SlideShare ist ein Scribd-Unternehmen logo
1 von 8
Downloaden Sie, um offline zu lesen
IBP555_03
RISK BASED INSPECTION PLANNING OF THE OLAPA PIPELINE
Renato Mendes1
, Álvaro Correia Neto2
, Maher Nessim3
, Amir Muradali4
Copyright 2003, Brazilian Petroleum and Gas Institute - IBPilian Petroleum and Gas Institute - IBP
This paper was prepared for presentation at the Rio Pipeline Conference & Exposition 2003, held in October, 22-24, Brazil, Rio de Janeiro.This paper was prepared for presentation at the Rio Pipeline Conference & Exposition 2003, held in October, 22-24, Brazil, Rio de Janeiro.
This paper was selected for presentation by the Event Technical Committee following review of information contained in an abstract
submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the IBP. Organizers will neither translate nor
correct texts received. The material, as presented, does not necessarily reflect any position of the Brazilian Petroleum and Gas Institute, its
officers, or members. It’s Author’s knowledge and approval that this Technical Paper will be published in the Rio Pipeline Conference &
Exposition 2003 “brouchure”
This paper was selected for presentation by the Event Technical Committee following review of information contained in an abstract
submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the IBP. Organizers will neither translate nor
correct texts received. The material, as presented, does not necessarily reflect any position of the Brazilian Petroleum and Gas Institute, its
officers, or members. It’s Author’s knowledge and approval that this Technical Paper will be published in the Rio Pipeline Conference &
Exposition 2003 “brouchure”
Abstract
OLAPA is a 93.5 km, 12.75 inch pipeline transporting low and high vapor liquid products in
both directions between the REPAR refinery and a terminal near Paranagua, TEPAR.
Initially installed in 1976 with X46 steel and coal tar coating, OLAPA traverses various types
of land use and crosses a number of major roads and waterways. A quantitative risk-based
maintenance planning study is being carried out on OLAPA. The objectives of the study are
to identify key hazards that could lead to pipeline failure, estimate the operating risk
associated with these hazards, carry out risk sensitivity analyses for key parameters, and
identify optimal future maintenance activities. This analysis is being carried out using the
quantitative risk analysis model PIRAMID™, which makes extensive use of engineering
models to calculate probabilities and consequences of failure. This paper describes the
quantitative risk analysis approach used in the study and preliminary outcomes from this
study.
Introduction
This paper summarizes a Risk Based Inspection (RBI) study on Petrobras’ OLAPA pipeline
conducted by C-FER Technologies (C-FER) under sub contract to Bureau Veritas (BV). The
objectives of the study were to identify key hazards that could lead to pipeline failure,
estimate the operating risk associated with these hazards, carry out risk sensitivity analyses
for key parameters, and identify optimal future maintenance activities.
1 – Pipeline System
OLAPA is a 93.5 km, 12.75 inch pipeline transporting liquid products between the Petrobras
Parana refinery (REPAR) and terminal near Paranagua (TEPAR). The pipeline transports
Low Vapor Pressure (LVP) liquids as well as High Vapor Pressure (HVP) Liquefied
Petroleum Gases (LPG) in both directions.
1
PETROBRAS/ENGENHARIA, Rio de Janeiro, Brazil.
2
PETROBRAS/TRANSPETRO, Rio de Janeiro, Brazil.
3,4
C-FER Technologies, Edmonton, AB. Canada.
IBP555_03
OLAPA was initially installed in 1976 using X46 grade steel and coal tar external coating. In
addition to the two remote control end valves, 11 manually operated valves are installed at
different locations along the pipeline length. The pipeline traverses various types of land use
including residential, commercial, industrial, agricultural, parkland and remote. It also
crosses a number of waterways, streams and roadways. The 3 km segment immediately
adjacent to the terminal is located offshore in Paranagua Bay, running parallel to the shoreline
in an average water depth of 1.7 m in high tide. The pipeline has an elevation differential of
approximately 900m, most of which occurs between the terminal and the mid-point of the
pipeline.
Since the year 2001, the pipeline has been inspected for metal loss with a Magnetic Flux
Leakage (MFL) tool. Most of the defects reported have been excavated and repairs were
carried out where necessary. In addition, sections subject to slope movement have been stress
relieved and an extensive slope-monitoring program has been put in place. To prevent
mechanical damage, the pipeline is buried to a depth between 0.8 and 1.34 m, patrolled
monthly, and marked with highly visible and closely spaced signs.
2 – Project Methodology
The analysis was carried out using C-FER’s pipeline risk analysis model PIRAMID™
(PIpeline Risk Analysis for Maintenance and Inspection Decisions) (Nessim et al 1996, 1998,
2000). The following tasks were undertaken to achieve the project objectives:
1. Data transfer. The key failure causes for OLAPA were identified and data required
for PIRAMID™ analysis (failure cause and consequence modeling) was collected
under this task. BV and Petrobras performed majority the data collection, with C-FER
providing assistance and advice.
2. Risk analysis. Using information on the characteristics of the pipeline and right-of-
way, the probabilities and of small leak, large leak and rupture failures were estimated
for key failure causes including equipment impact, corrosion (external and internal),
manufacturing defects, seam weld cracks, and ground movement (transverse and
longitudinal). The consequences of failure were also calculated for small leaks, large
leaks and ruptures. Consequences are expressed in terms of total cost as a measure of
financial impact, expected number of fatalities as a measure of safety impact and
expected spill volume (adjusted for site sensitivity) as a measure of environmental
impact. The probability and consequence measures were calculated as functions of
km post along the pipeline. Risk at any location along the line was then calculated as
the sum of the failure probability multiplied by the failure consequences for all failure
causes and failure modes (i.e. small leak, large leak and rupture).
2
IBP555_03
3. Scenario analysis. A “what-if” scenario is defined as a copy of the original pipeline
model, in which one or more parameters are changed to reflect proposed inspection
and maintenance activities (or any other changes in operational parameters) or other
operational changes. A number of scenarios were defined in consultation with
Petrobras and each scenario was analyzed to calculate the impact of the proposed
changes on the overall risk. Where appropriate, scenarios were evaluated on a cost-
benefit basis to identify the most cost effective inspection and maintenance strategies.
4. Development of conclusions and recommendations. The results of the risk and
scenario analyses were used to develop a set of recommendations regarding inspection
and maintenance of the OLAPA pipeline.
3 – Risk Analysis
The following highlights the assumptions made in analyzing the OLAPA pipeline. Presented
are the primary inputs used to estimate the failure probability (for each hazard) and the
consequences for the pipeline. All failure causes, with the exception of “seam weld cracks”
and “other causes”, are estimated using structural reliability based models in PIRAMID™
(Nessim et al. 1996, 1998, 2000). Seam weld cracks are estimated using a simplified
historical based model in PIRAMID™
(Nessim et al. 1996, 1998, 2000).
Equipment Impact. Both the onshore and offshore sections of OLAPA face the possibility of
damage due to third party. For onshore sections, typical pipelines face the threat of damage
due to third party excavations. Whereas offshore pipelines face the threat of damage due to
dragged objects (anchors and fishing nets) as well as boat grounding. In further evaluating
the offshore section for OLAPA (in Paranagua Bay), the threat for damage was considered to
be negligible considering the bathymetry of the bay, the types of boats in this vicinity and the
pipeline depth of burial. Therefore only the onshore section of OLAPA is being evaluated for
equipment impact hazard.
External and Internal Corrosion. In 2001, an In Line Inspection (ILI) was carried out. All
metal loss defects with maximum depths greater than 25% of the wall thickness are
conservatively considered for this failure cause analysis since these are significant in size and
can potentially grow due to corrosion. This calculation is being refined further to account for
all defects smaller than 25% wall thickness.
Mill Defects. The ILI tool also detected metal loss defects due to mill construction. A mill
defect that has survived the commissioning pressure test does not represent a concern unless it
grows with time. If these defects were formed by cold working (e.g. a gouge), they could
have hardened metal at the base, from which a sharp crack could initiate and further grow by
fatigue under pressure cycling. Since the mechanism by which these defects were formed is
not known, this scenario is conservatively assumed to apply to all defects whose maximum
3
IBP555_03
depths are greater than 25% wall thickness. Similar to the case for corrosion, this calculation
is also being refined further to consider the smaller defects.
Seam Weld Cracks. The failure rate due to seam weld cracks is calculated from the magnitude
and frequency of hoop stress cycles using an S-N relationship.
Ground Movement. The OLAPA pipeline traverses a number of moving slopes between km
45 and km 61. In 2001, Petrobras undertook an extensive ground movement management
program, which included a) excavation of all locations experiencing significant soil
movement, replacement of damaged sections, stress relief of the pipeline, and installation of
surface drains to reduce the soil moisture content and limit the amount of ground movement,
b) Installation of a number of inclinometers on each slope to monitor the magnitude and
direction of movement, and c) pipe-soil interaction analyses, which involved characterizing
the soil mechanical properties and developing force-displacement relationships for soil loads
on the pipe in both the transverse and longitudinal directions. All ground movement failure
rate calculations are based on information developed by Petrobras under this program and
provided to C-FER for the RBI study. This information includes ground movement
characterizations from inclinometer data at specific locations and soil stiffness and strength
values from the pipe-soil interaction analysis. Further refinement of this analysis will include
considering potential ground movement at all sloped locations.
Stress Corrosion Cracking. No significant evidence of SCC was found and therefore this
failure cause is not considered in the analysis.
Other Causes. This failure cause covers failures due to miscellaneous events such as
defective girth, fabrication and repair welds, operator error, lightning and vandalism.
Consequences Estimation. Of primary concern for OLAPA in the event of a failure are the
costs associated to site restoration, compensation costs, environmental fines and costs due to
loss of production. Petrobras provided all relevant costs, which are used to estimate the
consequences of product spilled using PIRAMID™
(Nessim et al. 1996, 1998, 2000).
Figure 1 shows the Expected Cost (financial risk) profiles by failure cause. Apart from the
miscellaneous failures category (referred to as other causes), equipment impact is the highest
contributor to overall risk at present. Corrosion, mill defects and seam weld cracks have a
negligible contribution to risk at present; however, the contributions of these cause increase
with time. Figure 2 shows the change in Expected Cost by failure cause over time at one
point along the pipeline (km 55). Corrosion risk increases to a value similar to equipment
impact within approximately 10 years. Mill defects and seam weld fatigue remain
insignificant for 30 years, although they reach perceptible levels for the thinnest segment of
the pipeline (km 0 to 36.5). Transverse and longitudinal ground movements contribute to the
4
IBP555_03
risk at specific locations, and similar to corrosion, their contributions could become
significant within the 30-year analysis period.
Figure 1 Expected Cost by Failure Cause
Figure 2 Expected Cost by Failure Cause Over Time at km 55
5
IBP555_03
4 – Inspection and Maintenance Planning
The proposed inspection and maintenance plan focuses on mitigating risks due to the primary
contributors namely, equipment impact, metal loss corrosion defects, and ground movement.
Prevention of equipment impact. A number of possible mitigation strategies are considered
including installation of above ground markers consisting of closely spaced posts at selected
locations, installation of mechanical protection at high risk locations and increasing the right-
of-way patrol frequency from once per month to twice per week. PIRAMID™ results from a
benefit-cost analysis for these actions are shown in Figure 3. A benefit-cost ratio below one
indicates that the scenario is not economically viable as its costs exceed its economic benefits.
Figure 3 indicates that installation of mechanical protection and increasing the right-of-way
patrol frequency are not cost-effective. Installation of above ground alignment markers is
economically viable (after 6 years) and a sustained reduction in risk over the entire 30-year
analysis period.
Figure 3 Benefit-Cost Ratio for Equipment Impact Mitigation Actions
Defect rehabilitation. The rehabilitation scenarios considered included, hydrostatic testing at
a pressure of 1.25 MAOP and inspection with a high-resolution magnetic flux leakage tool.
Combined with the inspection, two possible repair criteria were considered based on
minimum required thickness values of 70% and 75% of the original wall. Figure 4 shows
results from a cost optimization analysis using PIRAMID™. The most cost-effective solution
can be identified as the lowest cost point on this figure. Figure 4 shows that the status quo
(do nothing) is the most cost-effective option for a period of 20 years. This indicates that an
6
IBP555_03
ILI or Hydrostatic test need not be undertaken in the near future. Although, the results
suggest that the status quo is optimal for 20 years, it is considered prudent to re-visit this
conclusion within a shorter period (e.g. 10 years). This conclusion is preliminary and is based
on assessing defects larger than 25% wall thickness.
Figure 4 Cost Optimization for Defect Rehabilitation Actions
Ground movement mitigation. Since Petrobras has an extensive program in monitoring the
ground movement at hilly locations where the pipeline crosses, this mitigation action involved
providing some correlation of the failure rate and risk to the amount of ground movement.
The probability of failure due to ground movement was estimated as a function of soil
movement magnitude (see Figure 5). Since the pipe and soil properties are the same in all
locations involving slope movement, the results of this analysis apply to all such locations.
The results show that transverse ground movement is initially more likely to lead to a failure,
but that the failure probability due to longitudinal ground movement increases at a higher rate
and surpasses the failure probability due to transverse movement at 400 mm of total
movement.
7
IBP555_03
1.00E-12
1.00E-11
1.00E-10
1.00E-09
1.00E-08
1.00E-07
1.00E-06
1.00E-05
1.00E-04
1.00E-03
1.00E-02
1.00E-01
1.00E+00
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Ground Movement (mm)
ProbabilityofFailure(perlocation)
Longitudinal
Transverse
Figure 5 Probability of Failure as a Function of Ground Movement Magnitude
5 – Summary
A Risk Based Inspection (RBI) study is being performed on Petrobras’ pipeline, OLAPA, the
approach of which is summarized in this paper. OLAPA is 93.5 km in length transporting
liquid products together with High Vapor Product (HVP) Liquefied Propane Gas (LPG). For
this pipeline, the risk analysis and scenario analysis considering various risk mitigative
actions is being performed by C-FER using PIRAMID™ software. Preliminary results from
this study indicate that the dominant failure causes for this pipeline are metal loss corrosion,
ground movement and third party damage, and the main driver for total economic risk is spill
volume.
6 – Acknowledgements
The authors would like to thank Bureau Veritas Brazil for their support during the data-
gathering phase of this project and their continued support in making this work possible.
7 – References
Nessim, M.A., Stephens, M.J. and Zimmerman, T.J.E. Risk-based Maintenance Planning for
Offshore Pipelines. Presented at the 2000 Offshore Technology Conference (OTC), Houston,
Texas, May 1-4
Nessim, M.A. and Stephens, M.J. 1998. Managing the Operating Risk Posed by Metal Loss
Corrosion and Mechanical Interference. Pipe Line and Gas Industry, Gulf Publishing, Part 1-
June and Part 2-August, 1998.
Stephens, M.J. and Nessim, M.A. 1996. Pipeline Maintenance Planning Based on
Quantitative Risk Analysis. Proceedings of the International Pipeline Conference, 1996.
Sponsored by the American Society of Mechanical Engineers (ASME). Calgary, Alberta.
8

Weitere ähnliche Inhalte

Was ist angesagt?

Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...IJECEIAES
 
registro de pozoz
registro de pozozregistro de pozoz
registro de pozozopulento22
 
Infos y pricing studies brownfields for refurbish
Infos y pricing studies brownfields for refurbish Infos y pricing studies brownfields for refurbish
Infos y pricing studies brownfields for refurbish Fands-llc
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerationsalco345ua
 
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTRAPHAEL AGORUA
 
iMPD Equipment
iMPD EquipmentiMPD Equipment
iMPD EquipmentKen Angus
 
IMPROVED RESERVOIR EVALUATION (Final report pge 405)
IMPROVED RESERVOIR EVALUATION (Final report pge 405)IMPROVED RESERVOIR EVALUATION (Final report pge 405)
IMPROVED RESERVOIR EVALUATION (Final report pge 405)Modou.L. Jarju
 
IMPROVED RESERVOIR EVALUATION 
IMPROVED RESERVOIR EVALUATION IMPROVED RESERVOIR EVALUATION 
IMPROVED RESERVOIR EVALUATION Modou.L. Jarju
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Society of Petroleum Engineers
 
Hydaulic Design for Highways
Hydaulic Design for HighwaysHydaulic Design for Highways
Hydaulic Design for Highwaysarvindjangid01
 
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesAudubon Engineering Company
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15Monica Riccio
 
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...Mohanned Mahjoup
 
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...IJMER
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines Audubon Engineering Company
 

Was ist angesagt? (20)

Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
 
External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA) External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA)
 
T4501109116
T4501109116T4501109116
T4501109116
 
registro de pozoz
registro de pozozregistro de pozoz
registro de pozoz
 
Sopaqu
SopaquSopaqu
Sopaqu
 
Infos y pricing studies brownfields for refurbish
Infos y pricing studies brownfields for refurbish Infos y pricing studies brownfields for refurbish
Infos y pricing studies brownfields for refurbish
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerations
 
Resume_-_Muthalib_Mohammad1
Resume_-_Muthalib_Mohammad1Resume_-_Muthalib_Mohammad1
Resume_-_Muthalib_Mohammad1
 
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORTPIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
PIPELINE DESIGN, INTEGRITY AND RELIABILITY REPORT
 
iMPD Equipment
iMPD EquipmentiMPD Equipment
iMPD Equipment
 
IMPROVED RESERVOIR EVALUATION (Final report pge 405)
IMPROVED RESERVOIR EVALUATION (Final report pge 405)IMPROVED RESERVOIR EVALUATION (Final report pge 405)
IMPROVED RESERVOIR EVALUATION (Final report pge 405)
 
IMPROVED RESERVOIR EVALUATION 
IMPROVED RESERVOIR EVALUATION IMPROVED RESERVOIR EVALUATION 
IMPROVED RESERVOIR EVALUATION 
 
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
Creating a Worldwide Unconventional Revolution Through a Technically Driven S...
 
Hydaulic Design for Highways
Hydaulic Design for HighwaysHydaulic Design for Highways
Hydaulic Design for Highways
 
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid PipelinesPresentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
Presentation Slides: PHMSA Final Rule (Part 1) for Hazardous Liquid Pipelines
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15
 
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
 
Icrc 002-4033
Icrc 002-4033Icrc 002-4033
Icrc 002-4033
 
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
 

Andere mochten auch

Diaz patsy actividad9
Diaz patsy actividad9Diaz patsy actividad9
Diaz patsy actividad9Patsy Diaz
 
ใบงานที่ 1 แบบสำรวจตัวเอง
ใบงานที่ 1  แบบสำรวจตัวเองใบงานที่ 1  แบบสำรวจตัวเอง
ใบงานที่ 1 แบบสำรวจตัวเองNatapon Mac
 
Statistical methods for microarray data analysis
Statistical methods for microarray data analysisStatistical methods for microarray data analysis
Statistical methods for microarray data analysisSpringer
 
Tarea semana 10
Tarea semana 10Tarea semana 10
Tarea semana 10Tupak Dx
 
Encyclopedia of radiation oncology
Encyclopedia of radiation oncologyEncyclopedia of radiation oncology
Encyclopedia of radiation oncologySpringer
 
Oregon smokesteak presentation final
Oregon smokesteak presentation finalOregon smokesteak presentation final
Oregon smokesteak presentation finalDavid LaValley
 
Head & neck cancer current perspectives, advances, and challenges
Head & neck cancer current perspectives, advances, and challengesHead & neck cancer current perspectives, advances, and challenges
Head & neck cancer current perspectives, advances, and challengesSpringer
 
Vm ware ha-ver-0.0.1
Vm ware ha-ver-0.0.1Vm ware ha-ver-0.0.1
Vm ware ha-ver-0.0.1pdnsoftco
 

Andere mochten auch (10)

из рио 8 авг. пам. вов куйтун нукутский р-н 3 обик
из рио 8 авг. пам. вов куйтун нукутский р-н 3 обикиз рио 8 авг. пам. вов куйтун нукутский р-н 3 обик
из рио 8 авг. пам. вов куйтун нукутский р-н 3 обик
 
Diaz patsy actividad9
Diaz patsy actividad9Diaz patsy actividad9
Diaz patsy actividad9
 
ใบงานที่ 1 แบบสำรวจตัวเอง
ใบงานที่ 1  แบบสำรวจตัวเองใบงานที่ 1  แบบสำรวจตัวเอง
ใบงานที่ 1 แบบสำรวจตัวเอง
 
Living Word - Matthew 2.1-12
Living Word - Matthew 2.1-12Living Word - Matthew 2.1-12
Living Word - Matthew 2.1-12
 
Statistical methods for microarray data analysis
Statistical methods for microarray data analysisStatistical methods for microarray data analysis
Statistical methods for microarray data analysis
 
Tarea semana 10
Tarea semana 10Tarea semana 10
Tarea semana 10
 
Encyclopedia of radiation oncology
Encyclopedia of radiation oncologyEncyclopedia of radiation oncology
Encyclopedia of radiation oncology
 
Oregon smokesteak presentation final
Oregon smokesteak presentation finalOregon smokesteak presentation final
Oregon smokesteak presentation final
 
Head & neck cancer current perspectives, advances, and challenges
Head & neck cancer current perspectives, advances, and challengesHead & neck cancer current perspectives, advances, and challenges
Head & neck cancer current perspectives, advances, and challenges
 
Vm ware ha-ver-0.0.1
Vm ware ha-ver-0.0.1Vm ware ha-ver-0.0.1
Vm ware ha-ver-0.0.1
 

Ähnlich wie 860686

Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...
Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...
Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...ijtsrd
 
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.IJRES Journal
 
CV - Khoi TU
CV - Khoi TUCV - Khoi TU
CV - Khoi TUKhoi Tu
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodpaulus konda
 
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...IRJET Journal
 
Determination of the corrosion rate of a mic influenced pipeline using four c...
Determination of the corrosion rate of a mic influenced pipeline using four c...Determination of the corrosion rate of a mic influenced pipeline using four c...
Determination of the corrosion rate of a mic influenced pipeline using four c...GeraldoRossoniSisqui
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsJean-Francois Saint-Marcoux
 
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...theijes
 
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...Ives Equipment
 
PA DEP Proposal to Study Radiation Levels Associated with Shale Drilling
PA DEP Proposal to Study Radiation Levels Associated with Shale DrillingPA DEP Proposal to Study Radiation Levels Associated with Shale Drilling
PA DEP Proposal to Study Radiation Levels Associated with Shale DrillingMarcellus Drilling News
 
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1Penchala Vineeth
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Projectashkan ezazi
 
An optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundAn optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundPatrick Schüller
 
Corrosion Assesment and Exceedance
Corrosion Assesment and ExceedanceCorrosion Assesment and Exceedance
Corrosion Assesment and ExceedanceDNV_Columbus
 
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...IRJET Journal
 
Safety excellence journey
Safety excellence journeySafety excellence journey
Safety excellence journeySandeep Gupta
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsssuser8fec94
 
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraJim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraContract Cities
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferenceJohn Grover
 
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortCUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortGary Penney
 

Ähnlich wie 860686 (20)

Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...
Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...
Simulation and Modelling of Pipeline Corrosion and Integrity Management in Oi...
 
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
Modelling and Stress Analysis of the Pig Loop Module of a Piping System.
 
CV - Khoi TU
CV - Khoi TUCV - Khoi TU
CV - Khoi TU
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT method
 
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
 
Determination of the corrosion rate of a mic influenced pipeline using four c...
Determination of the corrosion rate of a mic influenced pipeline using four c...Determination of the corrosion rate of a mic influenced pipeline using four c...
Determination of the corrosion rate of a mic influenced pipeline using four c...
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
 
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
 
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...
Claus Sulfur Recovery Tail Gas Applying 100 Million Hours of Operational Time...
 
PA DEP Proposal to Study Radiation Levels Associated with Shale Drilling
PA DEP Proposal to Study Radiation Levels Associated with Shale DrillingPA DEP Proposal to Study Radiation Levels Associated with Shale Drilling
PA DEP Proposal to Study Radiation Levels Associated with Shale Drilling
 
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1
IDENTIFYING RISK ZONE ALONG GAIL PIPELINE IN 1
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Project
 
An optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundAn optimised approach for the inspection of aboveground
An optimised approach for the inspection of aboveground
 
Corrosion Assesment and Exceedance
Corrosion Assesment and ExceedanceCorrosion Assesment and Exceedance
Corrosion Assesment and Exceedance
 
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
Ensuring Safety for the Construction Workers involved in Metro Tunnelling Pro...
 
Safety excellence journey
Safety excellence journeySafety excellence journey
Safety excellence journey
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impacts
 
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraJim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
 
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortCUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
 

860686

  • 1. IBP555_03 RISK BASED INSPECTION PLANNING OF THE OLAPA PIPELINE Renato Mendes1 , Álvaro Correia Neto2 , Maher Nessim3 , Amir Muradali4 Copyright 2003, Brazilian Petroleum and Gas Institute - IBPilian Petroleum and Gas Institute - IBP This paper was prepared for presentation at the Rio Pipeline Conference & Exposition 2003, held in October, 22-24, Brazil, Rio de Janeiro.This paper was prepared for presentation at the Rio Pipeline Conference & Exposition 2003, held in October, 22-24, Brazil, Rio de Janeiro. This paper was selected for presentation by the Event Technical Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the IBP. Organizers will neither translate nor correct texts received. The material, as presented, does not necessarily reflect any position of the Brazilian Petroleum and Gas Institute, its officers, or members. It’s Author’s knowledge and approval that this Technical Paper will be published in the Rio Pipeline Conference & Exposition 2003 “brouchure” This paper was selected for presentation by the Event Technical Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the IBP. Organizers will neither translate nor correct texts received. The material, as presented, does not necessarily reflect any position of the Brazilian Petroleum and Gas Institute, its officers, or members. It’s Author’s knowledge and approval that this Technical Paper will be published in the Rio Pipeline Conference & Exposition 2003 “brouchure” Abstract OLAPA is a 93.5 km, 12.75 inch pipeline transporting low and high vapor liquid products in both directions between the REPAR refinery and a terminal near Paranagua, TEPAR. Initially installed in 1976 with X46 steel and coal tar coating, OLAPA traverses various types of land use and crosses a number of major roads and waterways. A quantitative risk-based maintenance planning study is being carried out on OLAPA. The objectives of the study are to identify key hazards that could lead to pipeline failure, estimate the operating risk associated with these hazards, carry out risk sensitivity analyses for key parameters, and identify optimal future maintenance activities. This analysis is being carried out using the quantitative risk analysis model PIRAMID™, which makes extensive use of engineering models to calculate probabilities and consequences of failure. This paper describes the quantitative risk analysis approach used in the study and preliminary outcomes from this study. Introduction This paper summarizes a Risk Based Inspection (RBI) study on Petrobras’ OLAPA pipeline conducted by C-FER Technologies (C-FER) under sub contract to Bureau Veritas (BV). The objectives of the study were to identify key hazards that could lead to pipeline failure, estimate the operating risk associated with these hazards, carry out risk sensitivity analyses for key parameters, and identify optimal future maintenance activities. 1 – Pipeline System OLAPA is a 93.5 km, 12.75 inch pipeline transporting liquid products between the Petrobras Parana refinery (REPAR) and terminal near Paranagua (TEPAR). The pipeline transports Low Vapor Pressure (LVP) liquids as well as High Vapor Pressure (HVP) Liquefied Petroleum Gases (LPG) in both directions. 1 PETROBRAS/ENGENHARIA, Rio de Janeiro, Brazil. 2 PETROBRAS/TRANSPETRO, Rio de Janeiro, Brazil. 3,4 C-FER Technologies, Edmonton, AB. Canada.
  • 2. IBP555_03 OLAPA was initially installed in 1976 using X46 grade steel and coal tar external coating. In addition to the two remote control end valves, 11 manually operated valves are installed at different locations along the pipeline length. The pipeline traverses various types of land use including residential, commercial, industrial, agricultural, parkland and remote. It also crosses a number of waterways, streams and roadways. The 3 km segment immediately adjacent to the terminal is located offshore in Paranagua Bay, running parallel to the shoreline in an average water depth of 1.7 m in high tide. The pipeline has an elevation differential of approximately 900m, most of which occurs between the terminal and the mid-point of the pipeline. Since the year 2001, the pipeline has been inspected for metal loss with a Magnetic Flux Leakage (MFL) tool. Most of the defects reported have been excavated and repairs were carried out where necessary. In addition, sections subject to slope movement have been stress relieved and an extensive slope-monitoring program has been put in place. To prevent mechanical damage, the pipeline is buried to a depth between 0.8 and 1.34 m, patrolled monthly, and marked with highly visible and closely spaced signs. 2 – Project Methodology The analysis was carried out using C-FER’s pipeline risk analysis model PIRAMID™ (PIpeline Risk Analysis for Maintenance and Inspection Decisions) (Nessim et al 1996, 1998, 2000). The following tasks were undertaken to achieve the project objectives: 1. Data transfer. The key failure causes for OLAPA were identified and data required for PIRAMID™ analysis (failure cause and consequence modeling) was collected under this task. BV and Petrobras performed majority the data collection, with C-FER providing assistance and advice. 2. Risk analysis. Using information on the characteristics of the pipeline and right-of- way, the probabilities and of small leak, large leak and rupture failures were estimated for key failure causes including equipment impact, corrosion (external and internal), manufacturing defects, seam weld cracks, and ground movement (transverse and longitudinal). The consequences of failure were also calculated for small leaks, large leaks and ruptures. Consequences are expressed in terms of total cost as a measure of financial impact, expected number of fatalities as a measure of safety impact and expected spill volume (adjusted for site sensitivity) as a measure of environmental impact. The probability and consequence measures were calculated as functions of km post along the pipeline. Risk at any location along the line was then calculated as the sum of the failure probability multiplied by the failure consequences for all failure causes and failure modes (i.e. small leak, large leak and rupture). 2
  • 3. IBP555_03 3. Scenario analysis. A “what-if” scenario is defined as a copy of the original pipeline model, in which one or more parameters are changed to reflect proposed inspection and maintenance activities (or any other changes in operational parameters) or other operational changes. A number of scenarios were defined in consultation with Petrobras and each scenario was analyzed to calculate the impact of the proposed changes on the overall risk. Where appropriate, scenarios were evaluated on a cost- benefit basis to identify the most cost effective inspection and maintenance strategies. 4. Development of conclusions and recommendations. The results of the risk and scenario analyses were used to develop a set of recommendations regarding inspection and maintenance of the OLAPA pipeline. 3 – Risk Analysis The following highlights the assumptions made in analyzing the OLAPA pipeline. Presented are the primary inputs used to estimate the failure probability (for each hazard) and the consequences for the pipeline. All failure causes, with the exception of “seam weld cracks” and “other causes”, are estimated using structural reliability based models in PIRAMID™ (Nessim et al. 1996, 1998, 2000). Seam weld cracks are estimated using a simplified historical based model in PIRAMID™ (Nessim et al. 1996, 1998, 2000). Equipment Impact. Both the onshore and offshore sections of OLAPA face the possibility of damage due to third party. For onshore sections, typical pipelines face the threat of damage due to third party excavations. Whereas offshore pipelines face the threat of damage due to dragged objects (anchors and fishing nets) as well as boat grounding. In further evaluating the offshore section for OLAPA (in Paranagua Bay), the threat for damage was considered to be negligible considering the bathymetry of the bay, the types of boats in this vicinity and the pipeline depth of burial. Therefore only the onshore section of OLAPA is being evaluated for equipment impact hazard. External and Internal Corrosion. In 2001, an In Line Inspection (ILI) was carried out. All metal loss defects with maximum depths greater than 25% of the wall thickness are conservatively considered for this failure cause analysis since these are significant in size and can potentially grow due to corrosion. This calculation is being refined further to account for all defects smaller than 25% wall thickness. Mill Defects. The ILI tool also detected metal loss defects due to mill construction. A mill defect that has survived the commissioning pressure test does not represent a concern unless it grows with time. If these defects were formed by cold working (e.g. a gouge), they could have hardened metal at the base, from which a sharp crack could initiate and further grow by fatigue under pressure cycling. Since the mechanism by which these defects were formed is not known, this scenario is conservatively assumed to apply to all defects whose maximum 3
  • 4. IBP555_03 depths are greater than 25% wall thickness. Similar to the case for corrosion, this calculation is also being refined further to consider the smaller defects. Seam Weld Cracks. The failure rate due to seam weld cracks is calculated from the magnitude and frequency of hoop stress cycles using an S-N relationship. Ground Movement. The OLAPA pipeline traverses a number of moving slopes between km 45 and km 61. In 2001, Petrobras undertook an extensive ground movement management program, which included a) excavation of all locations experiencing significant soil movement, replacement of damaged sections, stress relief of the pipeline, and installation of surface drains to reduce the soil moisture content and limit the amount of ground movement, b) Installation of a number of inclinometers on each slope to monitor the magnitude and direction of movement, and c) pipe-soil interaction analyses, which involved characterizing the soil mechanical properties and developing force-displacement relationships for soil loads on the pipe in both the transverse and longitudinal directions. All ground movement failure rate calculations are based on information developed by Petrobras under this program and provided to C-FER for the RBI study. This information includes ground movement characterizations from inclinometer data at specific locations and soil stiffness and strength values from the pipe-soil interaction analysis. Further refinement of this analysis will include considering potential ground movement at all sloped locations. Stress Corrosion Cracking. No significant evidence of SCC was found and therefore this failure cause is not considered in the analysis. Other Causes. This failure cause covers failures due to miscellaneous events such as defective girth, fabrication and repair welds, operator error, lightning and vandalism. Consequences Estimation. Of primary concern for OLAPA in the event of a failure are the costs associated to site restoration, compensation costs, environmental fines and costs due to loss of production. Petrobras provided all relevant costs, which are used to estimate the consequences of product spilled using PIRAMID™ (Nessim et al. 1996, 1998, 2000). Figure 1 shows the Expected Cost (financial risk) profiles by failure cause. Apart from the miscellaneous failures category (referred to as other causes), equipment impact is the highest contributor to overall risk at present. Corrosion, mill defects and seam weld cracks have a negligible contribution to risk at present; however, the contributions of these cause increase with time. Figure 2 shows the change in Expected Cost by failure cause over time at one point along the pipeline (km 55). Corrosion risk increases to a value similar to equipment impact within approximately 10 years. Mill defects and seam weld fatigue remain insignificant for 30 years, although they reach perceptible levels for the thinnest segment of the pipeline (km 0 to 36.5). Transverse and longitudinal ground movements contribute to the 4
  • 5. IBP555_03 risk at specific locations, and similar to corrosion, their contributions could become significant within the 30-year analysis period. Figure 1 Expected Cost by Failure Cause Figure 2 Expected Cost by Failure Cause Over Time at km 55 5
  • 6. IBP555_03 4 – Inspection and Maintenance Planning The proposed inspection and maintenance plan focuses on mitigating risks due to the primary contributors namely, equipment impact, metal loss corrosion defects, and ground movement. Prevention of equipment impact. A number of possible mitigation strategies are considered including installation of above ground markers consisting of closely spaced posts at selected locations, installation of mechanical protection at high risk locations and increasing the right- of-way patrol frequency from once per month to twice per week. PIRAMID™ results from a benefit-cost analysis for these actions are shown in Figure 3. A benefit-cost ratio below one indicates that the scenario is not economically viable as its costs exceed its economic benefits. Figure 3 indicates that installation of mechanical protection and increasing the right-of-way patrol frequency are not cost-effective. Installation of above ground alignment markers is economically viable (after 6 years) and a sustained reduction in risk over the entire 30-year analysis period. Figure 3 Benefit-Cost Ratio for Equipment Impact Mitigation Actions Defect rehabilitation. The rehabilitation scenarios considered included, hydrostatic testing at a pressure of 1.25 MAOP and inspection with a high-resolution magnetic flux leakage tool. Combined with the inspection, two possible repair criteria were considered based on minimum required thickness values of 70% and 75% of the original wall. Figure 4 shows results from a cost optimization analysis using PIRAMID™. The most cost-effective solution can be identified as the lowest cost point on this figure. Figure 4 shows that the status quo (do nothing) is the most cost-effective option for a period of 20 years. This indicates that an 6
  • 7. IBP555_03 ILI or Hydrostatic test need not be undertaken in the near future. Although, the results suggest that the status quo is optimal for 20 years, it is considered prudent to re-visit this conclusion within a shorter period (e.g. 10 years). This conclusion is preliminary and is based on assessing defects larger than 25% wall thickness. Figure 4 Cost Optimization for Defect Rehabilitation Actions Ground movement mitigation. Since Petrobras has an extensive program in monitoring the ground movement at hilly locations where the pipeline crosses, this mitigation action involved providing some correlation of the failure rate and risk to the amount of ground movement. The probability of failure due to ground movement was estimated as a function of soil movement magnitude (see Figure 5). Since the pipe and soil properties are the same in all locations involving slope movement, the results of this analysis apply to all such locations. The results show that transverse ground movement is initially more likely to lead to a failure, but that the failure probability due to longitudinal ground movement increases at a higher rate and surpasses the failure probability due to transverse movement at 400 mm of total movement. 7
  • 8. IBP555_03 1.00E-12 1.00E-11 1.00E-10 1.00E-09 1.00E-08 1.00E-07 1.00E-06 1.00E-05 1.00E-04 1.00E-03 1.00E-02 1.00E-01 1.00E+00 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Ground Movement (mm) ProbabilityofFailure(perlocation) Longitudinal Transverse Figure 5 Probability of Failure as a Function of Ground Movement Magnitude 5 – Summary A Risk Based Inspection (RBI) study is being performed on Petrobras’ pipeline, OLAPA, the approach of which is summarized in this paper. OLAPA is 93.5 km in length transporting liquid products together with High Vapor Product (HVP) Liquefied Propane Gas (LPG). For this pipeline, the risk analysis and scenario analysis considering various risk mitigative actions is being performed by C-FER using PIRAMID™ software. Preliminary results from this study indicate that the dominant failure causes for this pipeline are metal loss corrosion, ground movement and third party damage, and the main driver for total economic risk is spill volume. 6 – Acknowledgements The authors would like to thank Bureau Veritas Brazil for their support during the data- gathering phase of this project and their continued support in making this work possible. 7 – References Nessim, M.A., Stephens, M.J. and Zimmerman, T.J.E. Risk-based Maintenance Planning for Offshore Pipelines. Presented at the 2000 Offshore Technology Conference (OTC), Houston, Texas, May 1-4 Nessim, M.A. and Stephens, M.J. 1998. Managing the Operating Risk Posed by Metal Loss Corrosion and Mechanical Interference. Pipe Line and Gas Industry, Gulf Publishing, Part 1- June and Part 2-August, 1998. Stephens, M.J. and Nessim, M.A. 1996. Pipeline Maintenance Planning Based on Quantitative Risk Analysis. Proceedings of the International Pipeline Conference, 1996. Sponsored by the American Society of Mechanical Engineers (ASME). Calgary, Alberta. 8