Safety First
Our Safety Statistics
2011 2012 2013 2014 2015
YTD*
Hours Worked 788,079 701,814 850,233 1,070,244 190,425
Average #
Employees
392 378 446 557 573
Lost time injury
cases
1 0 0 0 0
OSHA recordables 2 0 0 0 0
We’ve worked over 3.23 million hours and 1,345 days
since our last lost time injury.
Our goal?
No one gets hurt. Ever.
* Through 3/3/2015
About Us …
Our Profile
• Founded in Bellingham, WA in 1971 on the belief that
when a service provider meets or exceeds client
expectations they will be rewarded with more work
• Specialize in providing project management, engineering,
procurement, and construction coordination services
• Serve the oil and gas industry
– 98% of our work is process plant related
– Mostly small to medium projects, generally under $20MM
total installed cost (TIC)
– Often larger projects, $50MM - $200MM TIC
– Typically programs of multiple projects
Engineering & Design
• Process
• Civil
• Structural
• Mechanical Equipment
• HVAC/Fire Protection
• Piping
– Laser Scanning
• Control Systems
• Electrical
• Procurement
Project Management
• Project Management
• Project Controls
– Total Project Reporting
• Information Technology
• Technical Writing
• Document Services
Field Services
• Construction Coordination
• Field Engineering
• QA/QC
– Field Inspection
– Shop Inspection
About Us …
About Us …
Our Make-up
• Home Office
– Bellingham, WA (Since 1971) 415
• Branch Offices
– Billings, MT (Since 1999) 115
– Concord, CA (Since 2001) 15
• Joint Venture
– Doyon Anvil, Alaska 60
605
About Us …
Our People
• Employee owners – We are 100% ESOP-owned Company
• Client focused
• Unusually deep in technical expertise
• Committed - Low turnover
• Share common values
About Us …
Project Services
Manager
Walter Michelutti
Billings Branch
Manager
Dan Oakes
Doyon Anvil
President, General
Manager
Werner Plagge
President
Gordy Lindell
Safety Manager
Eric Peterson
Manager of
Resources
Ross Warne
Information
Technology
Services Manager
Doug Williams
Manager of
Programs
Jim Turner
Concord Branch
Manager
Jeff Wong
Business Services
Manager
Rob Farrow
BD/Marketing
Manager
Jim Jansky
Quality Manager
Ken Koenig
Our Primary Clients …
Refining
• BP
• CHS
• Chevron
– West Coast Facilities
• Exxon Mobil
• Flint Hills Resources
• Holly Frontier Oil
• Husky Energy
• Petro Star
• Phillips 66
– Billings
– Ferndale
– Rodeo
• Shell
• Tesoro
• US Oil
• Valero
Oil & Gas Production
• BP Exploration
• Caelus Energy
• Cook Inlet Energy
• ConocoPhillips Alaska
• ConocoPhillips LCGP
• Doyon Emerald
• Hilcorp
• Marathon
• XTO Energy
Gas & Liquid Pipelines & Terminals
• Alyeska Pipeline
• BP Pipelines
• BP Terminals
• Chevron Terminals
• Corval/ONEOK
• Phillips 66 Pipelines & Transportation
Our Expertise …
• Process Plants
– 98% of our work is process plant related
• Fit for purpose design
– Delivering just what the project requires
• Modular design
– Optimizing local fabrication and construction know-how
• Project Size
– Mostly small to medium, generally under $20MM TIC
– Often larger projects, $50MM - $200MM TIC
Our Strengths …
We’re really good at…
• Solving tough problems
• Implementing client methods and preferences
• Cooperating with all project participants to ensure overall
project success
– Taking an Owner’s view
– Coordination and Planning with Constructor
– Procurement and Expediting on Schedule Driven Projects
• Being a flexible organization
– Adapting and supplementing to meet the needs
• Controlling Projects
– Being a steward of our clients time and money
To Contact Us …
Corporate Office: Billings Office:
1675 West Bakerview Road 1015 Broadwater Ave.
Bellingham, WA 98226 Billings, MT 59102
360.671.1450 406.245.9258
Primary Contact: Primary Contact:
James M. Jansky, Sr. V.P. Daniel Oakes
Marketing Manager Branch Manager
360.937.0550 406.238.1250
jjansky@anvilcorp.com doakes@anvilcorp.com

Weitere ähnliche Inhalte

Ähnlich wie About Anvil Presentation Mar 2015 Billings

OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGY
OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGYOPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGY
OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGYwle-ss
 
Fisher Practice Areas 2012
Fisher Practice Areas 2012Fisher Practice Areas 2012
Fisher Practice Areas 2012fish1960
 
PiT 29 October 2014 Presentation - Seqwater
PiT 29 October 2014 Presentation - SeqwaterPiT 29 October 2014 Presentation - Seqwater
PiT 29 October 2014 Presentation - SeqwaterDigital Queensland
 
Process Skid Engineering - EPIC Process Systems
Process Skid Engineering - EPIC Process SystemsProcess Skid Engineering - EPIC Process Systems
Process Skid Engineering - EPIC Process SystemsEPIC Systems
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald MorrisFloridaPipeTalk
 
Preparing for growt: How Odfjell Drilling is benefiting from running IFS App...
Preparing  for growt: How Odfjell Drilling is benefiting from running IFS App...Preparing  for growt: How Odfjell Drilling is benefiting from running IFS App...
Preparing for growt: How Odfjell Drilling is benefiting from running IFS App...IFS
 
Progressive G Lobal Energy
Progressive G Lobal EnergyProgressive G Lobal Energy
Progressive G Lobal Energyoanaene
 
Build Your Business On Dell Technology: Dell OEM Solutions
Build Your Business On Dell Technology: Dell OEM SolutionsBuild Your Business On Dell Technology: Dell OEM Solutions
Build Your Business On Dell Technology: Dell OEM SolutionsDell World
 
NCB PROFILE - with vocational training
NCB PROFILE - with vocational trainingNCB PROFILE - with vocational training
NCB PROFILE - with vocational trainingrsadekar
 
Fire alarm ppt_presentation_to_suppliers_november_2015
Fire alarm ppt_presentation_to_suppliers_november_2015Fire alarm ppt_presentation_to_suppliers_november_2015
Fire alarm ppt_presentation_to_suppliers_november_2015MuhamedAshraf4
 
MTI Power Presentation R6 Dated 02-09-2016
MTI Power Presentation R6 Dated 02-09-2016MTI Power Presentation R6 Dated 02-09-2016
MTI Power Presentation R6 Dated 02-09-2016Stephen Shoemaker
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience PresentationJerry Rodgers
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience PresentationJerry Rodgers
 
Point energy llp final_pres
Point energy llp final_presPoint energy llp final_pres
Point energy llp final_presJing Deng
 
JDD-Resume (4) (1)
JDD-Resume (4) (1)JDD-Resume (4) (1)
JDD-Resume (4) (1)James Drapal
 
Perficient's Reliable Asset World Keynote
Perficient's Reliable Asset World KeynotePerficient's Reliable Asset World Keynote
Perficient's Reliable Asset World KeynotePerficient, Inc.
 
Cleared Job Fair Handbook | November 15
Cleared Job Fair Handbook | November 15Cleared Job Fair Handbook | November 15
Cleared Job Fair Handbook | November 15ClearedJobs.Net
 
Honeywell MD Offerings Brochure
Honeywell MD Offerings BrochureHoneywell MD Offerings Brochure
Honeywell MD Offerings BrochureAdam J. Yoder
 

Ähnlich wie About Anvil Presentation Mar 2015 Billings (20)

OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGY
OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGYOPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGY
OPERATOR ANALYTICS FROM IMPLEMENTING AN OPERATE BY EXCEPTION STRATEGY
 
Fisher Practice Areas 2012
Fisher Practice Areas 2012Fisher Practice Areas 2012
Fisher Practice Areas 2012
 
PiT 29 October 2014 Presentation - Seqwater
PiT 29 October 2014 Presentation - SeqwaterPiT 29 October 2014 Presentation - Seqwater
PiT 29 October 2014 Presentation - Seqwater
 
Solectron Case Study
Solectron Case StudySolectron Case Study
Solectron Case Study
 
Process Skid Engineering - EPIC Process Systems
Process Skid Engineering - EPIC Process SystemsProcess Skid Engineering - EPIC Process Systems
Process Skid Engineering - EPIC Process Systems
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
 
Preparing for growt: How Odfjell Drilling is benefiting from running IFS App...
Preparing  for growt: How Odfjell Drilling is benefiting from running IFS App...Preparing  for growt: How Odfjell Drilling is benefiting from running IFS App...
Preparing for growt: How Odfjell Drilling is benefiting from running IFS App...
 
Progressive G Lobal Energy
Progressive G Lobal EnergyProgressive G Lobal Energy
Progressive G Lobal Energy
 
Paul O'Halloran CV
Paul O'Halloran CV Paul O'Halloran CV
Paul O'Halloran CV
 
Build Your Business On Dell Technology: Dell OEM Solutions
Build Your Business On Dell Technology: Dell OEM SolutionsBuild Your Business On Dell Technology: Dell OEM Solutions
Build Your Business On Dell Technology: Dell OEM Solutions
 
NCB PROFILE - with vocational training
NCB PROFILE - with vocational trainingNCB PROFILE - with vocational training
NCB PROFILE - with vocational training
 
Fire alarm ppt_presentation_to_suppliers_november_2015
Fire alarm ppt_presentation_to_suppliers_november_2015Fire alarm ppt_presentation_to_suppliers_november_2015
Fire alarm ppt_presentation_to_suppliers_november_2015
 
MTI Power Presentation R6 Dated 02-09-2016
MTI Power Presentation R6 Dated 02-09-2016MTI Power Presentation R6 Dated 02-09-2016
MTI Power Presentation R6 Dated 02-09-2016
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience Presentation
 
Overview of Experience Presentation
Overview of Experience PresentationOverview of Experience Presentation
Overview of Experience Presentation
 
Point energy llp final_pres
Point energy llp final_presPoint energy llp final_pres
Point energy llp final_pres
 
JDD-Resume (4) (1)
JDD-Resume (4) (1)JDD-Resume (4) (1)
JDD-Resume (4) (1)
 
Perficient's Reliable Asset World Keynote
Perficient's Reliable Asset World KeynotePerficient's Reliable Asset World Keynote
Perficient's Reliable Asset World Keynote
 
Cleared Job Fair Handbook | November 15
Cleared Job Fair Handbook | November 15Cleared Job Fair Handbook | November 15
Cleared Job Fair Handbook | November 15
 
Honeywell MD Offerings Brochure
Honeywell MD Offerings BrochureHoneywell MD Offerings Brochure
Honeywell MD Offerings Brochure
 

About Anvil Presentation Mar 2015 Billings

  • 2. Safety First Our Safety Statistics 2011 2012 2013 2014 2015 YTD* Hours Worked 788,079 701,814 850,233 1,070,244 190,425 Average # Employees 392 378 446 557 573 Lost time injury cases 1 0 0 0 0 OSHA recordables 2 0 0 0 0 We’ve worked over 3.23 million hours and 1,345 days since our last lost time injury. Our goal? No one gets hurt. Ever. * Through 3/3/2015
  • 3. About Us … Our Profile • Founded in Bellingham, WA in 1971 on the belief that when a service provider meets or exceeds client expectations they will be rewarded with more work • Specialize in providing project management, engineering, procurement, and construction coordination services • Serve the oil and gas industry – 98% of our work is process plant related – Mostly small to medium projects, generally under $20MM total installed cost (TIC) – Often larger projects, $50MM - $200MM TIC – Typically programs of multiple projects
  • 4. Engineering & Design • Process • Civil • Structural • Mechanical Equipment • HVAC/Fire Protection • Piping – Laser Scanning • Control Systems • Electrical • Procurement Project Management • Project Management • Project Controls – Total Project Reporting • Information Technology • Technical Writing • Document Services Field Services • Construction Coordination • Field Engineering • QA/QC – Field Inspection – Shop Inspection About Us …
  • 5. About Us … Our Make-up • Home Office – Bellingham, WA (Since 1971) 415 • Branch Offices – Billings, MT (Since 1999) 115 – Concord, CA (Since 2001) 15 • Joint Venture – Doyon Anvil, Alaska 60 605
  • 6. About Us … Our People • Employee owners – We are 100% ESOP-owned Company • Client focused • Unusually deep in technical expertise • Committed - Low turnover • Share common values
  • 7. About Us … Project Services Manager Walter Michelutti Billings Branch Manager Dan Oakes Doyon Anvil President, General Manager Werner Plagge President Gordy Lindell Safety Manager Eric Peterson Manager of Resources Ross Warne Information Technology Services Manager Doug Williams Manager of Programs Jim Turner Concord Branch Manager Jeff Wong Business Services Manager Rob Farrow BD/Marketing Manager Jim Jansky Quality Manager Ken Koenig
  • 8. Our Primary Clients … Refining • BP • CHS • Chevron – West Coast Facilities • Exxon Mobil • Flint Hills Resources • Holly Frontier Oil • Husky Energy • Petro Star • Phillips 66 – Billings – Ferndale – Rodeo • Shell • Tesoro • US Oil • Valero Oil & Gas Production • BP Exploration • Caelus Energy • Cook Inlet Energy • ConocoPhillips Alaska • ConocoPhillips LCGP • Doyon Emerald • Hilcorp • Marathon • XTO Energy Gas & Liquid Pipelines & Terminals • Alyeska Pipeline • BP Pipelines • BP Terminals • Chevron Terminals • Corval/ONEOK • Phillips 66 Pipelines & Transportation
  • 9. Our Expertise … • Process Plants – 98% of our work is process plant related • Fit for purpose design – Delivering just what the project requires • Modular design – Optimizing local fabrication and construction know-how • Project Size – Mostly small to medium, generally under $20MM TIC – Often larger projects, $50MM - $200MM TIC
  • 10. Our Strengths … We’re really good at… • Solving tough problems • Implementing client methods and preferences • Cooperating with all project participants to ensure overall project success – Taking an Owner’s view – Coordination and Planning with Constructor – Procurement and Expediting on Schedule Driven Projects • Being a flexible organization – Adapting and supplementing to meet the needs • Controlling Projects – Being a steward of our clients time and money
  • 11. To Contact Us … Corporate Office: Billings Office: 1675 West Bakerview Road 1015 Broadwater Ave. Bellingham, WA 98226 Billings, MT 59102 360.671.1450 406.245.9258 Primary Contact: Primary Contact: James M. Jansky, Sr. V.P. Daniel Oakes Marketing Manager Branch Manager 360.937.0550 406.238.1250 jjansky@anvilcorp.com doakes@anvilcorp.com