Trc pull vs. push process lss 002 08
1. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
TRC
Download & Sort Pull vs. Push
Process
LEAN SIX SIGMA PROJECT
LSS 002-08
2. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
2
Lean Six Sigma Charter - TRC Download / Sort Process
Project Information Process Importance
Leader: Bruce Parker
Black Belt: Charlie Martin High Priority
Project Start: 17 Feb 2008 Better utilization of Floor Space, Manpower,
Project End: 18 Jun 2008 Yard Space, and Equipment
DPPM or COQ: N/A
Team Members Process Problem
Sponsor Bruce Parker
Black Belt: Charlie Martin Retrograde received a Level III CAR
Green Belt N/A The processes are redundant and
Subject Matter Experts there are manning issues
Bob Gardner, Eric Lang, Michelle Goods
Original Process Start/Stop Project Goals
Start Point: Container Received Reduce redundant process steps
Stop Point: Shipped to CRSP or DRMO Increase Manpower
Provide solid corrective and preventive
New Process Start /Stop actions for CARs.
Start Point: Container is downloaded Process Measurement
Stop Point : Material Loaded onto truck Task Time – Time Studies
for delivery. Value Stream Mapping
Monitor number of employees reassigned
3. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
3
Define Phase
4. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
4
Process Discrepancies Indentified
Before Lean
• Material being removed from incoming
containers faster than it can be processed
creating a “Push System”.
• Material setting on pallets in the open for too
long
• No location system, creating loss time relocating
material after documentation is received.
• Loss of Documentation
• Material being transported by truck to other
locations to set A/W documentation.
5. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
5
Measure Phase
6. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
6
• There have been 1 Level III CAR, 2 Level
II CARS and 2 ICARS written against the
TRC department. Items that need to be
resolved immediately are:
• 1) SARSS Training
• 2) Property Accountability
• 3) Key control for sensitive items
7. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
7
Analyze Phase
8. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
8
Process Flow Prior to Lean
Containers
Received
Material from
containers
unloaded
onto ground
Material is
separated by
serviceable and
unserviceable
Material is shipped
to CRSP or
DRMO
Documentation is
taken back to
Download / Sort Yard
MRO, Bin
Tickets Printed
in Horseshoe
Documented
serviceable is
sent to W7A
Document is
matched with
material
Material is listed
on inventory
sheets Sub to
Stk. Cont.
Material is
relocated after
search
Items with no
documentation are
sent to Classification
There is no continuity with this process. Documents are frequently lost,
material is exposed to weather, damage, and theft for long periods of time.
9. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
9
CONTAINER STAGING AREA
PREVIOUS PUSH
PROCESS
CONTCONT CONTCONTCONTCONTCONT
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
10. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
10
Previous Flow
“Push System”
• The current flow is designed to download and “un-stuff” containers
as quickly as possible. This system “Over-runs” the yard with
material faster than can be properly classified or documented. Items
with no documentation are transported to the Classification yard
where it can sit for days unprocessed and not in the SARSS
records. Material is exposed to weather, damage, and theft and is
difficult to match back up with the documentation after it is received
from Stock Control.
11. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
11
Improve Phase
12. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
12
Process Flow After Lean
Container is
Unloaded
Container is
“Un-stuffed”
Material is
Sorted, listed on
Inventory List
MRO or Bin Ticket is given
back to Processing Team
with Inventory Sheet
MRO or Bin
Tickets Printed
Material is loaded onto
trucks for delivery
Stock Control
Processes into
SARSS
Document is
Matched to
Material
Inventory list is given
to Stock Control
Material is not removed from the containers until a team has 100% processed
the previous container.
13. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
13
CONTAINER STAGING AREA
PROPOSED
PULL PROCESS
CONTCONT CONTCONTCONTCONTCONT
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
PALLETS
Process to trucks for delivery after documented
DRMO Storage W7A
14. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
14
PROPOSED FLOW
“PULL SYSTEM
• The proposed pull system is designed to process as we go. Separate teams will be
developed to “un-stuff” one container at a time to include processing material through
Stock Control and bringing it to the SARRS records. The team will consist of the
following:
1 Western Supply Employee (Multiple Teams)
1 TRC Inspector (Multiple Teams)
1 SARRS Operator (Multiple Teams)
4 ETCNs
• Multiple teams will be processing simultaneously.
• Special teams will be developed to process frustrated cargo and classified, sensitive
items and weapons.
15. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
15
Control Phase
16. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
16
• Provide SARSS Training for all employees that operate
the SARSS.
• Use the “Pull System” for accountability particularly for
Sensitive, High Dollar Items.
• Use of identified teams will eliminate the issue with
matching up documentation with material.
• Periodic Inventories to confirm accountability for
material.
• POP, SOP, and Work Instruction Training.
• Conduct Gap analysis with Internal Documents vs the
Statement of Work.
• Conduct self audits.
• Scheduled internal Audits and Inspections.
17. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
17
SUMMARY
The following two slides will show the process improvements.
The key improvement is with the increase in TEU production.
The SOW identifies the production goal of 1800 TEUs per month.
February’s production was at 2705 TEUs
March Production was at 3169 TEUs
April’s Production was at 3417 TEUs.
18. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
18
W2N 30 MAR
5 APR
6-12
APR
13-19
APR
20-26
APR
APR
Totals
SOW CDRL
TEU’s Processed 845 960 829 783 3417
450 TEU’s
per week C.5.1.24.5
Containers In-gated 203 149 81 180 613 NONE NONE
Containers Awaiting Breakdown 326 287 239 303 N/A NONE NONE
TEU’s Backlogged, Class IX Yard
48 34 33 26 25 NONE NONE
TEU’s Shipped to W7A 88 138 125 114 465 NONE NONE
TEU’s Shipped to TARP Facility 28 23 32 45 128 NONE NONE
TEU’s Shipped to DRMO 443 520 435 373 1771 NONE NONE
TEU’s Shipped to CONUS 20 16 34 37 107 NONE NONE
MRO’s Processed 9,442 8,476 6,710 6,900 31,528 NONE NONE
Monthly Production
19. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
19
TEU’s Processed vs. TEU’s Shipped
SOW Requirement 1800 TEU’s Per
Month
20. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
20
Old Class II & IV Yard
Before Lean
21. CSA, Ltd., ...Unlimited In Quality
Ltd.“IN SUPPORT OF COMBAT SUPPORT ASSOCIATES AND CSSC-K”
21
8,000 Pallet Backlog at Zero –
Class II & IV Yard
After Lean
Editor's Notes
Tire Yard
Actions/ Issues
- TRC personnel no longer interface with the DRMO Tire vendor.
COR: MAJ Fishburn Ph# 986-7290
Accountable Officer: Mr. Castillo Ph#:789-7393
Actions to date
-Currently storing tires in limited space, with the vendor when picking up tires.
-DRMO is now working.
Discussions
-The TRC is running out of room to store tires because DRMO subcontractors are not picking up sufficient numbers of tires to offset the current
inventory.
Future Actions
-DRMO to increase the number of vendors.
Rock/Gravel
Action/Issue
-Rock / Gravel urgently needed in the TRC Download & Sort Yard, Ship II Yard, Tire & Track Yard, Class II, IV, VII, and IX Yards, and Wash Rack; Due IPB Board 18 FEB 08.
COR: MAJ Fishburn Ph# 986-7290
DPW: Mr. Onyenedum Ph# 906-9180
Actions to date
-Proceeding with guidance as per DPW for gravel installation in TRC.
-Submitted request for gravel on 26 Jan 08.
-Met IPB Board on 18 Feb 08; Awaiting DPW engineer evaluation of yards.
Discussions
-Powdery dust reduces visibility and creates unhealthy work environment for TRC employees.
Future Actions
-Create priority list, in agreement with DPW, for gravel installation into yards.
Generator Maintenance
Action/Issue
-Generator Maintenance contract urgently needed.
-Generators were purchased and utilized by KBR and later transferred to CSA in extremely poor service condition.
-DPW only offers emergency service and PWD’s contract does not permit them perform generator service or maintenance in Zone 7.
Contract Specialist: Mr. Dwayne Bell Ph# 660-7033
Actions to date
-Resubmitted a copy of the generator maintenance PR for ACO approval on 25 JAN 08; Awaiting purchasing quotes
Discussions
-Generators power over 21 RLBs throughout the TRC Yard during 24/7 operations.
-Generators provide power for computer workstations to include SARSS CPUs and printers as well as office lights and other necessary equipment.
Future Actions
-Awaiting ACO approval.
Latrine Trailers
Action/Issue
-Latrine Trailers are needed for the TRC Department in Zone 7 to accommodate well over 500 TRC employees during 24-7 operations.
Contract Specialist: Mr. Dwayne Bell Ph# 660-7033
Chief of Plans & Design: Mr. Philip Onyenedum Ph# 961-8230
Actions to Date
-Project packet for Latrine approved by DOL Director; Met IPB Project Board on
18 Feb 08.
Discussions
-Currently portable toilets are being used for both male and female during summer
months.
-Portable toilets tend to leak from the ceiling during the cooler rainy months.
Future Actions
-Submit request personnel information to DPW on 25 Feb 08.
TRC Improvement Plan Action List
Action/Issue
-30 Day improvement plan is in work.
Actions to date
-48 of 60 items closed
Discussions
-Action items assigned to TRC personnel; ECD’s established.
Future Actions
-Proceed with Lean Six Initiatives.