SlideShare ist ein Scribd-Unternehmen logo
1 von 40
Downloaden Sie, um offline zu lesen
A Schedule-Centric View of
Contract Administration
Chris Carson, PMP, PSP, CCM
Alpha Corporation
Corporate Director of Project Controls

Dennis Sobota, P.E., CDT, LEED AP
Clark Nexsen Architecture & Engineering
Associate, Director of Construction Administration
A Schedule-Centric View of Contract
                                Administration
•   Contracts
•   Contract requirements
•   Scheduling requirements
•   Contract management
• Dennis Sobota
   – 40+ years in claims avoidance contract administration
   – Primarily Owner representative
   – Several years working for Contractors
• Chris Carson
   – 38+ years in construction management, focusing on project
     controls
   – Primarily Contractor representative
   – 12 years working as consultant for Owners
A Schedule-Centric View of Contract
                                 Administration
• Contract administration & construction management
   – Seem simple
   – Review the Contractor’s work timely and accurately
   – Project is successful
• However
   – Without a good understanding of time related issues
   – Without administering the contract from a schedule perspective
• Projects fail
   – Late completion
   – Blown budgets
   – Disputes resulting in costly legal resolution
A Schedule-Centric View of Contract
                                 Administration
• Construction management & administration
   – Unique of all types of projects
   – One design, one location, one new set of stakeholders
   – End user is facility management, different needs
• Construction management is different from
  administration
   – May be a professional CM on project
   – May be administered by A/E
      • May or may not have any depth of CM background
      • Professionals, certified by state, for technical knowledge
   – CM not generally part of the A/E certification
      • State of Virginia now has CM as one of P.E. disciplines
A Schedule-Centric View of Contract
                                Administration
• Although there are more bells & whistles, CM has not
  changed significantly through the years
   – Some components are evolving
      • Computer based project management
      • LEED certification
      • Increased ramifications of change management
   – Many components have not changed
      • Means and methods still essentially the same
      • Few major changes in construction techniques
   – Good news is lessons learned can be used over and over
A Schedule-Centric View of Contract
                                  Administration
• Do you want to be the most important person involved
  with the construction project?
• READ the contract
   –   Not just the technical sections
   –   Read the General Conditions
   –   Read the bid form
   –   Read the Division One requirements
• Because most people don’t!
   – AACEi session several years ago yielded survey
      • More than half project controls professionals did not even
        read the scheduling specification
• How many professionals never read the contract?
A Schedule-Centric View of Contract
                                 Administration
• Dennis wrote a article for the National Society of
  Professional Engineers’ magazine (NSPE)
   – In 93% of all claims against A/Es in 2009, non-technical issues
     were present
       • Schedule control
       • Project team capabilities
       • Construction-phase services
   – A/Es often concentrate on design goals, technical sections,
     coordination among design disciplines
• However, these areas are rarely the only or primary
  source of disputes
A Schedule-Centric View of Contract
                                Administration
• General Conditions of the Contract
   – Contains all basic contractual & admin details for project
   – For Virginia construction
      • 50 sections
      • 50 pages long
      • Still much shorter than the government’s Federal Acquisition
        Regulations (FAR)
   – GCs contain many potentially critical items
      • Notification requirements
      • Submission requirements
      • Change management process
      • Dispute resolution process
A Schedule-Centric View of Contract
                                Administration
• For example
  – In Virginia General Conditions Section 47, Contractual Disputes
      • A claim must be filed “at time of occurrence”
      • “the filing of a timely notice is a prerequisite to recovery
        under this Section”
      • Documentation supplied with the claim is vital to negotiated
        settlements
          – “all claims shall be submitted with all practically available
            supporting evidence and documentation”
A Schedule-Centric View of Contract
                                Administration
• How are GCs altered in the contract?
   – By add Supplemental General Conditions
• Precedence among the contract documents
   – Contract agreement between Owner and Contractor
   – Supplemental General Conditions
   – General Conditions
• Must read these sections!
A Schedule-Centric View of Contract
                                 Administration
• Starts with Bid Form
   – May establish cost/pricing issues
   – May establish time constraints
   – May dictate phasing requirements
• Next, Division One of the Specifications
   – Why should contractors bother to read?
      • Contains specific work restrictions at site
      • Includes project management and coordination requirements
   – Why should A/E be concerned?
      • Contractor is relying on A/E to act as contract administration
      • Contractor is relying on A/E’s understanding of project
      • GCs define roles of all stakeholders
      • Defines assignment of risk
A Schedule-Centric View of Contract
                                 Administration
• Continues with the Scheduling Specification, Section 19
  in Virginia’s standard specs, Section ~01300 in other
  specs
   – Schedule review is not typically an expertise found in-house at
     the A/E
   – Complex projects need expert help in review and claims
     avoidance
• Always treat time like money
• RFIs are an example
   – If handled timely
       • Surveys show that relationships are improved when mistakes
         are corrected, unless not done timely and accurately
       • Slow response will spark delays and claims
A Schedule-Centric View of Contract
                                                Administration

• First and last rule – Document, Document, Document
   – If it isn’t written, it didn’t happen
   – In litigation, the one with the most paper wins
       • This means relevant paper
       • Contemporaneous project documentation is highest of all
           “proofs” required in litigation
• Primary goal should be to avoid disputes
   –   Produce accurate and timely meeting minutes
   –   Summarize points of agreement from meetings
   –   Ensure full and complete daily reports
   –   Use statistics rather than vague terms “many”, “a number”
   –   Use “reasonable standard of care”
• Think of documentation as building a case
   – Even if no one is claims oriented
   – No one plans to litigate, but too many projects fail
• Lessons learned from dispute resolution process
   – Memories are inconsistent and misleading
   – Emotions rule when contemporaneous documents are not
     available
   – Many claims cannot be proven due to the lack of support
     documentation
   – Many claims chase weak or incorrect issues, and ignore
     legitimate delays or disruption
   – Costs of entering into formal dispute resolution are 5 to 10 times
     as much as negotiating the issues without attorneys
• Scheduling oriented process
   – All contracts have some level of requirements for schedule
     control
   – First rule: manage the project from the schedule
      • Require schedules as specified
      • Perform technical schedule reviews
      • Discuss ramifications of time at every meeting
      • If the Contractor appears weak in scheduling, take extra care
      • Recognize that all technical engineering components of the
         project have time components
           – RFIs have response needs
           – Shop drawings dictate sequence of installation
           – Quality control failure has time ramifications
Success Factors for Projects

• From “Scheduling Practice & Project Success” by Dr.
  Andrew Griffith
• Study identifying characteristics of schedules that
  correlated with better project performance (success)
   –   Integration of all project phases into a single schedule
   –   Application of Critical Path Method (CPM) scheduling
   –   Resource-loading of project schedule
   –   Detailed review of schedule by project team
Success Factors for Projects

• Integration of all project phases into a single schedule
   – Includes full scope of work
   – Allows for planning for interfaces between project phases (pre-
     design, design, procurement, construction, post-construction)
   – Limited use of constraints
   – Better cost performance & less schedule slip
Success Factors for Projects

• Application of Critical Path Method (CPM) scheduling
   – Forces team to break down project into discrete activities,
     estimate durations, identify & review sequencing
   – Network is permitted to calculate accurately, providing better tool
     with reasonable Critical Path and float values
   – Unrelated to project size
   – Better cost performance & less schedule slip
Success Factors for Projects

• Resource-loading of project schedule
   –   Helps to ensure alignment between cost & schedule
   –   Allows evaluation of peak labor
   –   Focuses the team on critical resources
   –   Better cost performance & less schedule slip
Success Factors for Projects

• Detailed review of schedule by project team
   – Provides a check on accuracy
   – Allows functional leaders to verify that means & methods are
     represented in the schedule
   – Supports buy-in by project team
   – Demonstrated less cost growth
Success Factors for Projects

• Lessons Learned
  – Benchmark schedule development
  – Schedule definition developed early in project when ability to
    influence outcome is greatest
  – Allocate resources to develop & use an integrated project
    schedule
  – Proper planning and scheduling are worth the investment since
    they contribute to project success
Developing a Schedule-
                             Centric Culture
• Project management requires
   –   Planning and management skills
   –   Nimble response to daily occurrences on a project
   –   Hundreds of quick decisions
   –   Problem solving
• PM often evolves into a pattern of crisis project
  management.
• Major step to eliminating systematic crisis
  management:
   – Development of a scheduling program – place the company
     on a schedule-driven project management program
Developing a Schedule-Centric
                                    Culture
• If a program has symptoms that include
   –   Late completion of projects
   –   Just-in-time completion of projects
   –   Consistent two-minute warning completions
   –   Budget-busting completions
• The company needs to put a schedule-driven program in
  place.

• Implementing the program consists of:
   – Senior Management buy-in for:
     • Planning and scheduling
     • Dedicated schedule development and maintenance
     • Elimination of crisis management
     • Good analytical software use
   – A process of mandated schedule development, updating and
     analysis, with consistent monitoring
Developing a Schedule-Centric
                                              Culture
•   Senior management
     – Little recognition of the problems behind visible symptoms
     – Uses management “club” to treat those symptoms, including for
       project managers
• Senior management must be convinced
     – Stop focusing on the project managers “failings”
     – Support dedicating time to planning the projects
• Project managers have so many responsibilities that they cannot
  control
     –   Invoicing, cost control, budgeting
     –   Problem resolution, client communications
     –   Resource management
     –   Communications & paperwork demands
• Scheduling will not be consistently managed
• Senior management must mandate a schedule-driven program.
Developing a Schedule-Centric
                                            Culture
•   Development of effective and simple reports
     – Senior level management reports
       • At-a-glance style for all projects
       • Clear, meaningful metrics
     – Project level management reports
       • Predictive information
       • Focus on Critical Path work
       • Clear, meaningful metrics
•   Training the entire PM team in scheduling philosophy, with
    technical training for scheduler
•   Implementation of the process, with scheduling taking a
    prominent role in PM meetings
•   Follow through to ensure the process is adopted
•   Assessment of results
Developing a Schedule-Centric
                                           Culture
• The scheduling program:
   – Must be written down & explained step by step
• Every project (no matter how small):
   – Develop a detailed schedule
   – Project management team has buy-in to the plan by participating in
     development
   – Project managed by the schedule
   – Schedule updated & analyzed frequently
   – Schedule progress reported regularly
   – Schedule prominent in meeting agenda.
• Running meetings by the schedule is the best way to
  show dedicated schedule planning
• Once schedule is updated, analyzed, reported, if
  slippage shown, must involve resolution.
Developing a Schedule-Centric
                                       Culture
• Developing senior management reports is crucial
   – Frequent updates promote use of schedule for management
   – Frequency depends on project performance
Developing a Schedule-Centric
                                            Culture
• Senior management should take report when they drive
  by sites. This provides visual overview of progress
  compared against plan.
• Project manager gets a copy of report, so he knows what
  information is reported.
• Project manager level reports
   –   Most important report - Critical & Near-Critical Path
   –   PM walks the job with the report in hand
   –   PM verifies that Critical & Near Critical Path is being worked
   –   PM also verifies that other “mass volume” work is progressing
       and not eroding Total Float (or Free Float)
Developing a Schedule-Centric
                                        Culture
• Field visit forms to capture schedule information
Mitigation Schedule Analysis
• Triple constraints
   – Time
   – Cost
   – Scope/quality
   – Fourth constraint often added; risk
• Most programs are driven by one of the constraints
   – When one constraint must be fixed, others will vary
   – In this case, time was the fixed constraint
   – This requires a focus on mitigation of delays
• A structured effort is essential
Developing a Schedule-Centric
                                          Culture
• Scheduler should take field visit report to walk project
   – Meet with superintendent or project manager
   – Fill out field data sheet
• The process forces attention onto the schedule
   – Triple constraints
      • Time
      • Cost
      • Scope/quality
      • Fourth constraint often added; risk
   – Most programs are driven by one of the constraints
      • When one constraint must be fixed, others will vary
• Schedule is the one constraint that monitors all others
Developing a Schedule-Centric
                                          Culture
• Meeting agenda for schedule-centric contract admin
• Current Project Status:
   – CCD
   – Time extension requests
      • Need to analyze
      • Submitted, waiting on negotiation/approval
   – Change order requests
   – Outstanding issues
Developing a Schedule-Centric
                                           Culture
•   Meeting agenda for schedule-centric contract admin
•   Owner responsibility issues
•   Third party responsibility issues
•   Baseline approval
    – Status of buy-outs
• Update
    –   Approved?
    –   TIAs?
    –   Changed conditions?
    –   Production issues?
Developing a Schedule-Centric
                                         Culture
• Meeting agenda for schedule-centric contract admin
• Short interim look-ahead schedule
   – Subcontractors
      • Scheduled
      • Shared with other projects
      • Problem subs
          – Start problems
          – Production problems
          – Finish problems
Developing a Schedule-Centric
                                         Culture
• Meeting agenda for schedule-centric contract admin
• Long lead time issues
• Submittals/Approvals
   – Status of scheduled shop drawings
   – Status of scheduled submittals
   – Status of approvals
• RFIs
   – Missing/needed RFIs/answers
   – Outstanding RFIs
Developing a Schedule-Centric
                                         Culture
• Meeting agenda for schedule-centric contract admin
• Change orders
   – Owner
   – Subcontractors
• Quality control issues
• Schedule revisions
   – Missing scope of work in schedule?
   – Changes to logic due to work plan changes
   – Changes due to additional work
• Out of sequence work
Was the message clear?


• Construction management implementation changes
  according to phases in the project lifecycle
• Need to understand contracts and project delivery
  systems because they affect management of projects
• Success in construction projects is driven primarily by
  the project controls effort
• The better and more comprehensive the project
  controls system, the higher likelihood of project
  success
Thank You
For Attending!

Weitere ähnliche Inhalte

Was ist angesagt?

Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
Brown Smith Wallace
 
Contract construction-management142
Contract construction-management142Contract construction-management142
Contract construction-management142
rkress61
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
NASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rick
NASAPMC
 

Was ist angesagt? (20)

Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Claims
ClaimsClaims
Claims
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
 
Contract construction-management142
Contract construction-management142Contract construction-management142
Contract construction-management142
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 

Andere mochten auch

FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
Adrias TAN
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
yenohhoney
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
FitBlar Mit
 

Andere mochten auch (20)

Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
Resolving TIAs
Resolving TIAsResolving TIAs
Resolving TIAs
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng120606  Contract Management Skill Checklist & Experience Grid   Andrew Ng
120606 Contract Management Skill Checklist & Experience Grid Andrew Ng
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Fidic
FidicFidic
Fidic
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Fundamentals of Claims Management
Fundamentals of Claims ManagementFundamentals of Claims Management
Fundamentals of Claims Management
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 

Ähnlich wie Schedule-Centric View Of Contract Admin

Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
videoaakash15
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
TRIslides
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
Allan Berry
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptx
ssuserb5044d
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
Allan Berry
 

Ähnlich wie Schedule-Centric View Of Contract Admin (20)

INAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsINAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications Professionals
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
PEEM 2.pptx
PEEM 2.pptxPEEM 2.pptx
PEEM 2.pptx
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptx
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Pre-Application Advice in Kirklees MBC
Pre-Application Advice in Kirklees MBCPre-Application Advice in Kirklees MBC
Pre-Application Advice in Kirklees MBC
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
PM Related Info
PM Related InfoPM Related Info
PM Related Info
 

Mehr von Chris Carson

Mehr von Chris Carson (10)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 

Schedule-Centric View Of Contract Admin

  • 1.
  • 2. A Schedule-Centric View of Contract Administration Chris Carson, PMP, PSP, CCM Alpha Corporation Corporate Director of Project Controls Dennis Sobota, P.E., CDT, LEED AP Clark Nexsen Architecture & Engineering Associate, Director of Construction Administration
  • 3. A Schedule-Centric View of Contract Administration • Contracts • Contract requirements • Scheduling requirements • Contract management
  • 4. • Dennis Sobota – 40+ years in claims avoidance contract administration – Primarily Owner representative – Several years working for Contractors • Chris Carson – 38+ years in construction management, focusing on project controls – Primarily Contractor representative – 12 years working as consultant for Owners
  • 5. A Schedule-Centric View of Contract Administration • Contract administration & construction management – Seem simple – Review the Contractor’s work timely and accurately – Project is successful • However – Without a good understanding of time related issues – Without administering the contract from a schedule perspective • Projects fail – Late completion – Blown budgets – Disputes resulting in costly legal resolution
  • 6. A Schedule-Centric View of Contract Administration • Construction management & administration – Unique of all types of projects – One design, one location, one new set of stakeholders – End user is facility management, different needs • Construction management is different from administration – May be a professional CM on project – May be administered by A/E • May or may not have any depth of CM background • Professionals, certified by state, for technical knowledge – CM not generally part of the A/E certification • State of Virginia now has CM as one of P.E. disciplines
  • 7. A Schedule-Centric View of Contract Administration • Although there are more bells & whistles, CM has not changed significantly through the years – Some components are evolving • Computer based project management • LEED certification • Increased ramifications of change management – Many components have not changed • Means and methods still essentially the same • Few major changes in construction techniques – Good news is lessons learned can be used over and over
  • 8. A Schedule-Centric View of Contract Administration • Do you want to be the most important person involved with the construction project? • READ the contract – Not just the technical sections – Read the General Conditions – Read the bid form – Read the Division One requirements • Because most people don’t! – AACEi session several years ago yielded survey • More than half project controls professionals did not even read the scheduling specification • How many professionals never read the contract?
  • 9. A Schedule-Centric View of Contract Administration • Dennis wrote a article for the National Society of Professional Engineers’ magazine (NSPE) – In 93% of all claims against A/Es in 2009, non-technical issues were present • Schedule control • Project team capabilities • Construction-phase services – A/Es often concentrate on design goals, technical sections, coordination among design disciplines • However, these areas are rarely the only or primary source of disputes
  • 10. A Schedule-Centric View of Contract Administration • General Conditions of the Contract – Contains all basic contractual & admin details for project – For Virginia construction • 50 sections • 50 pages long • Still much shorter than the government’s Federal Acquisition Regulations (FAR) – GCs contain many potentially critical items • Notification requirements • Submission requirements • Change management process • Dispute resolution process
  • 11. A Schedule-Centric View of Contract Administration • For example – In Virginia General Conditions Section 47, Contractual Disputes • A claim must be filed “at time of occurrence” • “the filing of a timely notice is a prerequisite to recovery under this Section” • Documentation supplied with the claim is vital to negotiated settlements – “all claims shall be submitted with all practically available supporting evidence and documentation”
  • 12. A Schedule-Centric View of Contract Administration • How are GCs altered in the contract? – By add Supplemental General Conditions • Precedence among the contract documents – Contract agreement between Owner and Contractor – Supplemental General Conditions – General Conditions • Must read these sections!
  • 13. A Schedule-Centric View of Contract Administration • Starts with Bid Form – May establish cost/pricing issues – May establish time constraints – May dictate phasing requirements • Next, Division One of the Specifications – Why should contractors bother to read? • Contains specific work restrictions at site • Includes project management and coordination requirements – Why should A/E be concerned? • Contractor is relying on A/E to act as contract administration • Contractor is relying on A/E’s understanding of project • GCs define roles of all stakeholders • Defines assignment of risk
  • 14. A Schedule-Centric View of Contract Administration • Continues with the Scheduling Specification, Section 19 in Virginia’s standard specs, Section ~01300 in other specs – Schedule review is not typically an expertise found in-house at the A/E – Complex projects need expert help in review and claims avoidance • Always treat time like money • RFIs are an example – If handled timely • Surveys show that relationships are improved when mistakes are corrected, unless not done timely and accurately • Slow response will spark delays and claims
  • 15. A Schedule-Centric View of Contract Administration • First and last rule – Document, Document, Document – If it isn’t written, it didn’t happen – In litigation, the one with the most paper wins • This means relevant paper • Contemporaneous project documentation is highest of all “proofs” required in litigation • Primary goal should be to avoid disputes – Produce accurate and timely meeting minutes – Summarize points of agreement from meetings – Ensure full and complete daily reports – Use statistics rather than vague terms “many”, “a number” – Use “reasonable standard of care”
  • 16. • Think of documentation as building a case – Even if no one is claims oriented – No one plans to litigate, but too many projects fail • Lessons learned from dispute resolution process – Memories are inconsistent and misleading – Emotions rule when contemporaneous documents are not available – Many claims cannot be proven due to the lack of support documentation – Many claims chase weak or incorrect issues, and ignore legitimate delays or disruption – Costs of entering into formal dispute resolution are 5 to 10 times as much as negotiating the issues without attorneys
  • 17. • Scheduling oriented process – All contracts have some level of requirements for schedule control – First rule: manage the project from the schedule • Require schedules as specified • Perform technical schedule reviews • Discuss ramifications of time at every meeting • If the Contractor appears weak in scheduling, take extra care • Recognize that all technical engineering components of the project have time components – RFIs have response needs – Shop drawings dictate sequence of installation – Quality control failure has time ramifications
  • 18. Success Factors for Projects • From “Scheduling Practice & Project Success” by Dr. Andrew Griffith • Study identifying characteristics of schedules that correlated with better project performance (success) – Integration of all project phases into a single schedule – Application of Critical Path Method (CPM) scheduling – Resource-loading of project schedule – Detailed review of schedule by project team
  • 19. Success Factors for Projects • Integration of all project phases into a single schedule – Includes full scope of work – Allows for planning for interfaces between project phases (pre- design, design, procurement, construction, post-construction) – Limited use of constraints – Better cost performance & less schedule slip
  • 20. Success Factors for Projects • Application of Critical Path Method (CPM) scheduling – Forces team to break down project into discrete activities, estimate durations, identify & review sequencing – Network is permitted to calculate accurately, providing better tool with reasonable Critical Path and float values – Unrelated to project size – Better cost performance & less schedule slip
  • 21. Success Factors for Projects • Resource-loading of project schedule – Helps to ensure alignment between cost & schedule – Allows evaluation of peak labor – Focuses the team on critical resources – Better cost performance & less schedule slip
  • 22. Success Factors for Projects • Detailed review of schedule by project team – Provides a check on accuracy – Allows functional leaders to verify that means & methods are represented in the schedule – Supports buy-in by project team – Demonstrated less cost growth
  • 23. Success Factors for Projects • Lessons Learned – Benchmark schedule development – Schedule definition developed early in project when ability to influence outcome is greatest – Allocate resources to develop & use an integrated project schedule – Proper planning and scheduling are worth the investment since they contribute to project success
  • 24. Developing a Schedule- Centric Culture • Project management requires – Planning and management skills – Nimble response to daily occurrences on a project – Hundreds of quick decisions – Problem solving • PM often evolves into a pattern of crisis project management. • Major step to eliminating systematic crisis management: – Development of a scheduling program – place the company on a schedule-driven project management program
  • 25. Developing a Schedule-Centric Culture • If a program has symptoms that include – Late completion of projects – Just-in-time completion of projects – Consistent two-minute warning completions – Budget-busting completions • The company needs to put a schedule-driven program in place. • Implementing the program consists of: – Senior Management buy-in for: • Planning and scheduling • Dedicated schedule development and maintenance • Elimination of crisis management • Good analytical software use – A process of mandated schedule development, updating and analysis, with consistent monitoring
  • 26. Developing a Schedule-Centric Culture • Senior management – Little recognition of the problems behind visible symptoms – Uses management “club” to treat those symptoms, including for project managers • Senior management must be convinced – Stop focusing on the project managers “failings” – Support dedicating time to planning the projects • Project managers have so many responsibilities that they cannot control – Invoicing, cost control, budgeting – Problem resolution, client communications – Resource management – Communications & paperwork demands • Scheduling will not be consistently managed • Senior management must mandate a schedule-driven program.
  • 27. Developing a Schedule-Centric Culture • Development of effective and simple reports – Senior level management reports • At-a-glance style for all projects • Clear, meaningful metrics – Project level management reports • Predictive information • Focus on Critical Path work • Clear, meaningful metrics • Training the entire PM team in scheduling philosophy, with technical training for scheduler • Implementation of the process, with scheduling taking a prominent role in PM meetings • Follow through to ensure the process is adopted • Assessment of results
  • 28. Developing a Schedule-Centric Culture • The scheduling program: – Must be written down & explained step by step • Every project (no matter how small): – Develop a detailed schedule – Project management team has buy-in to the plan by participating in development – Project managed by the schedule – Schedule updated & analyzed frequently – Schedule progress reported regularly – Schedule prominent in meeting agenda. • Running meetings by the schedule is the best way to show dedicated schedule planning • Once schedule is updated, analyzed, reported, if slippage shown, must involve resolution.
  • 29. Developing a Schedule-Centric Culture • Developing senior management reports is crucial – Frequent updates promote use of schedule for management – Frequency depends on project performance
  • 30. Developing a Schedule-Centric Culture • Senior management should take report when they drive by sites. This provides visual overview of progress compared against plan. • Project manager gets a copy of report, so he knows what information is reported. • Project manager level reports – Most important report - Critical & Near-Critical Path – PM walks the job with the report in hand – PM verifies that Critical & Near Critical Path is being worked – PM also verifies that other “mass volume” work is progressing and not eroding Total Float (or Free Float)
  • 31. Developing a Schedule-Centric Culture • Field visit forms to capture schedule information
  • 32. Mitigation Schedule Analysis • Triple constraints – Time – Cost – Scope/quality – Fourth constraint often added; risk • Most programs are driven by one of the constraints – When one constraint must be fixed, others will vary – In this case, time was the fixed constraint – This requires a focus on mitigation of delays • A structured effort is essential
  • 33. Developing a Schedule-Centric Culture • Scheduler should take field visit report to walk project – Meet with superintendent or project manager – Fill out field data sheet • The process forces attention onto the schedule – Triple constraints • Time • Cost • Scope/quality • Fourth constraint often added; risk – Most programs are driven by one of the constraints • When one constraint must be fixed, others will vary • Schedule is the one constraint that monitors all others
  • 34. Developing a Schedule-Centric Culture • Meeting agenda for schedule-centric contract admin • Current Project Status: – CCD – Time extension requests • Need to analyze • Submitted, waiting on negotiation/approval – Change order requests – Outstanding issues
  • 35. Developing a Schedule-Centric Culture • Meeting agenda for schedule-centric contract admin • Owner responsibility issues • Third party responsibility issues • Baseline approval – Status of buy-outs • Update – Approved? – TIAs? – Changed conditions? – Production issues?
  • 36. Developing a Schedule-Centric Culture • Meeting agenda for schedule-centric contract admin • Short interim look-ahead schedule – Subcontractors • Scheduled • Shared with other projects • Problem subs – Start problems – Production problems – Finish problems
  • 37. Developing a Schedule-Centric Culture • Meeting agenda for schedule-centric contract admin • Long lead time issues • Submittals/Approvals – Status of scheduled shop drawings – Status of scheduled submittals – Status of approvals • RFIs – Missing/needed RFIs/answers – Outstanding RFIs
  • 38. Developing a Schedule-Centric Culture • Meeting agenda for schedule-centric contract admin • Change orders – Owner – Subcontractors • Quality control issues • Schedule revisions – Missing scope of work in schedule? – Changes to logic due to work plan changes – Changes due to additional work • Out of sequence work
  • 39. Was the message clear? • Construction management implementation changes according to phases in the project lifecycle • Need to understand contracts and project delivery systems because they affect management of projects • Success in construction projects is driven primarily by the project controls effort • The better and more comprehensive the project controls system, the higher likelihood of project success