 Brinckerhoff Phase 2/ May-14
FIRE STATION/ Parsons FHWA/PFA
4 $5,600,000.00 $11,000,000.00 Dec-12
HOTEL COMPANY Brinckerhoff OOI/CIP
-
Tip Top FHWA/DPNR
5 FORT CHRISTIAN $4,477,726.92 $4,477,726.92 $3,780,734.79 84%
Construction, Inc. PFA
-
FORT CHRISTIAN
6 TBD $2,580,000.00 FHWA/PFA
PARKING LOT
- - -
MAIN STREET Jaredian
7 $8,245,281.72 $8,245,281.72 100% FHWA $430,306.96 5% May-13
ENHANCEMENT Design Group
SIDE STREETS
• Nye*Gade
Nye
8 • Raadet’s Gade
*Raadet's Gade TBD $3,506,000.00 DOI 0%
• StorTove Gade
*Stor Tove Gade
*Back Street
- - -
• Back Street
WAPA ELECTRIC
9
UNDERGROUND
Fortress Electric $2,180,405.00 $2,180,405.00 FEMA
- Sep-11
Funded by Driehaus
Dover, Kohl &
Charitable Trust &
THE TOWN'S Partners
10
BLUEPRINT DPW
DPNR
- The Community
Foundation of the
DPNR/ DPW
- Dec-11
Virgin Islands
HARBOR
11 RFP Issued DPW Dec-12
TRANSPORTAION - - -
TOTAL $95,607,732.64 $54,921,732.64 57% $10,379,668.48 11%
Composed by the Virgin Islands Department of Public Works and the Office of the Governor - Status as of September 30, 2012