SlideShare ist ein Scribd-Unternehmen logo
1 von 13
Port Wentworth, Georgia
Mixed Bed Polisher
(MBP)
ENERGY OPTIMIZATION PROJECT NO. PW13901
BY AUSTON BAGNAS (MBP DESIGNER)
YEAR 2016
Project Overview:
This project is intended to remove impurities from
the boiler feed water process.
This facility would be located before the boiler and
reduce contaminates from entering the boiler
system.
Contaminates can clog or foul piping within the
boiler system.
This would affect the quality and quantity of the
process and may require additional shut down
maintenance periods to repair any damage
caused by these impurities.
Ideation Process:
Layout:
The vendor supplies assemblies were skid based equipment
and had no layout requirements. Layout was primarily dictated
on available space and distance between assemblies.
Placement:
An existing building scheduled for demolition was chosen to
house the facility.
Process:
Since this facility polishes boiler feed water it was located at
the near the boiler feed water tank.
Maintenance:
The mill had a lot to say about the general arrangement on
this project. Maintenance and operations from the mill helped
determine how this facility would operate. Therefore the layout
was greatly determined by the accessibility to the assemblies
in the facility.
(Picture: different skid locations & questions)
Piping & Instrumentation Diagram (P.&I.D.s)
A flow diagram, or piping schematic, is used
to show the process flow for a facility or
process.
This design was a collaboration with the
vendor, myself, and the project engineer for
the CRP facility.
This flow diagram best represents how the
piping will be designed. It also locates
instrumentation and assemblies that will be
installed.
This drawing is a valuable source of
information for other drawings such as the
piping plans, isometrics, tie-in drawings, and
can further be used by operations after
installation.
General Arrangements (G.A.s)
The general arrangements are drawn to show tank & vessel locations along with the structural design
and sometimes maintenance access. These drawings are very basic for clarity.
Piping Plans & Sections
These drawings show the piping layout, vessel locations, and structural information. The P.&I.D.s, G.A.s, Tie-in
drawings, and isometrics will be the primary source for information when installing prefabricated items on this project.
MBP 3D Model
A 3D model was created to best identify any
layout concerns.
The skids & vessels were created and inserted
along with the chemical containment and any
large bore piping.
Multiple disciplines were incorporated into the
design. Access for electrical and instruments
were considered. The structural department
located steel members based on a stress
analysis of the building. Foundations were
designed to accommodate pumps and vessels.
A containment was designed and added as
well.
Many existing vessels and structures were
used in this project. They were also modeled to
show any interferences and possible uses.
MBP 3D Model (cont.)
Alternating views were utilized for
orientation and installation of assemblies
and equipment. Instrumentation was
able to identify locations for instruments
and junction boxes based on space and
accessibility. Repair, removal, and
maintenance was also considered in
locating any equipment.
Sample locations were installed for
operations to conduct necessary
analysis of the process.
This model was also used by
construction to better understand how
the facility would look when installed.
Construction & Installation
After pipe and vessel fabrication construction
crews began installation of the facility. Here are
two photos taken during the construction phase
of the MBP facility.
Scaffolding is erected for access and
installation of piping.
Minor field modifications were made. I was
onsite and able to work through some
unforeseen challenges.
Installed, commissioned, & running.
December 2016 the MBP was finally brought online and is now
successfully polishing condensate and removing impurities from the
boiler feed water.
There were a couple lessons learned on this project, one including an
over designed feed pipe but nothing substantial.
Overall the project was a great success and finalized on time and on
budget.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (19)

Cube srl - Engineering Consulting
Cube srl - Engineering ConsultingCube srl - Engineering Consulting
Cube srl - Engineering Consulting
 
ERICK RENALDI REZAL CV
ERICK RENALDI REZAL CVERICK RENALDI REZAL CV
ERICK RENALDI REZAL CV
 
Mohamed osama cv piping
Mohamed osama cv pipingMohamed osama cv piping
Mohamed osama cv piping
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
Rajesh
RajeshRajesh
Rajesh
 
Resume - W. Travis Scott
Resume - W. Travis ScottResume - W. Travis Scott
Resume - W. Travis Scott
 
Structural Design and FEM Analysis of Bleeder in Steam Turbine Casing
Structural Design and FEM Analysis of Bleeder in Steam Turbine CasingStructural Design and FEM Analysis of Bleeder in Steam Turbine Casing
Structural Design and FEM Analysis of Bleeder in Steam Turbine Casing
 
SISCO - Presentation
SISCO - PresentationSISCO - Presentation
SISCO - Presentation
 
MATT CV ROEVIN
MATT CV ROEVINMATT CV ROEVIN
MATT CV ROEVIN
 
PIPING DESIGNER
PIPING DESIGNERPIPING DESIGNER
PIPING DESIGNER
 
IRJET- Design and Analysis of Anchor Block and Penstock Pipe of a Hydroelectr...
IRJET- Design and Analysis of Anchor Block and Penstock Pipe of a Hydroelectr...IRJET- Design and Analysis of Anchor Block and Penstock Pipe of a Hydroelectr...
IRJET- Design and Analysis of Anchor Block and Penstock Pipe of a Hydroelectr...
 
KM_Information_Jan_2016_Red
KM_Information_Jan_2016_RedKM_Information_Jan_2016_Red
KM_Information_Jan_2016_Red
 
Sultan C.V
Sultan C.VSultan C.V
Sultan C.V
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
DOMTAR LIGNOBOOST
DOMTAR LIGNOBOOSTDOMTAR LIGNOBOOST
DOMTAR LIGNOBOOST
 
Ali Al-Hamdadah - Resume
Ali Al-Hamdadah - ResumeAli Al-Hamdadah - Resume
Ali Al-Hamdadah - Resume
 
Tanveer_Phansopkar_-__piping_Draughtsman (1)
Tanveer_Phansopkar_-__piping_Draughtsman (1)Tanveer_Phansopkar_-__piping_Draughtsman (1)
Tanveer_Phansopkar_-__piping_Draughtsman (1)
 

Andere mochten auch

Communication Plan Portfolio
Communication Plan PortfolioCommunication Plan Portfolio
Communication Plan PortfolioShannyn Rickman
 
84 Tears (2010 Comic) - Freelance Talents
84 Tears (2010 Comic) - Freelance Talents84 Tears (2010 Comic) - Freelance Talents
84 Tears (2010 Comic) - Freelance TalentsMohit Sharma
 
Te Matcha con Ginseng y Latte Freddo Fantastico
Te Matcha con Ginseng y Latte Freddo FantasticoTe Matcha con Ginseng y Latte Freddo Fantastico
Te Matcha con Ginseng y Latte Freddo FantasticoITALY COFFEE TEA STORE
 
How to interpret turnitin reports
How to interpret turnitin reportsHow to interpret turnitin reports
How to interpret turnitin reportsDileeka Fernando
 
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 Intro
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 IntroAWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 Intro
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 IntroAmazon Web Services Korea
 
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016Amazon Web Services Korea
 
Development of the Cell theory
Development of the Cell theoryDevelopment of the Cell theory
Development of the Cell theoryJoseph Alvarico
 
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance Seminar
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance SeminarAWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance Seminar
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance SeminarAmazon Web Services Korea
 
Arthropod classification
Arthropod classificationArthropod classification
Arthropod classificationJessi Dildy
 
TareqZantoot-Haddop_Administrator_Security
TareqZantoot-Haddop_Administrator_SecurityTareqZantoot-Haddop_Administrator_Security
TareqZantoot-Haddop_Administrator_SecurityTarek Elzanaty
 

Andere mochten auch (17)

Communication Plan Portfolio
Communication Plan PortfolioCommunication Plan Portfolio
Communication Plan Portfolio
 
84 Tears (2010 Comic) - Freelance Talents
84 Tears (2010 Comic) - Freelance Talents84 Tears (2010 Comic) - Freelance Talents
84 Tears (2010 Comic) - Freelance Talents
 
Te Matcha con Ginseng y Latte Freddo Fantastico
Te Matcha con Ginseng y Latte Freddo FantasticoTe Matcha con Ginseng y Latte Freddo Fantastico
Te Matcha con Ginseng y Latte Freddo Fantastico
 
Caffe Freddo al Ginseng Excelente
Caffe Freddo al Ginseng ExcelenteCaffe Freddo al Ginseng Excelente
Caffe Freddo al Ginseng Excelente
 
Yoga Therapy CME at MGMCRI 2015
Yoga Therapy CME at MGMCRI 2015Yoga Therapy CME at MGMCRI 2015
Yoga Therapy CME at MGMCRI 2015
 
flex_rewards
flex_rewardsflex_rewards
flex_rewards
 
How to interpret turnitin reports
How to interpret turnitin reportsHow to interpret turnitin reports
How to interpret turnitin reports
 
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 Intro
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 IntroAWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 Intro
AWS 클라우드 보안 및 규정 준수 소개 - 박철수 솔루션즈 아키텍트:: AWS Cloud Track 1 Intro
 
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016
스플렁크를 이용한 AWS운영 인텔리전스 확보:: Splunk 최승돈 :: AWS Summit Seoul 2016
 
Stem cells
Stem cellsStem cells
Stem cells
 
Development of the Cell theory
Development of the Cell theoryDevelopment of the Cell theory
Development of the Cell theory
 
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance Seminar
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance SeminarAWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance Seminar
AWS Security 솔루션 자세히 살펴보기 :: 신용녀 :: AWS Finance Seminar
 
Lesson 9 cells
Lesson 9   cellsLesson 9   cells
Lesson 9 cells
 
Immunity2
Immunity2Immunity2
Immunity2
 
Lesson 6 making biological drawings & using keys
Lesson 6   making biological drawings & using keysLesson 6   making biological drawings & using keys
Lesson 6 making biological drawings & using keys
 
Arthropod classification
Arthropod classificationArthropod classification
Arthropod classification
 
TareqZantoot-Haddop_Administrator_Security
TareqZantoot-Haddop_Administrator_SecurityTareqZantoot-Haddop_Administrator_Security
TareqZantoot-Haddop_Administrator_Security
 

Ähnlich wie Port Wentworth MBP Water Optimization Project

Justin N Drude Resume 10-16
Justin N Drude Resume 10-16Justin N Drude Resume 10-16
Justin N Drude Resume 10-16Justin Drude
 
The Process and 101 Guide for Spool Drawing
The Process and 101 Guide for Spool DrawingThe Process and 101 Guide for Spool Drawing
The Process and 101 Guide for Spool DrawingAEO Design Consultants
 
Industrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USAIndustrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USABrian Cherry
 
Streamlining the Construction Project
Streamlining the Construction ProjectStreamlining the Construction Project
Streamlining the Construction ProjectJoshua Zimmerman
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15Dave Beveridge
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Steve James Resume
Steve James   ResumeSteve James   Resume
Steve James Resumesejames8808
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L NBasavaraj L N
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newlisa zhang
 
GARYCV_2015_Dec_complete
GARYCV_2015_Dec_completeGARYCV_2015_Dec_complete
GARYCV_2015_Dec_completeGary Randall
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & mariaMaria Archana
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816William Deskin
 

Ähnlich wie Port Wentworth MBP Water Optimization Project (20)

CRP Presentation
CRP PresentationCRP Presentation
CRP Presentation
 
Justin N Drude Resume 10-16
Justin N Drude Resume 10-16Justin N Drude Resume 10-16
Justin N Drude Resume 10-16
 
Dons Res Mech Des 2012
Dons Res Mech Des 2012Dons Res Mech Des 2012
Dons Res Mech Des 2012
 
Mvcv v10
Mvcv v10Mvcv v10
Mvcv v10
 
The Process and 101 Guide for Spool Drawing
The Process and 101 Guide for Spool DrawingThe Process and 101 Guide for Spool Drawing
The Process and 101 Guide for Spool Drawing
 
Industrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USAIndustrial Refrigeration Drafter - Comfortsystems USA
Industrial Refrigeration Drafter - Comfortsystems USA
 
Streamlining the Construction Project
Streamlining the Construction ProjectStreamlining the Construction Project
Streamlining the Construction Project
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15
 
Amar Updated CV
Amar Updated CVAmar Updated CV
Amar Updated CV
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Heathman.Amanda resume
Heathman.Amanda resumeHeathman.Amanda resume
Heathman.Amanda resume
 
Steve James Resume
Steve James   ResumeSteve James   Resume
Steve James Resume
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L N
 
Lisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -newLisa_zhang2016 piping designer -new
Lisa_zhang2016 piping designer -new
 
M.foreman's resume'
M.foreman's resume'M.foreman's resume'
M.foreman's resume'
 
GARYCV_2015_Dec_complete
GARYCV_2015_Dec_completeGARYCV_2015_Dec_complete
GARYCV_2015_Dec_complete
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & maria
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816
 

Port Wentworth MBP Water Optimization Project

  • 1. Port Wentworth, Georgia Mixed Bed Polisher (MBP) ENERGY OPTIMIZATION PROJECT NO. PW13901 BY AUSTON BAGNAS (MBP DESIGNER) YEAR 2016
  • 2. Project Overview: This project is intended to remove impurities from the boiler feed water process. This facility would be located before the boiler and reduce contaminates from entering the boiler system. Contaminates can clog or foul piping within the boiler system. This would affect the quality and quantity of the process and may require additional shut down maintenance periods to repair any damage caused by these impurities.
  • 3. Ideation Process: Layout: The vendor supplies assemblies were skid based equipment and had no layout requirements. Layout was primarily dictated on available space and distance between assemblies. Placement: An existing building scheduled for demolition was chosen to house the facility. Process: Since this facility polishes boiler feed water it was located at the near the boiler feed water tank. Maintenance: The mill had a lot to say about the general arrangement on this project. Maintenance and operations from the mill helped determine how this facility would operate. Therefore the layout was greatly determined by the accessibility to the assemblies in the facility. (Picture: different skid locations & questions)
  • 4. Piping & Instrumentation Diagram (P.&I.D.s) A flow diagram, or piping schematic, is used to show the process flow for a facility or process. This design was a collaboration with the vendor, myself, and the project engineer for the CRP facility. This flow diagram best represents how the piping will be designed. It also locates instrumentation and assemblies that will be installed. This drawing is a valuable source of information for other drawings such as the piping plans, isometrics, tie-in drawings, and can further be used by operations after installation.
  • 5. General Arrangements (G.A.s) The general arrangements are drawn to show tank & vessel locations along with the structural design and sometimes maintenance access. These drawings are very basic for clarity.
  • 6. Piping Plans & Sections These drawings show the piping layout, vessel locations, and structural information. The P.&I.D.s, G.A.s, Tie-in drawings, and isometrics will be the primary source for information when installing prefabricated items on this project.
  • 7. MBP 3D Model A 3D model was created to best identify any layout concerns. The skids & vessels were created and inserted along with the chemical containment and any large bore piping. Multiple disciplines were incorporated into the design. Access for electrical and instruments were considered. The structural department located steel members based on a stress analysis of the building. Foundations were designed to accommodate pumps and vessels. A containment was designed and added as well. Many existing vessels and structures were used in this project. They were also modeled to show any interferences and possible uses.
  • 8. MBP 3D Model (cont.) Alternating views were utilized for orientation and installation of assemblies and equipment. Instrumentation was able to identify locations for instruments and junction boxes based on space and accessibility. Repair, removal, and maintenance was also considered in locating any equipment. Sample locations were installed for operations to conduct necessary analysis of the process. This model was also used by construction to better understand how the facility would look when installed.
  • 9.
  • 10.
  • 11.
  • 12. Construction & Installation After pipe and vessel fabrication construction crews began installation of the facility. Here are two photos taken during the construction phase of the MBP facility. Scaffolding is erected for access and installation of piping. Minor field modifications were made. I was onsite and able to work through some unforeseen challenges.
  • 13. Installed, commissioned, & running. December 2016 the MBP was finally brought online and is now successfully polishing condensate and removing impurities from the boiler feed water. There were a couple lessons learned on this project, one including an over designed feed pipe but nothing substantial. Overall the project was a great success and finalized on time and on budget.