SlideShare ist ein Scribd-Unternehmen logo
1 von 5
Downloaden Sie, um offline zu lesen
Operations: 84 Wilkinson Road, Freetown, Sierra Leone
T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003
Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189
Title
SECONDARY BLASTING STANDARD OPERATING PROCEDURE
Purpose
• To outline the standard parameters and procedure to be followed when conducting
secondary blasting
Scope
• This procedure is applicable to all personnel involved in secondary blasting starting from
preparation, marking, drilling, measuring, charging, stemming to firing of boulders and toes
APPROVAL SIGNATURE RECORD
Reviewer Role Title Approval
Document Compiler Blasting Engineer Collins Sikanyika
Reviewer 1 Drilling Manager Corne Muller
Reviewer 2 Chief Safety Officer Derick Van Der Merwe
Final Approval General Manager Christo Swanepoel
1. Introduction
Secondary blasting involves boulder blasting and toe blasting. There are two
methods of secondary blasting namely Popping and Plaster or Mud Blasting. Both of
these methods can generate significant nuisance from airblast (noise) and flyrock.
Popping uses fewer explosives than plaster but it involves considerable drilling
expense. Sometimes use of mechanical rock breakers to reduce oversize (boulders)
is preferred because is too noisy and more expensive.
This standard operating procedure highlights how secondary blasting is safely
conducted at Koidu Mine site it using the method of Popping.
2. Objective
To provide a standard safe work practice for drilling and blasting of boulders and toes
to minimize the risks of airblast and flyrocks
Operations: 84 Wilkinson Road, Freetown, Sierra Leone
T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003
Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189
2 of 4
3. Definitions
Secondary blasting - blasting of oversize rocks usually from previous blast
Popping – secondary blasting where an explosive charge is placed in a hole drilled
to center of rock then stemmed for blasting
Plaster or Mud blasting – secondary blasting where explosives are on top of the
boulder and packed in place with mud or clay for blasting
Boulder - any rock which due to its geometry cannot be safely loaded out of the face
by the available digging equipment
Primer – cap sensitive cartridge of high explosive which is used to initiate explosion
Misfire – charge or part of charge that has failed to fire as planned
Toe – an undesirable part of the blast which does not get blasted properly as
planned with the production blast and cannot be mine out
Flyrock – undesirable rock that is propelled through air from a blast
Airblast – shock wave travelling through the air resulting from the detonation of
explosive
Blasthole – a hole drilled into a rock for the placement of explosive to break the rock
Stemming – Inert material used in the collar part of the blasthole to confine the
energy (gases) generated during detonation
Blast Crew - personnel who are working under the direction of the Blasting Engineer
4. Procedure
4.1. Boulder Blasting
Preparation
Where possible, any boulder should be removed from the face and out of the
loading area prior to drilling. If room is available, boulders should be
arranged in a line on the bench in an area that is out of the way and which
provides adequate access for the drill.
Marking and Observation
Where possible, any boulder that is set aside for blasting should be marked
with spray paint by the Blasting Engineer. The marking should include the
blasthole position and the depth alongside to be drilled. Wherever practical,
all the boulders in one particular location should be marked for drilling from
the same side.
The position of the blasthole is determined by the size and shape (geometry)
of the boulder. In principle the blasthole should be positioned in the center of
the boulder and the depth should be determined in such a way that it just past
the center of the boulder about 50% to 60% of the boulder thickness as
illustrated in Table 4.1 below.
If more than one (1) blasthole is required due to the geometry of the rock,
care shall be taken to ensure that the blastholes do not intersect. Where
possible, only the minimum number of holes should be drilled in each
oversize rock so that the charges can work effectively. Where possible, all
blastholes marked shall be accessible from the bench floor.
Operations: 84 Wilkinson Road, Freetown, Sierra Leone
T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003
Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189
3 of 4
Drilling
When drilling boulder, each blasthole should be drilled on the marked position
and to the correct depth as marked by the Blast Engineer. It is the
responsibiltity of the Drilling Manager to ensure that blastholes are drilled as
marked or planned.
Once a blasthole is drilled and the depth has been checked to ensure that the
hole does not daylight, it should be marked with a painted circle by the Drilling
Shift Boss. If a hole is too short, daylights or is otherwise in-effective, it should
be marked with a painted cross by the Drilling Shift Boss.
If a blasthole has already been drilled whether it be from a previous shift or an
old Butt from the shot it was pulled from, the Drilling Shift Boss will inspect the
rock to see if the hole has penetrated the boulder right through. If the
blasthole has not been drilled right through, the Drilling Shift Boss must
instruct the driller to drill another blasthole in the same direction ensuring that
the barrels do not intersect.
Care should be taken with large rocks to avoid aiming the blasthole in the
direction of something vulnerable to the rifle barrel effect.
Charging
Before charging boulders, all the blastholes should be rechecked for drilling
accuracy as explained above under drilling by the blasting crew. When
charging, each hole shall be loaded with just enough charge to fracture or
split the rock. The charge shall be pushed to end of the blastholes using a
charging stick made out of a non-sparking material. Charging will be done
using either of the two explained methods below;
Method 1: Using a primer (bomb) consisting of Cartridge(s) of splitex and
downline with 500ms or cortex 10g and the charges will be determines and
guided as depicted in Table 4.1 below. The advantage of charging boulders
with cartridges is that there is easy regulation of the amount of charge to put
in the blastholes.
Table 4.1: Guide lines for Boulder Blasting in Granite
Operations: 84 Wilkinson Road, Freetown, Sierra Leone
T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003
Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189
4 of 4
Method 2: Using primer (bomb) consisting of 400g booster and downline with
500ms or cortex 10g then dipped in bulk emulsion e.g. HEF 100 before
charging to increase the energy. No pumping of bulk emulsion in the blasthole
will be done in boulder blasting apart from just dipping the prime in bulk
emulsion because it very trick to regulate pumping of smaller quantities of
bulk emulsion in the blastholes using the charging unit.
When fired, the blasting accessories and product used to break the boulder
should be recorded by the blasting crew.
Stemming
Once charged, blasthole shall be carefully stemmed to the collar with either
tailings or drill chipping or mud tamped into the hole to increase breakage and
minimize airblast and flyrocks.
Firing
Prior to firing boulders, the site should be physically walked by the blast crew
to ensure that each blasthole is tied in. After firing, the area must be re-
walked by the blast crew to ensure that each hole has been initiated and that
there are no signs of visible misfire.
Blasting of boulder shall be conducted as per Blasting Awareness Procedure
and on specific dates and time in line with the blasting schedules for the
week.
4.2. Floor and Toe Blasting
Preparation
Blasting Engineer should ensure that hard toe area is proper clean and
exposed. It should be ensured that no loose material should be on top of the
toe area before marking or staking of the drill pattern is done.
Marking and Observation
The blasting Engineer is responsible in marking the blasthole location (XY) on
the floor and toe blasting area then survey is responsible for determining the
hole depths (Z) and allocation of blasthole IDs or numbers. In determining the
pattern size, the blasting engineer will be guided by the average depths of
blastholes using the Table 4.2 below as a guideline.
Drilling
All blastholes should be drilled on the marked locations to the planned
depths. Poor drilling accuracy (XYZ) may cause smaller burdens and
spacings which increase the chance of flyrocks and airblast as the energy will
not be properly distributed in the rock.
Charging
All blastholes shall be checked for drilling accuracy (XYZ) against the planned
by the blasting crew. If the drilling accuracy is correct, they should be charged
using bulk explosive (HEF 100) and if not, they should be indicated as redrills
as per Drilling and Blasting Parameters Standard Operating Procedure but
the charges will be regulated as the guideline below in Table 4.2.
Operations: 84 Wilkinson Road, Freetown, Sierra Leone
T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003
Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189
5 of 4
Table 4.2: Guideline for Toe Blasting
NB: Small Toes which are less 1.5m depth or thickness on the floor and side
wall will also be drilled, charged, stemmed and fired as boulders above.
Stemming
Stemming of all blastholes shall be done using aggregate or crushed stones
to the collar just like production blasholes to provide effective stemming to
minimize flyrocks and airblast.
Firing
The charged blastholes shall be tie up for firing just like production blastholes.
All the blasholes will be inspected to insure that they are tie in and after the
blast inspection shall be done for misfires by the blasting crew.
Blasting of toes shall be conducted as per Blasting Awareness Procedure and
on specific dates and time in line with the blasting schedules for the week.
5. Reference Documents
Drilling and Blasting Standard Operating Procedure
Blasting Safety Awareness Standard Operating Procedure
<END>

Weitere ähnliche Inhalte

Was ist angesagt?

Blast design in opencast mining
Blast design in opencast miningBlast design in opencast mining
Blast design in opencast mininggopal karmakar
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall MiningVR M
 
support system in metal mine
support system in metal minesupport system in metal mine
support system in metal minejyotiranavasiya
 
Drilling in Surface Mine.pdf
Drilling in Surface Mine.pdfDrilling in Surface Mine.pdf
Drilling in Surface Mine.pdfBIT Sindri
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in miningEder Reyes
 
Techniques of Controlled Blasting
Techniques of Controlled BlastingTechniques of Controlled Blasting
Techniques of Controlled Blastingpartha sharma
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drillpavan kumar
 
Drop raising in underground mines
Drop raising in underground minesDrop raising in underground mines
Drop raising in underground minespartha sharma
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesAnurag Jha
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal minesSunil Varma
 

Was ist angesagt? (20)

Blast design in opencast mining
Blast design in opencast miningBlast design in opencast mining
Blast design in opencast mining
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
 
Subsidence
SubsidenceSubsidence
Subsidence
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptxBENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
 
Basics of drilling 1
Basics of drilling 1Basics of drilling 1
Basics of drilling 1
 
support system in metal mine
support system in metal minesupport system in metal mine
support system in metal mine
 
Mining methods
Mining methodsMining methods
Mining methods
 
Side discharge loader
Side discharge loaderSide discharge loader
Side discharge loader
 
Drilling in Surface Mine.pdf
Drilling in Surface Mine.pdfDrilling in Surface Mine.pdf
Drilling in Surface Mine.pdf
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in mining
 
Room and Pillar Mining Method
Room and Pillar Mining MethodRoom and Pillar Mining Method
Room and Pillar Mining Method
 
Techniques of Controlled Blasting
Techniques of Controlled BlastingTechniques of Controlled Blasting
Techniques of Controlled Blasting
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drill
 
Applicability of hydraulic mining
Applicability of hydraulic miningApplicability of hydraulic mining
Applicability of hydraulic mining
 
Drop raising in underground mines
Drop raising in underground minesDrop raising in underground mines
Drop raising in underground mines
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast mines
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal mines
 
Square set stoping
Square set stopingSquare set stoping
Square set stoping
 

Andere mochten auch

A step by-step guide to the sandblasting process
A step by-step guide to the sandblasting processA step by-step guide to the sandblasting process
A step by-step guide to the sandblasting processJack Smith
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedureDanai Thongsin
 
terminal services division
terminal services divisionterminal services division
terminal services divisionAiDY
 
standard operating procedure pharmacy
standard operating procedure pharmacystandard operating procedure pharmacy
standard operating procedure pharmacysagar858
 
Sop (textile finishing)
Sop (textile finishing)Sop (textile finishing)
Sop (textile finishing)Mizan Rahman
 
Standard Operating procedure
Standard Operating procedureStandard Operating procedure
Standard Operating procedureFiras M. Yahia
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocksijsrd.com
 
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...Ir. Abdul Aziz Abas
 
2 sop keuangan perencanaan
2 sop keuangan perencanaan2 sop keuangan perencanaan
2 sop keuangan perencanaanbedhoo
 
Map Projections, Datums, GIS and GPS for Everyone
Map Projections, Datums, GIS and GPS for EveryoneMap Projections, Datums, GIS and GPS for Everyone
Map Projections, Datums, GIS and GPS for EveryoneDr. Geophysics
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedureUMP
 
Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003Yogesh Ghule
 
Front office SOP
Front office SOPFront office SOP
Front office SOPHarry Singh
 
Explosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting OperationsExplosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting Operationspartha sharma
 

Andere mochten auch (18)

A step by-step guide to the sandblasting process
A step by-step guide to the sandblasting processA step by-step guide to the sandblasting process
A step by-step guide to the sandblasting process
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedure
 
terminal services division
terminal services divisionterminal services division
terminal services division
 
standard operating procedure pharmacy
standard operating procedure pharmacystandard operating procedure pharmacy
standard operating procedure pharmacy
 
Draw 111- mechanical drawing and orthographic drawing
Draw 111- mechanical drawing and orthographic drawingDraw 111- mechanical drawing and orthographic drawing
Draw 111- mechanical drawing and orthographic drawing
 
Sop (textile finishing)
Sop (textile finishing)Sop (textile finishing)
Sop (textile finishing)
 
Standard Operating procedure
Standard Operating procedureStandard Operating procedure
Standard Operating procedure
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...
Standard Operating Procedure (SOP) proposal for flood preparedness in shah al...
 
2 sop keuangan perencanaan
2 sop keuangan perencanaan2 sop keuangan perencanaan
2 sop keuangan perencanaan
 
Food and beverage standard procedures
Food and beverage standard proceduresFood and beverage standard procedures
Food and beverage standard procedures
 
Map Projections, Datums, GIS and GPS for Everyone
Map Projections, Datums, GIS and GPS for EveryoneMap Projections, Datums, GIS and GPS for Everyone
Map Projections, Datums, GIS and GPS for Everyone
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedure
 
Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003
 
Food & beverage sop's
Food & beverage sop'sFood & beverage sop's
Food & beverage sop's
 
04 sequence of service
04  sequence of service04  sequence of service
04 sequence of service
 
Front office SOP
Front office SOPFront office SOP
Front office SOP
 
Explosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting OperationsExplosives, Theory Of Breakage And Blasting Operations
Explosives, Theory Of Breakage And Blasting Operations
 

Ähnlich wie Secondary Blasting Standard Operating Procedure

Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana missSHAMJITH KM
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
4. Drilling and Blasting Techniques in mines.docx
4. Drilling and Blasting Techniques in mines.docx4. Drilling and Blasting Techniques in mines.docx
4. Drilling and Blasting Techniques in mines.docxAzazAlamKhan
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101SHAZEBALIKHAN1
 
Extraction of developed pillars - a case study
Extraction of developed pillars - a case studyExtraction of developed pillars - a case study
Extraction of developed pillars - a case studyTIKESHWAR MAHTO
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasyq q
 
A poster presentation on raise boring machine
A poster presentation on raise boring machineA poster presentation on raise boring machine
A poster presentation on raise boring machineMd. Shahadot Hossain
 
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...Control and Prediction of Blast Fragmentation and It's effect on the Comminut...
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...James Dunford
 
underwater Drilling &B lasting.pptx
underwater Drilling &B lasting.pptxunderwater Drilling &B lasting.pptx
underwater Drilling &B lasting.pptxPavanNadgouda2
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case studyTIKESHWAR MAHTO
 
IRJET - Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified ApproachIRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET - Enhancing Productivity in Opencast Mines – A Quantified ApproachIRJET Journal
 
Reservior engineering presentation for Petroleum science
Reservior engineering presentation for Petroleum scienceReservior engineering presentation for Petroleum science
Reservior engineering presentation for Petroleum scienceStanleyJilong
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageDavid H Moloney
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.pptDAYANANDWANDRE
 

Ähnlich wie Secondary Blasting Standard Operating Procedure (20)

Blast Design-2.pdf
Blast Design-2.pdfBlast Design-2.pdf
Blast Design-2.pdf
 
Types of Drilling
Types of Drilling Types of Drilling
Types of Drilling
 
Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana miss
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
4. Drilling and Blasting Techniques in mines.docx
4. Drilling and Blasting Techniques in mines.docx4. Drilling and Blasting Techniques in mines.docx
4. Drilling and Blasting Techniques in mines.docx
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
 
Extraction of developed pillars - a case study
Extraction of developed pillars - a case studyExtraction of developed pillars - a case study
Extraction of developed pillars - a case study
 
Chapter 09
Chapter 09Chapter 09
Chapter 09
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
 
A poster presentation on raise boring machine
A poster presentation on raise boring machineA poster presentation on raise boring machine
A poster presentation on raise boring machine
 
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...Control and Prediction of Blast Fragmentation and It's effect on the Comminut...
Control and Prediction of Blast Fragmentation and It's effect on the Comminut...
 
underwater Drilling &B lasting.pptx
underwater Drilling &B lasting.pptxunderwater Drilling &B lasting.pptx
underwater Drilling &B lasting.pptx
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case study
 
Pillar design
Pillar designPillar design
Pillar design
 
IRJET - Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified ApproachIRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET - Enhancing Productivity in Opencast Mines – A Quantified Approach
 
Reservior engineering presentation for Petroleum science
Reservior engineering presentation for Petroleum scienceReservior engineering presentation for Petroleum science
Reservior engineering presentation for Petroleum science
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.ppt
 

Secondary Blasting Standard Operating Procedure

  • 1. Operations: 84 Wilkinson Road, Freetown, Sierra Leone T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003 Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189 Title SECONDARY BLASTING STANDARD OPERATING PROCEDURE Purpose • To outline the standard parameters and procedure to be followed when conducting secondary blasting Scope • This procedure is applicable to all personnel involved in secondary blasting starting from preparation, marking, drilling, measuring, charging, stemming to firing of boulders and toes APPROVAL SIGNATURE RECORD Reviewer Role Title Approval Document Compiler Blasting Engineer Collins Sikanyika Reviewer 1 Drilling Manager Corne Muller Reviewer 2 Chief Safety Officer Derick Van Der Merwe Final Approval General Manager Christo Swanepoel 1. Introduction Secondary blasting involves boulder blasting and toe blasting. There are two methods of secondary blasting namely Popping and Plaster or Mud Blasting. Both of these methods can generate significant nuisance from airblast (noise) and flyrock. Popping uses fewer explosives than plaster but it involves considerable drilling expense. Sometimes use of mechanical rock breakers to reduce oversize (boulders) is preferred because is too noisy and more expensive. This standard operating procedure highlights how secondary blasting is safely conducted at Koidu Mine site it using the method of Popping. 2. Objective To provide a standard safe work practice for drilling and blasting of boulders and toes to minimize the risks of airblast and flyrocks
  • 2. Operations: 84 Wilkinson Road, Freetown, Sierra Leone T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003 Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189 2 of 4 3. Definitions Secondary blasting - blasting of oversize rocks usually from previous blast Popping – secondary blasting where an explosive charge is placed in a hole drilled to center of rock then stemmed for blasting Plaster or Mud blasting – secondary blasting where explosives are on top of the boulder and packed in place with mud or clay for blasting Boulder - any rock which due to its geometry cannot be safely loaded out of the face by the available digging equipment Primer – cap sensitive cartridge of high explosive which is used to initiate explosion Misfire – charge or part of charge that has failed to fire as planned Toe – an undesirable part of the blast which does not get blasted properly as planned with the production blast and cannot be mine out Flyrock – undesirable rock that is propelled through air from a blast Airblast – shock wave travelling through the air resulting from the detonation of explosive Blasthole – a hole drilled into a rock for the placement of explosive to break the rock Stemming – Inert material used in the collar part of the blasthole to confine the energy (gases) generated during detonation Blast Crew - personnel who are working under the direction of the Blasting Engineer 4. Procedure 4.1. Boulder Blasting Preparation Where possible, any boulder should be removed from the face and out of the loading area prior to drilling. If room is available, boulders should be arranged in a line on the bench in an area that is out of the way and which provides adequate access for the drill. Marking and Observation Where possible, any boulder that is set aside for blasting should be marked with spray paint by the Blasting Engineer. The marking should include the blasthole position and the depth alongside to be drilled. Wherever practical, all the boulders in one particular location should be marked for drilling from the same side. The position of the blasthole is determined by the size and shape (geometry) of the boulder. In principle the blasthole should be positioned in the center of the boulder and the depth should be determined in such a way that it just past the center of the boulder about 50% to 60% of the boulder thickness as illustrated in Table 4.1 below. If more than one (1) blasthole is required due to the geometry of the rock, care shall be taken to ensure that the blastholes do not intersect. Where possible, only the minimum number of holes should be drilled in each oversize rock so that the charges can work effectively. Where possible, all blastholes marked shall be accessible from the bench floor.
  • 3. Operations: 84 Wilkinson Road, Freetown, Sierra Leone T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003 Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189 3 of 4 Drilling When drilling boulder, each blasthole should be drilled on the marked position and to the correct depth as marked by the Blast Engineer. It is the responsibiltity of the Drilling Manager to ensure that blastholes are drilled as marked or planned. Once a blasthole is drilled and the depth has been checked to ensure that the hole does not daylight, it should be marked with a painted circle by the Drilling Shift Boss. If a hole is too short, daylights or is otherwise in-effective, it should be marked with a painted cross by the Drilling Shift Boss. If a blasthole has already been drilled whether it be from a previous shift or an old Butt from the shot it was pulled from, the Drilling Shift Boss will inspect the rock to see if the hole has penetrated the boulder right through. If the blasthole has not been drilled right through, the Drilling Shift Boss must instruct the driller to drill another blasthole in the same direction ensuring that the barrels do not intersect. Care should be taken with large rocks to avoid aiming the blasthole in the direction of something vulnerable to the rifle barrel effect. Charging Before charging boulders, all the blastholes should be rechecked for drilling accuracy as explained above under drilling by the blasting crew. When charging, each hole shall be loaded with just enough charge to fracture or split the rock. The charge shall be pushed to end of the blastholes using a charging stick made out of a non-sparking material. Charging will be done using either of the two explained methods below; Method 1: Using a primer (bomb) consisting of Cartridge(s) of splitex and downline with 500ms or cortex 10g and the charges will be determines and guided as depicted in Table 4.1 below. The advantage of charging boulders with cartridges is that there is easy regulation of the amount of charge to put in the blastholes. Table 4.1: Guide lines for Boulder Blasting in Granite
  • 4. Operations: 84 Wilkinson Road, Freetown, Sierra Leone T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003 Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189 4 of 4 Method 2: Using primer (bomb) consisting of 400g booster and downline with 500ms or cortex 10g then dipped in bulk emulsion e.g. HEF 100 before charging to increase the energy. No pumping of bulk emulsion in the blasthole will be done in boulder blasting apart from just dipping the prime in bulk emulsion because it very trick to regulate pumping of smaller quantities of bulk emulsion in the blastholes using the charging unit. When fired, the blasting accessories and product used to break the boulder should be recorded by the blasting crew. Stemming Once charged, blasthole shall be carefully stemmed to the collar with either tailings or drill chipping or mud tamped into the hole to increase breakage and minimize airblast and flyrocks. Firing Prior to firing boulders, the site should be physically walked by the blast crew to ensure that each blasthole is tied in. After firing, the area must be re- walked by the blast crew to ensure that each hole has been initiated and that there are no signs of visible misfire. Blasting of boulder shall be conducted as per Blasting Awareness Procedure and on specific dates and time in line with the blasting schedules for the week. 4.2. Floor and Toe Blasting Preparation Blasting Engineer should ensure that hard toe area is proper clean and exposed. It should be ensured that no loose material should be on top of the toe area before marking or staking of the drill pattern is done. Marking and Observation The blasting Engineer is responsible in marking the blasthole location (XY) on the floor and toe blasting area then survey is responsible for determining the hole depths (Z) and allocation of blasthole IDs or numbers. In determining the pattern size, the blasting engineer will be guided by the average depths of blastholes using the Table 4.2 below as a guideline. Drilling All blastholes should be drilled on the marked locations to the planned depths. Poor drilling accuracy (XYZ) may cause smaller burdens and spacings which increase the chance of flyrocks and airblast as the energy will not be properly distributed in the rock. Charging All blastholes shall be checked for drilling accuracy (XYZ) against the planned by the blasting crew. If the drilling accuracy is correct, they should be charged using bulk explosive (HEF 100) and if not, they should be indicated as redrills as per Drilling and Blasting Parameters Standard Operating Procedure but the charges will be regulated as the guideline below in Table 4.2.
  • 5. Operations: 84 Wilkinson Road, Freetown, Sierra Leone T: +232 (0)22 232 257 F: +232 (0)22 230 476 Reg. No. 1057/2003 Registered Office: Akara Building, 24 De Castro Street, Wickhams Cay 1, Road Town, Tortola, British Virgin Islands, Reg. No. 552189 5 of 4 Table 4.2: Guideline for Toe Blasting NB: Small Toes which are less 1.5m depth or thickness on the floor and side wall will also be drilled, charged, stemmed and fired as boulders above. Stemming Stemming of all blastholes shall be done using aggregate or crushed stones to the collar just like production blasholes to provide effective stemming to minimize flyrocks and airblast. Firing The charged blastholes shall be tie up for firing just like production blastholes. All the blasholes will be inspected to insure that they are tie in and after the blast inspection shall be done for misfires by the blasting crew. Blasting of toes shall be conducted as per Blasting Awareness Procedure and on specific dates and time in line with the blasting schedules for the week. 5. Reference Documents Drilling and Blasting Standard Operating Procedure Blasting Safety Awareness Standard Operating Procedure <END>