SlideShare ist ein Scribd-Unternehmen logo
1 von 2
Salford City College
Eccles Sixth Form Centre
BTec Level 3
Extended Diploma in Creative Media Production
Games Design
Final Major Project
Production Log
Name Jason Finch
Date Comments
Wednesday
27.02.13
This week, I booked my meeting with my Project Manager for March 5
th
, in this I have to do a pitch about my project.
I started my project this week by researching popular kids shows from around the 50’s and those at this present day and why. There were a few iconic ones I found such as Tom
and Jerry, Regular Show etc. I also researched the environments from the 50’s and in the future.
I also had to research Cell Animations to see what it is and how it works, since I am doing a Cell Animation for my FMP.
Finally, from my research I collected earlier in that week, I started thinking of story ideas that could blend both classic and modern cartoon show elements together.
Wednesday
06.03.13
This week, I continued story planning and developed a Story Board, coming up with a Sci-Fi Sitcom that involves Time-Travel; I also researched shows which were popular from
surveys that I made last week like Tom and Jerry, Ed Edd n Eddy, Adventure Time etc.
I did my pitch this week as well, explaining what I plan to do with my FMP, what I have been researching, what I have found etc. I talked about the environment of both the past
and the future, even technology from the past and future and the cartoons made past and present.
Wednesday
13.03.13
I began researching my findings to get an idea of what sort of humour was in those cartoons and take ideas from those. I also finished it within the same week and began to get
more ideas for my story, I also got the risk assessment done this week, making myself aware of possible hazards and how they can happen.
Wednesday
20.03.13
This week I did the pre-production of my FMP, I had to figure out how much everything I would need to do my FMP would cost, getting all of the stuff I needed etc.
Wednesday
27.03.13
I didn’t produce anything this week.
Wednesday
03.04.13
This week, I made a start at producing the backgrounds that I plan to use based on the storyboards I did, I decided to design them in black and white because most cartoons in
the past were in a Black and White Style. The backgrounds I did this week were both outside buildings next to roads.
Wednesday
10.04.13
I had finished all my black and white backgrounds this week and moved on to start designing different backgrounds for Flash, most of which were based in a single room from
different perspectives, from the back, the front, etc.
Wednesday
17.04.13
I updated my schedule this week as I knew that I wasn’t going to have enough time to finish the project off, so I extended it by taking 2 weeks off my spare time. I started doing
the Animations of my Characters. I started with the Futuristic Scenes since I had already done those on Flash.
I did the Scene of when the Main Character “Tinuem”, goes to the future. I got half way through doing this since this was a really long Scene.
Wednesday
24.04.13
I finished 2 scenes this week; including the one I got half way though. The second Scene that I finished was of hover cars flying outside as my main character was looking at them.
I started work on the scene where Tinuem’s Future self finds his past self in his home, mistaking him for an intruder.
Wednesday
01.05.13
I finished the Scene mentioned last week while moving onto the scene where the 2 Tinuems are talking to one another. However, during the week, the file got corrupt so I had to
start again from the previous file, I did manage to catch up with my work by the end of the week though by getting half way through the second scene again. I then began the
scene where Future Tinuem explains about the robot power core and what dangerous effects it could cause if not properly used.
Wednesday
08.05.13
I finished the explanation scene midway through the week. I then did the final scene where Past Tinuem returns to his own time. I also did a Title scene and a To be continued
scene. I also had to edit my schedule since I didn’t feel that I would have enough time to finish.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (19)

Thriller opening proposal new
Thriller opening proposal newThriller opening proposal new
Thriller opening proposal new
 
Thriller opening proposal new
Thriller opening proposal newThriller opening proposal new
Thriller opening proposal new
 
Diary of a day shooting 3
Diary of a day shooting 3Diary of a day shooting 3
Diary of a day shooting 3
 
Copyright power point
Copyright power pointCopyright power point
Copyright power point
 
The pitch
The pitchThe pitch
The pitch
 
Frank's day quiz
Frank's day quizFrank's day quiz
Frank's day quiz
 
Cttc Productions Film Pitch
Cttc Productions Film PitchCttc Productions Film Pitch
Cttc Productions Film Pitch
 
1. initial plans mv 2018 (1)
1. initial plans mv 2018 (1)1. initial plans mv 2018 (1)
1. initial plans mv 2018 (1)
 
Question 1
Question 1Question 1
Question 1
 
Blind spot
Blind spotBlind spot
Blind spot
 
Blind spot
Blind spotBlind spot
Blind spot
 
Blind spot
Blind spotBlind spot
Blind spot
 
2. fmp proposal
2. fmp proposal2. fmp proposal
2. fmp proposal
 
Blind spot
Blind spotBlind spot
Blind spot
 
Evidence and organisation
Evidence and organisationEvidence and organisation
Evidence and organisation
 
2. fmp proposal
2. fmp proposal2. fmp proposal
2. fmp proposal
 
Assignment 4 slide show.
Assignment 4 slide show.Assignment 4 slide show.
Assignment 4 slide show.
 
Question 1
Question 1Question 1
Question 1
 
1. initial plans
1. initial plans1. initial plans
1. initial plans
 

Ähnlich wie 1950s and Future Cartoons

Fmp production log_10th_apr_2013
Fmp production log_10th_apr_2013Fmp production log_10th_apr_2013
Fmp production log_10th_apr_2013Jason
 
Fmp production log_17th_apr_2013
Fmp production log_17th_apr_2013Fmp production log_17th_apr_2013
Fmp production log_17th_apr_2013Jason
 
Fmp production log_3rd_apr_2013
Fmp production log_3rd_apr_2013Fmp production log_3rd_apr_2013
Fmp production log_3rd_apr_2013Jason
 
Fmp production log_20th_mar_2013
Fmp production log_20th_mar_2013Fmp production log_20th_mar_2013
Fmp production log_20th_mar_2013Jason
 
Fmp production log_27th_mar_2013
Fmp production log_27th_mar_2013Fmp production log_27th_mar_2013
Fmp production log_27th_mar_2013Jason
 
Fmp production log_13th_mar_2013
Fmp production log_13th_mar_2013Fmp production log_13th_mar_2013
Fmp production log_13th_mar_2013Jason
 
Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013Jason
 
Fmp production log_finished
Fmp production log_finishedFmp production log_finished
Fmp production log_finishedwarburton9191
 
Fmp production log_27th_feb_2013
Fmp production log_27th_feb_2013Fmp production log_27th_feb_2013
Fmp production log_27th_feb_2013Jason
 
5. pre production
5. pre production5. pre production
5. pre productionJack Bevens
 
Factual proposal
Factual proposalFactual proposal
Factual proposalLily809411
 
Fmp production log
Fmp production logFmp production log
Fmp production logdontask5555
 
3. Problem Solving and Experiments.pptx
3. Problem Solving and Experiments.pptx3. Problem Solving and Experiments.pptx
3. Problem Solving and Experiments.pptxSecurityPuppetProduc
 

Ähnlich wie 1950s and Future Cartoons (20)

Fmp production log_10th_apr_2013
Fmp production log_10th_apr_2013Fmp production log_10th_apr_2013
Fmp production log_10th_apr_2013
 
Fmp production log_17th_apr_2013
Fmp production log_17th_apr_2013Fmp production log_17th_apr_2013
Fmp production log_17th_apr_2013
 
Fmp production log_3rd_apr_2013
Fmp production log_3rd_apr_2013Fmp production log_3rd_apr_2013
Fmp production log_3rd_apr_2013
 
Fmp production log_20th_mar_2013
Fmp production log_20th_mar_2013Fmp production log_20th_mar_2013
Fmp production log_20th_mar_2013
 
Fmp production log_27th_mar_2013
Fmp production log_27th_mar_2013Fmp production log_27th_mar_2013
Fmp production log_27th_mar_2013
 
Fmp production log_13th_mar_2013
Fmp production log_13th_mar_2013Fmp production log_13th_mar_2013
Fmp production log_13th_mar_2013
 
Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013
 
Fmp production log_finished
Fmp production log_finishedFmp production log_finished
Fmp production log_finished
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
Fmp production log_27th_feb_2013
Fmp production log_27th_feb_2013Fmp production log_27th_feb_2013
Fmp production log_27th_feb_2013
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
5. pre production
5. pre production5. pre production
5. pre production
 
Reflection - FMP
Reflection - FMPReflection - FMP
Reflection - FMP
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
Factual proposal
Factual proposalFactual proposal
Factual proposal
 
4. Pre-Production.pptx
4. Pre-Production.pptx4. Pre-Production.pptx
4. Pre-Production.pptx
 
Fmp production log
Fmp production logFmp production log
Fmp production log
 
3. Problem Solving and Experiments.pptx
3. Problem Solving and Experiments.pptx3. Problem Solving and Experiments.pptx
3. Problem Solving and Experiments.pptx
 

Mehr von Jason

Final project schedule 22nd may 2013
Final project schedule 22nd may 2013Final project schedule 22nd may 2013
Final project schedule 22nd may 2013Jason
 
Final project schedule 15th may 2013
Final project schedule 15th may 2013Final project schedule 15th may 2013
Final project schedule 15th may 2013Jason
 
Final project schedule 8th may 2013
Final project schedule 8th may 2013Final project schedule 8th may 2013
Final project schedule 8th may 2013Jason
 
Production log e6 9 november
Production log e6 9 novemberProduction log e6 9 november
Production log e6 9 novemberJason
 
Production log e6 7 december
Production log e6 7 decemberProduction log e6 7 december
Production log e6 7 decemberJason
 
Production log e6 30 november
Production log e6 30 novemberProduction log e6 30 november
Production log e6 30 novemberJason
 
Production log e6 26 october
Production log e6 26 octoberProduction log e6 26 october
Production log e6 26 octoberJason
 
Production log e6 23 november
Production log e6 23 novemberProduction log e6 23 november
Production log e6 23 novemberJason
 
Production log e6 2 november
Production log e6 2 novemberProduction log e6 2 november
Production log e6 2 novemberJason
 
Production log e6 16 november
Production log e6 16 novemberProduction log e6 16 november
Production log e6 16 novemberJason
 
Production log e6 14 december
Production log e6 14 decemberProduction log e6 14 december
Production log e6 14 decemberJason
 
Unit6 cacmp response_240112_01
Unit6 cacmp response_240112_01Unit6 cacmp response_240112_01
Unit6 cacmp response_240112_01Jason
 
L3 gd unit6cacmp_task3_121211
L3 gd unit6cacmp_task3_121211L3 gd unit6cacmp_task3_121211
L3 gd unit6cacmp_task3_121211Jason
 
Final project schedule 1st may 2013
Final project schedule 1st may 2013Final project schedule 1st may 2013
Final project schedule 1st may 2013Jason
 
App questionnaire results
App questionnaire resultsApp questionnaire results
App questionnaire resultsJason
 
L3 gd ethical_061111_01
L3 gd ethical_061111_01L3 gd ethical_061111_01
L3 gd ethical_061111_01Jason
 
L3 gd ip_061111_01
L3 gd ip_061111_01L3 gd ip_061111_01
L3 gd ip_061111_01Jason
 
L3 gd contractual_061111_01
L3 gd contractual_061111_01L3 gd contractual_061111_01
L3 gd contractual_061111_01Jason
 

Mehr von Jason (18)

Final project schedule 22nd may 2013
Final project schedule 22nd may 2013Final project schedule 22nd may 2013
Final project schedule 22nd may 2013
 
Final project schedule 15th may 2013
Final project schedule 15th may 2013Final project schedule 15th may 2013
Final project schedule 15th may 2013
 
Final project schedule 8th may 2013
Final project schedule 8th may 2013Final project schedule 8th may 2013
Final project schedule 8th may 2013
 
Production log e6 9 november
Production log e6 9 novemberProduction log e6 9 november
Production log e6 9 november
 
Production log e6 7 december
Production log e6 7 decemberProduction log e6 7 december
Production log e6 7 december
 
Production log e6 30 november
Production log e6 30 novemberProduction log e6 30 november
Production log e6 30 november
 
Production log e6 26 october
Production log e6 26 octoberProduction log e6 26 october
Production log e6 26 october
 
Production log e6 23 november
Production log e6 23 novemberProduction log e6 23 november
Production log e6 23 november
 
Production log e6 2 november
Production log e6 2 novemberProduction log e6 2 november
Production log e6 2 november
 
Production log e6 16 november
Production log e6 16 novemberProduction log e6 16 november
Production log e6 16 november
 
Production log e6 14 december
Production log e6 14 decemberProduction log e6 14 december
Production log e6 14 december
 
Unit6 cacmp response_240112_01
Unit6 cacmp response_240112_01Unit6 cacmp response_240112_01
Unit6 cacmp response_240112_01
 
L3 gd unit6cacmp_task3_121211
L3 gd unit6cacmp_task3_121211L3 gd unit6cacmp_task3_121211
L3 gd unit6cacmp_task3_121211
 
Final project schedule 1st may 2013
Final project schedule 1st may 2013Final project schedule 1st may 2013
Final project schedule 1st may 2013
 
App questionnaire results
App questionnaire resultsApp questionnaire results
App questionnaire results
 
L3 gd ethical_061111_01
L3 gd ethical_061111_01L3 gd ethical_061111_01
L3 gd ethical_061111_01
 
L3 gd ip_061111_01
L3 gd ip_061111_01L3 gd ip_061111_01
L3 gd ip_061111_01
 
L3 gd contractual_061111_01
L3 gd contractual_061111_01L3 gd contractual_061111_01
L3 gd contractual_061111_01
 

1950s and Future Cartoons

  • 1. Salford City College Eccles Sixth Form Centre BTec Level 3 Extended Diploma in Creative Media Production Games Design Final Major Project Production Log Name Jason Finch Date Comments Wednesday 27.02.13 This week, I booked my meeting with my Project Manager for March 5 th , in this I have to do a pitch about my project. I started my project this week by researching popular kids shows from around the 50’s and those at this present day and why. There were a few iconic ones I found such as Tom and Jerry, Regular Show etc. I also researched the environments from the 50’s and in the future. I also had to research Cell Animations to see what it is and how it works, since I am doing a Cell Animation for my FMP. Finally, from my research I collected earlier in that week, I started thinking of story ideas that could blend both classic and modern cartoon show elements together. Wednesday 06.03.13 This week, I continued story planning and developed a Story Board, coming up with a Sci-Fi Sitcom that involves Time-Travel; I also researched shows which were popular from surveys that I made last week like Tom and Jerry, Ed Edd n Eddy, Adventure Time etc. I did my pitch this week as well, explaining what I plan to do with my FMP, what I have been researching, what I have found etc. I talked about the environment of both the past and the future, even technology from the past and future and the cartoons made past and present. Wednesday 13.03.13 I began researching my findings to get an idea of what sort of humour was in those cartoons and take ideas from those. I also finished it within the same week and began to get more ideas for my story, I also got the risk assessment done this week, making myself aware of possible hazards and how they can happen. Wednesday 20.03.13 This week I did the pre-production of my FMP, I had to figure out how much everything I would need to do my FMP would cost, getting all of the stuff I needed etc. Wednesday 27.03.13 I didn’t produce anything this week. Wednesday 03.04.13 This week, I made a start at producing the backgrounds that I plan to use based on the storyboards I did, I decided to design them in black and white because most cartoons in the past were in a Black and White Style. The backgrounds I did this week were both outside buildings next to roads. Wednesday 10.04.13 I had finished all my black and white backgrounds this week and moved on to start designing different backgrounds for Flash, most of which were based in a single room from different perspectives, from the back, the front, etc. Wednesday 17.04.13 I updated my schedule this week as I knew that I wasn’t going to have enough time to finish the project off, so I extended it by taking 2 weeks off my spare time. I started doing the Animations of my Characters. I started with the Futuristic Scenes since I had already done those on Flash. I did the Scene of when the Main Character “Tinuem”, goes to the future. I got half way through doing this since this was a really long Scene. Wednesday 24.04.13 I finished 2 scenes this week; including the one I got half way though. The second Scene that I finished was of hover cars flying outside as my main character was looking at them. I started work on the scene where Tinuem’s Future self finds his past self in his home, mistaking him for an intruder.
  • 2. Wednesday 01.05.13 I finished the Scene mentioned last week while moving onto the scene where the 2 Tinuems are talking to one another. However, during the week, the file got corrupt so I had to start again from the previous file, I did manage to catch up with my work by the end of the week though by getting half way through the second scene again. I then began the scene where Future Tinuem explains about the robot power core and what dangerous effects it could cause if not properly used. Wednesday 08.05.13 I finished the explanation scene midway through the week. I then did the final scene where Past Tinuem returns to his own time. I also did a Title scene and a To be continued scene. I also had to edit my schedule since I didn’t feel that I would have enough time to finish.