SlideShare a Scribd company logo
1 of 9
Download to read offline
Diagnosing Bridge Crane Tracking Problems
Introduction
Poor bridge tracking can be a stubborn and expensive maintenance issue for overhead cranes.
Tracking problems are difficult to diagnose due to the many different conditions that cause
them. If not rectified promptly the destructive action feeds on itself. Problems can multiply,
diagnosis becomes more difficult, and the fix becomes more expensive.
This article provides guidance for maintenance technicians and engineers on solving tracking
problems by the process of elimination.
Normal vs. Abnormal Bridge Tracking Behavior
Skewing, side thrust, and wheel/rail wear occur naturally during bridge tracking. Design
specifications for cranes and runways provide for lateral crane loads and forces caused by
steering and skewing. For certain hard worked crane applications, wheels and rails may almost
be considered consumable items. For these cranes it is difficult to discern between normal and
abnormal behavior. For abnormal tracking behavior look for one or more of the following
symptoms:
• Worn wheels, wheel bearings, and rails.
• Broken tie-backs between runway beams and columns.
• Extra drive power required to muscle through certain areas of the runway.
• Broken wheel flanges.
• Loud scraping sounds.
• Wheel flanges pressed hard against the rail head.
• End trucks cracked near the wheel assemblies.
• Loose girder connections.
• Wheel flanges attempt to climb over the rail then suddenly crash down.
• Bridge derailment.
Even if these symptoms are not present, the suggestions in this guide will help improve bridge
tracking performance and reduce maintenance.
Skewing occurs when there is a difference in traction (or speed) between opposite ends of the bridge. For this description we will assume that
skewing is initiated by one drive end moving faster than the other, or from drive wheel skidding/slippage. When this happens, the following
events are set into motion:
1. The drive effectively delivers a larger traction force to one end of the bridge.
2. The difference in traction between the driven ends causes the bridge span to act as a lever arm. Figure 2 shows the lever arm forces (F)
being resisted by lateral loading of the wheels and rail.
3. The lever-arm action causes the bridge frame to temporarily deform as shown in Figure 1.
4. The deformation causes the corners of the bridge frame to twist, and the wheels to become temporarily misaligned. If the frame is not stiff
enough, the misalignment will contribute to the tracking problem.
5. The frame will remain deformed as long as there is a difference in traction force between the driven ends.
6. The traction difference causes the crane to steer to one side of the runway.
7. The crane will continue to steer to one side until the wheel flange touches the side of the rail head.
8. The wheel flange applies a lateral force to the runway (F in Figure 2).
9. The lateral force creates a friction force parallel to the runway.
10. The friction force counteracts the traction force.
11. The random differences of the friction forces between bridge ends causes the skew angle to intermittently increase and decrease.
12. See Figure 2. The crane rotates (in plan) until the sum of the wheel flange friction is equal to the traction force difference between the
driven ends. The angle of rotation is the skew angle.
13. If the skew angle becomes large enough, the friction force parallel to the runway will equal or exceed the traction force and the crane will
bind and come to a halt.
14. If the drives have sufficient power and traction, the wheels will climb up the rail and the crane may derail.
The skew angle can be prevented from becoming large by using a smaller wheel/rail float (Figure 3). If the runway is properly aligned, then a
smaller wheel/rail float can improve tracking performance.
Suggestions for Diagnosing Tracking Problems
The following tables contain conditions to investigate. The tables are ordered by their likelihood to cause tracking problems.
Notes: See references 1 and 2 for runway alignment tolerances.
Notes:
2.1. See reference 2 for wheel alignment tolerance. Wheel alignment surveys are difficult to
perform and should only be completed by qualified personnel who are experienced with
this work. Piloted flange capsules can be replaced with eccentric bores for adjustment.
Bearing alignments can only be made to spherical roller bearings.
Notes:
3.1. There is a common misconception that bumping the crane against the end stops will
“square” the bridge frame. This procedure is not recommended due to the following:
• The end stops may not be perpendicular to the runway.
• The bridge bumpers may not be square to the bridge alignment.
• Girder connections should hold the corner joint completely rigid and not be “adjustable”.
Notes:
4.2 When the bridge travels across the runway beam, it deflects downward and assumes a
concave shape. The bridge then travels on a downward slope until it reaches the mid span of the
beam. After passing the mid span, the bridge travels uphill. More power is required for travelling
uphill, and less for downhill. This condition creates a difference in traction force between the
driven ends and can cause skewing.
Conclusion
Use these tables as a starting point to create a disciplined and systematic troubleshooting procedure that is suitable for your
cranes and runways. The investigation phase should be carried out by qualified personnel who have experience solving tracking
problems for a variety of different crane application.
 

More Related Content

What's hot

Theory for Welded connection.pdf
Theory for Welded connection.pdfTheory for Welded connection.pdf
Theory for Welded connection.pdfYatiTank
 
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad Pro
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad ProDesign of Water Tank for the Town of Population 50000 and Analysis by- Staad Pro
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad ProIRJET Journal
 
Equivalencias - Dibujo 2º Bach.
Equivalencias - Dibujo 2º Bach.Equivalencias - Dibujo 2º Bach.
Equivalencias - Dibujo 2º Bach.Lau Visual Arts
 
Steel connections in steel structure
Steel connections in steel structureSteel connections in steel structure
Steel connections in steel structureENGR MOTI RAM
 

What's hot (6)

Theory for Welded connection.pdf
Theory for Welded connection.pdfTheory for Welded connection.pdf
Theory for Welded connection.pdf
 
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad Pro
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad ProDesign of Water Tank for the Town of Population 50000 and Analysis by- Staad Pro
Design of Water Tank for the Town of Population 50000 and Analysis by- Staad Pro
 
Círculo Vasarely
Círculo VasarelyCírculo Vasarely
Círculo Vasarely
 
Equivalencias - Dibujo 2º Bach.
Equivalencias - Dibujo 2º Bach.Equivalencias - Dibujo 2º Bach.
Equivalencias - Dibujo 2º Bach.
 
Steel connections in steel structure
Steel connections in steel structureSteel connections in steel structure
Steel connections in steel structure
 
16- caténaires
16- caténaires16- caténaires
16- caténaires
 

Similar to Crane Tracking problems

01-Rail span correction compressor house
01-Rail span correction compressor house01-Rail span correction compressor house
01-Rail span correction compressor houseDeepak kumar sahoo
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...Hossam Shafiq I
 
Gear Drives.pptx
Gear Drives.pptxGear Drives.pptx
Gear Drives.pptxsateeshka
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdfTVijayaGowri
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent waydhara dattani
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its typeYash Patel
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepRAMPRASAD KUMAWAT
 
Study of different types of Gears
Study of different types of Gears   Study of different types of Gears
Study of different types of Gears Mesum Raza Naqvi
 
Roller adjustment-and-skew
Roller adjustment-and-skewRoller adjustment-and-skew
Roller adjustment-and-skewmkpq pasha
 
Axle load for Rail way - linkedin
Axle load for Rail way - linkedinAxle load for Rail way - linkedin
Axle load for Rail way - linkedinHamad Al-oqayli
 
chapter-3 Track Stracture.pptx
chapter-3  Track Stracture.pptxchapter-3  Track Stracture.pptx
chapter-3 Track Stracture.pptxMamushLeta
 
Yaw stability of single versus tandem axle tractors
Yaw stability of single versus tandem axle tractorsYaw stability of single versus tandem axle tractors
Yaw stability of single versus tandem axle tractorsRoberto Davis
 

Similar to Crane Tracking problems (20)

01-Rail span correction compressor house
01-Rail span correction compressor house01-Rail span correction compressor house
01-Rail span correction compressor house
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 
Gear Drives.pptx
Gear Drives.pptxGear Drives.pptx
Gear Drives.pptx
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
GEARS PPT.pptx
GEARS PPT.pptxGEARS PPT.pptx
GEARS PPT.pptx
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail Creep
 
Study of different types of Gears
Study of different types of Gears   Study of different types of Gears
Study of different types of Gears
 
Roller adjustment-and-skew
Roller adjustment-and-skewRoller adjustment-and-skew
Roller adjustment-and-skew
 
Active suspension
Active suspensionActive suspension
Active suspension
 
Axle load for Rail way - linkedin
Axle load for Rail way - linkedinAxle load for Rail way - linkedin
Axle load for Rail way - linkedin
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Roller
RollerRoller
Roller
 
Roller
RollerRoller
Roller
 
Roller
RollerRoller
Roller
 
chapter-3 Track Stracture.pptx
chapter-3  Track Stracture.pptxchapter-3  Track Stracture.pptx
chapter-3 Track Stracture.pptx
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Reare axle
Reare axleReare axle
Reare axle
 
Yaw stability of single versus tandem axle tractors
Yaw stability of single versus tandem axle tractorsYaw stability of single versus tandem axle tractors
Yaw stability of single versus tandem axle tractors
 

More from Amin Paniwala

01. drop pit table august 2016
01. drop pit table  august 201601. drop pit table  august 2016
01. drop pit table august 2016Amin Paniwala
 
Bogie turn table (amin)
Bogie turn table (amin)Bogie turn table (amin)
Bogie turn table (amin)Amin Paniwala
 
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.Amin Paniwala
 
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...Amin Paniwala
 
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...Amin Paniwala
 
1.presentation Box Portal traverser
1.presentation   Box Portal traverser 1.presentation   Box Portal traverser
1.presentation Box Portal traverser Amin Paniwala
 

More from Amin Paniwala (6)

01. drop pit table august 2016
01. drop pit table  august 201601. drop pit table  august 2016
01. drop pit table august 2016
 
Bogie turn table (amin)
Bogie turn table (amin)Bogie turn table (amin)
Bogie turn table (amin)
 
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.
Cranes & Railway Equipment by Unique Handlers Pvt. Ltd.
 
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...
Multi track pit traverser vs 2 track Surface Traverser with Slightly Submerge...
 
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...
Rail levels & solutions (6 jan 2014) (Prepared for guidance to users of Trave...
 
1.presentation Box Portal traverser
1.presentation   Box Portal traverser 1.presentation   Box Portal traverser
1.presentation Box Portal traverser
 

Crane Tracking problems

  • 1. Diagnosing Bridge Crane Tracking Problems Introduction Poor bridge tracking can be a stubborn and expensive maintenance issue for overhead cranes. Tracking problems are difficult to diagnose due to the many different conditions that cause them. If not rectified promptly the destructive action feeds on itself. Problems can multiply, diagnosis becomes more difficult, and the fix becomes more expensive. This article provides guidance for maintenance technicians and engineers on solving tracking problems by the process of elimination. Normal vs. Abnormal Bridge Tracking Behavior Skewing, side thrust, and wheel/rail wear occur naturally during bridge tracking. Design specifications for cranes and runways provide for lateral crane loads and forces caused by steering and skewing. For certain hard worked crane applications, wheels and rails may almost be considered consumable items. For these cranes it is difficult to discern between normal and abnormal behavior. For abnormal tracking behavior look for one or more of the following symptoms: • Worn wheels, wheel bearings, and rails. • Broken tie-backs between runway beams and columns. • Extra drive power required to muscle through certain areas of the runway. • Broken wheel flanges. • Loud scraping sounds. • Wheel flanges pressed hard against the rail head. • End trucks cracked near the wheel assemblies. • Loose girder connections. • Wheel flanges attempt to climb over the rail then suddenly crash down. • Bridge derailment. Even if these symptoms are not present, the suggestions in this guide will help improve bridge tracking performance and reduce maintenance.
  • 2.
  • 3. Skewing occurs when there is a difference in traction (or speed) between opposite ends of the bridge. For this description we will assume that skewing is initiated by one drive end moving faster than the other, or from drive wheel skidding/slippage. When this happens, the following events are set into motion: 1. The drive effectively delivers a larger traction force to one end of the bridge. 2. The difference in traction between the driven ends causes the bridge span to act as a lever arm. Figure 2 shows the lever arm forces (F) being resisted by lateral loading of the wheels and rail. 3. The lever-arm action causes the bridge frame to temporarily deform as shown in Figure 1. 4. The deformation causes the corners of the bridge frame to twist, and the wheels to become temporarily misaligned. If the frame is not stiff enough, the misalignment will contribute to the tracking problem. 5. The frame will remain deformed as long as there is a difference in traction force between the driven ends. 6. The traction difference causes the crane to steer to one side of the runway. 7. The crane will continue to steer to one side until the wheel flange touches the side of the rail head. 8. The wheel flange applies a lateral force to the runway (F in Figure 2). 9. The lateral force creates a friction force parallel to the runway. 10. The friction force counteracts the traction force. 11. The random differences of the friction forces between bridge ends causes the skew angle to intermittently increase and decrease. 12. See Figure 2. The crane rotates (in plan) until the sum of the wheel flange friction is equal to the traction force difference between the driven ends. The angle of rotation is the skew angle. 13. If the skew angle becomes large enough, the friction force parallel to the runway will equal or exceed the traction force and the crane will bind and come to a halt. 14. If the drives have sufficient power and traction, the wheels will climb up the rail and the crane may derail. The skew angle can be prevented from becoming large by using a smaller wheel/rail float (Figure 3). If the runway is properly aligned, then a smaller wheel/rail float can improve tracking performance.
  • 4. Suggestions for Diagnosing Tracking Problems The following tables contain conditions to investigate. The tables are ordered by their likelihood to cause tracking problems.
  • 5. Notes: See references 1 and 2 for runway alignment tolerances. Notes: 2.1. See reference 2 for wheel alignment tolerance. Wheel alignment surveys are difficult to perform and should only be completed by qualified personnel who are experienced with this work. Piloted flange capsules can be replaced with eccentric bores for adjustment. Bearing alignments can only be made to spherical roller bearings.
  • 6.
  • 7. Notes: 3.1. There is a common misconception that bumping the crane against the end stops will “square” the bridge frame. This procedure is not recommended due to the following: • The end stops may not be perpendicular to the runway. • The bridge bumpers may not be square to the bridge alignment. • Girder connections should hold the corner joint completely rigid and not be “adjustable”. Notes: 4.2 When the bridge travels across the runway beam, it deflects downward and assumes a concave shape. The bridge then travels on a downward slope until it reaches the mid span of the beam. After passing the mid span, the bridge travels uphill. More power is required for travelling uphill, and less for downhill. This condition creates a difference in traction force between the driven ends and can cause skewing.
  • 8.
  • 9. Conclusion Use these tables as a starting point to create a disciplined and systematic troubleshooting procedure that is suitable for your cranes and runways. The investigation phase should be carried out by qualified personnel who have experience solving tracking problems for a variety of different crane application.