PERT (Program Evaluation and Review Technique) is a project management tool developed by the US Navy to analyze complex projects by breaking them into tasks, estimating activity times, and identifying the critical path of tasks. It facilitates decision making by determining the earliest and latest start/finish times and calculating slack time to reduce project time and costs. PERT uses a network diagram and beta distribution to model activity times and account for uncertainty in complex, non-routine projects.
2. Program Evaluation and Review Technique.
Analyze the tasks.
United States Navy.
Event-oriented Technique
Major Factor – Time
Ex: 1968 Winter Olympics in Grenoble
3. The main objective of PERT :
To facilitate decision making and
To reduce both the time and cost required to complete a
project.
Related Tools:
Critical Path Method.
Gantt chart
Applied to:
Very large-scale,
One-time,
Complex,
Non-routine infrastructure and
Research and Development projects
4. Specific activities and milestones.
Sequence of the activities.
Network diagram.
Estimate the time.
Critical path.
Update the PERT chart.
5.
Activities.
Milestones.
It is helpful to list the tasks in a table.
6.
May be combined with the activity identification
step
Since the activity sequence is evident for some tasks.
Other tasks may require more analysis
To determine the exact order in which they must be
performed.
7.
Activity sequence information
A network diagram can be drawn showing the sequence of
the serial and parallel activities.
Each activity represents: A node in the network,
The arrows represent: The relation between
activities.
Software packages simplify this task
By automatically converting tabular activity information into
a network diagram.
8.
Weeks are a commonly used unit of time for activity
completion.
A distinguishing feature of PERT.
Its ability to deal with uncertainty in activity completion time.
Optimistic time(O)
The shortest time in which the activity can be completed.
To specify optimistic time to be three standards deviations from the
mean.
Most likely time(M)
The completion time having the highest probability.
9. Pessimistic time (P)
the maximum possible time required to accomplish a task,
assuming everything goes wrong (but excluding major
catastrophes).
PERT assumes a beta probability distribution for the
time estimates.
Estimated Time(TE)
The best estimate of the time required to accomplish a task,
accounting for the fact that things don't always proceed as
normal.
TE = (O + 4M + P) ÷ 6
10.
The critical path is
Determined by adding the times for the activities in each sequence.
Determining the longest path in the project.
The critical path determines the total calendar time required
for the project.
If activities outside the critical path speed up or slow down
(within limits), the total project time does not change.
The amount of time that a non – critical path activity can be
delayed without the project is referred to as a slack time.
11. Critical Path is helpful to determine
ES – Earliest Start time
EF - Earliest Finish time
LS – Latest Start time
LF - Latest Finish time
The variance in the project completion time can be
calculated by summing the variances in the completion
times of the activities in the critical path.
The project can be accelerated by adding the resources
required to decrease the time for the activities in the
critical path.
Shortening of the project sometimes is referred to as
Project Crashing.
12.
Make adjustments in the PERT chart as the project
progresses.
As the project unfolds, the estimated times can be
replaced with actual times.
In cases where
There are delays,
Additional resources may be needed to stay on schedule
The PERT chart may be modified to reflect the new
situation.
13. Explicitly defines and makes visible dependencies
between the WBS elements
Facilitates identification of the critical path.
Facilitates identification of
Start date,
End date, and
Slack time for each activity,
Provides potentially reduced project duration.
The large amount of project data can be organized &
presented in diagram for use in decision making.
14. Hundreds or thousands of activities and individual
dependency relationships
Not easily scalable for smaller projects
The network charts tend to be large and unwieldy requiring
several pages to print.
The lack of a timeframe on most charts makes it harder to
show status although colours can help
When the charts become unwieldy, they are no longer used
to manage the project.
15. In this Case Study, the Project manager knows
The succession of the project activities ,
Optimistic Time,
Pessimistic Time and
Most Likely Time
All the times known are in weeks.
Editor's Notes
-1-PERT was developed primarily to simplify the planning and scheduling of large and complex projects-3-First developed by the United States Navy in 1950s.-4-Event-oriented Technique rather than start- and completion-oriented.
The critical path method (CPM) is an algorithm for scheduling a set of project activities.
-1-Identify the specific activities and milestones.-2-Determine the proper sequence of the activities.-3-Construct a network diagram.-4-Estimate the time required for each activity.-5-Determine the critical path.-6-Update the PERT chart as the project progresses.
-1-The activities are the tasks required to complete a project.-2-The milestones are the events marking the beginning and the end of one or more activities.-3-It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
-1-Weeks are a commonly used unit of time for activity completion, any consistent unit of time can be used.-3-2-So that there is a approximately a 1% chance that the activity will be completed within the optimistic time.-4-Note that this time is different from the expected time.
The implication being thatthe expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time.
-1-A work breakdown structure element may be a product, data, a service, or any combination-4-Better understanding of dependencies leading to improved overlapping of activities and tasks were feasible.