SlideShare a Scribd company logo
1 of 20
Presented By:

Abhishek Pachisia

   B.Tech IT

   090102801
   Program Evaluation and Review Technique.

   Analyze the tasks.

   United States Navy.

   Event-oriented Technique

   Major Factor – Time

   Ex: 1968 Winter Olympics in Grenoble
   The main objective of PERT :
     To facilitate decision making and
     To reduce both the time and cost required to complete a
      project.

   Related Tools:
     Critical Path Method.
     Gantt chart

   Applied to:
     Very large-scale,
     One-time,
     Complex,
     Non-routine infrastructure and
     Research and Development projects
   Specific activities and milestones.

   Sequence of the activities.

   Network diagram.

   Estimate the time.

   Critical path.

   Update the PERT chart.




     Activities.


     Milestones.


     It is helpful to list the tasks in a table.



     May be combined with the activity identification
      step
        Since the activity sequence is evident for some tasks.


     Other tasks may require more analysis
        To determine the exact order in which they must be
         performed.


     Activity sequence information
        A network diagram can be drawn showing the sequence of
         the serial and parallel activities.
     Each activity represents: A node in the network,
     The arrows represent: The relation between
      activities.
     Software packages simplify this task
        By automatically converting tabular activity information into
         a network diagram.




     Weeks are a commonly used unit of time for activity
      completion.
     A distinguishing feature of PERT.
         Its ability to deal with uncertainty in activity completion time.

     Optimistic time(O)
         The shortest time in which the activity can be completed.
         To specify optimistic time to be three standards deviations from the
          mean.

     Most likely time(M)
         The completion time having the highest probability.
 Pessimistic time (P)
    the maximum possible time required to accomplish a task,
     assuming everything goes wrong (but excluding major
     catastrophes).

 PERT assumes a beta probability distribution for the
  time estimates.
 Estimated Time(TE)
    The best estimate of the time required to accomplish a task,
     accounting for the fact that things don't always proceed as
     normal.

          TE = (O + 4M + P) ÷ 6





     The critical path is
         Determined by adding the times for the activities in each sequence.
         Determining the longest path in the project.

     The critical path determines the total calendar time required
      for the project.
     If activities outside the critical path speed up or slow down
      (within limits), the total project time does not change.
     The amount of time that a non – critical path activity can be
      delayed without the project is referred to as a slack time.
 Critical Path is helpful to determine
     ES – Earliest Start time
     EF - Earliest Finish time
     LS – Latest Start time
     LF - Latest Finish time

 The variance in the project completion time can be
  calculated by summing the variances in the completion
  times of the activities in the critical path.
 The project can be accelerated by adding the resources
  required to decrease the time for the activities in the
  critical path.
 Shortening of the project sometimes is referred to as
  Project Crashing.


     Make adjustments in the PERT chart as the project
      progresses.
     As the project unfolds, the estimated times can be
      replaced with actual times.
     In cases where
        There are delays,
        Additional resources may be needed to stay on schedule
        The PERT chart may be modified to reflect the new
         situation.
   Explicitly defines and makes visible dependencies
    between the WBS elements

   Facilitates identification of the critical path.

   Facilitates identification of
     Start date,
     End date, and
     Slack time for each activity,

   Provides potentially reduced project duration.

   The large amount of project data can be organized &
    presented in diagram for use in decision making.
   Hundreds or thousands of activities and individual
    dependency relationships

   Not easily scalable for smaller projects

   The network charts tend to be large and unwieldy requiring
    several pages to print.

   The lack of a timeframe on most charts makes it harder to
    show status although colours can help

   When the charts become unwieldy, they are no longer used
    to manage the project.
   In this Case Study, the Project manager knows


     The succession of the project activities ,
     Optimistic Time,
     Pessimistic Time and
     Most Likely Time
    All the times known are in weeks.
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management

More Related Content

What's hot

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt chartsVARSHA RUSTAGI
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartMathew Varghese V
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTAbraham Ncunge
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method Mkaur01
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 

What's hot (20)

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Gantt Charts
Gantt ChartsGantt Charts
Gantt Charts
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 

Viewers also liked

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Operational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMOperational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMvckg1987
 
Production Management Introduction
Production Management IntroductionProduction Management Introduction
Production Management IntroductionDr. Gururaj Phatak
 
Numerical assignment
Numerical assignmentNumerical assignment
Numerical assignmentAnupam Kumar
 
Supervised Classification
Supervised ClassificationSupervised Classification
Supervised ClassificationChad Yowler
 
Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Susan Aragon
 
Land cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLand cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLisa Jensen
 
Graphical Method
Graphical MethodGraphical Method
Graphical MethodSachin MK
 
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerFew Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerSwetha A
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesKabir Uddin
 
Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Fredy Neira
 
Introduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageIntroduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageKabir Uddin
 
Original SOINN
Original SOINNOriginal SOINN
Original SOINNSOINN Inc.
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical MethodJoseph Konnully
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 

Viewers also liked (20)

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Operational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMOperational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPM
 
Production Management Introduction
Production Management IntroductionProduction Management Introduction
Production Management Introduction
 
Numerical assignment
Numerical assignmentNumerical assignment
Numerical assignment
 
Supervised Classification
Supervised ClassificationSupervised Classification
Supervised Classification
 
Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)
 
Land cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLand cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, California
 
graphical method
graphical method graphical method
graphical method
 
Clustering
ClusteringClustering
Clustering
 
Graphical Method
Graphical MethodGraphical Method
Graphical Method
 
NDVI
NDVINDVI
NDVI
 
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerFew Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite Images
 
Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009
 
Introduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageIntroduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat image
 
Original SOINN
Original SOINNOriginal SOINN
Original SOINN
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 

Similar to PERT Analysis Technique for Project Management

PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique) Tanoj Patidar
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review TechniqueSimonRobertson
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxmamtabisht10
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 

Similar to PERT Analysis Technique for Project Management (20)

or-pert
or-pertor-pert
or-pert
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
Pert and gantt chart.pptx
Pert and gantt chart.pptxPert and gantt chart.pptx
Pert and gantt chart.pptx
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
Control techniques
Control techniquesControl techniques
Control techniques
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Pert n gantt
Pert n gantt Pert n gantt
Pert n gantt
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Project management
Project managementProject management
Project management
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 

More from Abhishek Pachisia (20)

Telecom Industry
Telecom IndustryTelecom Industry
Telecom Industry
 
Strategic alignment model (SAM)
Strategic alignment model (SAM)Strategic alignment model (SAM)
Strategic alignment model (SAM)
 
V.G. siddhartha
V.G. siddharthaV.G. siddhartha
V.G. siddhartha
 
Boeing- The Frontiers
Boeing- The FrontiersBoeing- The Frontiers
Boeing- The Frontiers
 
Top Management of 5 recognized comapanies
Top Management of 5 recognized comapaniesTop Management of 5 recognized comapanies
Top Management of 5 recognized comapanies
 
Fourier transform
Fourier transformFourier transform
Fourier transform
 
Inference engine
Inference engineInference engine
Inference engine
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
IEEE 802.11
IEEE 802.11IEEE 802.11
IEEE 802.11
 
Cloud Service Models
Cloud Service ModelsCloud Service Models
Cloud Service Models
 
Exception handling in Java
Exception handling in JavaException handling in Java
Exception handling in Java
 
Perl
PerlPerl
Perl
 
Rpc
RpcRpc
Rpc
 
Hydrogen energy
Hydrogen energyHydrogen energy
Hydrogen energy
 
Rms titanic
Rms titanicRms titanic
Rms titanic
 
Vb.net (loop structure)
Vb.net (loop structure)Vb.net (loop structure)
Vb.net (loop structure)
 
Matrix Representation Of Graph
Matrix Representation Of GraphMatrix Representation Of Graph
Matrix Representation Of Graph
 
Tree
TreeTree
Tree
 
File System Implementation
File System ImplementationFile System Implementation
File System Implementation
 
Exception handling
Exception handlingException handling
Exception handling
 

Recently uploaded

Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxleah joy valeriano
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 

Recently uploaded (20)

Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 

PERT Analysis Technique for Project Management

  • 1. Presented By: Abhishek Pachisia B.Tech IT 090102801
  • 2. Program Evaluation and Review Technique.  Analyze the tasks.  United States Navy.  Event-oriented Technique  Major Factor – Time  Ex: 1968 Winter Olympics in Grenoble
  • 3. The main objective of PERT :  To facilitate decision making and  To reduce both the time and cost required to complete a project.  Related Tools:  Critical Path Method.  Gantt chart  Applied to:  Very large-scale,  One-time,  Complex,  Non-routine infrastructure and  Research and Development projects
  • 4. Specific activities and milestones.  Sequence of the activities.  Network diagram.  Estimate the time.  Critical path.  Update the PERT chart.
  • 5.  Activities.  Milestones.  It is helpful to list the tasks in a table.
  • 6.  May be combined with the activity identification step  Since the activity sequence is evident for some tasks.  Other tasks may require more analysis  To determine the exact order in which they must be performed.
  • 7.  Activity sequence information  A network diagram can be drawn showing the sequence of the serial and parallel activities.  Each activity represents: A node in the network,  The arrows represent: The relation between activities.  Software packages simplify this task  By automatically converting tabular activity information into a network diagram.
  • 8.  Weeks are a commonly used unit of time for activity completion.  A distinguishing feature of PERT.  Its ability to deal with uncertainty in activity completion time.  Optimistic time(O)  The shortest time in which the activity can be completed.  To specify optimistic time to be three standards deviations from the mean.  Most likely time(M)  The completion time having the highest probability.
  • 9.  Pessimistic time (P)  the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).  PERT assumes a beta probability distribution for the time estimates.  Estimated Time(TE)  The best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal. TE = (O + 4M + P) ÷ 6
  • 10.  The critical path is  Determined by adding the times for the activities in each sequence.  Determining the longest path in the project.  The critical path determines the total calendar time required for the project.  If activities outside the critical path speed up or slow down (within limits), the total project time does not change.  The amount of time that a non – critical path activity can be delayed without the project is referred to as a slack time.
  • 11.  Critical Path is helpful to determine  ES – Earliest Start time  EF - Earliest Finish time  LS – Latest Start time  LF - Latest Finish time  The variance in the project completion time can be calculated by summing the variances in the completion times of the activities in the critical path.  The project can be accelerated by adding the resources required to decrease the time for the activities in the critical path.  Shortening of the project sometimes is referred to as Project Crashing.
  • 12.  Make adjustments in the PERT chart as the project progresses.  As the project unfolds, the estimated times can be replaced with actual times.  In cases where  There are delays,  Additional resources may be needed to stay on schedule  The PERT chart may be modified to reflect the new situation.
  • 13. Explicitly defines and makes visible dependencies between the WBS elements  Facilitates identification of the critical path.  Facilitates identification of  Start date,  End date, and  Slack time for each activity,  Provides potentially reduced project duration.  The large amount of project data can be organized & presented in diagram for use in decision making.
  • 14. Hundreds or thousands of activities and individual dependency relationships  Not easily scalable for smaller projects  The network charts tend to be large and unwieldy requiring several pages to print.  The lack of a timeframe on most charts makes it harder to show status although colours can help  When the charts become unwieldy, they are no longer used to manage the project.
  • 15. In this Case Study, the Project manager knows  The succession of the project activities ,  Optimistic Time,  Pessimistic Time and  Most Likely Time All the times known are in weeks.

Editor's Notes

  1. -1-PERT was developed primarily to simplify the planning and scheduling of large and complex projects-3-First developed by the United States Navy in 1950s.-4-Event-oriented Technique rather than start- and completion-oriented.
  2. The critical path method (CPM) is an algorithm for scheduling a set of project activities.
  3. -1-Identify the specific activities and milestones.-2-Determine the proper sequence of the activities.-3-Construct a network diagram.-4-Estimate the time required for each activity.-5-Determine the critical path.-6-Update the PERT chart as the project progresses.
  4. -1-The activities are the tasks required to complete a project.-2-The milestones are the events marking the beginning and the end of one or more activities.-3-It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
  5. -1-Weeks are a commonly used unit of time for activity completion, any consistent unit of time can be used.-3-2-So that there is a approximately a 1% chance that the activity will be completed within the optimistic time.-4-Note that this time is different from the expected time.
  6. The implication being thatthe expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time.
  7. -1-A work breakdown structure element may be a product, data, a service, or any combination-4-Better understanding of dependencies leading to improved overlapping of activities and tasks were feasible.