SlideShare ist ein Scribd-Unternehmen logo
1 von 19
1
An Engineering Challenge
Building Hauls Roads for These Ultra Class Dump Trucks
with GVW 600t
Location : Bowen Basin Queensland, Australia
August2015
2
TheChallenge
Liebherr weighs the same as A380 Jumbo
3
TheChallenge
Purpose of Presentation is “Information Sharing Only” and opinions
shared are of the author only
4
TheChallenge Liebherr T282B
Gross Vehicle Weight (GVW): 600 ton
Payload Class: 363 ton
Empty Vehicle Weight (EVW): 237 ton
5
TheChallenge What does the project involve
Mine Upgrade 2012 involves the introduction of additional fleets:
 2 x Liebherr R9800 excavators (800t)
 12 x Liebherr T282B dump trucks
Construction of 12km of new hauls for T282B fleet
6
TheChallenge What does the project involve ?
Mine Upgrade 2012 involves the introduction of additional fleets:
 2 x Liebherr R9800 excavators (800t)
 12 x Liebherr T282B dump trucks
Construction of 12km of new hauls for T282B fleet
7
TheChallenge
Existing hauls roads
constructed from
overburden,
 not weather proof
 Roads will not
sustain T282 loads
8
ProjectOverview Process for tackling this Project July 2012 start
 Principal & Main Contractor Sign New Mining Operations Contract
 Scope of Works for Construction of New Hauls Completed
 Appointment of Specialised Consultants (Pells Sullivan Meynink
Geotechnical Engineers)
 Source Rock Assessment (On-Site Sandstone)
 Source Rock Assessment (External Quarry Sites)
 Review Past Learning from other Mining Projects in QLD and NSW
 Review Technical Papers by Robert Thompson and others
9
ProjectOverview
10
ProjectOverview
T282B vehicle Dimensions Width = 9.69m
Haul Road Width = 40m
11
MineSiteOverview
 Pad set up with sandstone that hs been used to build 800t excavator and withstood heavy
loading
Mechanical Team on were going to get site assessed by
Geotechnical as a 250T crawler crane was going to
operate on this hardstand for plant build of Liebherr
R9800 800t excavator and T282B dump truck builds
12
MineSiteOverview PMS site investigation confirmed a large variability in sandstone rock geotechnical properties
 Thorough and carefully material selection would be very important
13
MineSiteOverview
Potential sandstone source for suitable material for mobile crushing plant n site
however large mudstone deposit also present within source
14
MineSiteOverview Challenge on site was to work on Change Management and work with
Mining Team to : build and assign correct resources and equipment to
construct haul route with appropriate material rather overburden
which is unsatisfactory in wet weather
15
PMSSiteInspection Site Sandstone Rock
Variability
Red = Stop: Siltstone / Mudstone
(not suitable for road construction
Amber = Caution: Sandstone with
excessive quantity of siltstone
Green = Go : Sandstone with
suitable properties CBR 30 - 45
16
PreliminaryInvestigation
Adrian Smith’s from PSM Site inspection :
 Some potential to utilise some sound sandstone material on site
 Carefully mining will need to take place to only utilise certain sandstone
sources for feed to on site crushing and screen plant
 Multiple samples take as per Thiess request for Laboratory Testing
 Thiess and PMS to work together on optimising the pavement design based on
sandstone material on site
Dave Tulloch from Road Safety Training Services completed assessment
on site on Mine Road Friction Resistance
 Challenge was for Mining Management Team to incorporate these
initiatives and recommendations
17
MineSiteOverview Dave Tulloch from Road Safety Training Services completed assessment on
site on Friction Evaluation and Operational Protocol
 Challenge was for Mining Management Team to incorporate these
recommendation
 Construction of new haul roads would include recommendation from
report
 Challenge for site teams to “change mindset” and learn to use Vericom
system and adopt system of measuring and friction testing on haul
routes rather than using Open Cut Examiners judgement on safety of
haul roads post wet weather
18
ResultsofSiteInvestigation
Site Sandstone Rock Variability
 Sandstone with suitable
properties CBR 30 – 45
 However variability was
evident in test results
 PMS report provided guidance
on variability
19
Questions thank you for your time

Weitere ähnliche Inhalte

Was ist angesagt?

Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018SanjuBK
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction ExplainedDavid H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas PipelineBoudewijn Baan
 
Road and Bridges_3-D Milling_0311RB
Road and Bridges_3-D Milling_0311RBRoad and Bridges_3-D Milling_0311RB
Road and Bridges_3-D Milling_0311RBMark Mann
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Crosstown TO
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
2010 Visual Resume - Robert Tonn
2010 Visual Resume - Robert Tonn2010 Visual Resume - Robert Tonn
2010 Visual Resume - Robert Tonnroberttonn
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction TechniquesDavid H Moloney
 
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...Taylor Robinson
 
Evolving Frac Sand Supply Chain and Logistics Trends
Evolving Frac Sand Supply Chain and Logistics TrendsEvolving Frac Sand Supply Chain and Logistics Trends
Evolving Frac Sand Supply Chain and Logistics TrendsTaylor Robinson
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Curriculum Vitae Darren Shepherdson 2014
Curriculum Vitae Darren Shepherdson 2014Curriculum Vitae Darren Shepherdson 2014
Curriculum Vitae Darren Shepherdson 2014Darren Shepherdson
 

Was ist angesagt? (20)

Materialhandling
MaterialhandlingMaterialhandling
Materialhandling
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018Cv kanysh komyshev_21_12_2018
Cv kanysh komyshev_21_12_2018
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas Pipeline
 
Road and Bridges_3-D Milling_0311RB
Road and Bridges_3-D Milling_0311RBRoad and Bridges_3-D Milling_0311RB
Road and Bridges_3-D Milling_0311RB
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
2010 Visual Resume - Robert Tonn
2010 Visual Resume - Robert Tonn2010 Visual Resume - Robert Tonn
2010 Visual Resume - Robert Tonn
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
BPClairRidge
BPClairRidgeBPClairRidge
BPClairRidge
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...JP Morgan transportation and logistics frac sand logistics by plg consulting ...
JP Morgan transportation and logistics frac sand logistics by plg consulting ...
 
Evolving Frac Sand Supply Chain and Logistics Trends
Evolving Frac Sand Supply Chain and Logistics TrendsEvolving Frac Sand Supply Chain and Logistics Trends
Evolving Frac Sand Supply Chain and Logistics Trends
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Curriculum Vitae Darren Shepherdson 2014
Curriculum Vitae Darren Shepherdson 2014Curriculum Vitae Darren Shepherdson 2014
Curriculum Vitae Darren Shepherdson 2014
 

Andere mochten auch

The world’s largest dump trucks
The world’s largest dump trucksThe world’s largest dump trucks
The world’s largest dump trucksYanisDigital
 
Rigid dump trucks - 960_E - 2K
Rigid dump trucks - 960_E - 2KRigid dump trucks - 960_E - 2K
Rigid dump trucks - 960_E - 2Kkomatsuindia
 
MAKALAH ALAT BERAT (DUMPTRUCK)
MAKALAH ALAT BERAT (DUMPTRUCK)MAKALAH ALAT BERAT (DUMPTRUCK)
MAKALAH ALAT BERAT (DUMPTRUCK)atanoki
 
Project Report on Comparative Study Philips LED With Other Competitive Brands
Project Report on Comparative Study Philips LED With Other Competitive BrandsProject Report on Comparative Study Philips LED With Other Competitive Brands
Project Report on Comparative Study Philips LED With Other Competitive BrandsKapil Shelke
 

Andere mochten auch (8)

The world’s largest dump trucks
The world’s largest dump trucksThe world’s largest dump trucks
The world’s largest dump trucks
 
Dump truck
Dump truckDump truck
Dump truck
 
Rigid dump trucks - 960_E - 2K
Rigid dump trucks - 960_E - 2KRigid dump trucks - 960_E - 2K
Rigid dump trucks - 960_E - 2K
 
Mining dumper
Mining dumperMining dumper
Mining dumper
 
Presentasi alat berat jenis Dump Truck
Presentasi alat berat jenis Dump TruckPresentasi alat berat jenis Dump Truck
Presentasi alat berat jenis Dump Truck
 
MAKALAH ALAT BERAT (DUMPTRUCK)
MAKALAH ALAT BERAT (DUMPTRUCK)MAKALAH ALAT BERAT (DUMPTRUCK)
MAKALAH ALAT BERAT (DUMPTRUCK)
 
Project Report on Comparative Study Philips LED With Other Competitive Brands
Project Report on Comparative Study Philips LED With Other Competitive BrandsProject Report on Comparative Study Philips LED With Other Competitive Brands
Project Report on Comparative Study Philips LED With Other Competitive Brands
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Ähnlich wie Building Haul Roads for 600t Ultra Class Dump Trucks

Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LRAndrew de Villiers
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering projectLawrence Tjale
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16Edward Byrne
 
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICS
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICSGREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICS
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICSiQHub
 
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLift Events
 
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSiQHub
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Association for Project Management
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16Iain Cameron
 
1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside1255 - Roy Hill Port Landside
1255 - Roy Hill Port LandsideAnthony Jones
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptxLeyneth1
 
Rapidshor - notable projects
Rapidshor - notable projects Rapidshor - notable projects
Rapidshor - notable projects RMD Kwikform Ltd
 
Resume KV 2015
Resume KV 2015Resume KV 2015
Resume KV 2015Keith Vary
 
Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Shammy Puri
 

Ähnlich wie Building Haul Roads for 600t Ultra Class Dump Trucks (20)

Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offs
 
GEM - EMW Company Profile
GEM - EMW Company ProfileGEM - EMW Company Profile
GEM - EMW Company Profile
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering project
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16Eddie Byrne CV 1.06.16
Eddie Byrne CV 1.06.16
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICS
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICSGREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICS
GREEN TECHNOLOGY SOLUTIONS FOR DEEP SEA MINING LOGISTICS
 
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
 
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Satyavir-Resume_01
Satyavir-Resume_01Satyavir-Resume_01
Satyavir-Resume_01
 
RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16
 
1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside1255 - Roy Hill Port Landside
1255 - Roy Hill Port Landside
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptx
 
Rapidshor - notable projects
Rapidshor - notable projects Rapidshor - notable projects
Rapidshor - notable projects
 
Resume KV 2015
Resume KV 2015Resume KV 2015
Resume KV 2015
 
RA_CV - October 2016
RA_CV - October 2016RA_CV - October 2016
RA_CV - October 2016
 
Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011
 

Kürzlich hochgeladen

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 

Kürzlich hochgeladen (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 

Building Haul Roads for 600t Ultra Class Dump Trucks

  • 1. 1 An Engineering Challenge Building Hauls Roads for These Ultra Class Dump Trucks with GVW 600t Location : Bowen Basin Queensland, Australia August2015
  • 3. 3 TheChallenge Purpose of Presentation is “Information Sharing Only” and opinions shared are of the author only
  • 4. 4 TheChallenge Liebherr T282B Gross Vehicle Weight (GVW): 600 ton Payload Class: 363 ton Empty Vehicle Weight (EVW): 237 ton
  • 5. 5 TheChallenge What does the project involve Mine Upgrade 2012 involves the introduction of additional fleets:  2 x Liebherr R9800 excavators (800t)  12 x Liebherr T282B dump trucks Construction of 12km of new hauls for T282B fleet
  • 6. 6 TheChallenge What does the project involve ? Mine Upgrade 2012 involves the introduction of additional fleets:  2 x Liebherr R9800 excavators (800t)  12 x Liebherr T282B dump trucks Construction of 12km of new hauls for T282B fleet
  • 7. 7 TheChallenge Existing hauls roads constructed from overburden,  not weather proof  Roads will not sustain T282 loads
  • 8. 8 ProjectOverview Process for tackling this Project July 2012 start  Principal & Main Contractor Sign New Mining Operations Contract  Scope of Works for Construction of New Hauls Completed  Appointment of Specialised Consultants (Pells Sullivan Meynink Geotechnical Engineers)  Source Rock Assessment (On-Site Sandstone)  Source Rock Assessment (External Quarry Sites)  Review Past Learning from other Mining Projects in QLD and NSW  Review Technical Papers by Robert Thompson and others
  • 10. 10 ProjectOverview T282B vehicle Dimensions Width = 9.69m Haul Road Width = 40m
  • 11. 11 MineSiteOverview  Pad set up with sandstone that hs been used to build 800t excavator and withstood heavy loading Mechanical Team on were going to get site assessed by Geotechnical as a 250T crawler crane was going to operate on this hardstand for plant build of Liebherr R9800 800t excavator and T282B dump truck builds
  • 12. 12 MineSiteOverview PMS site investigation confirmed a large variability in sandstone rock geotechnical properties  Thorough and carefully material selection would be very important
  • 13. 13 MineSiteOverview Potential sandstone source for suitable material for mobile crushing plant n site however large mudstone deposit also present within source
  • 14. 14 MineSiteOverview Challenge on site was to work on Change Management and work with Mining Team to : build and assign correct resources and equipment to construct haul route with appropriate material rather overburden which is unsatisfactory in wet weather
  • 15. 15 PMSSiteInspection Site Sandstone Rock Variability Red = Stop: Siltstone / Mudstone (not suitable for road construction Amber = Caution: Sandstone with excessive quantity of siltstone Green = Go : Sandstone with suitable properties CBR 30 - 45
  • 16. 16 PreliminaryInvestigation Adrian Smith’s from PSM Site inspection :  Some potential to utilise some sound sandstone material on site  Carefully mining will need to take place to only utilise certain sandstone sources for feed to on site crushing and screen plant  Multiple samples take as per Thiess request for Laboratory Testing  Thiess and PMS to work together on optimising the pavement design based on sandstone material on site Dave Tulloch from Road Safety Training Services completed assessment on site on Mine Road Friction Resistance  Challenge was for Mining Management Team to incorporate these initiatives and recommendations
  • 17. 17 MineSiteOverview Dave Tulloch from Road Safety Training Services completed assessment on site on Friction Evaluation and Operational Protocol  Challenge was for Mining Management Team to incorporate these recommendation  Construction of new haul roads would include recommendation from report  Challenge for site teams to “change mindset” and learn to use Vericom system and adopt system of measuring and friction testing on haul routes rather than using Open Cut Examiners judgement on safety of haul roads post wet weather
  • 18. 18 ResultsofSiteInvestigation Site Sandstone Rock Variability  Sandstone with suitable properties CBR 30 – 45  However variability was evident in test results  PMS report provided guidance on variability
  • 19. 19 Questions thank you for your time